ID Subject Type Status Priority Assignee Start Finish Sequence


date date

457 Salzina Tab Phase In Normal 23 Jun 05 Oct


progress 2020 2020
459 PIS Development & Submission Phase Closed Normal Ayesha 26 Jun 03 Jul
Saeed 2020 2020
460 Financial Feseability Phase Closed Normal Ayesha 23 Jun 20 Jul
Saeed 2020 2020
467 Initiate Financial Feasibility Form Task Closed Normal Ayesha 07 Jul 07 Jul 230
Saeed 2020 2020
468 Propose MRP, Discount & Forecast Task Closed Normal Imran 08 Jul 10 Jul 235
Hussain 2020 2020
469 Receive Approved FF Form Task Closed Normal Ayesha 10 Jul 10 Jul 240
Saeed 2020 2020
470 Cost Finalization Task Closed Normal Asif Ali 29 Jun 20 Jul 245
2020 2020
482 Request Data Task Closed Normal Asif Ali 29 Jun 29 Jun 250
2020 2020
483 BoM Data Task Closed Normal Kamran 29 Jun 03 Jul 255
Alam 2020 2020
484 Material Price Info. Task Closed Normal Asif Iqbal 07 Jul 17 Jul 260
2020 2020
485 Costing Process Task Closed Normal Asif Ali 18 Jul 19 Jul 265
2020 2020
486 Analyze & Approve Costing Results Task In Normal Asif Ali 20 Jul 270
progress 2020
471 Intimate for Commercialization Task Closed Normal Ayesha 23 Jun 23 Jun 300
Saeed 2020 2020
458 Artwork Development & Approval Phase Closed Normal Ayesha 25 Jun 16 Jul
Saeed 2020 2020

04 Sep 2020 1/3


472 Prepare & Finalize Text Task Closed Normal Shagufta 25 Jun 10 Jul 305
Siddiqui 2020 2020
473 Define Tool & Sizing Task Closed Normal Kamran 25 Jun 02 Jul 310
Alam 2020 2020
474 Package Designing Task Closed Normal Adeel 25 Jun 10 Jul 315
Mirza 2020 2020
475 Approval Process in GoProof Task In Normal Ayesha 16 Jul 16 Jul 320
progress Saeed 2020 2020
462 Initiate PIS Task Closed Normal Ayesha 26 Jun 26 Jun 201
Saeed 2020 2020
463 Update Mfg. & Pkg. Details Task Closed Normal Kamran 26 Jun 02 Jul 205
Alam 2020 2020
464 Receive & Send Updated PIS Task Closed Normal Ayesha 02 Jul 03 Jul 215
Saeed 2020 2020
465 Review & Approve Task Closed Normal Imran 03 Jul 03 Jul 220
Hussain 2020 2020
466 Sign Off PIS Task Closed Normal Ayesha 03 Jul 03 Jul 225
Saeed 2020 2020
461 Procurement & Planning Phase Schedule Normal Asif Iqbal 25 Jun 04 Oct
d 2020 2020
476 Raw and Packing Material Availability Task In Normal Asif Iqbal 25 Jun 24 Sep 330
progress 2020 2020
487 Raw Material Task In Normal Asif Iqbal 25 Jun 31 Aug 335
progress 2020 2020
488 Packing Material Task In Normal Asif Iqbal 28 Jul 24 Sep 340
progress 2020 2020
477 BoM Document Task New Normal Kamran 21 Aug 05 Sep 345
Alam 2020 2020
478 Perform API Analysis Task New Normal Attique 01 Sep 05 Sep 350
Rahman 2020 2020
479 Mfg. and Packaging Task New Normal Kamran 08 Sep 30 Sep 360
Alam 2020 2020
480 Perform FG Analysis Task New Normal Attique 01 Oct 04 Oct 380
Rahman 2020 2020

04 Sep 2020 2/3


481 FG Stock Available Mileston Schedule Normal Asif Iqbal 05 Oct 05 Oct
e d 2020 2020

04 Sep 2020 3/3