You are on page 1of 2

01/04/2002

Pipeline Induction Heat Ltd


General Conditions of Contract
The following General Conditions shall be incorporated in all Contracts made between the CONTRACTOR and another party.

GC-1 DEFINITIONS officially declared or not, changes to governmental laws, legislation or regulations or
CONTRACTOR means Pipeline Induction Heat Ltd (PIH). other causes beyond the control of the CONTRACTOR which impinge upon the
The BUYER means the Main Contractor, his Subcontractor, Employer, Owner or CONTRACTOR’S ability to carry out the works.
other party or entity entering into a contract with PIH. As soon as is practicably ascertainable after the occurrence of a FORCE MAJEURE
COMPENSATION means the lump sum prices or quantified schedule of rates set event, the CONTRACTOR shall notify the BUYER of the cause of the delay or
out within the CONTRACTOR’S bid. suspension and the period for the performance of the SERVICES shall be extended
SERVICES means the services or goods which are the subject matter of the for a period of time reasonably necessary to overcome the effects of the FORCE
Contract. MAJEURE and the CONTRACTOR shall be reimbursed for the cost of such delays.
OWNER means the end user of the site, plant equipment or pipeline into which the GC-10 CONSEQUENTIAL LOSS
SERVICES shall be incorporated. Neither party to the contract shall be liable each to the other for any consequential
GC-2 ENTIRE AGREEMENT loss arising from this contract.
These General Conditions of Contract including the Special Conditions and other GC-11 IN-COUNTRY EXPENSES
documents or drawings agreed to in writing by the CONTRACTOR shall constitute When the SERVICES are to be performed outside the U.K. the BUYER shall be
the entire agreement between the CONTRACTOR and the BUYER. No change, responsible for and indemnify the CONTRACTOR in accordance with
amendment or modification to the SERVICES shall be valid unless agreed in writing “INDEMNITY” against all in-country expenses (except as may be expressly
by the CONTRACTOR. provided in the CONTRACTOR’S bid) and including but not limited to, customs
GC-3 SCOPE OF SERVICES duties, taxes, levies, drawback cargo charges and the like charges for the import
The scope of the SERVICES shall be limited to the extent of the services set out in and/or re-export of all items associated with the SERVICES.
the CONTRACTOR’S bid. GC-12 IN-COUNTRY TAXATION
GC-4 HEALTH AND SAFETY Where the SERVICES are to be performed outside the U.K. the BUYER shall be
The CONTRACTOR operates a Health and Safety Policy in accordance with U.K. responsible for and indemnify the CONTRACTOR in accordance with
legislation, where the project requires this is supplemented with Offshore Survival “INDEMNITY” against all in-country taxation on the SERVICES in general,
Training at approved centres. The CONTRACTOR shall provide a copy of its Health personnel taxation, VAT or equivalent, withholding tax and any other taxes, levies,
and Safety Policy at the BUYER’S request. duties or fiscal demands made by any government, public, local authority, police,
GC-5 DESIGN military or similar organisation in the country in which the SERVICES are to be
Unless other wise stated in the scope of the SERVICES the CONTRACTOR shall performed.
not be responsible for the design or selection of the SERVICES nor their suitability GC-13 IN-COUNTRY TRANSPORTATION
or fitness for the purpose of the BUYER. The BUYER shall be responsible for the provision of all in-country and within job
GC-6 COMPENSATION site limits transportation of the CONTRACTOR’S plant, equipment, consumables
(a) The CONTRACTOR shall be compensated at the lumps sums, rates and prices set and personnel associated with the performance of the SERVICES.
out in the CONTRACTOR’S bid. Where the CONTRACTOR has agreed to carry GC-14 INDEMNITY
out additional or varied SERVICES then the CONTRACTOR shall receive The BUYER hereby releases and shall indemnify, defend and hold harmless
COMPENSATION in accordance with the bid for like or analogous SERVICES, or CONTRACTOR and his subsidiaries, affiliates, officers, agents, employees,
where no applicable COMPENSATION is stated, at lump sums, rates and prices that successors and assigns and authorised representatives from and against any and all
are fair and reasonable in all the circumstances. suits, actions, legal, civil or administrative proceedings, claims demands, damages,
(b)Unless stated otherwise on PIH proposal/quotation document the validity of prices liabilities, interest, legal fees, costs and expenses of whatsoever nature, including
submitted expires 30 days from the date of the proposal/quotation. without limitation those arising from death or injury to the BUYER’S employees,
In the case of multiple items the proposal/quotation is for the whole consignment to whether arising before or after completion of the SERVICES and in any manner
be manufactured and delivered as a single lot. Please note that Part Orders will directly or indirectly caused, occasioned or contributed to in whole or in part, by
attract a surcharge. reason of any act, omission, fault or negligence whether active or passive of the
GC-7 PAYMENT BUYER, OWNER, their lower tier subcontractors or suppliers or of anyone acting
The BUYER shall compensate the CONTRACTOR in the full value of the under its’ direction or control or on it’s behalf in connection with or incidental to the
CONTRACTOR’s invoice within 30 days following the end of the month in which performance of the SERVICES.
the CONTRACTOR’S invoice is dated. Should the BUYER dispute the GC-15 INSURANCES
CONTRACTOR’S invoice in whole or in part then the BUYER shall, within 7 days The CONTRACTOR shall effect and maintain for the duration of the SERVICES the
of receipt of the CONTRACTOR’S invoice notify the CONTRACTOR of the following insurances.
disputed items and values and the undisputed monies shall be paid in accordance 1) Employer Liability to the statutory limits in compliance with U.K. laws with a limit
with these General Conditions. In respect of the disputed items both the of US$ 2,000,000 for each accident and for each employee.
CONTRACTOR and BUYER agree to use their best endeavours to reach an 2) Property damage for owned or rented plant, equipment and consumables. Where loss
amicable settlement, failing which the matter shall be referred in accordance with or damage is attributable to the CONTRACTOR.
DISPUTES clause below. Following agreement of the disputed items payment shall 3) Commercial General Liability with an aggregate total limit of US$ 2,000,000.
be made as stated herein. 4) Business Automobile including owned, non owned and hired automobiles
The CONTRACTOR reserves the right and the BUYER agrees to compensate the comprehensive with limits of US$ 1,000,000 any one occurrence and in aggregate.
CONTRACTOR for payments not made by the due date at the Bank of Boston Any and all other insurances necessary or deemed necessary by the BUYER or
corporate lending rate plus 5% per annum, such compensation being due OWNER shall be effected at their expense and maintained for the full duration of the
immediately upon receipt of the CONTRACTOR’S invoice by the BUYER. No SERVICES, such insurances shall note the interests of the CONTRACTOR as a joint
deductions or set off shall be made by the BUYER from any monies due to the assured and that a cross liability clause is inserted in all liability insurances.
CONTRACTOR without the CONTRACTOR’S prior agreement in writing. All insurance policies effected by the CONTRACTOR and the BUYER or OWNER
GC-8 COMMENCEMENT AND COMPLETION shall contain a waiver of subrogation in favour of each party against the other. If so
The CONTRACTOR shall not be obliged to undertake any work or provide any requested each party shall furnish to the other Certificates of Insurance, signed by
equipment or materials until the Contract has been executed with the BUYER. the Insurers, as proof that policies have been issued and containing provisions
The BUYER shall give the CONTRACTOR in writing the minimum notice to requiring prior notice of cancellation.
commence set out in the CONTRACTOR’S bid, which shall be commensurate with GC-16 WARRANTY
the nature and geographical location of the SERVICES. In no circumstances shall The CONTRACTOR warrants to the BUYER that equipment and materials
such period of notice to commence be less than 4 weeks. supplied under this contract shall be in accordance with the BUYER’S
Where the nature of the SERVICES requires repeated mobilisations then the specification, unless otherwise stated. All workmanship and training shall be
BUYER shall give the CONTRACTOR, after the initial mobilisation, an achievable performed in accordance with recognised practices within the industry.
and agreed period of notice in writing which shall, in any event be not less than 7 CONTRACTOR warrants materials and workmanship performed against defects
days for U.K. SERVICES and 30 days for overseas SERVICES. for a period from commencement of the SERVICES to a date 12 months after
The CONTRACTOR shall make it’s best endeavours to complete within the agreed completion of the SERVICES.
timescale but shall not be responsible for any failure to do so for reasons, howsoever If at any time during the warranty period the BUYER discovers any defect in
arising, beyond it’s control including but not limited to CHANGES in the scope of materials and workmanship it shall notify the CONTRACTOR in writing. The
SERVICES and revisions to the BUYER’S construction schedules. CONTRACTOR shall within a reasonable time propose corrective actions to
The CONTRACTOR shall not be liable to compensate the BUYER for any interim remedy the defect to meet the requirements of this contract.
or final disruption or delay in the performance of the SERVICES. The CONTRACTOR’S liability shall be limited, at its discretion, to the repair or
GC-9 FORCE MAJEURE replacement of the defect. Excavation, creating access for repair or replacement and
Any delay or failure by the CONTRACTOR in performance of the SERVICES shall afterwards backfilling and re-instating including the costs of any permits, way
be excused if and to the extent caused by FORCE MAJEURE which shall include leaves, licences, inspection, testing, loss of product or production shall be borne by
but not be limited to, acts of God, strikes, fire, flood, storms, sandstorms, the BUYER. The CONTRACTOR accepts no liability for the loss of use of any
exceptionally severe weather, sabotage, terrorism or acts of war or riot, whether

GEN-CON, REV 34
01/04/2002
pipeline or equipment or product carried therein due to defects or the discovery and GC-21 ASSIGNMENT
remedy thereof in workmanship and material. The BUYER shall not assign or novate this contract without prior written notice to,
The CONTRACTOR further warrants any remedial work it performs to correct and agreement of the CONTRACTOR. Following any assignment or novation of
defects for a further period of 12 months from completion of the corrective action. this contract the BUYER shall remain responsible for the discharge in full of all
Where the scope of the SERVICES includes the provision of ready manufactured debts due to the CONTRACTOR for SERVICES under this contract.
plant or equipment the CONTRACTOR’S liability will be limited to the warranty GC-22 SECURITY
or remedy recoverable from the manufacturer. The BUYER shall at all times be responsible for the security of the
The only warranties made by the CONTRACTOR are those stated in this clause CONTRACTOR’S personnel, equipment and materials and shall indemnify the
GC-14 and all other warranties are expressly excluded. CONTRACTOR as set out in “INDEMNITY”. Where the CONTRACTOR
GC–17YEAR 2000 COMPLIANCE considers that his personnel or property are at risk from insurgence or unrest at the
Notwithstanding the provisions of Article 16 above the CONTRACTOR shall have CONTRACTOR’S first request the BUYER will take immediate steps to evacuate
no liability to the BUYER or any THIRD PARTY in respect of failure to perform the CONTRACTOR’S personnel and property to a place of safety at the BUYERS
any or all of its obligations under these General Conditions at law or in cost. When the cause for the evacuation has ceased to exist and it is safe to do so,
tort, where the breach or failure to perform is attributable directly or indirectly to the CONTRACTOR shall re-mobilise to complete the SERVICES and be paid for
an event or events arising from Year 2000.The CONTRACTOR shall not be liable such remobilisation in accordance with COMPENSATION.
for any direct, indirect loss or damages, consequential loss, loss of profits, GC-23 CONFIDENTIALITY
production or replacement of any completed work or goods supplied or any other The BUYER accepts that the CONTRACTOR’S bid and other documents as may
costs, charges or expenses howsoever arising from Year 2000. be supplied by the CONTRACTOR and the execution of the SERVICES may
GC-18 TITLE disclose confidential information, trade secrets or trade know-how and the BUYER
Where the services comprise the sale of equipment or consumables to the BUYER, agrees not to divulge such confidential matters to others or to bring them into the
then title in the SERVICES shall be vested in the CONTRACTOR until payment in public domain without the prior written agreement of the CONTRACTOR.
full, has been made by the BUYER. The CONTRACTOR shall be entitled to Photographs or promotional literature showing the CONTRACTOR’S equipment,
recover, and the BUYER agrees to surrender the SERVICES if payment is not working methods or describing the same shall not be published without consent of
made in accordance with this contract. the CONTRACTOR in writing.
The BUYER agrees not to transfer title in the SERVICES until after the transfer GC-24 NON-WAIVER
has been made from the CONTRACTOR to the BUYER. Failure by the CONTRACTOR to insist upon strict performance of any conditions
GC-19 TERMINATION of this contract, or failure or delay to exercise any rights or remedies provided
Either party may terminate this contract by written notice to the other party upon herein or by law or failure to properly notify the BUYER of any obligations under
the other party becoming insolvent or committing any act of bankruptcy. this contract shall not be deemed a waiver of any right of the CONTRACTOR to
TERMINATION BY THE CONTRACTOR insist upon any of it’s rights or remedies as to any prior or subsequent default or
In the event of any material breach or default under this contract by the BUYER operate as a waiver of any Conditions of this contract.
including but not limited to failure to commence the works or instruct mobilisation GC –25 SEVERABILITY
of the CONTRACTOR or failure to make payment by the due date the Any provision or part of this contract held to be void shall be struck out and all the
CONTRACTOR may give notice in writing of it’s intention to terminate the remaining conditions shall continue to be binding on both the CONTRACTOR
contract, specifying the grounds for termination unless such breach or default shall and the BUYER
be remedied by the BUYER within 21 days after the notice is received GC-26 DISPUTES
TERMINATION BY THE BUYER In the event of any difference or dispute arising under this contract the parties agree
Should the BUYER seek to terminate the contract for any reason whatsoever, then to use their best endeavours to reach an amicable settlement. The party raising the
the BUYER shall give notice in writing to the CONTRACTOR 21 days in advance difference or dispute shall, within 7 days of the difference or dispute coming into
of the date of termination and specifying the reasons for the termination. Where the existence give written notice to the other party detailing the nature of the difference
intention to terminate the contract arises from the alleged default of the or dispute and specifying the remedy required. Within a further 7 days each party
CONTRACTOR then the CONTRACTOR shall be given 21 days from receipt of shall nominate a senior member of management with authority to settle the
the notice to remedy the defect or to issue a commitment so to do. difference who will meet within 42 days of receipt of the written notice of the
In the event that either the BUYER or CONTRACTOR terminates the contract, difference or dispute. If the parties cannot reach an amicable settlement then
except for reason of the CONTRACTOR’S default, the CONTRACTOR shall be within 56 days from the date of the written notice of the difference or dispute, the
compensated as follows:- dispute shall be referred to mediation at a date agreed between the parties or in the
1) Immediate payment in accordance with COMPENSATION for all work properly event of their failing to agree a date fixed by the mediator. The parties will convene
completed. to agree the name of a mediator within 56 days of the date of the written notice of
2) The full cost including delivery and disposal charges of all consumables properly dispute or difference and if they cannot reach agreement within 14 days of this date
purchased for the SERVICES. a nomination shall be sought from CEDR [Centre for Effective Dispute Resolution,
3) The cancellation costs of all irrevocable purchase orders, subcontracts or other London]. If a mediated settlement cannot be achieved then the difference or dispute
Agreements entered into for the performance of the SERVICES. shall be referred to arbitration in accordance with the then existing Rules of
4) The costs of demobilisation of all the CONTRACTOR’S personnel, plant Conciliation and Arbitration of the International Chamber of Commerce. The place
equipment and residual items related to the SERVICES. of arbitration shall be Manchester, England and the proceedings and all
5) In addition to items (2)-(4) above a sum equal to 35% of the value of the documentation shall be in the English Language. Judgement upon the Arbitrator’s
unperformed SERVICES which is agreed to be a reasonable estimate of the award, which shall be final and binding may be entered in any Court having
CONTRACTOR’S overheads, administration, loss and damage due to termination jurisdiction over the assets of the debtor party.
of the contract. GC-27 NOTICES
Following termination of the contract by either party the BUYER shall bear the All notices concerning this contract shall be issued in writing to the
sole responsibility for the security and safekeeping of the CONTRACTOR’S CONTRACTOR at Pipeline Induction Heat Ltd, The Pipeline Centre, Farrington
property until safely demobilised from the country where the SERVICES were to Road, Rossendale Road Industrial Estate, Burnley, Lancashire BB11 5SW,
be performed. England, and unless stated otherwise to the BUYER at it’s registered office.
No termination of this contract shall relieve the BUYER of his obligations that GC-28 GOVERNING LAW
have accrued prior to termination. These Conditions of Contract shall be governed and interpreted in accordance with
GC-20 SUSPENSION the laws of England and Wales. The language of the Contract shall be the English
Should the BUYER suspend the performance of the SERVICES for any reason Language.
whatsoever the CONTRACTOR shall be compensated for the costs of the
suspension period as follows:-
1) Standby rates for personnel and equipment in accordance with COMPENSATION
for the period from cessation of the SERVICES until recommencement of the
SERVICES.
2) Demobilisation and re-mobilisation charges in accordance with COMPENSATION
schedule.
3) All other costs incurred by the CONTRACTOR that flow from the suspension of
the SERVICES.
4) Should the period of suspension exceed 90 days then either party may terminate the
contract by giving the other party 21 days written notice. Should the contract be
terminated for this reason the CONTRACTOR shall be compensated in accordance
with Article GC15 “Termination by the BUYER” (1) -(7).
GEN-CON, REV 34

You might also like