Professional Documents
Culture Documents
1 INTRODUCTION | 3
6 ANNEX | 20
Introduction
India’s renewable energy development has become
a symbol of the country’s ability to rapidly adopt new
technology and a focal point of India’s efforts to avoid
greenhouse gas emissions while meeting its growing
energy needs.
Key market
trends
In the first half of 2019, India continues to be the second
largest market for corporate PPAs, with a global share of
7.4% (440 MW installed). However, estimates suggest that
the annual corporate PPA renewable addition in India in
2019 will be about 30-35% lower than installations in 2018.
16
14
Annual capacity addition (GW)
12
10
17
18
10
11
12
13
14
15
16
19
09
20
20
20
20
20
20
20
20
20
20
20
H1
Global India
Source: Bloomberg New Energy Finance, JMK Research
According to Bloomberg New led by the withdrawal of open UTTAR PRADESH AND
Energy Finance, India was the access waivers for new third- HARYANA LEAD NEW
second largest growth market for party PPAs in most states. INSTALLATIONS AND
corporate renewable PPAs after
• Leadership of information APPROVALS
the US in 2018, with an addition
of 1.6 GW of capacity. In the first technology (IT), automotive,
electrical manufacturing, Between April 2017 and March
half of 2019, India continues to
construction/infrastructure 2018, companies installed 1,855
be the second largest market
and metal companies MW of third-party sale and open
for corporate PPAs, with a global
in adopting corporate access solar and wind projects
share of 7.4% (440 MW installed).
renewable PPAs. in India. Nearly 81% of these
However, estimates suggest
installations were in Karnataka
that the annual corporate PPA
• Increased participation as the state had offered a
renewable addition in India in 2019
of specialized national 10-year waiver on most open
will be about 30-35% lower than
developers in acquiring access charges for projects
installations in 2018.
key corporate contracts commissioned until 31 March
Several key market trends have as regional players cede 2018. After the government
affected the growth over the ground. withdrew these exemptions, the
past six months. These are: market contracted significantly,
• Growth in the rooftop solar as shown in figure 2.
• The emergence of two market for PPA projects in
northern states – Haryana India continuing to dominate
and Uttar Pradesh – as growth in projects based on
important markets, with captive installations.
more than 1 GW of group
• Developers and corporate
captive solar projects
customers aligning project
approved.
schedules to avoid paying
• The transition of the Indian a safeguard duty on solar
corporate renewable PPA panels.
market from predominantly
We examine each of these
third-party PPA models to
market trends in more detail
group captive PPA models,
below.
FIGURE 2: Third-party sale and open access project installations across different states (MW)
Others states
200
1400
1200
150
1000
Capacity (MW)
Capacity (MW)
800
100
600
400
50
200
0 0 es ra
at
sh
tra
ng st
es a
du il
a
Na am
an
an
ad hy
ha
Be We
ak
ar
ad h
de
h
al
h
h
Pr And
Pr ad
g
ry
st
T
uj
as
at
an
ra
G
Ha
ja
M
rn
ar
lP
Ra
l
Te
Ka
ah
ha
M
ac
m
Hi
Solar – FY2018 (April 2017 – March 2018) Wind – FY2018 (April 2017 – March 2018)
Solar – FY2019 (April 2018 – March 2019) Wind – FY2019 (April 2018 – March 2019)
Between April 2018 and March In March 2019, Uttar Pradesh If the consumer itself is an RPO
2019, companies added approved 340 MW of projects obligated entity, then the solar
494 MW of capacity through under the group captive model power generated counts as part
corporate renewable PPAs and on a first-come, first-served of the fulfillment of its own RPO,
under the open access route. basis. The process included while excess power generated
Of this, 158 MW was from solar submission of an application to beyond the consumer’s own
projects and 336 MW from the power distribution company RPO obligation counts as part of
wind, highlighting a significant (DISCOM) for approval. Approval the DISCOM’s RPO.
reduction in solar installations has typically depended on the
compared to the previous year. grid’s technical ability to connect This is a new approach for
power generating capacity at the DISCOMs to try and fulfil their
However, the north Indian states local sub-station. RPO requirements without
of Haryana and Uttar Pradesh entering into public procurement
now show signs of growth A key reason for Haryana and of power on their own. Such an
recovery. In July 2019, the state Uttar Pradesh DISCOMs to fast approach can help DISCOMs
power transmission company, track permits for group captive meet their RPOs at little or no
Haryana Vidyut Prasaran Nigam solar projects is to use them to cost while significantly speeding
(HVPNL) approved about 550 fulfill their renewable purchase up corporate renewable open
MW of projects under the group obligation (RPO). Haryana, under access capacity addition. Other
captive model. The state had its Solar Power Policy 2016,2 states emulating this approach
received applications for more waived all charges for private will be a key trend to watch for in
than 1,916 MW.1 renewable projects subject 2020.
to the condition that the solar
power will be utilized within
the state and will be counted
towards the RPO of the DISCOM.
1
http://hareda.gov.in/sites/default/files/2019-02/Regarding-proposal-submitted-for-approval.pdf
2
Source: Haryana Renewable Energy Development Agency (HAREDA)
8
Tariff (INR/kWh)
3
na
ra
at
a
k
sh
ad
es
es
es
ar
ht
ta
ya
ga
th
di
ad
ad
ad
il N
uj
as
na
s
r
O
G
Ha
ja
Pr
Pr
Pr
la
ar
r
m
Ra
Ka
Te
ah
Ta
a
ta
hr
hy
M
Ut
ad
An
M
Third party sale Group captive
5
Analysis by CleanMax Solar.
50
45
40
35
Capacity installed (MW)
Honda
CISCO
ACC
30
Bangalore Airport
Oracle, Mindtree
GE
25
Others: Adobe,
Roha Dyechem
Others: Spicer, Volvo
Qualcomm
20
Narayana Hospitals
Others
Adamas
Manipal Healthcare
Kennametal
MSL Ltd.
ABB
SKF
15
United Brewery
KFIL
Others
Honeywell
Astrazencea
Grindwell
BASF
10
Others
Carlsberg
Trust
Sobha
0
ra &
tu n/
IT
al
re
al
al
al
iv
ve od
ic
ci
uc io
ge
ca
re
et
ic
ot
er
tr
tr ct
be Fo
lth
m
M
m
ec
m
as ru
he
to
ea
om
El
fr st
Au
C
H
in on
C
C
FIGURE 5: Power supplier segmentation for open access solar markets in India
As of 31 Mar. 2017 As of 31 Mar. 2019
100% = 1,110 MW 100% = 2,910 MW
SHIFT FROM REGIONAL In the last two years, the open as well as access to financing
PLAYERS TO SPECIALIZED access PPA solar market has sources with a lower cost of
DEVELOPERS grown more than 2.5 times to capital.
2.9 GW. With the growth of the
open access market, large-sized In the last two years, the shares
Mid-sized regional developers of independent power producers
independent power producers
have been responsible for and specialized developers have
with a national presence, such
structuring most early open increased while the shares of
as ReNew and Avaada, and other
access renewable PPA projects regional players have decreased
specialized project developers,
as they have had easier access to (see figure 5).
such as CleanMax, Amplus
land and have been better placed
and AMP Solar, have begun to
to deal with local DISCOMs and Figure 6 highlights projects
considerably increase their market
regulators. Regional developers developed by independent
share. These national developers
include companies such as Ujaas power producers and specialized
have the competitive advantage of
(focus on Madhya Pradesh), Enrich developers offering PPAs under
access to large corporate buyers
(Maharashtra) and Rays Experts the group captive model.
(Rajasthan).
FIGURE 6: Installations and project pipeline for key developers under open access and group captive models,
as of 31 August 2019
900
800
700
600
Capacity (MW)
500
400
300
200
100
0
ew
s
ax
da
r
er nt
rts r
la
fra r
pe e
u
e
M
En ra
Ex Pow
pl
So
aa
w
gy
an
Am
Re
n Vib
Po
Av
In
le
s
AM
s
y
y
Ra
Ra
e
re
G
Commissioned Pipeline
Source: JMK Research
FIGURE 7: Capacities planned by rooftop solar focused companies under the group captive model, as of 31 August
2019
250
200
Capacity (MW)
150
100
50
0
r tn r th
ce
re
tri lis
ab SE
u
O So
ur
G
Pa ou
er
um
s
ns
le
o
F
Su
ns
Su
w
ne
re
Source: JMK Research
3
Onsite installations include open ground spaces, roofs, parking lots or any other area within the premises.
2000 40%
37.5%
1800 35%
34.3%
1600
689 30%
1400
239 25%
Capacity (MW)
1200
1000 20%
392
17.1%
800 15%
600 1157 1148
10%
400 750
5%
200
0 0%
Until FY 2017 FY 2018 FY 2019
Policy and
regulatory
update
As the corporate renewable PPA market in India is closely
linked to the evolving policy and regulatory environment
at the state level, tracking such changes becomes
important for both renewable electricity buyers and
sellers.
PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 13
Policy and regulatory update
Over the past six months, we mechanisms supporting the These regulations are determined
have seen that the government corporate renewable PPA market primarily at the state level
has withdrawn several in India, we outline the relevant under a framework provided at
exemptions for open access changes in these regulations the national level. Changes in
charges and banking provisions. during the last year below. these regulations can materially
While some of these changes affect the viability of renewable
may negatively impact financial procurement from off-site
viability for new installations in projects. We detail state-level
affected states, these changes
OPEN ACCESS changes in these regulations
do bring open access renewable REGULATIONS below.
power up to par with regulations Open access regulations
for traditional sources, removing We provide a comparison of
determine the charges and open access exemptions for
uncertainty arising from short- procedures for using the public
term support mechanisms, renewable power procurement
grid to wheel power from an provided by various states and
thereby making cash-flow offsite renewable power plant
projections for renewable how it has changed in the last
to the premises of a corporate year in the Annex.
contracts more predictable and buyer.
stable. As open access and
net-metering are key regulatory
The policy introduced in January 2019 withdraws the exemptions for electricity duty, CSS and wheeling losses4
for projects selling renewable power to private consumers. According to the previous policy, these exemptions
Andhra were available for projects built until March 2020.
Pradesh
The new policy has also capped the purchase of unused banked energy at 10% of total banked energy per year
and reduced the average power purchase cost (APPC) compensation from 100% to 50%.
Haryana amended its solar policy in March 2019. The most significant change in the policy has been the
withdrawal of exemptions from wheeling and transmission charges, CSS and additional surcharges for third-
Haryana party sales of power. The previous policy waived these charges for 10 years. However, the new policy restricts
the eligibility of these exemptions to only captive/group captive solar projects, for which companies acquired
land and incurred capital expenditures of at least INR 10 million/MW before 13 February 2019.
For open access renewable plants commissioned before 31 March 2018, Karnataka had waived
Pulp & paper
transmission, wheeling, banking and CSS charges for 10 years. The state government decided to discontinue
Karnataka
these waivers for plants commissioned after 31 March 2018 despite several requests for extension.
In July 2019, Maharashtra issued the first amendment to the distribution open access regulations and
transmission open access regulations. As per this amendment, it reduced the banking period for open
access projects from 1 year to 1 month. The amendment further restricts banking by allowing withdrawal
Maharashtra
of energy banked during peak time of day (TOD) slots at off-peak TOD slots and not vice-versa. It has also
capped the monthly unused banked power at 10% of total generation and increased transmission charges
for all open access transactions.
In Rajasthan, the government had waived CSS for all solar plants commissioned between April 2014 and
March 2019. However, it did not extend the exemptions beyond 31 March 2019. For third-party sale/open
Rajasthan y access projects, the government has changed the banking period from an annual basis to a monthly basis.
Moreover, only 10% of banked energy is now eligible for payment at 60% of energy charges applicable under
the notified industrial tariff.
In September 2019, Uttar Pradesh introduced its Captive and Renewable Energy Generating Plants
Regulations, 2019, under which it gives a 50% exemption on wheeling and transmission charges for captive
Uttar Pradesh
and third-party sale renewable projects. There is also a 100% waiver on transmission for interstate sales and
a 100% exemption of state CSS for interstate sales of power for captive/third-party use.
4
Wheeling losses or power distribution losses, pre-determined by regulators and applicable to power generating plants.
Rajasthan reduced its energy banking period for net metering from 1 year to 1 month for commercial and
Rajasthan industrial customers. This change has raised questions about the viability of several projects, particularly those
with seasonal power demand.
In March 2019, the Tamil Nadu Electricity Regulatory Commission (TNERC) allowed net-metering connections
only for the low tension (LT) consumer category (typically customers with small connected loads), thereby
Tamil Nadu
restricting net-metering for large customers. The 2013 regulations will continue to govern existing consumers
using the net metering scheme.
In Uttar Pradesh, under new regulations issued in January 2019, net-metering is no longer available for
commercial, industrial and public buildings. These customers can now only opt for gross metering. Under
Uttar Pradesh gross metering, excess electricity for C&I customers will receive compensation at a fixed price of INR 2/unit,
which is much less than what they would receive under net-metering and, in fact, lower than the average
power purchase cost borne by the state for conventional sources of power.
Overall, the removal of open access charges and net metering benefits across several states indicates
that regulators and DISCOMs are pushing back at offering incentives for renewable power indefinitely. The
increased viability of solar projects due to continued cost reductions should help counteract part of the
negative impact of these policy and regulatory changes.
Risks and
challenges
for corporate
renewable PPAs
Even though India is the second largest growth market
for corporate renewable PPAs, its current growth is far
lower than its potential.
PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 16
Policy and regulatory update
Most risks and challenges banking. This would lead to as Maharashtra, Rajasthan and
hampering its growth pertain to developers not being able to sell Telangana.
policy uncertainty and limited a part of the generated power,
cooperation with DISCOMs. increasing power tariffs. Similar ROLLBACK OF FAVORABLE
These challenges, unless changes in other states will likely NET-METERING PROVISIONS
addressed, can imperil the to lead to an overall increase in
It took several years for the
long-term growth of the market renewable power tariffs offered
central government to get all
and its associated value chain. to corporate buyers.
states to offer net-metering
The following highlights the key
to promote rooftop solar
challenges that have emerged
installations in the country. Policy
over the past six months.
POOR PERFORMANCE ON changes restricting net-metering
DISCOM APPROVALS for corporate customers in Uttar
Pradesh and Tamil Nadu are
ROLLBACK OF FAVORABLE Despite progress in Uttar a major setback in that effort.
BANKING PROVISIONS Pradesh and Haryana, getting DISCOM incentives under phase
an open access approval from II of the national rooftop solar
Since there is a wide seasonal DISCOMs has been a key scheme may help to halt this
variation in power generation challenge for the corporate trend.
from renewable sources, the renewable PPA market. The
annual banking of power is reason often cited for denial
crucial to improving project of permission is the technical
bankability. Annual banking helps inability of the local substation
consumers use the excess to allow drawing of power. It
power generated during peak is often difficult to ascertain
seasons in non-peak seasons. such technical limitations.
Maharashtra and Rajasthan Developers are increasingly
have recently shifted to monthly facing challenges in receiving
banking instead of annual any approvals in states such
Outlook for
corporate
renewable PPAs
PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 18
Outlook for corporate renewable PPAs
FIGURE 9: Expected project capacity under the group captive model by state
800
700
600
Capacity (MW)
500
400
300
200
100
0
a
ra
u
an
ad
s
es
ht
ga
de
ry
ad
il N
as
tis
ra
Ha
Pr
ar
m
at
rP
ah
Ta
ra
hh
ta
dh
C
Ut
An
Source: JMK Research
As shown in figure 9, India has a without entering into a PPA market inefficiencies that
development pipeline of almost agreement. Currently this is currently influence how
2 GW for corporate renewable still a work in progress and tariffs are set and reduce
PPAs. A small part of this will as per the last update, in May the unpredictability around
come online in the current 2019, the Central Electricity cross-subsidization of tariffs.
financial year (April 2019 – March Regulatory Commission Most significantly, there may
2020) – leading to lower capacity (CERC) has ordered the be a proposal in the new
addition this year as compared to Indian Energy Exchange tariff policy or an amended
last year. (IEX) to seek comments and Electricity Act to remove
feedback on GTAM from all cross-subsidy charges
However, we do expect this stakeholders, after which it levied on private renewable
pipeline to expand and a plans to approve it. energy procurement.
significant proportion of this to
be installed in the next financial • New power tariff policy We would like to reiterate the
year (April 2020 to March 2021), and amendments to the importance of the March 2019
resulting in a bounce back. Electricity Act: The Union amendment to the Haryana
Cabinet is considering a Solar Policy that has opened the
The Indian government is new power tariff policy door for DISCOMs to meet their
considering several new policy for approval. It is also RPOs by leveraging corporate
initiatives that may positively considering reforms focused renewable PPAs. This is a novel
impact the corporate renewable on empowering consumers approach that can bring more
PPA market: by giving them the right states and DISCOMs on board
to choose their power to pro-actively support such
• Green Term Ahead Market
supplier. Additionally, the projects and would remove a
(GTAM): GTAM is an initiative
government is considering key bottleneck for growth. Other
planned by the government
a direct transfer of benefits states may explore this option as
that would allow spot
from the government to the well.
trading of renewable energy
bank accounts of customers
through power exchanges.
eligible for subsidies. This
This trading window would
should help eliminate the
let corporate consumers
maze of subsidies and
buy renewable power
Annex
PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 20
TABLE 1: Open access waivers for solar projects across states, as of 31 August 2019
Waivers for solar open access projects applicable Changes enforced between April 2018 and August
States
until 31 March 2018 2019
• CSS waiver for five years from commercial • Wheeling and transmission charge exemptions
operation date (COD) limited to only interstate supply of power; no
exemptions are applicable for intrastate projects
• Transmission and wheeling charge waiver for
captive model/third-party sale within the state • Withdrawal of CSS waiver, distribution losses and
Andhra Pradesh all other exemptions; purchase of unused banked
• Exemption from distribution losses for projects energy capped at 10% of total banked energy
injecting at 33kV or below during a year
• Transmission and wheeling charges for renewable • Transmission and wheeling charges for renewable
energy plants to be levied at 2% of energy energy plants to be levied at 2% of energy
Punjab injected for FY 2018-19. injected extended to FY 2019-20.
• CSS waived for all solar plants commissioned • Withdrawal of exemptions from 31 March 2019
Rajasthan between April 2014 and March 2019 onwards
• No additional surcharge
Gujarat
• Incentives apply for 25 years from COD for
projects built by March 2020
PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 24
OTHER PARTNER INITIATIVES
PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 25
World Business Council
for Sustainable Development
WBCSD
Maison de la Paix
Chemin Eugene-Rigot 2B
CP 2075, 1211 Geneva 1
Switzerland
WBCSD India
4th Floor, WorldMark 2, Aerocity
New Delhi, 110037, India
www.wbcsd.org