1. Sleeve Installation
a) Sleeve installation 1
b) Sleeve installation 2
c) Sleeve installation 3
Installation Manual
Sleeve installation - 1
Sleeve
1 RC Beam Sleeve
a1
D
Beam Height
1 2
D
b a2
Selection of "d"
500 ≦ D < 700 : 175 ≧ d a1, a2 ≧ min (1.2D , 1000mm)
700 ≦ D < 900 : 200 ≧ d
900 ≦ D b≧ 3X
: 250 ≧ d 2
* If sleeve need to install out of above area, discuss with structure engineer for permission before installation
F.L
Mark the sleeve location,
500
size etc by permanent
PVC Pipe
marker
Beam width -5mm
Support
Bar
Lean concrete
Marking Mark the sleeve location, size etc on lean concrete (by MEP work)
Re-bar Stirrup re-bar should avoid to install at sleeve location (Civil work)
Sleeve installation Re-check the sleeve location (horizontal, vertical). Fix support bar on
stirrup re-bar, and install sleeve on support bar with tighten GI wire and protect both ends
by plastic tape to prevent cement mortar seepage into the sleeve. (MEP work )
Reinforcement
Form work
Concreting
1 Installation of actual size of pipe as sleeve for (1) By pass pipiing between T1 and T2 of under ground water tank
(2) Water outlet pipe and drain pipe of elevated water tank
Flange
Water Tank
Silicone
Sealant
Backup materials
Backup materials
PVC pipe sleeve Slope to outside
Fix support
Silicone Sealant
(Pipe)
A ≒ 30
Soil or Sand
Remarks
1) Install PVC pipe with slope to outside.
2) Sealant for gap filling shall be used Silicone type
■ Cables
The standard of copper cables are as follow
REMARK.
Color Code
Three Phase - L1 (Brown), L2 (Black), L3 (Grey), Neutral (Blue), Earth (Green/Yellow)
Single Phase - Line (Brown), Neutral (Blue), Eatrh (Green/Yellow)
Installation Manual
Electrical Materials - Conduit
Electrical
■ Compression Terminal
Compression Terminal is as follow
Standard
Name Remarks
Standard No Standard Name
Compression Terminal for copper
Compression Terminal BS 4579
cable
■ Conduit
1. Conduit
Conduit is as follows
1) for indoor use, use thin conduit or non screw type metal conduit
2)For outdoor use,use thick conduit or non-screw typr metal conduit
2.Accessories of conduit
Accessories of metal conduit is as follow
Standard
Purpose Remarks
No Name
For metal conduit Normal bend Thick, Thin and non-screw conduit
Coupling
Union coupling Thick conduit
BS 4568
Connector Thin, Non-screw conduit
BS EN ISO 1461
Bushing Thick, Thin conduit
Universal Thick, Thin and non-screw conduit
■ PVC CONDUIT ( Rigid Conduit) MADE IN MALAYSIA ■ PVC FLEXIBLE CONDUIT ( Corrugated Conduit) MADE IN MALAYSIA
Fixing screw
Cover Stainless steel
A、B:Max 350mm
B
Top Cover
B
Gasket
Fixing screw Gasket Cover
Stainless made
B
B) In case longitude
A A A A) In case longitude
length within 200mm
length exceed 200mm
Structure for outdoor pull box
Top cover type
Fixing screw
Stainless steel
■ PVC Pull Box ( USE WATER PROOF TYPE )
215X150X110
SIZE 215X215X 80
250X200X160
310X230X145
Installation Manual
Selection Hanger Rods For Metal Trunking
Electrical Work
Trunking Size Weight Support Interval Weitht of each support Hanger Rod Size
mm kg/m m kg mm
100x50 3.2 2.5 8 10
100x100 4.2 2.5 11 10
200x50 5.6 2.5 14 10
200X100 7.9 2.5 20 10
300x50 7 2.5 18 10
200x200 11 2.5 28 10
300x200 12.6 2.5 32 10
300x300 14.4 2.5 36 10
1.Conduit
Single suspension should be provided by hanger bolts of M10 at supporting intervals of 2 meters. Common suspension
or common wall supporting should be in accordance with Table-1 from which weight load is calculated and hanger
bolts are selected
2. Cable Ladder
Cables ladders size up to 1000W should be supported by hanger bolts of M10 at max support intervals of 2 m(Table-2)
Table-1 Table-2
Thin Conduit Thick Conduit Cable Ladder
EMT IMC
Size Weight Size Weight Size Weight Interval Load weight Rod Size
Notes
1. Anchor bolt
For bolts of 10mm OD or larger anchor bolts which are in principle driven in to building structure when concretes is
placed should be used in case inserts can not be used because of design issue etc. Obtain approval of a person in
charge of the system.
3. Color of Inserts
Inserts should be color coded- classified in accordance with each trade
Installation Manual
Conduit Support
Electrical
3) Maximum interval of support is3.6 m for 25 mm Dia metal conduit with saddle crip
4)When the conduit install on ceiling or wall surface, use hanger or saddle fitting to fix it on with max 2m interval.
However, additional support shall be installed at near the connection point and pipe end
Saddle Conduit
Max 3,600
As near as
Pump Room
and Fire Alarm Piping
below 95 max 20
below 240 max 15
over 240 max 12
Max 3600
max 300
Channel
max 300
DB or
PVC WP Pull Box
max 300
■Conduit Installation
1.Conduit fabrication
1) Cut the pipe vertically to the pipe centre
a)Debar the cut end of conduit and file it.
2) In case of bending of conduit, consider to take enough radius. If necessary,
install pull box in the middle of conduit pass.
a) internal radius for bending shall be more than 6 times of pipe diameter. Due to structure issue,
further bending will allow if conduit side is below 25mm.
b) Conduit bend shall not be arranged more than 3 points in between boxes.
c) Install pull box when the pass exceed 30m or due to site installation
Min 6xD
2. Connection of conduit
1)When connecting conduit, use coupling or non-screw coupling
3) The connection between conduit and box or metal duct shall be fixed perfectly with pipe screw,
connector,bushing etc.
Installation Manual
Conduit Installation - 2
Electrical
■Embedded Conduit-1
When the conduit required to be embedded in concrete floor or etc., consider the structure strength.
1. For embedded conduit in slab, max outside diameter shall be 1/4 of slab thickness (Max 32mmDia)
3. Cut the pipe vertically to the pipe centre. Remover bur on pipe by leamer, but extra careful to don’t damage coating
4. If many conduit need to embedded in concrete, consider the structure stlength to maintain and
each conduit shall be keep 30mm distance for enough concrete to pour
5. In case of double re-bar, the conduit shall be laid between top and bottom re-bar.
In case of single re-bar, the conduit shall be laid in centre of wall or floor
6. Conduit location shall be decided with co-ordinating with duct opening and opening reinforcement re-bar
8. Metal conduit shall be tighten with re-bar by steel wire to avoid moving by concrete pouring
Fixing distance is max 2m. But the fixing shall be arrange with parallel re-bar and cross re-bar
10. Outlet box and conduit shall be fixed well to avoid that box to move up.
11. Conduit which connecting box shall be fixed with re-bar at 300mm from the box
Steel Re-Bar
Fixing Wire
max 300 max 300
■Embedded Conduit-2
12.Vertical conduit from concrete slab shall be kept 100 to 150mm from slab, and cover the conduit end with plastic
or end cap.
min 30
Steel Wire
End cap
Temp Support
Support fitting
100~150
Re-Bar
LIGHTING SYSTEM
b) Fixing by support fitting
a) Fixing by steel wire
13. Concrete box, outlet box etc shall be fixed strongly with proper protection
14. Conduit support for concrete without re-bar may use cramp with every 2m. Joint shall be coupling etc.
max 3600
max 300
A B C
Re-bar
Cable size
Safety ratio
Single core(mm )Multi core (mm2 )
3)If the conduit length is less than 6m, and not much bending in the pass, total cable section area
with safety ratio shall be less than 48% of conduit section area.
Installation Manual
Flexible Conduit - 2
Electrical
■Embedded Conduit
1.The points of installation
When the conduit required to embedded in concrete floor or etc., consider the structure strength
1. For embedded conduit in slab, max outside diameter shall be 1/4 of slab thickness (Max 32 mmDia)
3. If many conduit need to embedded in concrete, consider the structure length to maintain and
each conduit shall be keep 30mm distance for enough concrete to pour
4. In case of double re-bar, the conduit shall be laid between top and bottom re-bar.
In case of single re-bar, the conduit shall be laid in centre of wall of floor
5. Internal radius for bending shall be more than 6 times of pipe diameter. Due to structure issue, futher bending
will allow if conduit is below 20 mm.
6. Conduit bend shall not be arranged more than 3 points in between boxes.
7. Install pull box when the pass exceed 30m or due to site installation.
8. Metal conduit shall be tighten with re-bar by steel wire to avoid moving by concrete pouring fixing distance is
max 1m. But the fixing shall be arrange with parallel re-bar and cross re-bar at the elbow,
wire fixing shall be every 300mm.
Fixing Wire
Flexible Conduit
Top re-bar
Bottom re-bar
max 300 max 1.000
Notes:
1.PARALLEL ARRANGEMENT OF WIRES:
Take care not to include electromagnetic unbalance inside the conduit pipe when wires are provided in parallel
in an AC circuit.
2.BEND OF PIPE:
When pipe is bent, pipe section should have no serious deformation and the bending
radius should exceed 6 times of the pipe internal diameter.
3.EARTHING RESISTANCE OF PIPE:
Electric resistance between the fartherst end of metal conduit and earthing wire directly connected to earthing
plate should not be more than 2 ohm.
4.ISOLATION DISTANCE FROM GAS PIPE, ETC.:
Do not encounter low tension wiring directly with weak current wiring, metal water pipe, air conditioning duct,gas
pipe,etc.
5.CONNECTION OF PANEL AND CONDUIT PIPE:
When panel casing does not has any components in it, conduit pipes should be connected to the panel. (This
prevents attachement of cut dust, etc.)
a) Cable Rack
b) Selection Hanger Rods for tray
c) Selection Hanger Rods for cable Ladder
Installation Manual
Electrical Materials - Cable Rack
Electrical
■ Cable Rack
Cable rack structure and materials shall be as follow
1)The type of cable rack
2)Cable rack will be used straight type, L shape, T shape and cross shape type
3)Bolt/Nut for connection of cable rack will be followed
Type Bolt / Nut
Steel cable rack Galvanized type
Galvanized steel cable rack Stainless or galvanized type
Aluminium cable rack Stainless or cromed galvanized
4)1 piece of cable rack length is based on manufacture's standard
The interval of support bar of ladder type cable rack is as follow
Steel made - Max 300mm
the interval of support bar for others shall be at reasonable arrangement
5)Cable ladder shall be fastened firmly to the building members at intervals not exceeding 2.0 meters.
Tray Size Weight Support Interval Weitht of each support Hanger Rod Size
mm kg/m m kg mm
100x50 3.2 2.5 8 10
100x100 4.2 2.5 11 10
200x50 5.6 2.5 14 10
200x100 7.9 2.5 20 10
300x50 7 2.5 18 10
200x200 11 2.5 28 10
300x200 12.6 2.5 32 10
300x300 14.4 2.5 36 10
1. Cable Ladder
Cables ladders size up to 1000W should be supported by hanger bolts of M10 at max support intervals of 2 m (Table)
Cable Ladder
WxHmm kg/m m kg mm
200 x 50 7.9 2 15.8 10
300 x50 12.4 2 24.8 10
400 x 50 16.4 2 33.8 10
500 x 50 21.4 2 42.8 10
200 x 100 17.2 2 34.1 10
300 x100 24.4 2 48.8 10
400 x100 49.7 2 99.4 10
500 x 100 61 2 122 10
600 x 100 71.2 2 142.4 10
800 x100 106.4 2 212.8 10
1000 x 100 129.1 2 258.2 10
Notes
1. Anchor bolt
For bolts of 10mm OD or lager anchor bolts which are in principle driven in to building structure when concretes is
placed should be used inn case inserts can not be used because of design issue etc. Obtain approval of a person in
charge of the system.
3. Color of Inserts
Inserts should be color - classified in accordance with each trade
Remark :
Cable Ladder For Trench At Electrical Room Only
1. Electrical Installation Manual
4. Earthing Installation
Installation Manual
Earthing Installation
Electrical
1. Electrical Installation Manual
Notes:
1.Terminal box for testing
The box should be of rigid PVC or non-magnetic materials (brass,Aluminium) with terminals indicating
the services such as lightning protection test-link.
3.Connection terminals
Down conductor and ground wire should be connected to connection terminal.
Notes:
2.Connection terminals
One end of ground wire to be welded to rebar, the other end shall be clamp to earth rod.
Installation Manual
Connecting detail of earth rod, conductor
Electrical work
Hostel A at Axis HA/6 / HA/7 and Hostel B at Aixs HB/1 - HB/2 / HB/9 - HB/10
NOTES:
1.WATER SLOPE
Provide slope to penetrating copper tape so that water can flow outdoor(minimum 1/10)
2.PENETRATION LOCATION
Penetration should be above the water-proof membrance. Do not penetrate the water-proof
membrane.
1. Electrical Installation Manual
Administration Building
a-1) Switch installation detail – Administration Building
a-2) Switch installation detail – Administration Building
a-3) Switch installation detail – Administration Building
a-4) Switch installation detail – Administration Building
a-5) Switch installation detail – Administration Building
=>Detail Dimension Checked by Shop Drawing.
Teaching Building
a-6) Switch installation detail – Teaching Building
a-7) Switch installation detail – Teaching Building
a-8) Switch installation detail – Teaching Building
a-9) Switch installation detail – Teaching Building
a-10) Switch installation detail – Teaching Building
a-11) Switch installation detail – Teaching Building
a-12) Switch installation detail – Teaching Building
a-13) Switch installation detail – Teaching Building
a-14) Switch installation detail – Teaching Building
=>Detail Dimension Checked by Shop Drawing.
Hostel-A Building
a-15) Switch installation detail – Hostel A Building
a-16) Switch installation detail – Hostel A Building
a-17) Switch installation detail – Hostel A Building
a-18) Switch installation detail – Hostel A Building
=>Detail Dimension Checked by Shop Drawing.
Hostel-B Building
a-19) Switch installation detail – Hostel B Building
a-20) Switch installation detail – Hostel B Building
a-21) Switch installation detail – Hostel B Building
a-22) Switch installation detail – Hostel B Building
a-23) Switch installation detail – Hostel B Building
=>Detail Dimension Checked by Shop Drawing.
Dining Hall
a-24) Switch installation detail – Dining Hall
a-25) Switch installation detail – Dining Hall
a-26) Switch installation detail – Dining Hall
a-27) Switch installation detail – Dining Hall
a-28) Switch installation detail – Dining Hall
a-29) Switch installation detail – Dining Hall
a-30) Switch installation detail – Dining Hall
a-31) Switch installation detail – Dining Hall
a-32) Switch installation detail – Dining Hall
Administration Building
a-33) Socket, telephone & data outlet installation detail
=>Detail Dimension Checked by Shop Drawing.
Teaching Building
a-34) Socket, telephone & data outlet installation detail
=>Detail Dimension Checked by Shop Drawing.
Hostel A and Hostel B Building
a-35) Socket, telephone & data outlet installation detail –
=>Detail Dimension Checked by Shop Drawing.
Dining Hall
a-36) Socket outlet & switch installation detail
b) Lighting Fixture
b-1) Lighting fixture installation detail 1
b-2) Lighting fixture installation detail 2
b-3) Lighting fixture installation detail 3
b-4) Lighting fixture installation detail 4
b-5) Lighting fixture installation detail 5
b-6) Lighting fixture installation detail 6
b-7) Lighting fixture installation detail 7
b-8) Lighting fixture installation detail (high bay lamp & wall
lamp)
=>Detail Dimension Checked by Shop Drawing.
c) Speaker
c-1) Speaker installation detail 1
c-2) Speaker installation detail 2
=>Detail Dimension Checked by Shop Drawing.
e) MATV Fixture
e-1) MATV fixture installation
=>Detail Dimension Checked by Shop Drawing
Installation Manual
Socket Outlet & Switch Connection Detail
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual Socket, Telephone , Data & MATV Outlet Installation Detail - Administration
Electrical Building
Installation Manual
Socket, Telephone , Data & MATV Outlet Installation Detail - Teaching Building
Electrical
Installation Manual Socket, Telephone , Data & MATV Outlet Installation Detail - Hostel - A and
Electrical Hostel-B Building
Installation Manual
Socket Outlet Installation Detail - Dining Hall
Electrical
Installation Manual
Lighting Fixture Installation Detail 1
Electrical
Installation Manual
Lighting Fixture Installation Detail 2
Electrical
Installation Manual
Lighting Fixture Installation Detail 3
Electrical
Installation Manual
Lighting Fixture Installation Detail 4
Electrical
Installation Manual
Lighting Fixture Installation Detail 5
Electrical
Installation Manual
Lighting Fixture Installation Detail 6
Electrical
Installation Manual
Lighting Fixture Installation Detail 7
Electrical
Installation Manual
Lighting Fixture Installation Detail ( High Bay Lamp & Wall Lamp )
Electrical
Installation Manual
Speaker Installation Detail -1
Electrical
Installation Manual
Speaker Installation Detail 2
Electrical
Installation Manual
Installation Detail for Fire Alarm Bell and Manual Call Point
Electrical
Installation Manual
Installation Detail for Smoke Detector
Electrical
Installation Manual
MATV Fixture Installation
Electrical
SAFE WORK PROCEDUER
ELECTRICAL INSTALLATION
1. Preparation Work
3.Piping work
4.Clean up work
SAFE WORK PROCEDUER
1. Preparation Work
• Workplace check
1. Preparation
Work
Procedure Main Points
Type
1. To check worker attentdance and health conditoin.
1. Meeting before 2. To check worker's PPE and clothing (Safety helmat, clothing,
work starts Safety shoe, ect)
3. To explain workplace condition and environment.
4. To explain work distribution, work contents, method and
procedure and safety precations.
5. Appoint per in charge in each group.
6. To explain electrocution and fire hazards.
7. To provide guidance on correct method in use of electrical
tools.
8. To explain ' No Entry' area.
Preparation
2.Confirmation of When the work requires qualified personnel, to check and confirm in
qualified personnal advance if the proper qualification / Certification.
Work
Procedure Main Points
Type
1. After doing own inspection of electrical tools/ equipment, to
Submit appliction for inspection of electrical equipment by
3. Inspection SNK Electrical Inspector.
electrical tools and Obtain application from and fill in items required. They
equipment include the fllowings.
S/No.
Type of Equipment?Tools
Equipment Serial Number
Supply Voltage
Type of casing
Preparation
1. WORK FLOOR
1. Use of Mobile scaffolding (Rolling Tower)
2. Foot - mounted scaffolding ( if necessary)
2. CUTTING
2.1 Electric cutter
2.2 Gas cutting (if necessary)
(1) Protection tool
(2) Protection
(3) Ignition
(4) Gas cutting
2.3 Groove preparation
3. Welding on the floor
3.1 Protection tool
3.2 Protection
3.3 Welding
(1) Tack welding
(2) Main welding
2. CUTTING & WELDING WORK
Work
Main Points
Type Procedure
Work floor
Example:
H ≤ 7.7L -5
H: the height from bottom of wheel to floor
L : distance between main axis of foot wheel
Handrall height: 90cm & above
Work
Procedure Main Points
Type
2. Foot 1. The scaffold must be assembled according to approved
mounted procedure.
scaffolding 2. use rop / hoisting bag for hoisting/ lowering tool.
3. Put the rope arund your waist when going up/ down.
4. Park the scaffold near the work area.
5. Around opening, use insert and safety - belt must be
hooked.
6. Do not exceed SWL (Safe work load).
5. Aim blow pipe fire tip to the front, away from the body.
6. Release remaining gas from the hose, and switch off valve.
7. Open oxygen vavle slightly.
8. Open acetyllene valve much more than oxygen valve.
9. Use igniton gun.
10. Adjust to standard flame.
(4) Gas cutting 1.Preheat cutting area properly, and use oxygen to cut.
2. After cutting, close blow pipe valve immediately.
3. After cutting, remove cutting waste to prevent burn.
4. When sander is used to remove waste, secure the pipe.
5. Use goggel, mask and vibration - proof hand glove when
sander is used
Overlap Crack
Main Welding
3. PIPING WORK
1. WORK FLOOR
1. Use of Mobile scaffolding (Rolling Tower)
2. Foot - mounted scaffolding ( if necessary)
3. Single use of ladder
(1) Inspection
(2) Setting
(3) Work
(4) Tightening of threaded pipe
(5) Fitting of hanger band
3. PIPING WORK
Work
Procedure Main Points
Type
Work Floor
Example:
H ≤ 7.7L -5
H: the height from bottom of wheel to floor
L : distance between main axis of foot wheel
Handrall height: 90cm & above
Work
Procedure Main Points
Type
2. Foot 1. The scaffold must be assembled according to approved
mounted procedure.
scaffolding 2. use rop / hoisting bag for hoisting/ lowering tool.
3. Put the rope arund your waist when going up/ down.
4. Park the scaffold near the work area.
5. Around opening, use insert and safety - belt must be
hooked.
6. Do not exceed SWL (Safe work load).
3. Single -use of
ladder
(1) Inspection 1. Deformation and rusting of foot.
2. Deformation and damage of opening extender.
3. Deformation and damage of top plate and step
4. Damage of foot stopper.
Work
Procedure Main Points
Type
(2) Setting 1. Remove any obstruction on the floor.
2. The top plate should be level.
3. The opening extender should be fully opened.
4. Position it close to work area.
5. When the foundation is weak, not even, use protectionto make it
level.
6. Step on the first step, apply weight to test if it shakes.
7. Do not set it on the floor where there is work going on.
(3) Work 1. Use rope/ hoisting bag for hoisting / lowering tool.
2. Use rope around your waist when going up/ down.
3. Do not carry other person when working.
4. Do not use the top plate for working.
Single - use ladder
4. CLEAN UP WORK
1. Dismantling of scaffold
7. Checking
4. Clean up Work
Work
Main Points
Type Procedure
1. Dismantling of 1. Refer to Mobile scaffold dismantling ' and' Erection of
scaffold foot - mounted scaffold erection procedure 'section'.
at Opening. location.
6. Remove 1. Remove rope, danger sign, etc, and keep them at designated
" NO" Entry lacation.
Sign
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 1 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
5) Check the alarm & trip sensing cable are properly terminated.
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 2 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
4) Check flexible duct is provided between radiator & rigid duct and properly
tightened. Ensure no leak.
5) Check flexible joints is provided between exhaust & silencer and properly
tightened. Ensure no leak.
7) Check generator exhaust pipe is properly installed with the flippable end
cap and painted with heat resistant paint.
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 REV : O
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
10) Check doors hinges are bonded to frame with protective conductor.
14) Cable entry point into Panel is prevented from damage to cables
(sharp edges) & properly sealed from dust entry.
REMARK / NON-CONFORMANCE
8) Check all floor and fire wall penetration are sealed with approved
fire rated material
9) Check bending radius of cable not less than 6 times cable diameter.
10) Cable inside panel properly seperated & secured using cable tie.
12) Check feeder cable entry to all equipment are neat & not damaging.
REMARK / NON-CONFORMANCE
8) Check Cable layer and Warning Sign Tape before backfilling work
9) Check bending radius of cable not less than 6 times cable diameter.
10) Cable inside panel properly seperated & secured using cable tie.
12) Check feeder cable entry to all equipment are neat & not damaging.
REMARK / NON-CONFORMANCE
5) Check conduit joint boxes & outlet are properly tightened.If UPVC
conduit system,adhesive shall be applied.
7) For cast in PVC conduit,ensure all conduit are tied to rebar,boxes are
fully stuffed and check for conduit damage
8) Ensure conduits are installed between 1st & 2nd layer of slab rebar,
only bend down to formwork at junction box location.
REMARK / NON-CONFORMANCE
5) Check conduit joint boxes & outlet are properly tightened.If UPVC
conduit system,adhesive shall be applied.
7) Check ensure for exposed PVC or EMT conduit Pipe are properly
installed with Saddle
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 9 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
5) Check conduit joint boxes & outlet are properly tightened.If UPVC
conduit system,adhesive shall be applied.
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 10 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
6) Check all recessed light fittings on ceilings are provided with proper
hanging method & securely mounted for others.
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 11 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
5) Check main earth bar is installed with hard cover transparent plastic
sheet to prevent direct access.
7) Warning notice & tag are provided at all terminal bar and electrode.
8) Ensure that all earth resistance test are conduct and recorded < 5Ω.
10) Warning notice & tag are provided at all terminal bar & in chamber
REMARK / NON-CONFORMANCE
5) Check main earth bar is installed with hard cover transparent plastic
sheet to prevent direct access.
7) Warning notice & tag are provided at all terminal bar and electrode.
8) Ensure that all earth resistance test are conduct and recorded < 5Ω.
10) Warning notice & tag are provided at all terminal bar & in chamber
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 13 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
3) Check P.A.rack & equipment are in correct position & oreintation as per
approved drawings.
5) Check cabling size & type of cable installed as per approved drawings
6) Check for porper labelling for the cabling works at the P.A equipment.
8) Check for wall mounted speaker height are as per approved drawings.
9) Ensure continuity & insulation test are conducted before function test.
10) Check for interference noise from external sources during function test.
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 14 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
2) Check physical condition height, orientation of Push Button and Sounder and
Indication Lamp.
4) Check location and total zoning of Fire Alarm Panel according to approved
drawing.
5) Ensure continuity & insulation test are conducted before function test.
6) Check whether Centre Monitoring System (CMS) are install and tested.
REMARK / NON-CONFORMANCE
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 15 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
5) Check cabling size & type of cable installed as per approved drawings
6) Check for proper labelling for the cabling works & MATV equipment in risers.
8) Ensure continuity & insulation test are conducted before function test.
9) Check for interference noise from external sources during function test.
REMARK / NON-CONFORMANCE
5) Check cabling size & type of cable installed as per approved drawings
6) Check for proper labelling for the cabling works & TEL,DATA equipments
8) Ensure continuity & insulation test are conducted before function test.
9) Check for interference noise from external sources during function test.
REMARK / NON-CONFORMANCE
Result
Type of Test YES NO RESULT
REMARK/NON-CONFORMANCE
Result
Type of Test YES NO RESULT
REMARK/NON-CONFORMANCE
Result
Type of Test YES NO RESULT
Battery Test.
Charging Check
REMARK/NON-CONFORMANCE
Exhaust Fan installed : YES / NO Thermostat Function YES / NO Capacitor Bank Manufacturer :
** Note : Please indicate in Remark column if ACB is used as a coupler No. of Steps :
Breaker Outgoing Feeder ACB MCCB RCCB Indicator Light Result Capacitor Function Test Manual Remarks
Fuction Test
No Name Rating Setting Rating Setting Rating Setting R Y B OK / NO Step OK NO
(Yes / No / NA)
Step No. 1
Step No. 2
Step No. 3
Step No. 4
Step No. 5
Step No. 6
Step No. 7
Step No. 8
Step No. 9
Step No. 10
Step No. 11
Step No. 12
Circuit Load / Circuit MCB / MCCB RCCB Indicator Light Result Remarks
Fuction Test Fuction Test
No Name Rating Rating Setting R Y B (OK / NO)
(Yes / No / NA) (Yes / No / NA)
ISSUED DATE:20/05/2015
DOC NO.: ETC-06 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
TEST RESULT :-
3). Teat Result is acceptable or not. YES / NO (Delete where not applicatble)
REMARK/NON-CONFORMANCE
Testing Instrument : Maker / Model / Serial : Calibration Expiry date : Voltage Rating: Volts.
Note : Insulation resistance of cables should be more than 1 Mega Ohm
Insulation Resistance ( M ohm ) between line
Continuity Test . (YES or NO).
Circuit No x Core / Size Cable Route Phase to Phase Phase to Neutral Phase to Earth Remarks
No. Type of cable To Equipment, R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E N-E R Y B N E
(MYANMAR BRANCH)
ISSUED DATE:20/05/2015
DOC NO.: ETC-08 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
INSPECTION DATE:
PANEL/FEEDER NAME:
TYPE OF SERVICES:
SUPPLY FROM:
CABLE SIZE/TYPE:
LOCATION:
VOLTAGE TEST.
Testing Instrument : Mnfg / Model No :………………………………………………… Voltage Rating : …………….Volts.
YES NO YES NO
RYB
REMARK/NON-CONFORMANCE
ISSUED DATE:20/05/2015
DOC NO.: ETC-09 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
REMARK/NON-CONFORMANCE
ISSUED DATE:20/05/2015
DOC NO.: ETC-10 REV:0
E
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
REMARK/NON-CONFORMANCE
TEST/INSPECTION DATE :
LOCATION : DRAWING REFERENCE :
REMARK/NON-CONFORMANCE
ISSUED DATE:20/05/2015
DOC NO: ETC-12 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
REMARKS / NON-CONFORMANCE-
ISSUSED DATE:20/05/2015
DOC NPO:ETC-13-1 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
C STATUS MONITORING
C-1) Sprinkler / Hydrant / Hose Reel / Wet Riser (Delete Whichever Not Applicable)
PUMP SETS AC FAIL PUMP RUN PUMP TRIP
i) Jockey N/A N/A N/A
ii) Duty N/A N/A N/A
iii) Standby N/A N/A N/A
iv) Butterfly Valve Closed N/A
v) Gas Discharge (24V Signal) N/A
vi) Fire Tank Low Water Level N/A
vii) Genset Run And Trip N/A
C AFTER TESTING
C-1) System Reset To Normal
REMARKS / NON-CONFORMANCE
ISSUSED DATE:20/05/2015
DOC NO:ETC-13-2 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
LOCATION ; REFERNCE NO :
AVERAGE
THE SYSTEM HAS BEEN TESTED AND THE TOTOL EARTH RESISTANCE IS ………………………………………… OHMS
THERE WERE TOTAL ……………………………….. POINTS TESTED.
REMARKS / NON-CONFORMANCE
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)
ISSUSED DATE:20/05/2015
DOC NO:ETC-14 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE
REMARKS :
ISSUSED DATE:20/05/2015
DOC NO: ETC-15 REV:0