Professional Documents
Culture Documents
Keywords: Capping stack is an emergency shut-in technique that can effectively control offshore blowout accidents. This
Offshore safety technique stemmed the spilled oil well (Macondo) in 2010 Deepwater Horizon blowout accident. However, few
Blowout accidents efforts have been devoted to studying the way to efficiently and safely conduct the operation of capping stack. In
Capping stack this paper, program evaluation and review technique (PERT) was employed to quantitatively design the op-
Orthogonal test
eration procedure of capping stack. A mechanical model was established to determine the configuration scheme
Emergency preparedness
of capping stack. And a sensitivity analysis of operational factors of capping stack was conducted through or-
thogonal tests. Experimental results recommend to optimize the operation process by reducing the working time
of diamond cutting tool down-pass, Lower Marine Riser Package (LMRP) upper riser incision, LMRP and original
Blowout Preventer (BOP) separation, and LMRP recovery, in order to guarantee that the whole operation can be
completed as scheduled. The results show that the number of ram BOPs has little effect on the equivalent stress
of conductors. To improve system reliability, a five-ram capping stack is recommended to be applied in the
defined accident scenario. The maximum equivalent stress of conductors rates the drilling vessel offset as the
primary factor, followed by shut-in pressure, ocean current and top tension. The drilling vessel offset needs to be
given the priority control and the shut-in pressure should be jointly monitored.
1. Introduction techniques for the damage mitigation of deepwater blowout (Xue et al.,
2013).
The offshore oil industry is highly dangerous (Shaughnessy et al., Several deepwater blowout emergency techniques have been dis-
2007; Khan et al., 2017; Abimbola& Khan, 2018; Perez& Tan, 2018). cussed (Meng et al., 2019). Massey (2014) described the progress of
With the rapid increase of oil and gas production from subsea wells, it is Marine Well Containment Company (MWCC). Hurzeler and
even more demanding to maintain offshore activities at an acceptable Scheuermann (2012) presented the efforts of Helix Well Control Group
risk level. Many offshore accidents have happened in recent years (HWCG). Besides MWCC and HWCG, many organizations have con-
(Wang et al., 2011; Hayes, 2012; Verweijen& Lauche, 2019). Blowout tributed significantly to emergency response techniques for deepwater
accidents attracted huge public attention due to their significant con- blowout since 2010. They mainly devoted themselves to the industrial
sequences, especially in the wake of the Deepwater Horizon or Ma- research and application of capping stack. Ren et al. (2012) designed a
condo accident (Skogdalen et al., 2012), which caused 11 fatalities, rescue equipment for uncontrolled blowout. The fluid mechanic prop-
poured around 490 × 104bbl (1bbl = 0.159 m3) crude oil into the Gulf erty of their proposed equipment was studied. Wolinsky (2011) devel-
of Mexico (GOM) and led to the largest oil spill disaster in US history oped and demonstrated a device that can contain oil spewing from a
(U.S. Coast Guard, 2010; Dadashzadeh et al., 2013). defective blowout preventer (BOP) stack on seabed. Meng et al. (2012)
Blowout remains one of the riskiest accidents in offshore oil industry presented operational principle, working process, applicable condi-
(Skogdalen et al., 2011; Skogdalen and Vinnem, 2012; Cai et al., 2013; tions, design philosophy, maturity degree, and research emphasis of
Liu et al., 2018). As the oil industry moves towards deeper waters and each emergency technique for deepwater blowout. Furthermore, Lower
harsher operating environment, it is even more challenging to effec- Marine Riser Package (LMRP) cap was quantitatively designed based on
tively manage blowout risk. Due to huge personnel casualties, property program evaluation and review technique (PERT) (Meng et al., 2019).
losses and environmental disasters that deepwater blowout accidents The emergency techniques employed in Macondo emergency rescue
could cause, it is significant to conduct research on emergency represent the state-of-the-art in offshore oil industry (Osi, 2011; Smith,
*
Corresponding author.
E-mail addresses: menghuixing@tsinghua.edu.cn, huixing.meng@hotmail.com (H. Meng), gmchen@upc.edu.cn, offshore@126.com (G. Chen),
lxqmcae@163.com (X. Liu).
https://doi.org/10.1016/j.jlp.2019.103925
Received 8 February 2019; Received in revised form 21 June 2019; Accepted 20 July 2019
Available online 22 July 2019
0950-4230/ © 2019 Elsevier Ltd. All rights reserved.
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
Table 1
Rapid emergency techniques for deepwater blowout accidents (Meng et al., 2019).
Emergency techniques Brief description Characteristics
ROV intervention To trigger or repair failed BOP Rapid but depends heavily on BOP integrity
Top kill To pump mud with high pressure and high flow rate into wellbores through High pressure can lead to damage of BOP, wellhead and casings
choke and kill lines
Capping stack A new BOP assembly of fewer blind shear rams, to be installed on former Effective, but needs to notice similar risk as to Top kill
(failed) BOP
Static kill Similar to Top kill but merely can be applied after capping the well, that is, Effective but needs the well to be capped
stemming the flow
Containment dome To lower a big dome over leakage points on seabed and inducing oil to sea Confronted with a high risk of natural gas hydrates
surface through a pipe
Top hat Similar to Containment dome but smaller shape Facing risk of ice hydrates, but smaller than Containment dome,
meanwhile, lower oil recovery capacity
RITT To insert a long tube with a smaller diameter into the broken riser on seabed Oil recovery capacity is limited as there exist other leaking points, such as
and induce the oil to sea surface wellhead
LMRP cap A cap which is similar to Top hat, but installed on former BOP Effective, but require BOP up-right
2
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
Table 2
Industrial field experiments of capping stack.
Time Experimental sea Brief introduction
August 2017 Fensfjorden, Norway PSW Group conducted a capping stack exercise
April 2013 GOM, WD > 1524m Carried out by BSEE, Nobel Energy, HWCG. The capping stack was 6.10m tall, weighted 66.22t, with an experimental
wellhead pressure of 57.92 MPa.
July 2012 GOM, WD 2103m Accomplished by MWCC and Shell. The capping stack was 9.14m tall, weighted 100t, with an experimental wellhead
pressure of 68.95 MPa.
July 2011 UK Shetland, WD 305m Conducted by UK OSPRAG and Total. Capping stack was 7.14m tall, weighted 40t, can bear well pressure of 103.4 MPa and
temperature of 121 °C
May 2011 West Africa, Angola, WD > 2000m Completed by BP and Subsea 7, Oceaneering, FMC, Cameron
tLF (i, j) = min{tLS (j , k )} The mechanical model of a capping stack system is shown in Fig. 2.
(3)
k
The riser system is affected by top tension, self-weight, ocean cur-
rent and wave load, etc. The differential equation of the riser system is
tLS (i , j ) = tLF (i, j) t (i , j ) (4) given as (Sparks, 2007; Ju et al., 2012; Liu et al., 2016):
d4y d2y dy
R (i , j ) = tLF (i, j) tEF (i, j) = tLS (i, j) tES (i, j) (5) EI T (x ) w = f (x )
dx 4 dx 2 dx (7)
F (i , j ) = min{tES (j , k )} tES (i , j ) t (i, j) = min{tES (j , k )} tEF (i, j) where E denotes the elasticity modulus, Pa. I represents the cross-sec-
j j
tional moment of inertia, m4. W is the riser unit weight, kN. The top
(6) tension of the riser is given by:
where t (i, j) implies the activity duration time, tES and tEF are earliest l
T (x ) = T0 (D 2 d2) + d2 D2 B dx
activity start and finish time, respectively, tLS and tLF denote latest al- 0 4 s
4 m
4 l
(8)
lowable activity start and finish time, respectively, R indicates the total
where T0 is the top tension, kN. l is the whole length of the riser, m. D
activity slack, which measures the excess time available to complete a
and d are the outer and inner diameter of the riser, separately. s , m , l
project, F represents the activity free slack, with positive values in-
are the density of the riser, drilling fluid and seawater, respectively. kg/
dicating that a task is ahead of schedule, negative values implying that
m3;B is the unit buoyancy force of the riser buoyancy block, kN.
a task falls behind the schedule and with zero values revealing that a
Fc(x) denotes the unit ocean current force, kN, which is given as:
task is on time.
f (x ) = c D D u u + c M uD2
2 4 (9)
4. Configuration scheme
where cD is the drag coefficient, cM is the inertia coefficient. ρ denotes
Another key issue of capping stack is to determine the configuration the seawater density, kg/m3. D is the outer diameter of the riser, m. u
scheme (i.e., the number of ram preventers). Firstly, the operation risk represents the water particle speed, m/s. u is the acceleration speed of
analysis of capping stack is conducted through Preliminary Hazard the water particle, m/s2.
Analysis (PHA). Subsequently, the configuration scheme of capping The conductor is loaded by the vertical and horizontal force from
stack is proposed based on its mechanical model. bottom flexible joint, buoyant weight of BOP and wellhead, horizontal
wave-induced current force, skin friction and lateral soil reaction, thus
the conductor is vulnerable. The differential equation of the conductor
4.1. Risk analysis for static analysis is given as (Sparks, 2007; Liu et al., 2013; Yan et al.,
2015)
PHA analysis can identify, provide suggestions to prevent and
d2 d2y d dy
control risk (Vinnem, 2014). During an emergency plan design stage, it EI (x ) 2 + N (x ) + DC (x ) p (x , y ) = q (x )
is helpful to apply PHA to conduct risk analysis of emergency rescue
dx 2 dx dx dx (10)
process. The PHA analysis of capping stack is tabulated in Table 3. where DC (x ) is the outer diameter of conductors, m , N (x ) is the axial
Human and environmental factors can directly or indirectly influ- force, kN , p (x , y ) represents the horizontal base pressure per unit area,
ence the implementation of capping stack technique. Human errors can kPa/m2 , where positions above the mud line are zero, q (x ) is the ex-
lead to operational failures in emergency situations (Musharraf et al., ternal load per unit length, kN/m , positions below the mud line are
2019; Deacon et al., 2010). In Table 3, precautionary measures are zero, EI (x ) is the bending rigidity of the integrated string composed of
mainly related to human factors. Regarding environmental factors, se- the conductor, the concrete sheath, and the surface casing, kN m2 .
vere conditions in deep waters can significantly influence the success of The higher shut-in pressure of the capping stack, the higher failure
this technique, including sea state and hydrate. For instance, sea cur- risk of the conductor. The axial force of the conductor incorporated the
rent has been simulated in the mechanical model (see Fig. 2). shut-in pressure is given by:
As shown in Table 3, the collapse contributes actively to the op-
1 l
erational risk of capping stack. Since riser, capping stack, conductor, N (x ) = Tbottom + 2
Dsbop Pshut w (x )dx + Dc (x ) f
4 l1 (11)
and formation composes a coupling system, which can introduce vessel
offset, top tension, wave and ocean current load into the BOP, wellhead where Tbottom is the residual axial tensile force at the riser bottom, kN.
and conductor (Sun, 2009). Furthermore, capping stack brings addi- Dsbop represents the inner diameter of capping stack, m. Pshut is the shut-
tional large weight on the conductor. The conductor is vulnerable in the in pressure, kPa. w(x) is the conductor wet weight per unit length, kN. l
coupling system due to its risky load conditions. A mechanical model of and l1 are positions of conductor ends, m. f is the side frictional force
the capping stack system has been established (including the con- per unit area, kPa.
ductor). To ensure the conductor safety during the operation of capping
3
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
pressure
1.
2.
3.
1.
2.
3.
1.
2.
3.
4.
1.
Lead to work failure and secondary
Cannot tightly close rams
Work delayed heavily
accidents
(12)
Hydrate inhibitor injection system is failed
< [ ]
Has not scrupulously verified bolt strength
max
The high- pressure and low- temperature
Strength of lowering cable is insufficient
2.
3.
4.
1.
2.
3.
4.
1.
seabed
capping stack which holds more ram preventers to guarantee its op-
erational reliability. Nevertheless, the increment of the height and
II. Lower capping stack
weight of the capping stack can increase the failure risk of the con-
ductor.
By considering harsh operating environments in deepwater blowout
emergency scene, the most serious conditions are given priority to be
Work stage
(i.e., the initial number of the ram preventers i0 is 5). Once the con-
ductor strength can meet requirements, accident site decision makers
4
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
5. Case study
can choose any of the abovementioned capping stack forms. However, a 5.2.1. Basic parameters
five-ram capping stack is recommended at first. On the condition that The initial shut-in pressure of capping stack during the Macondo
the five-ram capping stack fails to satisfy the strength requirement, the accident is 45.5 MPa. The rated working pressures of the recommended
5
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
Table 5
Completion time and interrelationships of capping stack operation.
No. Name of the activity Symbol Duration/h Preceding activities
Fig. 5. PERT of capping stack emergency operation. Fig. 6. The critical path of capping stack operation.
subsea blowout preventer in API standard (API, 2012) are 5.2.3. Sensitivity analysis
13.8–103.5 MPa. Therefore, shut-in pressures of capping stack in this The operational factors of capping stack include top tension, vessel
study are set between 30 and 90 MPa. offset, ocean current speed and shut-in pressure. Based on orthogonal
The configuration scheme of capping stack in a deepwater well in tests, a sensitivity analysis of operational factors for capping stack is
the South China Sea is studied, and its related parameters are listed in carried out.
Table 7. The material of the conductor is X-56, and the allowable stress
is 257.3 MPa under the safety factor of 1.5. 5.2.3.1. Range analysis. During an emergency scenario of deepwater
blowout, four levels of each four parameters are put forward to
5.2.2. Configuration scheme establish an orthogonal table of L16(45). The range analysis of the
The mechanical model of capping stack system in the above well orthogonal test is shown in Table 9. It has been learned that the
was established. After the primary computation, four operation condi- maximum equivalent stress of conductors is affected by vessel offset,
tions are set using the vessel offset of 80, 85, 90 and 95m. First, the shut-in pressure, ocean current speed, and top tension successively.
maximum equivalent stress of conductors is obtained. Second, based on
the linear interpolation, the maximum allowable vessel offset is gained. 5.2.3.2. Variance analysis. Since the accuracy of above range analysis is
Finally, the configuration scheme of the capping stack in the South low, it can lead to misjudgment when the test error is large. Given a
China Sea is tabulated in Table 8. variance analysis can make full use of test information, its judgment
The results in Table 8 show that all forms of capping stack can be accuracy is higher. Because the quadratic sum of the error of top tension
applied once the vessel offset is less than 83.70m. Nevertheless, the and ocean current speed is little, they are classified into the error line.
five-ram capping stack is preferred to be employed for enhancing the The variance analysis for the maximum equivalent stress of conductors
work safety redundancy. Once the vessel offset is over 83.70m, the is shown in Table 10.
configuration scheme of capping stack is recommended to follow From orthogonal test results, it is found that vessel offset has a
Table 8. highly significant effect of the conductor stress under a significant level
Table 6
Computational table of capping stack operation.
Symbol Activity (i,j) t(i,j) tES(i,j) tEF(i,j) tLS(i,j) tLF(i,j) R(i,j) F(i,j)
A (1, 2) 12 0 12 20 32 20 12
B (1, 3) 10 0 10 22 32 22 12
C (1, 4) 8 0 8 −7 1 −7 8
H (2, 7) 5 12 17 32 37 20 5
G (2, 10) 15 12 27 33 48 21 21
dummy activity (3, 2) 0 10 10 32 32 22 2
D (4, 5) 5 8 13 1 6 −7 0
E (5, 6) 2 13 15 6 8 −7 0
dummy activity (6, 7) 0 15 15 37 37 22 2
F (6, 10) 40 15 55 8 48 −7 −7
I (7, 8) 3 17 20 37 40 20 0
J (8, 9) 6 20 26 40 46 20 0
K (9, 10) 2 26 28 46 48 20 20
6
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
Table 7
Related parameters of deepwater well in the South China Sea.
WD/m Former BOP length/ Former BOP weight/ LMRP length/m LMRP weight/kN Conductor length/m Conductor thickness/ Outer diameter of conductor/
m kN mm mm
Table 9
Range analysis for the maximum equivalent stress of conductor.
Factors Top tension Vessel offset Ocean current speed Shut-in pressure Random error
7
H. Meng, et al. Journal of Loss Prevention in the Process Industries 62 (2019) 103925
Table 10
Variance analysis for the maximum equivalent stress of conductors.
Error source Quadratic sum of the error Degree of freedom F value F0.05(3,9) F0.01(3,9) Significance
Acknowledgment mapping GO models into Bayesian networks. J. Loss Prev. Process. Ind. 52, 54–65.
Massey, M., 2014. MWCC's Expanded System: Enhancing Well Containment in the U.S.
Gulf of Mexico. Offshore Technology Conference, Houston, Texas.
This work is partially supported by the National Natural Science Meng, H., Chen, G., Zhu, Y., Liu, X., 2012. Classification and discussion on the direction of
Foundation of China (Grant No. 51809279), the National Key R&D emergency technology for deepwater blowout. Petrol. Drill. Tech. 40 (6), 27–32.
Program of China (Grant No. 2017YFC0804501), the Fundamental Meng, H., Chen, G., Liu, X., Zhu, Y., 2019. An oil recovery technique for emergency
response in deepwater blowout accidents. Saf. Sci. 113, 134–143.
Research Funds for Innovation Program of Seventh-generation Ultra Musharraf, M., Khan, F., Veitch, B., 2019. Modeling and simulation of offshore personnel
Deepwater Drilling Platform (Grant No. 2016[24]), and the during emergency situations. Saf. Sci. 111, 144–153.
Fundamental Research Funds for the Central Universities National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling, 2011.
Deep Water: the Gulf Oil Disaster and the Future of Offshore Drilling.
(17CX02025A).
(Washington D.C).
Neal Adams Firefighters, 1993. Joint Industry Program for Floating Vessel Blowout
References Control. (Houston).
Osi, L.K., 2011. BP's Deepwater Horizon Oil Spill: Engineering Failures, Environmental &
Economic Impact. The Cooper Union for the Advancement of Science and Art, New
Abimbola, M., Khan, F., 2018. Dynamic blowout risk analysis using loss functions. Risk York.
Anal. 38 (2), 255–271. Perez, P., Tan, H., 2018. Accident Precursor Probabilistic Method (APPM) for modeling
API, 2012. Blowout Prevention Equipment Systems for Drilling Wells STD 53. and assessing risk of offshore drilling blowouts–A theoretical micro-scale application.
Washington D.C. Saf. Sci. 105, 238–254.
API, 2014. Recommended Practice for Subsea Capping Stacks, RP 17W. Washington D.C. Rassenfoss, S., 2013. Well capping becomes an industry of its own. J. Pet. Technol. 65 (7),
Badiru, A.B., Osisanya, S.O., 2016. Project Management for the Oil and Gas Industry: a 41–47.
World System Approach. CRC Press. Ren, M., Li, X., Shi, F., Ma, L., Xu, D., 2012. The research of seabed rescue equipment and
BOEMRE, 2010. Statement of Compliance with Applicable Regulations and Evaluation of method of uncontrolled blowout in offshore drilling. In: IADC/SPE Asia Pacific
Information Demonstrating Adequate Spill Response and Well Containment Drilling Technology Conference and Exhibition, Tianjin, China.
Resources (Washington D.C). Shaughnessy, J.M., Daugherty, W.T., Graff, R.L., Durkee, T., 2007. More ultradeepwater
BOEMRE, 2011. Report Regarding the Causes of the April 20, 2010 Macondo Well drilling problems. In: SPE/IADC Drilling Conference, Amsterdam, The Netherlands.
Blowout. Skogdalen, J.E., Khorsandi, J., Vinnem, J.E., 2012. Evacuation, escape, and rescue ex-
BP, 2010. Deepwater Horizon Containment and Response: Harnessing Capabilities and periences from offshore accidents including the Deepwater Horizon. J. Loss Prev.
Lessons Learned. (London). Process. Ind. 25 (1), 148–158.
BSEE, 2016. Subsea Capping Stack Technology Requirements. Skogdalen, J.E., Utne, I.B., Vinnem, J.E., 2011. Developing safety indicators for pre-
Cai, B., Liu, Y., Zhang, Y., Fan, Q., Liu, Z., Tian, X., 2013. A dynamic Bayesian networks venting offshore oil and gas deepwater drilling blowouts. Saf. Sci. 49 (8–9),
modelling of human factors on offshore blowouts. J. Loss Prev. Process. Ind. 26 (4), 1187–1199.
639–649. Skogdalen, J.E., Vinnem, J.E., 2012. Quantitative risk analysis of oil and gas drilling,
Chen, J., Li, X., Xie, W., Kang, Y., 2013. Capping stack: an industry in the making. Eng. using Deepwater Horizon as case study. Reliab. Eng. Syst. Saf. 100, 58–66.
Sci. 11 (4), 17–23. Smith, L.M., 2012. A Review of Offshore Blowouts and Spills to Determine Desirable
Commission, 2011. Deep Water: the Gulf Oil Disaster and the Future of Offshore Drilling. Capabilities of a Subsea Capping Stack. Louisiana State University, Baton Rouge.
Dadashzadeh, M., Abbassi, R., Khan, F., Hawboldt, K., 2013. Explosion modeling and Sparks, C.P., 2007. Fundamentals of marine riser mechanics : basic principles and sim-
analysis of BP Deepwater Horizon accident. Saf. Sci. 57, 150–160. plified analyses. Penn Well.
Deacon, T., Amyotte, P.R., Khan, F.I., 2010. Human error risk analysis in offshore Spier, C., Stringfellow, W.T., Hazen, T.C., Conrad, M., 2013. Distribution of hydrocarbons
emergencies. Saf. Sci. 48 (6), 803–818. released during the 2010 MC252 oil spill in deep offshore waters. Environ. Pollut.
Hayes, J., 2012. Operator competence and capacity–lessons from the Montara blowout. 173, 224–230.
Saf. Sci. 50 (3), 563–574. Sun, Y., 2009. Strength Assessment for Deepwater Drilling Riser and Engineering
Henley, J., Wibner, C., Webb, T., Soliah, J., 2013. Subsea cap & contain method for a Application. Dongying, China University of Petroleum (East China), PhD thesis.
deepwater tension leg platform. In: 2013 SPE/IADC Drilling Conference and U.S. Coast Guard, 2010. Deepwater Horizon MC252 Gulf Incident Oil Budget.
Exhibition, Amsterdam, The Netherlands. (Washington D.C).
Hillier, F.S., Lieberman, G.J., 2002. Introduction to Operations Research. McGraw-Hill Vinnem, J.E., 2014. Offshore Risk Assessment. Springer-Verlag, London.
Higher Education. Verweijen, B., Lauche, K., 2019. How many blowouts does it take to learn the lessons? An
Hu, Y.Q., 2004. Fundamentals and Applications of Operations Research. Higher institutional perspective on disaster development. Saf. Sci. 111, 111–118.
Education Press. Wang, Y.F., Xie, M., Ng, K.M., Habibullah, M.S., 2011. Probability analysis of offshore fire
Hurzeler, K.L., Scheuermann, R., 2012. The development and maintenance of an "ever- by incorporating human and organizational factor. Ocean. Eng. 38 (17–18),
green" spill response capability in the Gulf of Mexico. In: Offshore Technology 2042–2055.
Conference, Houston, Texas, USA. Winston, W.L., Goldberg, J.B., 2004. Operations Research : Applications and Algorithms.
Ju, S., Chang, Y., Chen, G., Liu, X., Xu, L., Wang, R., 2012. Envelopes for connected Thomson/Brooks/Cole.
operation of the deepwater drilling riser. Pet. Explor. Dev. 39, 113–118. Wolinsky, S., 2011. Method and Apparatus for Containing Subsea Oil Spills Caused by a
Khan, F., Abimbola, M., Hashemi, S.J., 2017. Blowout Risk in Drilling and Production. Defective Blowout Preventer (BOP) Stack. The International Society of Offshore and
Encyclopedia of Maritime and Offshore Engineering, pp. 1–19. Polar Engineers.
Liu, X., Chen, G., Chang, Y., Xu, L., 2013. Wave induced fatigue analysis on deepwater Xue, L., Fan, J., Rausand, M., Zhang, L., 2013. A safety barrier-based accident model for
drilling riser-conductor system. Acta Pet. Sin. 34 (5), 977–982. offshore drilling blowouts. J. Loss Prev. Process. Ind. 26 (1), 164–171.
Liu, X., Chen, G., Chang, Y., Ji, J., Fu, J., Song, Q., 2016. Drift-off warning limits for Yan, W., Chen, Z.J., Deng, J.G., Zhu, H.Y., Deng, F.C., Liu, Z.L., 2015. Numerical method
deepwater drilling platform/riser coupling system. Pet. Explor. Dev. 43, 701–707. for subsea wellhead stability analysis in deepwater drilling. Ocean. Eng. 98, 50–56.
Liu, Z., Liu, Y., Wu, X., Cai, B., 2018. Risk analysis of subsea blowout preventer by