You are on page 1of 142

The Project for Improvement of Education College

in The Republic of the Union of Myanmar

Electrical Installation Manual

22-Jan-2016

Client : ベト ナム国 


Ministry フエ中央病院
of Education, The Republic of the
Union of Myanmar

Consultant : ベト
Theナム国  フエ中央病院
Consortium of Yamashita Sekkei Inc.
and Binko International Ltd.

Contractor : ベトナム国 
Kumagai フエ中央病院
Gumi Co.,Ltd

Yamashita Sekkei Kumagai Gumi


Contents(目次)

1. Electrical Installation Manual


1. Sleeve Installation
2. Electrical Piping Installation
3. Cable Tray, Rack, Trunking Installation
4. Earthing Installation
5. Lightning Protection Works
6. Electrical Equipment Installation

2. Safety Work Procedure for Electrical Work

3. Check List for Electrical Work

4. Test and Commissioning for Electrical Work


1. Electrical Installation Manual

1. Sleeve Installation

a) Sleeve installation 1
b) Sleeve installation 2
c) Sleeve installation 3
Installation Manual
Sleeve installation - 1
Sleeve

1 RC Beam Sleeve
a1

Beam Height
1 2

b a2

Selection of "d"
500 ≦ D < 700 : 175 ≧ d a1, a2 ≧ min (1.2D , 1000mm)
700 ≦ D < 900 : 200 ≧ d 
900 ≦ D b≧ 3X
: 250 ≧ d 2

* If sleeve need to install out of above area, discuss with structure engineer for permission before installation

2 PVC Beam Sleeve Size

Size of PVC Sleeve System

150  Sewer, Waste Pipe 100 

100  Sewer, Waste Pipe, Vent pipe 80 

80  Sewer, Waste Pipe, Vent pipe 65 0 

80  AC Drain 25 with insulation

50  Water Supply 32

50  Electrical Conduit 25


Installation Manual
Sleeve installation 2
Sleeve

Installation of sleeve in beam

F.L
Mark the sleeve location,

500
size etc by permanent
PVC Pipe
marker
Beam width -5mm

Example (Size/ Level)


D250/FL-500

Close by plastic tape


Re-Bar
Fix on Re-bar PVC
by GI wire sleeve

* Request for reinforcement around sleeve to main contractor

Support
Bar

The points of installation of sleeve

Preparation Material supply by MEP work

Lean concrete

Marking Mark the sleeve location, size etc on lean concrete (by MEP work)

Re-bar Stirrup re-bar should avoid to install at sleeve location (Civil work)

Sleeve installation Re-check the sleeve location (horizontal, vertical). Fix support bar on
stirrup re-bar, and install sleeve on support bar with tighten GI wire and protect both ends
by plastic tape to prevent cement mortar seepage into the sleeve. (MEP work )
Reinforcement
Form work
Concreting

Sleeve cleaning Don’t remove sleeve. Clean and protect sleeve.

: Shall be done by MEP work


Installation Manual
Sleeve installation - 3
Sleeve
■ Water Tank Sleeve

1 Installation of actual size of pipe as sleeve for (1) By pass pipiing between T1 and T2 of under ground water tank
(2) Water outlet pipe and drain pipe of elevated water tank

Water proof detail shall be confirmed


G1 Actual pipe with consultant
with paddle flange
Asphalt / Water proof (by structure)

Flange

(Under Water Level)


Actual Pipe
75
Fix Support

Water Tank

■ Underground Outdoor Wall Sleeve

Silicone
Sealant
Backup materials
Backup materials
PVC pipe sleeve Slope to outside
Fix support
Silicone Sealant

(Pipe)
A ≒ 30
Soil or Sand

Soil or Sand Detail - A

Silicone Sealant Silicone Sealant


(approximately 10mm depth)

PVC Pipe Sleeve

Outside Inside Building

Remarks
1) Install PVC pipe with slope to outside.
2) Sealant for gap filling shall be used Silicone type

■ External Wall Sleeve


1. Electrical Installation Manual

2. Electrical Piping Installation

a) Electrical materials – cables


b) Electrical materials – conduit
c) Electrical materials – plastic flexible conduit
d) Electrical materials – pull box
e) Selection hanger rods for metal trunking
f) Selection hanger rods for conduit and cable ladder
g) Conduit support
h) Conduit installation 1
i) Conduit installation 2
j) Conduit installation 3
k) Flexible conduit 1
l) Flexible conduit 2
m) Detail of exposed piping (indoor)
Installation Manual
Electrical Materials -Cables
Electrical

■ Cables
The standard of copper cables are as follow

System Type of cable Standard

1 LV INCOMING XLPE/SWA/PVC CABLE BS 5467


XLPE/SWA/PVC CABLE BS 5467
2 MAIN FEEDER SYSTEM
XLPE/PVC CABLE BS 5467
XLPE/PVC CABLE TIS 11 Part 3-2553,Table 1
3 POWER DISTRIBUTION
PVC/PVC CABLE BS 5467
60227 IEC 02 THW (f) TIS 11 Part 3-2553,Table 3
4 LIGHTING SYSTEM
NYY TIS 11 Part 101--2553,Table 3
60227 IEC 02 THW (f) TIS 11 Part 3-2553,Table 3
5 RECEPTACLE SYSTEM
NYY TIS 11 Part 101--2553,Table 3

6 EARTHING SYSTEM 60227 IEC 02 THW (f) TIS 11 Part 3-2553,Table 3

7 FIRE ALARM SYSTEM FR PVC IEC 60332-1-2

XLPE/PVC CABLE BS 5467


OUTDOOR LV INCOMING SYSTEM
8
XLPE/SWA/PVC CABLE BS 5467

REMARK.

Standard Mentioned BS5467 XLPE/SWA/PVC CABLE FROM SRI LANKA (ACL)

TIS XLPE/PVC ,PVC/PVC, PVC CABLE, WIRE FROM THAILAND ( YAZAKI)

IEC FR PVC FIRE RESISTANT CABLE FROM SINGAPORE

Color Code
Three Phase - L1 (Brown), L2 (Black), L3 (Grey), Neutral (Blue), Earth (Green/Yellow)
Single Phase - Line (Brown), Neutral (Blue), Eatrh (Green/Yellow)
Installation Manual
Electrical Materials - Conduit
Electrical

■ Compression Terminal
Compression Terminal is as follow
Standard
Name Remarks
Standard No Standard Name
Compression Terminal for copper
Compression Terminal BS 4579
cable

■ Conduit
1. Conduit
Conduit is as follows

Name Standard Use location Remarks


GI Conduit BS31-1940 and BS Expose(without false ceiling Plain end, Screw end
4568- 1970 and on wall),Fire alarm
Indoor use (false ceiling)/
PVC conduit Plain end
IEC 6138 6-2-1:2002 Embedded use

1) for indoor use, use thin conduit or non screw type metal conduit
2)For outdoor use,use thick conduit or non-screw typr metal conduit
2.Accessories of conduit
Accessories of metal conduit is as follow

Standard
Purpose Remarks
No Name
For metal conduit Normal bend Thick, Thin and non-screw conduit
Coupling
Union coupling Thick conduit
BS 4568
Connector Thin, Non-screw conduit
BS EN ISO 1461
Bushing Thick, Thin conduit
Universal Thick, Thin and non-screw conduit

For embedded Switch box For pre cast concrete


BS 4568
Outlet box Round & Square type
BS EN ISO 1461
Concrete box Round & Square type
For exposed BS 4568 Switch box
BS EN ISO 1461 Round box
Installation Manual
Electrical Materials - Plastic Flexible Conduit
Electrical

■ PVC Flexible conduit and accessories


1.PVCFlexible Conduit
PVC flexible conduit is as follow

Type of flexible Pipe layer Type of tube Standard


conduit
Liquidtight Flexible
Single layer corrugated Plain BS 4607 or Equivalent
non-metallic conduit

2. Accessories of PVC flexible conduit

Type Conduit type


Coupling Non-metallic PVC
Connector Non-metallic PVC
Combination Coupling Non-metallic PVC

CATALOGUE OF PVC CONDUIT

■ PVC CONDUIT ( Rigid Conduit) MADE IN MALAYSIA ■ PVC FLEXIBLE CONDUIT ( Corrugated Conduit) MADE IN MALAYSIA

* FIRE RETARDENT (FR)


Installation Manual
Electrical Materials - Pull Box
Electrical
■ Pull Box ( Metal )
Pull Box is as follows:
1. Material, Structure
1)Pull box shall be fabricated by metal and shall not be less than 1.6mm thickness.
2)Steel pull box (except galvanized or stainless steel made) shall be applied anti-corrosion paint.
3)Pull box for outdoor installation shall be used galvanized or stainless made pull box
1)Pull box shall be water-proofing type with water drain hole at bottom
2)Install water resist type gasket between pull box and cover
3)Fixing screw of cover and fixing bolt/nut for pull box cover should not be penetrate into pull box inside
4)Screw for pull box cover shall be made of stainless steel.
2.Manufacturing
1)Pull box shall be manufacture with considering of installation, cable connection, cable laying.
2)Pull box shall be smooth
3)Pull box shall be no twisting, bending or more.
4)Joint of pull box shall be welded
To apply silicone
around the screw

Fixing screw
Cover Stainless steel
A、B:Max 350mm
B

Top Cover
B

Gasket
Fixing screw Gasket Cover
Stainless made
B

B) In case longitude
A A A A) In case longitude
length within 200mm
length exceed 200mm
Structure for outdoor pull box
Top cover type
Fixing screw
Stainless steel
■ PVC Pull Box ( USE WATER PROOF TYPE )

215X150X110
SIZE 215X215X 80
250X200X160
310X230X145
Installation Manual
Selection Hanger Rods For Metal Trunking
Electrical Work

■ Hanger Rod for metal duct

Trunking Size Weight Support Interval Weitht of each support Hanger Rod Size

mm kg/m m kg mm
100x50 3.2 2.5 8 10
100x100 4.2 2.5 11 10
200x50 5.6 2.5 14 10
200X100 7.9 2.5 20 10
300x50 7 2.5 18 10
200x200 11 2.5 28 10
300x200 12.6 2.5 32 10
300x300 14.4 2.5 36 10

Condition of weight calculation


1. Effective sectional area of duct should be 20%

2. Weight should be the total weight of duct and cables

3. Steel sheet thickness should be 1.2mm


Installation Manual
Selection Hanger Rods For Conduit And Cable Ladder
Electrical Work

1.Conduit

Single suspension should be provided by hanger bolts of M10 at supporting intervals of 2 meters. Common suspension
or common wall supporting should be in accordance with Table-1 from which weight load is calculated and hanger
bolts are selected

2. Cable Ladder

Cables ladders size up to 1000W should be supported by hanger bolts of M10 at max support intervals of 2 m(Table-2)

Table-1 Table-2
Thin Conduit Thick Conduit Cable Ladder
EMT IMC
Size Weight Size Weight Size Weight Interval Load weight Rod Size

mm kg/m mm kg/m WxHmm kg/m m kg mm


20 0.9 16 1.2 200 x 50 7.9 2 15.8 10
25 1.3 22 1.7 300 x50 12.4 2 24.8 10
32 1.9 28 2.6 400 x 50 16.4 2 33.8 10
40 2.8 36 3.8 500 x 50 21.4 2 42.8 10
50 4.5 42 4.8 200 x 100 17.2 2 34.1 10
63 7.0 54 7.4 300 x100 24.4 2 48.8 10
75 9.8 70 9.8 400 x100 49.7 2 99.4 10
82 14.0 500 x 100 61 2 122 10
92 18.3 600 x 100 71.2 2 142.4 10
102 22.6 800 x100 106.4 2 212.8 10
1000 x 100 129.1 2 258.2 10
1. Effecttive sectional area of conduit pipe 1. Weight = Ladder + Cables
is calculated at 40% Remark
2. Weight = Conduit + Cables For Trench at Electrical Room

Notes
1. Anchor bolt
For bolts of 10mm OD or larger anchor bolts which are in principle driven in to building structure when concretes is
placed should be used in case inserts can not be used because of design issue etc. Obtain approval of a person in
charge of the system.

2. Weight at supporting point


Discuss with structure designer in case the weight imposed at the supporting point exceed 150kg

3. Color of Inserts
Inserts should be color coded- classified in accordance with each trade
Installation Manual
Conduit Support
Electrical

3) Maximum interval of support is3.6 m for 25 mm Dia metal conduit with saddle crip

4)When the conduit install on ceiling or wall surface, use hanger or saddle fitting to fix it on with max 2m interval.
However, additional support shall be installed at near the connection point and pipe end

Saddle Conduit

Max 3,600
As near as

Remark - Electrical Room Sample of saddle fixing

Pump Room
and Fire Alarm Piping

2. Support for vertical pipe


The max support interval shall be 3.6 m. However, additional support shall be installed at near the connection point
with pull box and conduit

Cable support interval in vertical pass

Cable size (mm2) Interval (m)


  below 35   max 30
  below 95   max 25
max3600

  below 95   max 20
  below 240   max 15
  over 240   max 12
Max 3600

max 300

Channel
max 300

DB or
PVC WP Pull Box

DB or PVC WP Pull Box


max 300

max 300

Support for vertical installation


Installation Manual
Conduit Installation -1
Electrical

■Conduit Installation
1.Conduit fabrication
1) Cut the pipe vertically to the pipe centre
a)Debar the cut end of conduit and file it.
2) In case of bending of conduit, consider to take enough radius. If necessary,
install pull box in the middle of conduit pass.
a) internal radius for bending shall be more than 6 times of pipe diameter. Due to structure issue,
further bending will allow if conduit side is below 25mm.

b) Conduit bend shall not be arranged more than 3 points in between boxes.

c) Install pull box when the pass exceed 30m or due to site installation

max 30m max 30m

a) Pipe bend b) Installation of pull box

Min 6xD
2. Connection of conduit
1)When connecting conduit, use coupling or non-screw coupling

a) When using non-screw coupling, conduit shall be inserted to the non-screw


coupling properly and tight screw well.
2)Concrete box, outlet box, pull box and joint box shall be used

List of concealed pipe and box installation

Location Conduit Type of box


Below E25x3 pipes Medium square concrete box 54
Ceiling in Slab or octagon concrete box 75
Below E25x4 pipes Large square concrete box 54
Below E32x2 pipes or Octagon concrete box 75
Below E25x1 pipe Single switch box or
Column/wall

Medium square outlet box 44


Except Below E25x3 pipes Double switch box or
Ceiling, Slab Medium square outlet box 44
and floor Below E32x2 pipes Large square outlet box 54
Below E25x3 pipes Medium square outlet box 54
Others

Below E25x4 pipes Large square outlet box 44


Below E32x2 pipes

3) The connection between conduit and box or metal duct shall be fixed perfectly with pipe screw,
connector,bushing etc.
Installation Manual
Conduit Installation - 2
Electrical

■Embedded Conduit-1
When the conduit required to be embedded in concrete floor or etc., consider the structure strength.

1. For embedded conduit in slab, max outside diameter shall be 1/4 of slab thickness (Max 32mmDia)

2. Concrete top up on conduit shall be more than 30mm

3. Cut the pipe vertically to the pipe centre. Remover bur on pipe by leamer, but extra careful to don’t damage coating

4. If many conduit need to embedded in concrete, consider the structure stlength to maintain and
each conduit shall be keep 30mm distance for enough concrete to pour

5. In case of double re-bar, the conduit shall be laid between top and bottom re-bar.
In case of single re-bar, the conduit shall be laid in centre of wall or floor

6. Conduit location shall be decided with co-ordinating with duct opening and opening reinforcement re-bar

7. In principal, beam penetration is prohibited,unless approval is obtained.

8. Metal conduit shall be tighten with re-bar by steel wire to avoid moving by concrete pouring
Fixing distance is max 2m. But the fixing shall be arrange with parallel re-bar and cross re-bar

9. In principal, the crossing of conduit is up to E32 and E25.

10. Outlet box and conduit shall be fixed well to avoid that box to move up.

11. Conduit which connecting box shall be fixed with re-bar at 300mm from the box

Steel Re-Bar

Fixing Wire
max 300 max 300

a) Fixing with conduit and re-bar

max 300 max 300 max 2.000


Top Re-Bar
Fixing Wire
Conduit
Bottom Re-Bar

Conduit End cover Re-bar support


KO box
Form work

b) Fixing with conduit and re-bar


Installation Manual
Conduit Installation - 3
Electrical

■Embedded Conduit-2
12.Vertical conduit from concrete slab shall be kept 100 to 150mm from slab, and cover the conduit end with plastic
or end cap.
min 30

Steel Wire
End cap

Temp Support

Support fitting
100~150

Re-Bar

LIGHTING SYSTEM
b) Fixing by support fitting
a) Fixing by steel wire

Vertical pipe from concrete slab

13. Concrete box, outlet box etc shall be fixed strongly with proper protection

14. Conduit support for concrete without re-bar may use cramp with every 2m. Joint shall be coupling etc.

max 3600

max 300

Conduit support in concrete without re-bar

1) The interval (A,B,C) should keep 30mm or more


If 30mm distance cannot keep, discuss with structure
engineer. To Install wire mesh is one of the solution

A B C
Re-bar

Conduit 2) Max embedded conduit size is E32


Conduit laying interval
Installation Manual
Flexible Conduit - 1
Electrical

■ Flexible conduit and accessories


1.Size of CD pipe
1) The size selection for CD pipe is as follow
Size selection sheet for CD pipe

Size of cable Number of cable


Single core Multi core 1 2 3 4 5 6 7 8 9 10
(mm) (mm) CD pipe minimum size
1.5 - 20 20 25
2.5 6 20 25
32
4 8 25
- 16 32
2) When several size of cable to install in same conduit, total cable section area with safety ratio
shall be less than 32% of conduit section area.

CD Pipe safety ratio

Cable size
Safety ratio
Single core(mm )Multi core (mm2 )

1.5 2.5 1.3


2.5 4 1.3
over 2.5 over 6 1.0

3)If the conduit length is less than 6m, and not much bending in the pass, total cable section area
with safety ratio shall be less than 48% of conduit section area.
Installation Manual
Flexible Conduit - 2
Electrical

■Embedded Conduit
1.The points of installation
When the conduit required to embedded in concrete floor or etc., consider the structure strength

1. For embedded conduit in slab, max outside diameter shall be 1/4 of slab thickness (Max 32 mmDia)

2.Concrete top up on conduit shall be more than 30mm

3. If many conduit need to embedded in concrete, consider the structure length to maintain and
each conduit shall be keep 30mm distance for enough concrete to pour

4. In case of double re-bar, the conduit shall be laid between top and bottom re-bar.
In case of single re-bar, the conduit shall be laid in centre of wall of floor

5. Internal radius for bending shall be more than 6 times of pipe diameter. Due to structure issue, futher bending
will allow if conduit is below 20 mm.

6. Conduit bend shall not be arranged more than 3 points in between boxes.

7. Install pull box when the pass exceed 30m or due to site installation.

8. Metal conduit shall be tighten with re-bar by steel wire to avoid moving by concrete pouring fixing distance is
max 1m. But the fixing shall be arrange with parallel re-bar and cross re-bar at the elbow,
wire fixing shall be every 300mm.

The following is one sample for embedded pipe installation in concrete

Fixing Wire
Flexible Conduit
Top re-bar
Bottom re-bar
max 300 max 1.000

Pipe and re-bar installation method Re-bar support


KO box Form work

2. The points of concealed pipe installation


1) The flexible pipe support at false ceiling or concealed pipe in LGS shall use saddle, clip, hanger etc.
The support interval is max 1.5m for concealed pipe, max 1.0m for exposed pipe.
Installation Manual
Detail Of Exposed Piping (Indoor)
Electrical work

Notes:
1.PARALLEL ARRANGEMENT OF WIRES:
Take care not to include electromagnetic unbalance inside the conduit pipe when wires are provided in parallel
in an AC circuit.
2.BEND OF PIPE:
When pipe is bent, pipe section should have no serious deformation and the bending
radius should exceed 6 times of the pipe internal diameter.
3.EARTHING RESISTANCE OF PIPE:
Electric resistance between the fartherst end of metal conduit and earthing wire directly connected to earthing
plate should not be more than 2 ohm.
4.ISOLATION DISTANCE FROM GAS PIPE, ETC.:
Do not encounter low tension wiring directly with weak current wiring, metal water pipe, air conditioning duct,gas
pipe,etc.
5.CONNECTION OF PANEL AND CONDUIT PIPE:
When panel casing does not has any components in it, conduit pipes should be connected to the panel. (This
prevents attachement of cut dust, etc.)

Remark- For Electrical Room, Pump Room


1. Electrical Installation Manual

3. Cable Tray, Rack, Trunking Installation

a) Cable Rack
b) Selection Hanger Rods for tray
c) Selection Hanger Rods for cable Ladder
Installation Manual
Electrical Materials - Cable Rack
Electrical

■ Cable Rack
Cable rack structure and materials shall be as follow
1)The type of cable rack

Type Material standard

Ladder Steel made ( GI )

Perforated Tray Hot roll mild steel sheet

2)Cable rack will be used straight type, L shape, T shape and cross shape type
3)Bolt/Nut for connection of cable rack will be followed
Type Bolt / Nut
Steel cable rack Galvanized type
Galvanized steel cable rack Stainless or galvanized type
Aluminium cable rack Stainless or cromed galvanized
4)1 piece of cable rack length is based on manufacture's standard
The interval of support bar of ladder type cable rack is as follow
Steel made - Max 300mm
the interval of support bar for others shall be at reasonable arrangement

5)Cable ladder shall be fastened firmly to the building members at intervals not exceeding 2.0 meters.

6)Sample sketch of cable rack are as follows:

Cable rack size


Outside distance
Support bar Main Bar

A) Ladder type B) Tray type

The interval of support bar

The length of straight cable rack

Remark - GI : Galvanized Steel Iron


Installation Manual
Selection Hanger Rods For Tray
Electrical Work

■ Hanger Rod for tray

Tray Size Weight Support Interval Weitht of each support Hanger Rod Size

mm kg/m m kg mm
100x50 3.2 2.5 8 10
100x100 4.2 2.5 11 10
200x50 5.6 2.5 14 10
200x100 7.9 2.5 20 10
300x50 7 2.5 18 10
200x200 11 2.5 28 10
300x200 12.6 2.5 32 10
300x300 14.4 2.5 36 10

Condition of weight calculation


1. Effective sectional area of duct should be 20%

2. Weight should be the total weight of tray and cables

3. Steel sheet thickness should be 1.2mm


Installation Manual
Selection Hanger Rods For Cable Ladder
Electrical Work

1. Cable Ladder

Cables ladders size up to 1000W should be supported by hanger bolts of M10 at max support intervals of 2 m (Table)

Cable Ladder

Size Weight Interval Load weight Rod Size

WxHmm kg/m m kg mm
200 x 50 7.9 2 15.8 10
300 x50 12.4 2 24.8 10
400 x 50 16.4 2 33.8 10
500 x 50 21.4 2 42.8 10
200 x 100 17.2 2 34.1 10
300 x100 24.4 2 48.8 10
400 x100 49.7 2 99.4 10
500 x 100 61 2 122 10
600 x 100 71.2 2 142.4 10
800 x100 106.4 2 212.8 10
1000 x 100 129.1 2 258.2 10

1. Effecttive sectional area of conduit pipe

2. Weight = Conduit + Cables

Notes
1. Anchor bolt
For bolts of 10mm OD or lager anchor bolts which are in principle driven in to building structure when concretes is
placed should be used inn case inserts can not be used because of design issue etc. Obtain approval of a person in
charge of the system.

2. Weight at supporting point


Discuss with structure designer in case the weight imposed at the supporting point exceed 150kg

3. Color of Inserts
Inserts should be color - classified in accordance with each trade

Remark :
Cable Ladder For Trench At Electrical Room Only
1. Electrical Installation Manual

4. Earthing Installation
Installation Manual
Earthing Installation
Electrical
1. Electrical Installation Manual

5. Lightning Protection Works

a) Mounting detail for with test-link box for lightning protection


system
b) Mounting detail for without test-link box for lightning
protection system
c) Connecting detail of earth rod, conductor
d) Penetration of copper tape through exterior wall
e) Attached drawing
Installation Manual
Mounting detail for with test-link box for lightning protcetion system
Electrical work

Notes:
1.Terminal box for testing
The box should be of rigid PVC or non-magnetic materials (brass,Aluminium) with terminals indicating
the services such as lightning protection test-link.

2.Indication for embedded material


Near the earth rod embedded in the ground, provide marker showing the location etc of an embedded earth
rod.

3.Connection terminals
Down conductor and ground wire should be connected to connection terminal.

4.Reinforcing steel tie


In case terminal box is embedded in RC structure, request to structure contractor to reinforce around terminal
box.
Installation Manual
Mounting detail for without test-link box for lightning protcetion system
Electrical work

Notes:

1.Indication for embedded material


Earth pit cover shall come with indication.

2.Connection terminals
One end of ground wire to be welded to rebar, the other end shall be clamp to earth rod.
Installation Manual
Connecting detail of earth rod, conductor
Electrical work

Service Earth Rod


Power Copper Bar
ELV OD: Min 15mm
Length: Min 1.8m
Lightning Conductor Copper Bar
OD: Min 15mm
Length: Min 1.8m
Installation Manual
Penetration Of Copper TapeThrough Exterior Wall
Electrical work

Hostel A at Axis HA/6 / HA/7 and Hostel B at Aixs HB/1 - HB/2 / HB/9 - HB/10

Other See at Shop Drawing

NOTES:

1.WATER SLOPE
Provide slope to penetrating copper tape so that water can flow outdoor(minimum 1/10)

2.PENETRATION LOCATION
Penetration should be above the water-proof membrance. Do not penetrate the water-proof
membrane.
1. Electrical Installation Manual

6. Electrical Equipment Installation

a) Wiring Devices system

- Socket Outlet & Switch Connection Detail

Administration Building
a-1) Switch installation detail – Administration Building
a-2) Switch installation detail – Administration Building
a-3) Switch installation detail – Administration Building
a-4) Switch installation detail – Administration Building
a-5) Switch installation detail – Administration Building
=>Detail Dimension Checked by Shop Drawing.

Teaching Building
a-6) Switch installation detail – Teaching Building
a-7) Switch installation detail – Teaching Building
a-8) Switch installation detail – Teaching Building
a-9) Switch installation detail – Teaching Building
a-10) Switch installation detail – Teaching Building
a-11) Switch installation detail – Teaching Building
a-12) Switch installation detail – Teaching Building
a-13) Switch installation detail – Teaching Building
a-14) Switch installation detail – Teaching Building
=>Detail Dimension Checked by Shop Drawing.

Hostel-A Building
a-15) Switch installation detail – Hostel A Building
a-16) Switch installation detail – Hostel A Building
a-17) Switch installation detail – Hostel A Building
a-18) Switch installation detail – Hostel A Building
=>Detail Dimension Checked by Shop Drawing.

Hostel-B Building
a-19) Switch installation detail – Hostel B Building
a-20) Switch installation detail – Hostel B Building
a-21) Switch installation detail – Hostel B Building
a-22) Switch installation detail – Hostel B Building
a-23) Switch installation detail – Hostel B Building
=>Detail Dimension Checked by Shop Drawing.
Dining Hall
a-24) Switch installation detail – Dining Hall
a-25) Switch installation detail – Dining Hall
a-26) Switch installation detail – Dining Hall
a-27) Switch installation detail – Dining Hall
a-28) Switch installation detail – Dining Hall
a-29) Switch installation detail – Dining Hall
a-30) Switch installation detail – Dining Hall
a-31) Switch installation detail – Dining Hall
a-32) Switch installation detail – Dining Hall

Administration Building
a-33) Socket, telephone & data outlet installation detail
=>Detail Dimension Checked by Shop Drawing.
Teaching Building
a-34) Socket, telephone & data outlet installation detail
=>Detail Dimension Checked by Shop Drawing.
Hostel A and Hostel B Building
a-35) Socket, telephone & data outlet installation detail –
=>Detail Dimension Checked by Shop Drawing.
Dining Hall
a-36) Socket outlet & switch installation detail

b) Lighting Fixture
b-1) Lighting fixture installation detail 1
b-2) Lighting fixture installation detail 2
b-3) Lighting fixture installation detail 3
b-4) Lighting fixture installation detail 4
b-5) Lighting fixture installation detail 5
b-6) Lighting fixture installation detail 6
b-7) Lighting fixture installation detail 7
b-8) Lighting fixture installation detail (high bay lamp & wall
lamp)
=>Detail Dimension Checked by Shop Drawing.
c) Speaker
c-1) Speaker installation detail 1
c-2) Speaker installation detail 2
=>Detail Dimension Checked by Shop Drawing.

d) Fire Alarm Equipment


d-1) Installation detail for fire alarm bell and manual call point
d-2) Installation detail for smoke detector
=>Detail Dimension Checked by Shop Drawing.

e) MATV Fixture
e-1) MATV fixture installation
=>Detail Dimension Checked by Shop Drawing
Installation Manual
Socket Outlet & Switch Connection Detail
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Administration Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Teaching Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-A Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Hostel-B Building
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual
Switch Installation Detail - Dining Hall
Electrical
Installation Manual Socket, Telephone , Data & MATV Outlet Installation Detail - Administration
Electrical Building
Installation Manual
Socket, Telephone , Data & MATV Outlet Installation Detail - Teaching Building
Electrical
Installation Manual Socket, Telephone , Data & MATV Outlet Installation Detail - Hostel - A and
Electrical Hostel-B Building
Installation Manual
Socket Outlet Installation Detail - Dining Hall
Electrical
Installation Manual
Lighting Fixture Installation Detail 1
Electrical
Installation Manual
Lighting Fixture Installation Detail 2
Electrical
Installation Manual
Lighting Fixture Installation Detail 3
Electrical
Installation Manual
Lighting Fixture Installation Detail 4
Electrical
Installation Manual
Lighting Fixture Installation Detail 5
Electrical
Installation Manual
Lighting Fixture Installation Detail 6
Electrical
Installation Manual
Lighting Fixture Installation Detail 7
Electrical
Installation Manual
Lighting Fixture Installation Detail ( High Bay Lamp & Wall Lamp )
Electrical
Installation Manual
Speaker Installation Detail -1
Electrical
Installation Manual
Speaker Installation Detail 2
Electrical
Installation Manual
Installation Detail for Fire Alarm Bell and Manual Call Point
Electrical
Installation Manual
Installation Detail for Smoke Detector
Electrical
Installation Manual
MATV Fixture Installation
Electrical
SAFE WORK PROCEDUER

THE PROJECT FOR IMPROVEMENT OF EDUCATION COOLEGE


IN TAUNGOO
THE REPUBLIC OF THE UNION OF MYANMAR

ELECTRICAL INSTALLATION

SAFE WORK PROCEDURE

1. Preparation Work

2.Cutting & welding Work

3.Piping work

4.Clean up work
SAFE WORK PROCEDUER

1. Preparation Work

• Meeting before Work starts

• Confirmation of qualified personnel

• Inspection of electrical tools and equipment

• Confirmation of material to used

• Temporary facility inspection

• Workplace check
1. Preparation
Work
Procedure Main Points
Type
1. To check worker attentdance and health conditoin.
1. Meeting before 2. To check worker's PPE and clothing (Safety helmat, clothing,
work starts Safety shoe, ect)
3. To explain workplace condition and environment.
4. To explain work distribution, work contents, method and
procedure and safety precations.
5. Appoint per in charge in each group.
6. To explain electrocution and fire hazards.
7. To provide guidance on correct method in use of electrical
tools.
8. To explain ' No Entry' area.
Preparation

2.Confirmation of When the work requires qualified personnel, to check and confirm in
qualified personnal advance if the proper qualification / Certification.
Work
Procedure Main Points
Type
1. After doing own inspection of electrical tools/ equipment, to
Submit appliction for inspection of electrical equipment by
3. Inspection SNK Electrical Inspector.
electrical tools and Obtain application from and fill in items required. They
equipment include the fllowings.
S/No.
Type of Equipment?Tools
Equipment Serial Number
Supply Voltage
Type of casing
Preparation

Monthly inspection of electrical equipment may be enforced


and for each month colour Code may be given.

4. Confirmation of 1. To check if the materials are correct.


materical to used 2. To check if quantity is correct and there is no damage.
3. To check if there is nay bend in hsting equipment.
4. To check if thee thread of hoisting bolt is not damaged.

5. Temporary 1. To check if there is safe passade way and lifting facility.


facitily 2. To check temporary power supply, lighting, ventilation
inspection. facility , ect, for any irregularity.
3. To check protection for opening.
4. To provide barricades and safety signboard.
5. To provide fire - extinguishers and check if they are in
usable condition.
6. To check if temporary equipment has proper approval
(label, tag, ect).

6. Workplace 1. To check if the floor of workplace is level.


check 2. To check if the area surrounding workplace is tidy and
arranged properly.
3. To communicate with other contractor on lifting and
lowering work.
4. To check location of power supply and sufficient lighting.
5. To check if there is electocution hazard.
SAFE WORK PROCEDUER

2. CUTTING & WELDING WORK

1. WORK FLOOR
1. Use of Mobile scaffolding (Rolling Tower)
2. Foot - mounted scaffolding ( if necessary)
2. CUTTING
2.1 Electric cutter
2.2 Gas cutting (if necessary)
(1) Protection tool
(2) Protection
(3) Ignition
(4) Gas cutting
2.3 Groove preparation
3. Welding on the floor
3.1 Protection tool
3.2 Protection
3.3 Welding
(1) Tack welding
(2) Main welding
2. CUTTING & WELDING WORK
Work
Main Points
Type Procedure
Work floor

1. Use of 1. The scaffold must be erected according to approved


Procedure.
Mobile 2. Scaffold erection, repair and modifacation should be done
Scaffolding under the supervison of an apporoved scaffold supervisor.
( Rolling 3. Brake must be applied, except when moving.
Tower) 4. Use rop/ hoisting/ lowering of tool.
5. Put the rope around yourwaist when going up/down.
6. No two persons should go up/down at the same time.
7. Do not put platform on top of mobile scffold.
8 . For duct hoisting the top and bottom should match
drawing.
9. Fitting of hoisting tools should be done by at lest 2 persons.
10. When lowering hand- rail that cause obstruction, use
hoisting tools, and safety belt must be hooked.
11. Do not carry any worker when moving.
12. When moving, no entry the work area.
13. Park the scaffold near the work area.
14. Do not exceed SWL (Safe Working Load).
Mobile Scaffold

Example:

Frame Plank Floor area SWL


Width (cm) (pcs) (m2) (kg)
160 152.5 3 2.7 250
150
121.9 120 2 1.8 230

H ≤ 7.7L -5
H: the height from bottom of wheel to floor
L : distance between main axis of foot wheel
Handrall height: 90cm & above
Work
Procedure Main Points
Type
2. Foot 1. The scaffold must be assembled according to approved
mounted procedure.
scaffolding 2. use rop / hoisting bag for hoisting/ lowering tool.
3. Put the rope arund your waist when going up/ down.
4. Park the scaffold near the work area.
5. Around opening, use insert and safety - belt must be
hooked.
6. Do not exceed SWL (Safe work load).

Example: Plywood platform SWL

t×W×L Weight SWL(kg)based on span(mm)


(cm) (kg) 1200mm 1500mm 1800mm 2100mm
2.8×24×400 18 172kg 137kg 114kg 98kg
Foot - Mounted
Scaffold
Work
Procedure Main Points
Type
2. Cutting 1. Cover floor with protection and set up machine.
2.1 Electrical 2. Secure pip materical.
Cutter 3. Use wooden support for long and big diameter items.
4. Pipe cutting surface and axis should be at right ngle.
5. Do not use hand to touch mach whlle operating.
6. After cutting, off the switch, and remove pipe only after
machine stop completely.
7. After cutting , collect the waste.
8. Switch off when power supply is off.
Electrical Cutter
Work
Procedure Main Points
Type
2. 2 Gas cutting
(1) Protection tool 1. Use goggle, mask, leather hand glove, arm cover and foot
cover.
(2) Protection 1. Remove flamable stuff.
2. To prevent spark falling off, cover urrounding opening.
3. To prevent sparkfrom flying around, protect the work area.
4. To protect work floor, cover with steel plate.
5. Provide wet blanket , fire -extinguisher and water bucket.

(3)Ignition 1. Ensure the blow pipe valve is closed.


2. Open fully pressure regulator.
3. Open gas cylinder valve, and adjust primary pressure
(high pressuer) to required pressure .
4. Adust secondary pressure (low pressure) by closing
GAS Cutter

5. Aim blow pipe fire tip to the front, away from the body.
6. Release remaining gas from the hose, and switch off valve.
7. Open oxygen vavle slightly.
8. Open acetyllene valve much more than oxygen valve.
9. Use igniton gun.
10. Adjust to standard flame.

(4) Gas cutting 1.Preheat cutting area properly, and use oxygen to cut.
2. After cutting, close blow pipe valve immediately.
3. After cutting, remove cutting waste to prevent burn.
4. When sander is used to remove waste, secure the pipe.
5. Use goggel, mask and vibration - proof hand glove when
sander is used

2.3 Groove 1. Usesander or file to get correct face.


Preparation 2. Do not use burner to do groove work.
3. When sander is used, protect yourself with goggle, mask
and vibration - proof hand glove.
Work
Procedure Main Points
Type
3. Welding on the floor 1 For welding, welder must be certified arc welder.

3.1 Protection tool 1. Remove all flammable stuff.


2. Flammable items that cannot br removed should be covered with
flame- proof sheets.
3. To prevent spark from flying around, use protection.
4. To prevent spark falling off, cover surrounding opening.
5. To protect work floor, cover with steel plate.
6. To protect other worker's eye, use protection board.
7. To prevent spark reaching secondary cable, use
protection.
8. Provide wet blanket , fire - extinguisher and water bucket.

3.2 Welding 1. Ventilation to be provided at confined space.


Welding

(1) Tack 2. Use mask to prevent inhaling of fume.


welding 3. Use dried welding rods.
4. Ensure earth clamp is attached welding material .
5. Engage panel switch, then welding machine switch.
6. Adjust welding current according to pipe diameter.
7. Electrode type, diameter should match material to be carried out to
avoid discrepancy.
8. Clean the area to be welded.
9. Pipe to pipe andipe to fittings alignment should be carried out to
avoid discrepancy.
10. Clip electrode with holder, and ensure arc is produced.
11. Tack weld first to confirm level and direction.
12. After completion of welding, switch off welding machine,
then panel.
13. When you stop welding for while, or leaving the work place for a
while, release electrode from holder, disengage welder switch and
panel switch.
14. When there is power failure, always turn off welding machine
switch.
15. No arc welding in wet condition where there is risk of
electrocution.
16. All electrode holders, welding cables, cable connectors,and other
arc welding equipment shall be inspected by safety officer at lest
once every 30 days.
17. Safety signs at suitable locations understood by all persons
working in the area.
Work
Procedure Main Points
Type
(2) Main Welding Apart from items in Tack welding, do the followings.
1. Remove slag, sputter from tack welding with brush or
slag hammer.
2. In multilayer welding, remove slag after each layr.
3. After completion welding, remove slag from welding area, and make
sure there is no defect in welding.

Example of defect in welded area

Defect Condition Defect Condition


Blow hole Undercut

Overlap Crack
Main Welding

Slag Poor pene


inclusion tration
SAFE WORK PROCEDUER

3. PIPING WORK
1. WORK FLOOR
1. Use of Mobile scaffolding (Rolling Tower)
2. Foot - mounted scaffolding ( if necessary)
3. Single use of ladder
(1) Inspection
(2) Setting
(3) Work
(4) Tightening of threaded pipe
(5) Fitting of hanger band
3. PIPING WORK
Work
Procedure Main Points
Type
Work Floor

1. Use of Mobile 1. The scaffold must be erected according to approved procedure.


Scaffolding 2. Scaffold erection, repair and modification should be done under the
(Rolling Tower) supervisoion of an approved scaffold supervisor.
3. Brack must be applied, except when moving.
4. Use rope/ hoisting bag for hoisting/ lowering of tool.
5. Put the rop around your waist when oing up? Down.
6. No two presons should go up / down at the same time.
7. Do not put platform on top of mobile scaffold.
8. For duct hoisting tools should be done by at lest 2 persons.
9.Fitting of hoisting tools should be done by at lest 2 persons.
10 When lowering hand -rail in order not to cause obstruction, use
hoisting tols, and safety belt must be hooked.
Mobile Scaffold

11. Do not carry any worker when moving.


12. When moving , no entry to the area for non - related workers.
13. Park the scaffold near the work area.
14. Do not exceed SWL (Safe Working Load)

Example:

Frame Plank Floor area SWL


Width (cm) (pcs) (m2) (kg)
160 152.5 3 2.7 250
150
121.9 120 2 1.8 230

H ≤ 7.7L -5
H: the height from bottom of wheel to floor
L : distance between main axis of foot wheel
Handrall height: 90cm & above
Work
Procedure Main Points
Type
2. Foot 1. The scaffold must be assembled according to approved
mounted procedure.
scaffolding 2. use rop / hoisting bag for hoisting/ lowering tool.
3. Put the rope arund your waist when going up/ down.
4. Park the scaffold near the work area.
5. Around opening, use insert and safety - belt must be
hooked.
6. Do not exceed SWL (Safe work load).

Example: Plywood platform SWL

t×W×L Weight SWL(kg)based on span(mm)


(cm) (kg) 1200mm 1500mm 1800mm 2100mm
2.8×24×400 18 172kg 137kg 114kg 98kg
Foot - Mounted
Scaffold

3. Single -use of
ladder
(1) Inspection 1. Deformation and rusting of foot.
2. Deformation and damage of opening extender.
3. Deformation and damage of top plate and step
4. Damage of foot stopper.
Work
Procedure Main Points
Type
(2) Setting 1. Remove any obstruction on the floor.
2. The top plate should be level.
3. The opening extender should be fully opened.
4. Position it close to work area.
5. When the foundation is weak, not even, use protectionto make it
level.
6. Step on the first step, apply weight to test if it shakes.
7. Do not set it on the floor where there is work going on.

(3) Work 1. Use rope/ hoisting bag for hoisting / lowering tool.
2. Use rope around your waist when going up/ down.
3. Do not carry other person when working.
4. Do not use the top plate for working.
Single - use ladder

5. Around opening area, hook up your safety -belt.


6. Do not lay your back on the ladder.
7. Do not jump from the ladder.
8. Do not use plank
9. Do not use support as replacement for ladder.
10. Do not use wooden plank and pipe at the foot.
Work
Procedure Main Points
Type
Tightening of Besides the main point highlighted in section tightening on the floor,
threaded pipe do the followings.
1. To make sure that already tightening position do not change ,
secure with pipe wrench.
2. Use waist pouch to prevent dropping of tools.
3. Do not put connection material under your eet.
4. At fall hazard location, hook up your safety - belt.
Tightening of Threaded Pipe

Fitting of hanger 1. Make sure that the band is properly fitted.


band
SAFE WORK PROCEDUER

4. CLEAN UP WORK

1. Dismantling of scaffold

2. Clear up of electrical equipment

3. Clean up of waste material

4. Protection at waste material

5. Clean up of temporary works facility

6. Remove (No Entry Sign)

7. Checking
4. Clean up Work
Work
Main Points
Type Procedure
1. Dismantling of 1. Refer to Mobile scaffold dismantling ' and' Erection of
scaffold foot - mounted scaffold erection procedure 'section'.

2. Clear up of 1. Switch off power at switch panel.


electrical 2. Collect electrical equipment and put back to designated stroage
equipment. area.

3. Clean up of 1. Separate waste material based on type, and put together at


waste designated location.
materical 2. Put waste in container, and keep at designated location.
3. Industrial waste has to be colleced and disposed off.

4. Protection 1. Dismantled protection materialto be returmed to ts original


CLEAN UP WORK

at Opening. location.

5. Clean up of 1. Upon completion of temporary work facility usage, keep them at


temporary works designated location.
facility 2 . Collect ventilation equipment, and keep at designated lacation.
3. Damaged temporary work facility should be segregated and keep
at designated location.

6. Remove 1. Remove rope, danger sign, etc, and keep them at designated
" NO" Entry lacation.
Sign

7. Checking 1. To check if panel switch of arc welding machine, electrical


equipment have been switched off.
2. To check if dismantled sfaety equipment have been restored.
3. To check there is no remaining welding spark.
4. To check tidiness, orderliness and cleanliness of workplace.
3. Check List for Electrical Work
(Internal Check List)

1) Pipe Sleeve Installation Check List


Check materials, locations, level, sizes, etc. by check list
---with drawings

2) HT Transformer Installation Check List


Check model, capacity, location, etc. by check list
---with drawings

3) Generator Installation Check List


Check model, capacity, dimension etc. by check list
---with drawings

4) Panel Board (MDB, SDB, DB, etc.) Installation Check List


Check dimension, location, level, etc. by check list
---with drawings and factory manufacture drawing

5) LV Cable Installation Check List


(a) Internal (SDB to DB) Installation by check list with drawings
(b) External (U/G) Installation by check list with drawings

6) Conduit Installation Check List


(a) Concealed Pipe (inside slab) Installation by check list with drawings
(b) Exposed Pipe (expose and inside ceiling) Installation by check list with
drawings

7) Underground Pipe Installation Check List


Check materials, locations, level, sizes, etc. by Check list
---with drawings

8) Lighting Fixture Installation Check List


Check visual, model, type, location, etc. by check list
---with drawings

9) Lightning Protection System Checklist


Check material, type, location etc. by check list
---with drawings
10) Earthing System Checklist
Check material, type, location etc. by check list
---with drawings

11) Public Address System Checklist


Check model, equipment accessories, location, etc. by check list
---with drawings

12) Fire Alarm System Installation System Checklist


Check model, equipment accessories, location etc. by check list
---with drawings

13) Master Antenna Television Installation Check List


Check model, equipment accessories, location etc. by check list
---with drawings

14) Telephone, Data System Installation Checklist


Check model, equipment accessories, location etc. by check list
---with drawings
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

PIPE SLEEVE INSTALLATION CHECKLIST


INSPECTION DATE :
DRAWING REFERENCE :
LOCATION :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance
1 Check whether approved piping materials is used.

2 Check pipe material as per specifications/standards is used.

3 Check whether anti-rust paint have been applied to pipe sleeve


internal surface.

4 Check whether the pipe sleeve is properly secured with brackets.

5 Check the levelling and positioning of the pipe sleeve


as per approved and coordinated drawings.

6 Check end-cap (tape) is properly installed at both ends.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 1 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

HT TRANSFORMER INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check HT and LT termination box are at correct orientation.

3) Check transformer's neutral is properly & securely earthed.

4) Check transformer body and cable boxes bonded to earth bar.

5) Check the alarm & trip sensing cable are properly terminated.

6) Check transformer base is properly secured & tightened.

7) Check overall cleanliness of the transformer

8) Check for transformer rating / serial no plate is installed.

9) Check drain plug for signs of leakage.

10) Check if the transformer room is locked or transformer area is


fenced to prevent un-authorised access.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 2 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

GENERATOR INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check position of Gen set and layout according to approved


drawing

2) Check Manufacturer, Make & Model according to approved list

3) Ensure generator are properly installed with anti-vibration isolators.

4) Check flexible duct is provided between radiator & rigid duct and properly
tightened. Ensure no leak.

5) Check flexible joints is provided between exhaust & silencer and properly
tightened. Ensure no leak.

6) Check Ait intake & discharge silencer dimensions are according to


approved drawing.

7) Check generator exhaust pipe is properly installed with the flippable end
cap and painted with heat resistant paint.

8) Check battery type & capacity is according to manufacturer's specs &


ensure electrolyte level is enough.

9) Check coolant level in radiator is sufficient.

10) Check overall cleanliness & oil leaks or spill on floor

11) Check for any obstructions during emergency operation.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 REV : O
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

Panel Board (MDB, SDB and DB, etc. ) INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION & PANEL NO: DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check overall cleanliness and free from physical damage of the


switchboard

3) Check mounting height according to approved drawing.

4) Check all panels are securely fastened on the wall/floor.

5) "DANGER" label to be displayed on removable panels.

6) Check all cable tray/ladder/trunking or conduits are bonded to


switchboard frame with protective conductor.

7) Check all cables are securely terminated with cable lugs,


c/w cable markers.
Check ensure Neutral Bar,Earth Bar and Active Link are
8)
Properly fit and correctly terminate.

9) Check all panels and outgoing breakers are properly labeled.

10) Check doors hinges are bonded to frame with protective conductor.

11) Check over-current & earth-leakage protection relay(if any) are


set & calibrated according to requirement.

12) As-built single-line diagram to be provided inside of panel door.

13) Check all components are according to approved drawings

14) Cable entry point into Panel is prevented from damage to cables
(sharp edges) & properly sealed from dust entry.

15) Check if the switch board is lockable for security reason.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 4 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

LV CABLE INSTALLATION CHECKLIST (INTERNAL)


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check routing is according to approved drawing.

2) Check material type & brand according to requirement

3) Check size and quantity according to approved drawing.

4) Check cable is securely fasten to tray/ladder/trunking or conduit


c/w earth links where necessary

5) Check all circuits are terminated to the correct breakers,properly


labelled according to approved drawing.

6) Check all cable glands/cable lugs are according to cable sizes

7) Check all cable used are of correct color code.

8) Check all floor and fire wall penetration are sealed with approved
fire rated material

9) Check bending radius of cable not less than 6 times cable diameter.

10) Cable inside panel properly seperated & secured using cable tie.

11) Check cable arrangement (trefoil) configuration.

12) Check feeder cable entry to all equipment are neat & not damaging.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 5 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

LV CABLE INSTALLATION CHECKLIST(EXTERNAL)


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check routing is according to approved drawing.

2) Check material type & brand according to requirement

3) Check size and quantity according to approved drawing.

4) Check Cable continuity and Insulation Resistance of each cable

5) Check all circuits are terminated to the correct breakers,properly


labelled according to approved drawing.

6) Check all cable glands/cable lugs are according to cable sizes

7) Check all cable used are of correct color code.

8) Check Cable layer and Warning Sign Tape before backfilling work

9) Check bending radius of cable not less than 6 times cable diameter.

10) Cable inside panel properly seperated & secured using cable tie.

11) Check cable arrangement configuration.

12) Check feeder cable entry to all equipment are neat & not damaging.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE : 13/05/2015


DOC. NO.: GCL-01 REV:O
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

CONDUIT INSTALLATION CHECKLIST(CONCEALED)


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location & layout of junction box according to approved drwg.

2) Check material type & brand according to requirement

3) Check size & type of conduit are according to approved drawing

4) Check conduit installed are properly painted & installed according to


approved drawing

5) Check conduit joint boxes & outlet are properly tightened.If UPVC
conduit system,adhesive shall be applied.

6) Check flexible conduit are properly fixed.Length of flexible conduit


are according to requirements.

7) For cast in PVC conduit,ensure all conduit are tied to rebar,boxes are
fully stuffed and check for conduit damage

8) Ensure conduits are installed between 1st & 2nd layer of slab rebar,
only bend down to formwork at junction box location.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :
ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 8 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

CONDUIT INSTALLATION CHECKLIST(EXPOSED)


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location & layout of junction box according to approved drwg.

2) Check material type & brand according to requirement

3) Check size & type of conduit are according to approved drawing

4) Check conduit installed are properly painted & installed according to


approved drawing

5) Check conduit joint boxes & outlet are properly tightened.If UPVC
conduit system,adhesive shall be applied.

6) Check flexible conduit are properly fixed.Length of flexible conduit


are according to requirements.

7) Check ensure for exposed PVC or EMT conduit Pipe are properly
installed with Saddle

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 9 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

UNDERGROUND PIPE INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location & layout of junction box according to approved drwg.

2) Check material type & brand according to requirement

3) Check size & type of conduit are according to approved drawing

4) Check conduit installed are properly painted & installed according to


approved drawing

5) Check conduit joint boxes & outlet are properly tightened.If UPVC
conduit system,adhesive shall be applied.

6) Check flexible conduit are properly fixed.Length of flexible conduit


are according to requirements.

7) Check Level and Entry of each conduit with specified accessories

8) Ensure conduits are installed between other service specified clearence

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company :YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 10 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

LIGHTING FIXTURES INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check brand & type are according to approved List

3) Check mounting height of the lighting are according to approved


drawing and specification.

4) Check earth continuity conductor are properly connected.

5) Ensure that cable continuity and resistance test are conducted


and recorded before power turn on.

6) Check all recessed light fittings on ceilings are provided with proper
hanging method & securely mounted for others.

7) Check functionability of switches and lighitng fixtures.

8) Ensure illumination level are recorded and according to specification.

9) Check overall cleanliness for light fittings.(paint,finger prints etc)

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 11 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

LIGHTNING PROTECTION SYSTEM CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check earth conductor size is according to approved drawing

3) Check all mechanical joint of earth terminal are properly tighten.

4) Check main earth bar provided according to specification and


earth cable are properly labeled.

5) Check main earth bar is installed with hard cover transparent plastic
sheet to prevent direct access.

6) Inspection chamber are provided for each set of earth electrode.

7) Warning notice & tag are provided at all terminal bar and electrode.

8) Ensure that all earth resistance test are conduct and recorded < 5Ω.

9) Ensure cable markers/signage are provided before backfill

10) Warning notice & tag are provided at all terminal bar & in chamber

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE : 13/05/2015


DOC. NO.: GCL-01 REV : O
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

EARTHING SYSTEM CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check earth conductor size is according to approved drawing

3) Check all mechanical joint of earth terminal are properly tighten.

4) Check main earth bar provided according to specification and


earth cable are properly labeled.

5) Check main earth bar is installed with hard cover transparent plastic
sheet to prevent direct access.

6) Inspection chamber are provided for each set of earth electrode.

7) Warning notice & tag are provided at all terminal bar and electrode.

8) Ensure that all earth resistance test are conduct and recorded < 5Ω.

9) Ensure cable markers/signage are provided before backfill

10) Warning notice & tag are provided at all terminal bar & in chamber

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 13 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

PUBLIC ADDRESS SYSTEM INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location,routing and layout according to approved drawing.

2) Check brand,model & type according to approved catalogue & drawings.

3) Check P.A.rack & equipment are in correct position & oreintation as per
approved drawings.

4) Check for any obstruction to normal operation of P.A. equipment.

5) Check cabling size & type of cable installed as per approved drawings

6) Check for porper labelling for the cabling works at the P.A equipment.

7) Check speakers are properly mounted with proper support.

8) Check for wall mounted speaker height are as per approved drawings.

9) Ensure continuity & insulation test are conducted before function test.

10) Check for interference noise from external sources during function test.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 14 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

FIRE ALARM SYSTEM INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance
1) Check location and layout of devices and junction box according to approved
drawing.

2) Check physical condition height, orientation of Push Button and Sounder and
Indication Lamp.

3) Check conduit joint boxes & outlet are properly tightened.

4) Check location and total zoning of Fire Alarm Panel according to approved
drawing.

5) Ensure continuity & insulation test are conducted before function test.

6) Check whether Centre Monitoring System (CMS) are install and tested.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE:13/05/2015
DOC. NO.: GCL-01 15 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

MASTER ANTENNA TELEVISION SYSTEM INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check Brand,model & type according to approved catalogue & drawings.

3) Check equipment are in correct position & oreintation as per approved


drawings.

4) Check for MATV Pole is properly tightened after alignment.

5) Check cabling size & type of cable installed as per approved drawings

6) Check for proper labelling for the cabling works & MATV equipment in risers.

7) Check mounting height & alignment are according to approved


drawing & specification.

8) Ensure continuity & insulation test are conducted before function test.

9) Check for interference noise from external sources during function test.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE : 13/05/2015


DOC. NO.: GCL-01 REV : O
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

TELEPHONE / DATA SYSTEM INSTALLATION CHECKLIST


INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Acceptability Remark / Non-


Item Description N/A
Yes No Conformance

1) Check location and layout according to approved drawing.

2) Check Brand,model & type according to approved catalogue & drawings.

3) Check equipment are in correct position & oreintation as per approved


drawings.

4) Check for PABX RACK is properly installed after alignment.

5) Check cabling size & type of cable installed as per approved drawings

6) Check for proper labelling for the cabling works & TEL,DATA equipments

7) Check mounting height & alignment are according to approved


drawing & specification.

8) Ensure continuity & insulation test are conducted before function test.

9) Check for interference noise from external sources during function test.

REMARK / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE.LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUE DATE : 13/05/2015


DOC. NO.: GCL-01 REV : O
4. Test and Commissioning for Electrical Work
(Internal Testing & Commissioning)

1) Transformer Function Test


Performance Test with factory manufacture’s check list
=> OK, Acceptable by Design Capacity with Factory
Manufacture’s Certified Check List &Test Report

-Will be submitted before commissioning.

2) AVR Function Test


Performance test with Factory Manufacture’s check list test report with
following data.
=>OK. Acceptable - (i) Input Voltage : 400V +20%
(ii) Output Voltage : 400V +1%
(iii) Frequency : 50 Hz
(iv) Output waveform : Sine wave
(v) Overall Efficiency : > 95% at full load

- Will be submitted before commissioning.

3) Generator Operation Function Test


Performance test with Factory Manufacture’s check list test report with
following data.
=> OK, Acceptable by Design Capacity with Factory Manufacture’s Test
Report.

4) MDB Function Test


Performance test by check list with Schematic Diagram.
=> OK, Acceptable with Specified Breaker Assembly and Dimension
without any damage.
MDB operation check by breaker ON / OFF

5) SDB & DB Function Test


Performance test by check list with Schematic Diagram.
=> OK, Acceptable with specified Breaker Assembly and Dimension without
any damage.
6) Earthing Resistance Test
Performance Test by check list with Drawing.
=> OK, Acceptable by Earth Test Resistance R <5Ω.

7) Cable Insulation / Continuity Test


Performance Test by check list with Drawing.
=> OK, Acceptable by Insulation Resistance ≥ 1.0MΩ.

8) Electrical Voltage And Phase Sequence Test


Performance Test by check list with Instrument.
=> OK, Acceptable – Line to line voltage nearly equal for load balance.
Line to Line
B, B, G
BB=BG=BG= 400 V ± 10%
Line to Neutral
BB=BB=GB= 230V +5%
- Phase Sequence Clockwise Direction.

9) Socket Outlet Test


Performance Test by check list
=> OK, Acceptable – Specified Location and Alignment
Polarity and Earth check by tester

10) Illumination Level Test


Performance Test by check list with Drawing
=> OK, Acceptable – With design calculation around 300 lux

11) PA System Operation Test


Performance Test by check list with test report interior function test
=> OK, Acceptable – With specified Sound Pressure Level (SPL)
With technical data from supplier.

12) Fire Alarm Function Test


Performance Test by check list with test report prior to conduction
acceptable test.
=> OK, Acceptable – With function test report from supplier the
Presence of interior.
-will be submitted before commissioning.
13) Lightning System Earth Resistant Test
Performance Test by check list with Drawing.
=> OK, Acceptable by Earth Test Resistance R <5Ω

14) MATV Test Table


Performance Test by check list with Drawing.
=> OK, Acceptable with Specified Data and Function Test Report.

- will be submitted before commissioning.

15) Telephone and Data Test Table


Performance Test by check list with Drawing.
=> OK, Acceptable with Specified Function Report Test from Supplier.

- Will be submitted before commissioning.


THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

TRANSFORMER FUNCTION TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :

Result
Type of Test YES NO RESULT

Applied potential test


Induced potential test
No-load loss by the average-voltage voltmeter method
(To be made after the impulse tests)
Exciting current test
Impedance and load loss at rated current on the rated voltage connection At Factory
Resistance measurements on all windings on the rated voltage connections
of the transformer and at each tap
Temperature rise test (At Factoy)
Ratio tests on the rates voltage connections and on all tap connections
Audible noise level tests shall be made in accordance with the applied
standard
Visual and dimension check

Measurement of voltage ratio (L-L=400V±L-N=230V±5%)


Measurement of no load loss and current (open circuit test) At Site
Measurement of insulation resistance R=1MΩ
Check of insulation oil

REMARK/NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

DOC NO.: ETC-04 ISSUED DATE:20/05/2015


REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

AVR FUNCTION TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :

Result
Type of Test YES NO RESULT

Resistance measurements on all windings on the rated voltage connections


of the transformer and at each tap
Temperature rise test
Ratio tests on the rates voltage connections and on all tap connections At Factory
Audible noise level tests shall be made in accordance with the applied
standard
Visual and dimension check
Measurement of voltage ratio
Phase Sequence Check by phase sequence metre At Site

Measurement of insulation resistance according to factory report

REMARK/NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

DOC NO.: ETC-04 ISSUED DATE:20/05/2015


REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

GENERATOR OPERATION FUNCTION TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :

Result
Type of Test YES NO RESULT
Battery Test.
Charging Check

AMF board Function Test.


- Gen-set to start automatically upon main power failure &
stop automatically after cool down operation when main supply resume.

- Auto change over switch to function after gen-set start


with timer delay. Change back after power supply resume.

- Check to ensure all indicator light function as specify.

Noise Level Check.


- Design requirement of lower than 85dBA at 1m from
generator.
Check condition by using Noise level meter.

REMARK/NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

DOC NO.: ETC-04 ISSUED DATE:20/05/2015


REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

MDB FUNCTION TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :
MSB NAME : Rating :

Exhaust Fan installed : YES / NO Thermostat Function YES / NO Capacitor Bank Manufacturer :
** Note : Please indicate in Remark column if ACB is used as a coupler No. of Steps :

Breaker Outgoing Feeder ACB MCCB RCCB Indicator Light Result Capacitor Function Test Manual Remarks
Fuction Test
No Name Rating Setting Rating Setting Rating Setting R Y B OK / NO Step OK NO
(Yes / No / NA)
Step No. 1
Step No. 2
Step No. 3
Step No. 4
Step No. 5
Step No. 6
Step No. 7
Step No. 8
Step No. 9
Step No. 10
Step No. 11
Step No. 12

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRCATOR) : APPROVED (CONSULTANT) :

Inspected by : Inspected by : Inspected by :


Name : Name : Name :
Company : SHIN NIPPON AIRTECH (SINGAPORE)PTE.LTD Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(MYANMAR BRANCH)
Date : Date : Date :

ISSUED DATE: 20/05/2015


DOC NO. : ETC-05 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

SDB-SWITCH BOARD / DISTRIBUTION BOARD FUNCTION TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :
SSB / DB NAME : Rating :

Exhaust Fan installed : YES / NO Function YES / NO Capacitor Bank Manufacturer :


** Note : Please indicate in Remark column if ACB is used as a coupler No. of Steps :

Circuit Load / Circuit MCB / MCCB RCCB Indicator Light Result Remarks
Fuction Test Fuction Test
No Name Rating Rating Setting R Y B (OK / NO)
(Yes / No / NA) (Yes / No / NA)

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRCATOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH (SINGAPORE)PTE.LTD Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(MYANMAR BRANCH)
Date : Date : Date :

ISSUED DATE:20/05/2015
DOC NO.: ETC-06 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

EARTHING RESISTANCE TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :

TYPE OF EARTHING TO BE TESTED :-

LV EARTH COMPUTER EARTH

HT FRAME/NEUTRAL EARTH TELEPHONE EARTH


(Delete where not applicable)
LIGHTNING PROCTECTION EARTH OTHERS

PARTICULARS OF EARTHING MATERIAL :-

Earth Electrode Rod & coupler Manufacturer :

Earth Clamp Manufacturer. :

Earth Chamber Type(Heavy / Light duty) :

Earth Tester used. : (Date )


(Date of calibation expiry).

TEST RESULT :-

1). Overall Earth Resistance Value : Ohms.

2). No of earth Point in this system. :


(Reference Only)
Earthing Number Resistance Value Earthing Number Resistance Value
Point of rod (Ohm) Point of rod (Ohm)
No.1. No.5.
No.2. No.6.
No.3. No.7.
No.4. No.8.

3). Teat Result is acceptable or not. YES / NO (Delete where not applicatble)

REMARK/NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :


ISSUED DATE:20/05/2015
DOC NO.: ETC-07 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

CABLE INSULATION/CONTINUITY TEST.


INSPECTION DATE : DB / PANEL NAME : Sheet _____of_____
LOCATION : DRAWING REFERENCE :

Testing Instrument : Maker / Model / Serial : Calibration Expiry date : Voltage Rating: Volts.
Note : Insulation resistance of cables should be more than 1 Mega Ohm
Insulation Resistance ( M ohm ) between line
Continuity Test . (YES or NO).
Circuit No x Core / Size Cable Route Phase to Phase Phase to Neutral Phase to Earth Remarks
No. Type of cable To Equipment, R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E N-E R Y B N E

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRCATOR) : APPROVED (CONSULTANT) :

Inspected by : Inspected by : Inspected by :

Name : Name : Name :


Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD

(MYANMAR BRANCH)

Date : Date : Date :

ISSUED DATE:20/05/2015
DOC NO.: ETC-08 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

ELECTRICAL VOLTAGE AND PHASE SEQUENCE TEST

INSPECTION DATE:
PANEL/FEEDER NAME:
TYPE OF SERVICES:
SUPPLY FROM:
CABLE SIZE/TYPE:
LOCATION:

VOLTAGE TEST.
Testing Instrument : Mnfg / Model No :………………………………………………… Voltage Rating : …………….Volts.

Note : Voltage drop shall not be less than 4 %

Voltage Between line.


R-Y R-B Y-B R-N Y-N B-N

PHASE ROTATION TEST. RESULT .

Pls Tick. Power Turn-ON Approved :-

YES NO YES NO
RYB

REMARK/NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

ISSUED DATE:20/05/2015
DOC NO.: ETC-09 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

SOCKET OUTLET TEST

DATE OF TEST : PANEL / DB NAME :


LOCATION : DRAWING REFERENCE :

MCB Socket Plug-Top Tester (Fault/ OK)


Circuit Number Quantity per circuit Remarks
Rating Seq No. Polarity check Earth check Result

REMARK/NON-CONFORMANCE

*Test Instrument : Neon indicator plug-top tester

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

ISSUED DATE:20/05/2015
DOC NO.: ETC-10 REV:0
E
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

ILLUMINATION LEVEL FUNCTION TEST


DATE OF TEST :
LOCATION : DRAWING REFERENCE :

Note : Acceptable more than 300 lux with design calculation

Design Measured (Lux) Level Acceptability


Floor Room Type of light
Level (Lux) Highest Lowest Average YES / NO

REMARK/NON-CONFORMANCE

Testing Instrument : Brand / Model No : Calibration Expiry Date :


Note: To attach lux layout indicate test points & quantity of point taken.

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :


ISSUED DATE: 20/05/2015
DOC NO.: ETC-11 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

PA SYSTEM OPERATION TEST

TEST/INSPECTION DATE :
LOCATION : DRAWING REFERENCE :

Result 'YES' or 'NO'


No. of Volume Normal Emergency
Zone No. Location Speakers Control Paging Paging Zone Selector Conformance

REMARK/NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

ISSUED DATE:20/05/2015
DOC NO: ETC-12 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

FIRE ALARM FUNCTION TEST (Page 1 of 2)


DATE OF TEST :
LOCATION :
DRAWING REFERENCE :

DETECTOR MANUAL CALL POINT


REMARKS /
ITEM FLOOR LOCATION ZONE
HEAT SMOKE RESULT B/GLASS BELL RESULT NON-CONFORMANCE

REMARKS / NON-CONFORMANCE-

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)
Date : Date : Date :

ISSUSED DATE:20/05/2015
DOC NPO:ETC-13-1 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

FIRE ALARM FUNCTION TEST (Page 2 of 2)


DATE OF TEST :
LOCATION :
DRAWING REFERENCE :
TOTAL OF ZONE :

ITEM STATUS REMARKS/NON-CONFORMANCE


A TEST FIRE ALARM PANEL
A-1) Bulb Test
i) All Indicaton Light List
A-2) Manual Test Zone Circuits
i) Alarm Zone / Point Tested And Bell Ringing
ii) Isolate Bell Switch & Bell Silence
iii) Isolate Alarm Zone / Point And Buzzer Sound
iv) Fault Line Tested And Buzzer Sound
v) Reset To Normal Condition
A-3) Check Change Over From AC 240V To DC 24 V

B FIRE TEST CONDITION


B-1) Test Smoke Detector
B-2) Test Heat Detector N/A
B-3) Test Manual Break Glass
B-4) Test Flow Switch N/A
B-5) Correct Status At Fire Alarm Panel And Print Out
B-6) Status Indicated At Mimic Panel And Colour Graphic Monitor N/A
B-7) Check The Following :
i) Alarm Bell Ringing
ii) Lift Homing N/A
iii) Pressurization System Activated N/A
iv) AHU Trip N/A
v) Smoke Spill System Activated N/A
vi) Fire Roller Shutter Closed N/A
vii) Magnetic Door Released N/A
viii) Central Monitoring System (CMS) Functioning N/A
ix) Other ( )

C STATUS MONITORING
C-1) Sprinkler / Hydrant / Hose Reel / Wet Riser (Delete Whichever Not Applicable)
PUMP SETS AC FAIL PUMP RUN PUMP TRIP
i) Jockey N/A N/A N/A
ii) Duty N/A N/A N/A
iii) Standby N/A N/A N/A
iv) Butterfly Valve Closed N/A
v) Gas Discharge (24V Signal) N/A
vi) Fire Tank Low Water Level N/A
vii) Genset Run And Trip N/A
C AFTER TESTING
C-1) System Reset To Normal

REMARKS / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR
(MYANMAR
BRANCH)
BRANCH)
Date : Date : Date :

ISSUSED DATE:20/05/2015
DOC NO:ETC-13-2 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

LIGHTNING SYSTEM EARTH RESISTANCE TEST

ATTACHMENT / DRAWINGS : DATE :

LOCATION ; REFERNCE NO :

INSTTRUMENT USED : TESTING METHOD :

CALIBRATION EXPRTY DATE :

Note : Acceptable by Earth Test Resistance R <5Ω

DATE / DATE / DATE / DATE /


POINT NO WEAT. OHM WEAT. OHM WEAT. OHM WEAT. OHM
TIME TIME TIME TIME

AVERAGE

THE SYSTEM HAS BEEN TESTED AND THE TOTOL EARTH RESISTANCE IS ………………………………………… OHMS
THERE WERE TOTAL ……………………………….. POINTS TESTED.

REMARKS / NON-CONFORMANCE

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :

Inspected by : Inspected by : Inspected by :

Name : Name : Name :


Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.

(SINGAPORE)PTE. LTD

(MYANMAR BRANCH)

Date : Date : Date :

ISSUSED DATE:20/05/2015
DOC NO:ETC-14 REV:0
THE PROJECT FOR IMPROVEMENT OF EDUCATION COLLEGE

MATV TEST TABLE

RANGE OF TEST : ( Minimum dB) to ( Maximum dB)

REFERNCE NO : DATE OF TESTING :

FIELD STRENGTH (dB)


LOCATIONS
CH CH CH CH CH CH CH FM FM REMARKS

REMARKS :

TESTER (SUB CONTRCATOR) : CHECKED (MAIN CONTRACTOR) : APPROVED (CONSULTANT) :


Inspected by : Inspected by : Inspected by :
Name : Name : Name :
Company : SHIN NIPPON AIRTECH Company : KUMAGAI GUMI CO.,LTD Company : YAMASHITA SEKKEI INC.
(SINGAPORE)PTE. LTD
(MYANMAR BRANCH)

Date : Date : Date :

ISSUSED DATE:20/05/2015
DOC NO: ETC-15 REV:0