You are on page 1of 26

India Corporate

Renewable PPA Forum


PPAs in India:
Market & Policy Update
December 2019
Contents

1 INTRODUCTION | 3

2 KEY MARKET TRENDS | 5

3 POLICY AND REGULATORY UPDATE | 13

4 RISKS AND CHALLENGES FOR CORPORATE


RENEWABLE PPAS | 16

5 OUTLOOK FOR CORPORATE RENEWABLE PPAS | 18

6 ANNEX | 20

PPAs in India: Market & Policy Update December 2019 2


1

Introduction
India’s renewable energy development has become
a symbol of the country’s ability to rapidly adopt new
technology and a focal point of India’s efforts to avoid
greenhouse gas emissions while meeting its growing
energy needs.

PPAs in India: Market & Policy Update December 2019 3


Introduction

Procuring renewable power We combined the learning In this second update, we


for their operations helps from this work with research elaborate on six recent market
businesses manage electricity on the regulatory environment trends. While a couple of these
expenditure and increase and market conditions in trends are secular and based
visibility over future costs, while India to produce the WBCSD on long-term renewable power
contributing to a renewable report: Accelerating corporate procurement fundamentals,
energy and/or carbon reduction procurement of renewable most are business reactions
target. energy in India (June 2018). to policy changes. This report
then goes on to explain the
One option for companies to Because the Indian power market policy direction based on recent
purchase renewable electricity is constantly evolving, we are changes at the state and central
is a corporate renewable producing twice yearly market government level. It concludes
power purchase agreement and policy reviews to keep our with an outlook for 2020.
(PPA), which is a contract members and other corporate
between the corporate buyer(s) customers informed of the latest This report assumes an
and the power producer developments. understanding of terms and
(developer, independent power concepts relating to corporate
producer, investor) to purchase We published our first review, renewable sourcing in India.
renewable electricity at a pre- Corporate Renewable PPAs For further information, please
agreed price for a pre-agreed in India – a market and policy see the glossary at the end
period. The contract contains update for 2019 in June. It of this report and refer to the
the commercial terms of the concluded that corporate WBCSD’s Accelerating corporate
electricity sale: contract length, renewable PPAs in India procurement of renewable
point of delivery, delivery flourished in 2017-18 due energy in India report (June
date/times, volume, price and to waivers on open access 2018).
product. Corporate renewable charges offered by states such
power purchase agreements as Karnataka, Andhra Pradesh
are an important instrument for and Telangana. The update also
accelerating renewable energy concluded that as the window
deployment. of opportunity to avail these
waivers ended in these states,
To increase the adoption of the extension of such waivers
corporate renewable PPAs in was equally unlikely in other
India, members of the World states across India.
Business Council for Sustainable
Development (WBCSD) formed This report is the second and
the India Corporate Renewable final update for 2019. It tracks
PPA Forum in 2017 to exchange policy changes, analyzes new
practical knowledge on the business models and explores
effective implementation of future trends that are likely to
corporate renewable PPAs for define the growth of corporate
both rooftop and utility-scale renewable PPAs in India.
renewable energy installations in
India.

PPAs in India: Market & Policy Update December 2019 4


2

Key market
trends
In the first half of 2019, India continues to be the second
largest market for corporate PPAs, with a global share of
7.4% (440 MW installed). However, estimates suggest that
the annual corporate PPA renewable addition in India in
2019 will be about 30-35% lower than installations in 2018.

PPAs in India: Market & Policy Update December 2019 5


Key market trends

FIGURE 1: Annual global corporate PPA market size

16

14
Annual capacity addition (GW)

12

10

17

18
10

11

12

13

14

15

16

19
09

20

20
20

20

20

20

20

20

20

20
20

H1
Global India
Source: Bloomberg New Energy Finance, JMK Research

According to Bloomberg New led by the withdrawal of open UTTAR PRADESH AND
Energy Finance, India was the access waivers for new third- HARYANA LEAD NEW
second largest growth market for party PPAs in most states. INSTALLATIONS AND
corporate renewable PPAs after
• Leadership of information APPROVALS
the US in 2018, with an addition
of 1.6 GW of capacity. In the first technology (IT), automotive,
electrical manufacturing, Between April 2017 and March
half of 2019, India continues to
construction/infrastructure 2018, companies installed 1,855
be the second largest market
and metal companies MW of third-party sale and open
for corporate PPAs, with a global
in adopting corporate access solar and wind projects
share of 7.4% (440 MW installed).
renewable PPAs. in India. Nearly 81% of these
However, estimates suggest
installations were in Karnataka
that the annual corporate PPA
• Increased participation as the state had offered a
renewable addition in India in 2019
of specialized national 10-year waiver on most open
will be about 30-35% lower than
developers in acquiring access charges for projects
installations in 2018.
key corporate contracts commissioned until 31 March
Several key market trends have as regional players cede 2018. After the government
affected the growth over the ground. withdrew these exemptions, the
past six months. These are: market contracted significantly,
• Growth in the rooftop solar as shown in figure 2.
• The emergence of two market for PPA projects in
northern states – Haryana India continuing to dominate
and Uttar Pradesh – as growth in projects based on
important markets, with captive installations.
more than 1 GW of group
• Developers and corporate
captive solar projects
customers aligning project
approved.
schedules to avoid paying
• The transition of the Indian a safeguard duty on solar
corporate renewable PPA panels.
market from predominantly
We examine each of these
third-party PPA models to
market trends in more detail
group captive PPA models,
below.

PPAs in India: Market & Policy Update December 2019 6


Key market trends

FIGURE 2: Third-party sale and open access project installations across different states (MW)
Others states

200
1400

1200
150
1000
Capacity (MW)

Capacity (MW)
800
100
600

400
50
200

0 0 es ra

at

sh

tra

ng st

es a

du il
a

Na am
an

an

ad hy
ha

Be We
ak

ar
ad h

de
h

al

h
h
Pr And

Pr ad
g

ry
st

T
uj

as
at

an
ra
G

Ha
ja

M
rn

ar
lP

Ra

l
Te
Ka

ah
ha

M
ac
m
Hi

Solar – FY2018 (April 2017 – March 2018) Wind – FY2018 (April 2017 – March 2018)
Solar – FY2019 (April 2018 – March 2019) Wind – FY2019 (April 2018 – March 2019)

Source: JMK Research


Note: Analysis includes data for captive power plants availing of open access as the split of data specific to corporate PPAs is not available.

Between April 2018 and March In March 2019, Uttar Pradesh If the consumer itself is an RPO
2019, companies added approved 340 MW of projects obligated entity, then the solar
494 MW of capacity through under the group captive model power generated counts as part
corporate renewable PPAs and on a first-come, first-served of the fulfillment of its own RPO,
under the open access route. basis. The process included while excess power generated
Of this, 158 MW was from solar submission of an application to beyond the consumer’s own
projects and 336 MW from the power distribution company RPO obligation counts as part of
wind, highlighting a significant (DISCOM) for approval. Approval the DISCOM’s RPO.
reduction in solar installations has typically depended on the
compared to the previous year. grid’s technical ability to connect This is a new approach for
power generating capacity at the DISCOMs to try and fulfil their
However, the north Indian states local sub-station. RPO requirements without
of Haryana and Uttar Pradesh entering into public procurement
now show signs of growth A key reason for Haryana and of power on their own. Such an
recovery. In July 2019, the state Uttar Pradesh DISCOMs to fast approach can help DISCOMs
power transmission company, track permits for group captive meet their RPOs at little or no
Haryana Vidyut Prasaran Nigam solar projects is to use them to cost while significantly speeding
(HVPNL) approved about 550 fulfill their renewable purchase up corporate renewable open
MW of projects under the group obligation (RPO). Haryana, under access capacity addition. Other
captive model. The state had its Solar Power Policy 2016,2 states emulating this approach
received applications for more waived all charges for private will be a key trend to watch for in
than 1,916 MW.1 renewable projects subject 2020.
to the condition that the solar
power will be utilized within
the state and will be counted
towards the RPO of the DISCOM.

1
http://hareda.gov.in/sites/default/files/2019-02/Regarding-proposal-submitted-for-approval.pdf
2
Source: Haryana Renewable Energy Development Agency (HAREDA)

PPAs in India: Market & Policy Update December 2019 7


Key market trends

FIGURE 3: Landed cost of solar power for industrial consumers

8
Tariff (INR/kWh)

3
na

ra

at

a
k

sh
ad

es

es

es

ar
ht

ta
ya

ga

th

di
ad

ad

ad
il N

uj
as

na

s
r

O
G
Ha

ja
Pr

Pr

Pr
la
ar

r
m

Ra
Ka

Te
ah
Ta

a
ta

hr

hy
M
Ut

ad
An

M
Third party sale Group captive

Source: JMK Research


Assumptions: (1) Solar power purchase cost is fixed at INR 4.00/kWh across states to highlight changes due to open access charges;
actual tariffs will vary. (2) The landed cost of solar is calculated for industrial consumers connected at 33 kV voltage.

SHIFT FROM THIRD- The CSS and AS waiver is a key


PARTY PPA MODELS driver for power consumers to
TO GROUP CAPTIVE opt for group captive models.
MODELS Companies have extensively
adopted the group captive
There has been a shift from model for wind power projects
the dominance of third-party in the past but the model had
PPAs over the last two years a relatively small share in solar
to group captive PPAs. This power procurement until 2018.
shift has mainly been due to
the withdrawal of open access After most states removed
waivers for new third-party PPAs CSS and AS waivers for third-
across multiple states. party sale projects, the landed
cost of solar for third-party sale
The group captive project projects for industrial consumers
structure continues to offer the at 33 kV levels increased more
advantage of a complete waiver significantly than under the
of the cross-subsidy surcharge group captive model. In only a
(CSS) and additional surcharge few states, such as Tamil Nadu,
(AS). These charges often form a Uttar Pradesh, Telangana and
significant portion of the overall Odisha, which continue to offer
open access charges and are waivers on third-party sale
less predictable than technical projects, is the cost difference
charges such as those for smaller (see figure 3).
transmission and wheeling of
power.

5
Analysis by CleanMax Solar.

PPAs in India: Market & Policy Update December 2019 8


Key market trends

FIGURE 4: Businesses procuring renewable power through corporate PPAs

50

45

40

35
Capacity installed (MW)

Honda
CISCO

ACC
30

Bangalore Airport
Oracle, Mindtree

GE

25
Others: Adobe,

Roha Dyechem
Others: Spicer, Volvo
Qualcomm

20

Narayana Hospitals
Others
Adamas

Manipal Healthcare
Kennametal

MSL Ltd.
ABB
SKF

15

United Brewery
KFIL
Others
Honeywell

Astrazencea

Grindwell
BASF
10

Others
Carlsberg

Trust
Sobha

0
ra &
tu n/
IT

al

re

al
al

al
iv

ve od
ic

ci
uc io

ge

ca
re

et

ic
ot

er
tr

tr ct

be Fo

lth

m
M
m

ec

m
as ru

he
to

ea

om
El

fr st
Au

C
H
in on

C
C

Source: JMK Research


Note: Data is not comprehensive but as a subset it is representative of the key customer categories in the Indian market.

IT, AUTOMOTIVE, As shown in figure 4, IT,


ELECTRICAL automotive, electrical
MANUFACTURING, manufacturing and construction/
CONSTRUCTION/ infrastructure and metal
companies were the leading
INFRASTRUCTURE AND
consumer segments procuring
METAL COMPANIES power through the open access
LEAD RENEWABLE route in the last two years.
ADOPTION
Together these five segments
In India, commercial and have procured more than 227
industrial consumers have MW of renewable power through
been increasingly procuring the third-party sale or group
renewable power through captive model. Data in the chart
the open access route. The below is not comprehensive but
key reasons are corporate points to a significant share of
decarbonization targets and cost renewable procurement coming
savings because of lower cost of from international companies.
renewable power vis-à-vis other This could be due to greater
sources. awareness and internal green
mandates that these companies
need to comply with for India
operations as well.

PPAs in India: Market & Policy Update December 2019 9


Key market trends

FIGURE 5: Power supplier segmentation for open access solar markets in India
As of 31 Mar. 2017 As of 31 Mar. 2019
100% = 1,110 MW 100% = 2,910 MW

Regional players Independent power producers Specialized developers Others

Source: JMK Research


Note: This chart includes only open access PPA solar projects, not captive projects.

SHIFT FROM REGIONAL In the last two years, the open as well as access to financing
PLAYERS TO SPECIALIZED access PPA solar market has sources with a lower cost of
DEVELOPERS grown more than 2.5 times to capital.
2.9 GW. With the growth of the
open access market, large-sized In the last two years, the shares
Mid-sized regional developers of independent power producers
independent power producers
have been responsible for and specialized developers have
with a national presence, such
structuring most early open increased while the shares of
as ReNew and Avaada, and other
access renewable PPA projects regional players have decreased
specialized project developers,
as they have had easier access to (see figure 5).
such as CleanMax, Amplus
land and have been better placed
and AMP Solar, have begun to
to deal with local DISCOMs and Figure 6 highlights projects
considerably increase their market
regulators. Regional developers developed by independent
share. These national developers
include companies such as Ujaas power producers and specialized
have the competitive advantage of
(focus on Madhya Pradesh), Enrich developers offering PPAs under
access to large corporate buyers
(Maharashtra) and Rays Experts the group captive model.
(Rajasthan).

FIGURE 6: Installations and project pipeline for key developers under open access and group captive models,
as of 31 August 2019

900

800

700

600
Capacity (MW)

500

400

300

200

100

0
ew

s
ax
da

r
er nt
rts r

la

fra r
pe e

u
e
M
En ra
Ex Pow

pl
So
aa

w
gy

an

Am
Re
n Vib

Po
Av

In
le
s

AM

s
y

y
Ra

Ra
e
re
G

Commissioned Pipeline
Source: JMK Research

PPAs in India: Market & Policy Update December 2019 10


Key market trends

FIGURE 7: Capacities planned by rooftop solar focused companies under the group captive model, as of 31 August
2019
250

200
Capacity (MW)

150

100

50

0
r tn r th

ce

re

tri lis

ab SE
u

O So
ur

G
Pa ou
er

um

s
ns

le
o
F

Su
ns
Su

w
ne
re
Source: JMK Research

GROWTH IN THE In FY 2019, growth in OPEX manage these assets through


ROOFTOP SOLAR projects reached 109%, while a third-party player. Only a few
MARKET FOR PPA projects set up with own cash-rich companies, such as
PROJECTS CONTINUES investments (CAPEX model) ITC, PepsiCo and The Coca-
reached 60%. The reasons for Cola Company, are building
TO DOMINATE
such growth in OPEX installations these assets on the CAPEX
include: model.
As of 31 March 2019, projects
setup under the OPEX model • The market has evolved • Most government/public
constituted more than 37% in the last few years and sector solar installations are
of cumulative rooftop3 solar lenders, developers and end based on the OPEX model
installations in India. Under the consumers are much more only. In FY 2019 (April 2018
OPEX model, a third-party project aware of the benefits of this – March 2019), this segment
developer finances and installs model. grew by 54% on a year-on-
the solar system on consumer year basis.
premises and sells power • The OPEX model is a
output under a long-term PPA preferred choice for a However, in the next two to three
agreement. lot of companies that do years, OPEX installations might
not want to invest in non- not see the same growth because
core operations. It’s also of market saturation of good
convenient for them to creditworthy commercial and
industrial (C&I) companies.

3
Onsite installations include open ground spaces, roofs, parking lots or any other area within the premises.

PPAs in India: Market & Policy Update December 2019 11


FIGURE 8: OPEX model-based installations in India

2000 40%
37.5%
1800 35%
34.3%
1600
689 30%
1400
239 25%
Capacity (MW)

1200

1000 20%
392
17.1%
800 15%
600 1157 1148
10%
400 750
5%
200

0 0%
Until FY 2017 FY 2018 FY 2019

CAPEX OPEX Share of OPEX

Source: Bridge to India, Rooftop Solar Map

DEVELOPERS Despite the withdrawal of open Overall, we see movement


AND CORPORATE access exemptions by various towards formalization and
CUSTOMERS ARE state agencies, this market is consolidation of the corporate
ALIGNING PROJECT adding significant capacity. renewable PPA market in India.
Established independent power
SCHEDULES TO However, as the market is still
producers (IPPs) have become
AVOID PAYMENT OF active in setting up open access grappling with a constantly
SAFEGUARD DUTY renewable projects. Two clear changing policy and regulatory
ON SOLAR PANELS advantages for these IPPs in environment, the section below
opting for corporate renewable highlights some of the recent
In 2018, the government imposed PPAs are: less dependency changes and the challenges that
a safeguard duty for two years on DISCOMs and better PPA the market faces due to these
for most imported solar modules. contract prices compared to changes.
For the first year, from July 2018 highly competitive tariff-based
to July 2019, the government auctions under central and state
fixed the duty at 25%, reducing schemes.
it subsequently by 5% every six
months for the next year, before
its scheduled expiry in July 2020.

To avoid paying the duties, many


developers have planned to set
up new projects that align their
module procurement with the
removal of safeguard duties.

PPAs in India: Market & Policy Update December 2019 12


3

Policy and
regulatory
update
As the corporate renewable PPA market in India is closely
linked to the evolving policy and regulatory environment
at the state level, tracking such changes becomes
important for both renewable electricity buyers and
sellers.

PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 13
Policy and regulatory update

Over the past six months, we mechanisms supporting the These regulations are determined
have seen that the government corporate renewable PPA market primarily at the state level
has withdrawn several in India, we outline the relevant under a framework provided at
exemptions for open access changes in these regulations the national level. Changes in
charges and banking provisions. during the last year below. these regulations can materially
While some of these changes affect the viability of renewable
may negatively impact financial procurement from off-site
viability for new installations in projects. We detail state-level
affected states, these changes
OPEN ACCESS changes in these regulations
do bring open access renewable REGULATIONS below.
power up to par with regulations Open access regulations
for traditional sources, removing We provide a comparison of
determine the charges and open access exemptions for
uncertainty arising from short- procedures for using the public
term support mechanisms, renewable power procurement
grid to wheel power from an provided by various states and
thereby making cash-flow offsite renewable power plant
projections for renewable how it has changed in the last
to the premises of a corporate year in the Annex.
contracts more predictable and buyer.
stable. As open access and
net-metering are key regulatory

State Update on open access regulations

The policy introduced in January 2019 withdraws the exemptions for electricity duty, CSS and wheeling losses4
for projects selling renewable power to private consumers. According to the previous policy, these exemptions
Andhra were available for projects built until March 2020.
Pradesh
The new policy has also capped the purchase of unused banked energy at 10% of total banked energy per year
and reduced the average power purchase cost (APPC) compensation from 100% to 50%.

Haryana amended its solar policy in March 2019. The most significant change in the policy has been the
withdrawal of exemptions from wheeling and transmission charges, CSS and additional surcharges for third-
Haryana party sales of power. The previous policy waived these charges for 10 years. However, the new policy restricts
the eligibility of these exemptions to only captive/group captive solar projects, for which companies acquired
land and incurred capital expenditures of at least INR 10 million/MW before 13 February 2019.

For open access renewable plants commissioned before 31 March 2018, Karnataka had waived
Pulp & paper
transmission, wheeling, banking and CSS charges for 10 years. The state government decided to discontinue
Karnataka
these waivers for plants commissioned after 31 March 2018 despite several requests for extension.

In July 2019, Maharashtra issued the first amendment to the distribution open access regulations and
transmission open access regulations. As per this amendment, it reduced the banking period for open
access projects from 1 year to 1 month. The amendment further restricts banking by allowing withdrawal
Maharashtra
of energy banked during peak time of day (TOD) slots at off-peak TOD slots and not vice-versa. It has also
capped the monthly unused banked power at 10% of total generation and increased transmission charges
for all open access transactions.

In Rajasthan, the government had waived CSS for all solar plants commissioned between April 2014 and
March 2019. However, it did not extend the exemptions beyond 31 March 2019. For third-party sale/open
Rajasthan y access projects, the government has changed the banking period from an annual basis to a monthly basis.
Moreover, only 10% of banked energy is now eligible for payment at 60% of energy charges applicable under
the notified industrial tariff.

In September 2019, Uttar Pradesh introduced its Captive and Renewable Energy Generating Plants
Regulations, 2019, under which it gives a 50% exemption on wheeling and transmission charges for captive
Uttar Pradesh
and third-party sale renewable projects. There is also a 100% waiver on transmission for interstate sales and
a 100% exemption of state CSS for interstate sales of power for captive/third-party use.

4
Wheeling losses or power distribution losses, pre-determined by regulators and applicable to power generating plants.

PPAs in India: Market & Policy Update December 2019 14


Policy and regulatory update

NET METERING While it took several years to


REGULATIONS bring most Indian states on board
to offer net metering, some states
Net metering is a key regulatory have started to put restrictions
provision that helps increase the and are asking for a shift to gross-
demand for and penetration of metering. We highlight state-level
rooftop solar installations. changes in these regulations
below.

State Update on net-metering regulations

Rajasthan reduced its energy banking period for net metering from 1 year to 1 month for commercial and
Rajasthan industrial customers. This change has raised questions about the viability of several projects, particularly those
with seasonal power demand.

In March 2019, the Tamil Nadu Electricity Regulatory Commission (TNERC) allowed net-metering connections
only for the low tension (LT) consumer category (typically customers with small connected loads), thereby
Tamil Nadu
restricting net-metering for large customers. The 2013 regulations will continue to govern existing consumers
using the net metering scheme.

In Uttar Pradesh, under new regulations issued in January 2019, net-metering is no longer available for
commercial, industrial and public buildings. These customers can now only opt for gross metering. Under
Uttar Pradesh gross metering, excess electricity for C&I customers will receive compensation at a fixed price of INR 2/unit,
which is much less than what they would receive under net-metering and, in fact, lower than the average
power purchase cost borne by the state for conventional sources of power.

Overall, the removal of open access charges and net metering benefits across several states indicates
that regulators and DISCOMs are pushing back at offering incentives for renewable power indefinitely. The
increased viability of solar projects due to continued cost reductions should help counteract part of the
negative impact of these policy and regulatory changes.

PPAs in India: Market & Policy Update December 2019 15


4

Risks and
challenges
for corporate
renewable PPAs
Even though India is the second largest growth market
for corporate renewable PPAs, its current growth is far
lower than its potential.

PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 16
Policy and regulatory update

Most risks and challenges banking. This would lead to as Maharashtra, Rajasthan and
hampering its growth pertain to developers not being able to sell Telangana.
policy uncertainty and limited a part of the generated power,
cooperation with DISCOMs. increasing power tariffs. Similar ROLLBACK OF FAVORABLE
These challenges, unless changes in other states will likely NET-METERING PROVISIONS
addressed, can imperil the to lead to an overall increase in
It took several years for the
long-term growth of the market renewable power tariffs offered
central government to get all
and its associated value chain. to corporate buyers.
states to offer net-metering
The following highlights the key
to promote rooftop solar
challenges that have emerged
installations in the country. Policy
over the past six months.
POOR PERFORMANCE ON changes restricting net-metering
DISCOM APPROVALS for corporate customers in Uttar
Pradesh and Tamil Nadu are
ROLLBACK OF FAVORABLE Despite progress in Uttar a major setback in that effort.
BANKING PROVISIONS Pradesh and Haryana, getting DISCOM incentives under phase
an open access approval from II of the national rooftop solar
Since there is a wide seasonal DISCOMs has been a key scheme may help to halt this
variation in power generation challenge for the corporate trend.
from renewable sources, the renewable PPA market. The
annual banking of power is reason often cited for denial
crucial to improving project of permission is the technical
bankability. Annual banking helps inability of the local substation
consumers use the excess to allow drawing of power. It
power generated during peak is often difficult to ascertain
seasons in non-peak seasons. such technical limitations.
Maharashtra and Rajasthan Developers are increasingly
have recently shifted to monthly facing challenges in receiving
banking instead of annual any approvals in states such

PPAs in India: Market & Policy Update December 2019 17


5

Outlook for
corporate
renewable PPAs

PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 18
Outlook for corporate renewable PPAs

FIGURE 9: Expected project capacity under the group captive model by state

800

700

600
Capacity (MW)

500

400

300

200

100

0
a

ra

u
an

ad
s

es
ht
ga
de
ry

ad

il N
as
tis
ra
Ha

Pr
ar

m
at
rP

ah

Ta
ra
hh
ta

dh
C
Ut

An
Source: JMK Research

As shown in figure 9, India has a without entering into a PPA market inefficiencies that
development pipeline of almost agreement. Currently this is currently influence how
2 GW for corporate renewable still a work in progress and tariffs are set and reduce
PPAs. A small part of this will as per the last update, in May the unpredictability around
come online in the current 2019, the Central Electricity cross-subsidization of tariffs.
financial year (April 2019 – March Regulatory Commission Most significantly, there may
2020) – leading to lower capacity (CERC) has ordered the be a proposal in the new
addition this year as compared to Indian Energy Exchange tariff policy or an amended
last year. (IEX) to seek comments and Electricity Act to remove
feedback on GTAM from all cross-subsidy charges
However, we do expect this stakeholders, after which it levied on private renewable
pipeline to expand and a plans to approve it. energy procurement.
significant proportion of this to
be installed in the next financial • New power tariff policy We would like to reiterate the
year (April 2020 to March 2021), and amendments to the importance of the March 2019
resulting in a bounce back. Electricity Act: The Union amendment to the Haryana
Cabinet is considering a Solar Policy that has opened the
The Indian government is new power tariff policy door for DISCOMs to meet their
considering several new policy for approval. It is also RPOs by leveraging corporate
initiatives that may positively considering reforms focused renewable PPAs. This is a novel
impact the corporate renewable on empowering consumers approach that can bring more
PPA market: by giving them the right states and DISCOMs on board
to choose their power to pro-actively support such
• Green Term Ahead Market
supplier. Additionally, the projects and would remove a
(GTAM): GTAM is an initiative
government is considering key bottleneck for growth. Other
planned by the government
a direct transfer of benefits states may explore this option as
that would allow spot
from the government to the well. 
trading of renewable energy
bank accounts of customers
through power exchanges.
eligible for subsidies. This
This trading window would
should help eliminate the
let corporate consumers
maze of subsidies and
buy renewable power

PPAs in India: Market & Policy Update December 2019 19


6

Annex

PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 20
TABLE 1: Open access waivers for solar projects across states, as of 31 August 2019

Waivers for solar open access projects applicable Changes enforced between April 2018 and August
States
until 31 March 2018 2019

• CSS waiver for five years from commercial • Wheeling and transmission charge exemptions
operation date (COD) limited to only interstate supply of power; no
exemptions are applicable for intrastate projects
• Transmission and wheeling charge waiver for
captive model/third-party sale within the state • Withdrawal of CSS waiver, distribution losses and
Andhra Pradesh all other exemptions; purchase of unused banked
• Exemption from distribution losses for projects energy capped at 10% of total banked energy
injecting at 33kV or below during a year

• Availability of exemptions for projects built by


March 2020
• Wheeling, transmission and distribution, CSS, • Reactive power charges, electricity duty, tax and
reactive power charges, electricity duty, tax cess waived for 25 years from COD
and cess waived for 25 years for projects
commissioned during the policy period • Wheeling and transmission charges exempted
for 10 years only for captive solar projects where
Haryana • Policy remains in force until new policy released companies have acquired land and incurred
capital expenditure of at least INR 10 million/MW
before 13 February 2019

• Banking facility not available for third-party sale


projects
• Wheeling charges and CSS waived for 10 years • No open access waivers after 31 March 2018

• Exemptions from transmission charges and


losses, and banking charges
Karnataka
• Reduced charges apply to plants built by 31
March 2018

• No exemptions • Banking period reduced from 1 year to 1 month

Maharashtra • Transmission charges increased for all open


access transactions

• No waivers • CSS exempted for renewable projects

• 80% of wheeling charge waived for consumers


Odisha drawing power from a renewable source
(excluding co-generation and biomass power
plant)

• Transmission and wheeling charges for renewable • Transmission and wheeling charges for renewable
energy plants to be levied at 2% of energy energy plants to be levied at 2% of energy
Punjab injected for FY 2018-19. injected extended to FY 2019-20.

• CSS waived for all solar plants commissioned • Withdrawal of exemptions from 31 March 2019
Rajasthan between April 2014 and March 2019 onwards

• Transmission, wheeling charges, scheduling • Transmission, wheeling charges, scheduling and


and system operation charges at 30% of system operation charges at 50% of conventional
conventional power power
Tamil Nadu
• 40% of CSS waived • 30% of CSS waived

• Waivers available for FY 2018-19

PPAs in India: Market & Policy Update December 2019 21


Waivers for solar open access projects applicable Changes enforced between April 2018 and August
States
until 31 March 2018 2019

• Wheeling charge of only 2% • No changes

• CSS and AS waived until November 2017


Madhya Pradesh
• Revision of policy has resulted in CSS and AS
being applicable from December 2017 onwards

• Electricity duty, 50% of CSS waived • No changes

• No additional surcharge
Gujarat
• Incentives apply for 25 years from COD for
projects built by March 2020

• CSS waived for five years from date of • No changes


commissioning

• Transmission and wheeling charges waived for 10


Telangana
years for captive consumption within the state

• Exemptions applicable only for projects built by


31 March 2020
• Exemption up to 50% of wheeling and • For captive and third-party sale RE projects, 50%
transmission charges for plants commissioned exemption is given on wheeling and transmission
between April 2017 and March 2022 for charges
intrastate sale of power
• 100% waiver on transmission for Interstate sale
Uttar Pradesh • Exemption from all wheeling and transmission
charges for interstate sale of power • 100% exemption of state CSS for Interstate sale
of power for Captive/Third Party use”
• Unless the policy and regulation are extended,
the exemptions shall not be available beyond
March 2022

Source: SERC tariff orders, JMK Research

PPAs in India: Market & Policy Update December 2019 22


Glossary
average power purchase commercial operation date states allow other sources to
cost (APPC): The weighted (COD): The date on which qualify as well.
average pooled price at which the commercial operation of
the distribution licensee has the power plant begins, after off-taker: The buyer of electricity
purchased the electricity successful testing and injection in a PPA.
including cost of self-generation. of power at delivery point (the
open access: A regulatory
metering point between the
additional surcharge (AS): mechanism allowing a grid-
power producer and the utility at
DISCOMs impose an additional connected bulk consumer, having
the pre-determined voltage level).
surcharge to recover stranded a valid contract demand of 1000
cost on account of stranded corporate PPA: An agreement kVA or above, to meet part of or
power purchase agreements between a private company and its entire electricity requirements
(PPAs) and stranded assets due a power producer (developer, through alternative sources.
to consumers procuring power independent power producer,
OPEX: This is an operating
through open access. investor) to purchase electricity at
expenditure-based model in
a mutually agreed tariff, tenor and
capacity utilization factor: which an investor invests the
capacity.
The ratio of the actual electricity upfront capital cost of the project
generated by a renewable energy cross-subsidy surcharge and the consumer pays for the
project over the year to the (CSS): A charge levied to recover electricity consumed/supplied by
equivalent electricity output at its the cost of the utility providing the project developer.
rated capacity over the year. subsidized power to certain
power purchase agreement
categories of consumers, such
captive buyer: The end user of (PPA): A contract between a
as the poor, religious entities and
the electricity generated by the power producer and a buyer of
agriculture.
captive generating plant. electricity for an agreed tariff,
group captive model: This is a tenor and capacity.
captive model: A power asset unique structure provided under
in which the captive buyer special purpose vehicle (SPV):
the 2003 Electricity Act where
consumes at least 51% of the A subsidiary company with an
C&I consumers are enabled to
electricity generated and owns at asset/liability structure and legal
set up power plants for their
least 26% of the equity. status that makes its obligations
collective use and which should
secure even if the parent
have a 26% equity in the plant
cess: A tax typically imposed company goes bankrupt.
and must consume 51% of the
by the government. It levies this
tax for a specific purpose until
power produced. State Electricity Regulatory
it has raised sufficient funds for Commission (SERC): The
distribution company
the stated purpose. For example, electricity regulator in each
(DISCOM): Supplies power to the
after seeking permission from Indian state. One of their key
consumer.
the regulator, a state utility can responsibilities is to determine
levy a cess on electricity duties independent power producers retail electricity tariffs and open
to upgrade infrastructure or to (IPP): An entity that is not a public access charges.
compensate for a shortfall in utility but that owns facilities to
tariff: The cost per unit of
revenue. generate electric power for sale
electricity that a buyer pays.
to utilities and end users.
commercial and industrial
utility: Local electricity
(C&I): A business segment set net-metering: A billing
distribution company.
up with the sole motive of gaining mechanism allowing onsite
profit. projects to feed excess electricity
to the grid, reducing their own
electricity bills. It is usually limited
to solar rooftop, though some

PPAs in India: Market & Policy Update December 2019 23


DISCLAIMER ABOUT WBCSD’S ABOUT THE WORLD
RESCALE PROJECT BUSINESS COUNCIL
This publication is released FOR SUSTAINABLE
in the name of the World REscale brings together leading DEVELOPMENT (WBCSD)
Business Council for Sustainable companies representing
Development (WBCSD). This the full renewable energy WBCSD is a global, CEO-led
document is the result of a value chain to accelerate the organization of over 200 leading
collaborative effort between deployment of renewables and businesses working together
WBCSD, JMK Research & the transition to a low-carbon to accelerate the transition to
Analytics and representatives electricity system. REscale a sustainable world. We help
from companies participating in members share the ambition to make our member companies
the India Corporate Renewable scale up renewable deployment more successful and sustainable
PPA Forum. A range of WBCSD beyond average growth. by focusing on the maximum
members reviewed the material, positive impact for shareholders,
thereby ensuring that the In 2017, REscale formed the
the environment and societies.
document broadly represents India Corporate Renewable
the majority view of the India PPA Forum to increase Our member companies come
Corporate Renewable PPA understanding and uptake from all business sectors and all
Forum. It does not mean, of corporate renewable major economies, representing a
however, that every company procurement in India. combined revenue of more than
within the forum agrees with USD $8.5 trillion and 19 million
To find out more about REscale,
every word. employees. Our global network
the Corporate Renewable PPA
of almost 70 national business
To contact WBCSD about this Forum and previous reports,
councils gives our members
report: visit our webpage or contact:
unparalleled reach across the
Lucy Hunt globe. WBCSD is uniquely
Jasmeet Khurana
Associate, Renewable Energy positioned to work with member
Manager, Climate & Energy
hunt@wbcsd.org companies along and across
khurana@wbcsd.org
value chains to deliver impactful
business solutions to the most
challenging sustainability issues.
ACKNOWLEDGEMENTS
Together, we are the leading
This paper was drafted by voice of business for
WBCSD and JMK Research sustainability: united by our
& Analytics. The paper has vision of a world where more
been prepared for general than 9 billion people are all living
informational purposes only and well and within the boundaries of
is not intended to be relied upon our planet, by 2050.
as accounting, tax, legal or other www.wbcsd.org
professional advice. We thank
the following co-authors: Follow us on Twitter and LinkedIn

Jyoti Gulia, Director, JMK


Research & Analytics

Shipra Arora, Manager, JMK


Research & Analytics

PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 24
OTHER PARTNER INITIATIVES

RE100 Green Power Market Renewable Energy


Development Group Demand Enhancement
RE100 is a collaborative, global (GPMDG) India (REDE)
initiative uniting influential
businesses committed to Green Power Market The Renewable Energy Demand
100% renewable electricity, Development Group (GPMDG) Enhancement (REDE) initiative
working to massively increase India is an industry-led initiative aims to build an alliance among
demand for – and the delivery aimed at rapidly increasing the corporate buyers (commercial
of – renewable energy. Led by share of renewable energy in and industrial consumers)
The Climate Group in partnership the overall energy consumption to increase commitments to
with CDP, RE100 brings together of commercial and industrial renewable energy procurement
the world’s most significant, establishments. This will be and to catalyze solutions to
ambitious and forward-thinking accomplished by addressing address challenges that are
companies that are accelerating the policy, regulatory and market significantly restricting demand.
the transition to a zero emissions barriers that currently impede By means of developing an
economy by committing to the growth of renewable energy appropriate interface between
100% renewable electricity sector. GPMDG works with buyers, suppliers and policy-
across their operations. government agencies and other makers, the initiative intends to
relevant institutions to help create a cohesive and informed
Shailesh Telang
member companies voluntarily market to meet corporate
Technical Manager (Renewable
set and achieve their renewable renewable energy demand.
Energy)
energy goals. REDE is built on the success of
CDP India
the Renewable Energy Buyers
shailesh.telang@cdp.net Deepak Krishnan Alliance (REBA) founded in June
Manager, Energy Program 2016 in the USA.
Atul Mudaliar
World Resources Institute India
Program Manager
DKrishnan@wri.org Bhavna Prasad
The Climate Group
Director, Sustainable Business
amudaliar@theclimategroup.org Ravi Chander Rangavajjula WWF-India
Principal Counsellor bprasad@wwfindia.net
Confederation of Indian Industry
ravi.c@cii.in Shuva Raha
Deputy Director and Head, New
Initiatives
Confederation of Indian Industry
shuva.raha@cii.in

PPAs inPPAs
India:inMarket
India:&Market
Policy&Update
Policy December 2019 25
World Business Council
for Sustainable Development
WBCSD
Maison de la Paix
Chemin Eugene-Rigot 2B
CP 2075, 1211 Geneva 1
Switzerland

WBCSD India
4th Floor, WorldMark 2, Aerocity
New Delhi, 110037, India

www.wbcsd.org

You might also like