Professional Documents
Culture Documents
ITTO Processes
Rolling Wave planning - projects get more detailed as time Project Management Body of Knowledge
progresses
Application of knowledge, skills, tools and techniques to the Temporary endeavor to create a unique product, service or
project work to meet the project requirements result
The reason a company does a project in the first place. PM Day to day work that is ongoing. Not unique, no start end
must ensure deliverables are providing value. dates
Takes input, applies tools and techniques in order to gain an Inputs, tools and techniques, outputs
output.
Phase Process Group
Set of processes defined by knowledge needed to manage that held at the end of each phase to determine if the project is
area. meeting goals and should continue
integration, scope, schedule, cost, quality, resources, product that is presented to customers or stakeholders for
communication, risk, procurement, stakeholders acceptance.
Series of phases the project will go through from start to finish Scope, time and cost are known early in the project
Adaptive life cycle Baselines
Standard Regulations
Scope is known early, but time and cost are refined as project
Time, scope, cost goes along.
takeaways documented at the end of each phase to help in collection of programs and projects implemented to achieve a
future projects/phases - what went well, what didn’t go well strategic goal managed by a portfolio manager
Official documents that provide gidelines that must be guidelines provided by an approved body. Compliance is
followed standard, but not mandatory.
System 3 types of PMOs
Resources, time, scope, cost, risk, quality, customer Organic/simple, virtual, project oriented, functional, matrix,
satisfaction hybrid
all the stages or phases a project goes through from beginning Functional, weak matrix, balanced matrix, strong matrix,
to end project oriented
measured by finishing the project within the constraints Term used to refer to different kinds of iterative development
EEF Change Request
of the work performed compared to the plan Overall status report of the project
Updates Leadership styles
the project team to complete the project work, deliver the final
Hands off, allows the team to make decisions product/service/result
Focused on the goals of the project and how to reward team Technical Project Management, Leadership, Strategic and
members Business Management
Focused on removing obstacles from the team and giving the Tries to empower the project team, motivate and inspire them
team what is needed to complete the work
Charismatic Leadership Business Documents
BCR, IRR, Opportunity Cost, Payback period, EVA, PV, Ratio of Benefit to Cost
NPV, ROI
Internal rate of return Economic value add
The difference between the present value of cash inflows and How long it will take to return the investment capital
the present value of cash outflows over a period of time
Ensuring info is available to stakeholders when needed Websites, libraries, articles, documents
Lessons Learned Register Final Transition
features and functions that charaterize a product, service or Triggers the PM to update the project management plan and
result. associated documents
work that his needed to deliver a product, service or result Outputs a Scope Management Plan
with specified features and functions.
Collect Requirements Conversation
Bringing stakeholders together to gather and prioritize how to rank and priotize ideas in brainstorming
requirements.
Working models of a product that stakeholders can interact Collect requirements from SMEs anonymously -- stakeholders
with. cannot influence one another.
visually show how a business process, other systems and Process where you create the project scope statement
people interact. Shows inputs and outputs
Project Management Plan Work breakdown Structure
taking project deliverables from the scope statement and Includes project and product scope
dividing them into work packages
Document containing additional information about each work Where project deliverables are formally inspected/accepted by
package. the project sponsor/customer
Rolling Wave planning Milestone List
FF FS
Form of progressive elaboration - work packages happening
All project or phase milestones soon can be decomposed now - later work packages will be
decomposed later
Process to put activities in order - yields a project schedule. List of all scheduled activities on a project. Detailed list of
Also shows relationships between activities work needed to complete each work package
Technique used to build a sequence using activities More detailed information about each activity.
A and B need to finish at the same time, but don’t have to start
Once you finish A, you can start B at the same time
SS Mandatory Dependencies
SF Discrectionary Dependencies
Soft logic - don't have to do something before something else B can't finish until A is started (rare)
(install OS updates before installing Office)
Activities are dependent on factors outside the team's control You need to know what the activities are and what the
(waiting on a permit) sequence is
Activities are dependent on factors inside the team's control Show an overlap or delay in the schedule
(testing a pc after software is installed)
Project Schedule Network Diagram Parametric Estimating
Uses Optimistic, most likely (realistic) and pessimistic values Analyze each activity to determine how long it will take to
to calculate cost or duration accomplish
Optimistic + 4 * Realistic + Pessimistic /6 OR (O+4*R+P)/6 Top down estimating; relies on historical information to assign
duration to activities - quick but less accurate
Lists all identified project risks, impact and response. Adding extra time to an activity because of risk
Listing of the project team who will be doing the work Output of EAD; length of time for each activity
What resources are required to do the work Longest path through a network diagram
Critical Chain Method Schedule Compression
Doing activities in parallel instead of sequencing Used to ensure the crirical path does not change
Part of the PMP, includes start and end dates, only changed by
Releasing the product in increments approved change request
Project Schedule Control Schedule
Series of formulas that are use to numerically analyze the Displays activity start dates, end dates, and durations
performance of a project's related time and costs.
Used on an agile project to track the work that needs to be Only displays a symmary of the major deliverables. No
done duration, just point in time
Included in the cost baseline, a cost the project will directly Delay between activities (can't start B until 2 days after A is
incur done)
Indirect cost that is not included in the project budget Cost that changes as the project progresses
Amount of money already spent Value analysis - used to find a less costly way of doing work
ROM Contingency Reserves
Unknown unknowns - requires approved change request Done during planning, has (-10% to +25%) variance
Rolling up the activity costs into work packages, then to when the organization limits funding because of year end
deliverables. Adding deliverable cost together makes the total budgets or other expenses throughout the year.
cost aggregation
Financing Trend Analysis
Measures the level of work that needs to be done to finish the Cost of the project, including all deliverables - includes
project within the budget contingency reserves
Amount of money worth of work that should have been done Amount of money worth of work you actually did (EV =
(PV=Planned % complete X BAC) Actual % complete X BAC)
Actual Cost (AC) Schedule Variance (SV)
Rate of how we are meeting the project schedule (should be Difference btween work done and money spent (positive is
>1) (SPI = EV / PV) good) (CV = EV - AC)
Forecasting total cost at the end basted on current spending Rate of how we are spending to actually earning (should be
(EAC = BAC / CPI) >1) (CPI = EV / AC)
Forecasting the amount that will be needed to complete based Difference between original busget and new forecasted
on current performance (ETC = EAC - AC) budgets (should be >1) (VAC = BAC - EAC)
To-Complete Performance Index Continuous Improvement
Ultimate test of quality - met by collecting understand and Little inventory, so they sell the latest products. Inventory has
managing their requirements high quality and low cost
Quality theory that looks to improve processes based on One event cant affect another event
standard deviation and bell curve
Mutual Exclusivity Cost Benefit Analysis
Displays subtopics that branch out from other topics, displays Visual representation of workflows
relationships
Quality Metrics Histogram
Checksheet Checklist
Bar charts that show the distribution of numerical data Used to determine if the products meet quality standards
Performed to ensure that the project is following the Used to put large amounts of data into categories
organization's quality policies.
Used by engineers to design a particular aspect of a product. Ishikawa/Fishbone, shows cause and effect and root causes
Help the PM determine what to check for when inspecting Gathers data on defects and keeos a running total.
deliverables
Statistical Sample Rule of seven
Made up of a X and Y axis, shows relationships between Audits, walk throughs, peer reviews to find defects or verify
variables and can identify trends defects have been repaired
Details roles and responsibilities, reporting relationships, how Charts that display standard deviation
to hire, manage and release the project team
Or Organizational Breakdown Structrure, shows the reporting Shows resources assigned to work packages
relationships in a project
RACI Staff acquisition
When and how to release the project team How the organization manages its resources
What training will be needed to ensure the team has the right Used to manage physical and staff resources.
skills
Colocation
When the project team has been selected by the functional Addressing saftey of the team
managers before the project starts
Document how you allocated physical resources to the project Outlines what is acceptable behavior in the team
Forming, Storming, Norming, Performing, Adjourning Hierarchical breakdown of resources by categories and types