Professional Documents
Culture Documents
Nobumasa Iwasaki, P.E.Jp, Fukken Co., LTD., Osaka, Japan; Shinji Tenma, P.E.Jp, Fukken Co., LTD., Hiroshima, Japan and
Akimitsu Kurita, Prof., Dr., Dept. of Civil Engineering and Urban Design, Faculty of Engineering, Osaka Institute of Technology,
Osaka, Japan. Contact: kurita@civil.oit.ac.jp
DOI: 10.2749/101686611X12994961034093
12000
having a steel composite girder as the
superstructure.
34
to design the girder–abutment con-
2100
nection in order to transfer bending
3300
34
300
Based on the constructed examples of
PFB in Japan5, the girder–abutment
1450 3 × 3000 = 9000 1450 Steel member
connection detailing is classified into
three groups with regard to the con- (b)
nection type: the headed stud, the
3550
13 800
tion A, only the steel cross section is
considered as the resisting member
against external forces.
2. Horizontal axial force and bend-
ing moment are transferred at the
(a) girder–abutment connection by
the resisting forces generated at the
perforated steel plate on the flange
PBL 100 × 25 × 1400
plates. Shear force of the steel girder,
12 950 namely, axial force at the abutment
16
is calculated by the bearing stress of
A B the concrete under the steel girder.
2000
2000
12 000
20 × 130
2919
Temporary
bearing 2. The moment is transmitted through
the resisting forces caused by all
(c)
Fig. 3: Shimotani ike Bridge: (a) side view; (b) cross-sectional view; (c) detail of steel
girder end8 (Units: mm)
200
400
200 200
perforated steel plates were used as
shear connectors at the girder–abut-
ment connection. By using the perfo-
rated steel plate, a simple structure
at the girder ends and also a ratio-
nal design concept for the girder–
abutment connection were realised for Fig. 5: Approach Slab of Nishihama Overpass10 (Units: mm)
this bridge.
Instead of using the perforated steel A New Approach Slab Finite Element Analyses for
plate as shear connector it is pos-
A rectangular approach slab,10 which
Stress in Asphalt Pavements11
sible to perforate the upper and lower
flange plates as well as the web plate has the same shape as applied in con- In order to clarify the effects of the
directly. This was first attempted at ventional bridges, was used from the approach slab on the stresses of
the Shimotani ike Bridge. It appears first stage onwards to construct the asphalt pavement, FE analyses were
that the design concept of transmit- PFB in Japan. However, the structural carried out for the loading case of
ting the shear force only to the girder– details of the approach slab have temperature. The computer program
abutment connection in this bridge has been constantly improved in order to DIANA was used for numerical
to be improved to a more economical prevent asphalt pavement cracking due analysis. Analysis parameters are the
one. to temperature changes and backfill shapes of the approach slab and the
settlement. Figure 5 shows an improved installed depth of the approach slab.
When the steel composite girders are approach slab where the shear pro- In the analysis, the shape and dimen-
selected as the superstructure, the jections are attached to the slab and sions of the Nishihama Overpass
reinforced concrete slab contains the the thickness of the slab at the tip is approach slab were applied, as
longitudinal re-bars which are very thinner than the rest. Also, the slab is shown in Fig. 5. The approach
effective in interconnecting the girder recessed 400 mm deep into the ground. slab has a length of 5 m and three
and abutment. However, the longitu- Therefore, the strains caused by any shear projections of 200 × 200 mm.
dinal re-bars in the concrete slab have deformations of the abutment are Its surface is inclined towards the
been neglected in the design of the smoothly distributed by the backfill. tip.
girder–abutment connection in PFBs.
Therefore, to improve the designing
method for the girder–abutment con- Case 1 Case 2 Case 3 Case 4
nection, longitudinal re-bars should Shear projection Yes No
be taken into account as a mem-
ber producing the resisting couple Installed depth Hg from road surface (mm) 450 650 850 450
moment. Table 3: List of analytical cases
The installed depth of the approach contact surface between two elements measured over a distance of 7 m from
slab in Nishihama Overpass was 400 was treated as free when tensile stress the edge of bridge are depicted in
mm from the lower surface of the occurred between them. Fig. 9 for Case 1 and Case 4. From the
asphalt pavement. In this analysis, comparison in Fig. 9a and b, it is recog-
Compulsory deformation was applied
three cases regarding the installed nised that the stress distribution of
at the end of the approach slab, consid-
depth were evaluated for the new slab Case 1, where the approach slab has
ering the load case of low temperature,
type, as shown in Table 3. Further, cal- the shear projection, is smoother than
as shown in Fig. 7. In the analysis, the
culation for the approach slab without that of Case 4. The maximum stress of
temperature-induced deformations
shear projection was done to compare about 0,8 N/mm2 is consistent in both
(d) were increased from 1 to 10 mm
the types. cases and the maximum occurs at 5,5
in 1 mm intervals. The deformation of
Figure 6 shows the FE analytical model and 4,7 m from the edge of bridge
d = 10 mm corresponds to the design
for Case 1. It comprises the asphalt for Case 1 and Case 4, respectively.
load case with low temperature and a
pavement, the backfill soil and the These maximum stresses indicate the
bridge length of about 50 m.
approach slab. The mechanical proper- mean values. However, the maximum
ties of all materials were assumed as in stress of 0,86 N/mm2 in Case 1 shows
a slightly smaller value than that of
linear elastic models. Two-dimensional Calculated Results and 0,93N/mm2 in Case 4.
stress analysis was performed by Discussion
using 3-node triangular and 4-node As shown in Fig. 9a, for Case 1 the
quadrilateral iso-parametric plane FE analysis was carried out for four difference between the stresses at the
stress elements and line-interface ele- cases, as shown in Table 3. From the upper and lower surfaces of the asphalt
ment for interactions between the soil calculated results it was found that pavement is not much. Therefore, a
and the approach slab. The FE ana- the maximum stress in the asphalt uniform tensile stress distribution can
lytical model is 15 m long, which is pavement occurred at the point near be assumed as acting throughout the
three times the slab length, and 6 m the approach slab tip. thickness of the asphalt pavement as
deep. Both dimensions were decided a result of the low temperature around
after taking into account the effects Figure 8 shows the relationship between
the bridge. However for Case 4, where
of ground deformation. The FEs of the maximum tensile stresses measured
the approach slab has no shear projec-
the asphalt pavement are divided into at the upper and lower surfaces of the
tion, the stress distribution at the upper
upper and lower layers. The mechani- asphalt pavement and the installed
surface of the asphalt pavement shows
cal properties of all the materials depth of the approach slab with shear
a large change as shown in Fig. 9b.
required for the numerical calculations projection. It is clear from Fig. 8 that
Accordingly, stress resultants of tensile
are listed in Table 4. the tensile stresses of the asphalt pave-
force and local bending moment exist
ment decrease in proportion to the
The boundary condition between the for Case 4. Figure 10a and b shows the
installed depth of the approach slab.
approach slab and soil was treated analytical results of deformation for
as non-linear, that is, the boundary The stress distributions of the asphalt Cases 1 and 4 at the loading condi-
between two elements was restrained pavement along the length and tion of d = 10 mm. From the results
by the upper value of shear stress
obtained from the Mohr’s envelope 0,9
when normal stress in soil was com-
0,8
pressive. On the other hand, the
Horizontal tensile stress (N/mm2)
0,7 Case 1
0,6 Case 2
0,3
6000
0,0
15 000 400 500 600 700 800 900
Installed depth Hg (mm)
Fig. 7: Compulsory deformation and
boundary conditions (Units: mm) Fig. 8: Maximum tensile stress of asphalt pavement (with shear projection)
0,6
end of the approach slab. But in Case
1, such gap is not seen.
0,5
0,7
0,6
0,5
Conclusions
0,4 A state of the art report regarding
0,3 the PFB in Japan was given in this
0,2 paper. The reason why IAB has not
0,1
been developed in Japan in spite of
Upper surface of pavement
numerous constructed examples in the
0,0 Lower surface of pavement
United States1 was also given.
–0,1
0 1 2 3 4 5 6 7
Horizontal distance (m)
Three typical structural detailing of
the girder–abutment connection which
Fig. 9: Effects of shear projection for stresses in asphalt pavement (a) Case 1: with shear links the superstructure and substruc-
projection (installed depth Hg = 450 mm); (b) Case 4: without shear projection (installed ture in the PFB, using steel compos-
depth Hg = 450 mm) ite girders were reported in relation
with the design concept. Naturally,
the improvement of structural detail-
ing of the girder–abutment connec-
tion was recognised from recently
constructed PFBs. To arrive at a
more economical solution for the PFB
design it was pointed out that the
longitudinal re-bars in the concrete
slab should be taken into account for
0,8
0,7
the design of the girder–abutment
0,6
0,5
connection, as is done in European
0,4
0,3
0,2
countries.
0,1
0
A new type of approach slab devel-
0,93 mm (a) oped in Japan was introduced and the
results of its numerical calculation by
a FE analytical model were also pre-
sented. The acceptance of this new
approach slab type will influence the
design of PFB or IAB in the future.
With regard to the future develop-
ment of IAB in Japan, behaviour
against seismic motion and low cycle
fatigue at the top of steel piles as a
result of the temperature change are
0,8
important topics to be addressed. It
0,7
0,6 also appears that the semi-IAB, which
0,5
0,4 does not have any specific design
0,3
0,2
0,1
problem, will develop faster than the
0 IAB. All said and done, the jointless
bridges such as PFB, IAB and semi-
(b)
IAB are welcomed by vehicle users
Fig. 10: Deformations in Case 1 and Case 4 at the loading condition of d = 10 mm and road administrations, because of
(a) Case 1: with shear projection (installed depth Hg = 450 mm); (b) Case 4: without comfortable driving and low main-
shear projection (installed depth Hg = 450 mm) tenance costs. The social demand to
Price:
CHF 40 for Members, CHF 70 for Non-Members
www.iabse.org/publications/onlineshop