Professional Documents
Culture Documents
Design Basis Report FOR Piping
Design Basis Report FOR Piping
NO:
SHEET: 1 of 32
SHEET: 2 of 32
SHEET: 3 of 32
1.0 SCOPE
4.0 MATERIALS
5.0 VALVING
6.0 GENERAL
8.0 PAINTING
SHEET: 4 of 32
1.0 SCOPE:
1.1 This specification describes the basis for the overall design of steam, water & utility
piping of the power plant. It is intended to establish designs confirming to codes and
accepted practices currently applicable to piping systems.
2.1 The main design codes and standards, which shall be considered as minimum
requirements are listed below. Latest version of these shall be followed.
ANSI B16.20 - Ring Joint gaskets and grooves for Steel pipe
Flanges
SHEET: 5 of 32
In addition to the above the following specifications shall form part of this project.
SHEET: 6 of 32
a) 1995 ASME boiler and pressure vessel code Sec. I and Sec. VIII apply to certain
integral portions of steam, feed water and blow-off piping associated with boilers
and steam generating equipment, as defined by that code.
b) Certain portions of external piping shall meet the requirements of ANSI B31.1,
(1992) Power Piping Code, as defined by that code.
c) Steam and Feed water piping coming under the purview of the Indian Boiler
Regulations shall be designed in accordance with that code. Annexure-G lays
down the major requirements of Indian Boiler Regulations. Nevertheless,
requirements spelt out in respective ASME / ANSI codes shall be adhered to, as a
minimum.
3.1.1 Design conditions of pressure and temperature will be the most severe conditions
expected to co-exist under long-term operating conditions. These usual operations
include all functions such as throttling, blowing and bypassing likely to be used for
operation and control.
Usual operating conditions do not include more severe temporary conditions, such as
those abnormal operations like turbine over speed / over pressure conditions, as long
as the duration and parameters do not exceed the values defined in the respective
codes.
SHEET: 7 of 32
The Design pressure of piping shall be the most severe condition of internal or
external fluid pressure, subject to conditions of Section 3.1 above arrived at in
conjunction with the following considerations.
Piping system shall be designed for 7000 cycle based on the plant life of 30 years,
such that it operates without replacement and with normal maintenance, and shall
withstand the fluctuations in operating parameters and cycling, normally expected.
All piping must be designed for thermal expansion under start-up, operating and shut
down conditions such that the actual stresses shall be well within the allowable limits
of the pipe material and the forces / moments on the equipment shall be within the
limits defined by the equipment supplier.
Provisions for expansion or contraction shall normally be made with bends, offsets
and expansion loops. Expansion joints may be used on large diameter piping, relief
systems or where they are acceptable process wise and economically justified.
Stress analysis shall be done for piping meeting the conditions specified in the stress
analysis design criteria attached as Annexure-F.
SHEET: 8 of 32
The Design and Selection of supports shall be based on Design procedures for pipe
supports attached as Annexure-E.
4.0 MATERIALS:
Piping material selection attached as Annexure-A includes line service, pipe material,
type of construction and ANSI Rating. Piping Material Selection for this project is
attached as Annexure-A. The basis for material selection is as per Material Selection
Chart attached as Annexure - B.
4.2.2 For IBR piping, refer to the requirements under the IBR regulations.
4.3.1 Reinforcement requirement for nozzles / stubs or other welded branch connections
shall be as per Section 104.3 of ANSI B31.1 and shall additionally meet the
requirements of IBR for piping systems under the purview of IBR.
Minimum line size shall be 1” for long runs in the offsite area. Exceptions are there
for instrument piping, which may be minimum 1/4”. Vents and Drains shall be 3/4”
min. Pipe sizes 1-1/4”, 2-1/2” and all other odd sizes such as 5” and 7” shall not be
used unless required to match the connections to Mechanical equipment.
4.5.1 Long radius welding elbows shall be used for changes in direction of piping. For
steam and feed water piping coming under the purview of the Indian Boiler
Regulation bend radii shall be as per that regulations. Short radius bends shall only be
used where space does not permit the use of long radius elbows and bends.
SHEET: 9 of 32
4.5.2 Welded mitre bends, with a maximum included angle of 22.5° per segment, may be
used in utility piping systems, for sizes NB 350 and over, where the pressure and
temperature does not exceed 10 kg/cm2 and 120°C respectively. In other services &
Higher-pressure conditions, the welded mitre bends may be used, provided they meet
process requirements.
5.0 VALVING:
5.1 Valves:
5.1.1 Design, fabrication and testing of valves shall generally conform to ANSI B16.34
(1981). Butterfly valves shall conform to AWWA C504.
5.1.2 All valves requiring attention during normal operation shall be accessible either from
grade, platform or Ladders.
5.1.3 All valves shall be suitable for installation in horizontal as well as vertical pipeline.
5.1.4 All globe valves shall be capable of being closed against the design pressure. Where
globe valve has been specified for regulation purpose, the disc shall be tapered plug
type and suitable for controlling throughout its lift.
5.1.5 All gate and globe valves shall have bonnet back seating arrangement to facilitate
easy replacement of packing with the valves in service.
5.1.6 All gate, globe and check valves shall be designed for reconditioning seating surfaces
and replacement of stem and disc without removing the valve body from the line.
5.1.7 Manual gear operators shall be provided to open / close the valve against the
maximum differential pressure across the valve such that the effort required to operate
does not exceed 25 kgf.
- Gate and Globe valves ANSI #150 with size 12” & larger
ANSI #300 with size 8” & larger
5.1.8 All gate and globe valves of size 50 mm and below in vacuum services shall have
extra deep gland packing without any provision for water gland sealing.
SHEET: 10 of 32
5.1.9 All gate and globe valves of size 80 mm NB and above in vacuum services shall have
adequately deep gland packing and shall be equipped with lantern rings to admit
pressurised water for gland sealing.
5.1.10 Integral bypass valves shall be provided for all gate valves as classified below. Size
and location of bypass valve shall be as per MSS-SP-45.
a) Under pressure class of 600 lbs and above, where the sizes are 100 mm NB and
above
b) Under pressure class of 300 lbs and 400 lbs where the sizes are 250 mm NB and
above.
5.1.11 Valve Data Sheets attached as Annexure - C gives a basis of valve selection for the
different systems
5.1.12 Valved drains, vents shall be installed at low and high points in piping systems, if
required for operation, maintenance or for draining purposes.
5.1.13 Drains & vents required purely for hydraulic or pneumatic test purposes are to be
shown on the isometric drawings and added to the P&ID’S by the Piping erection
contractor.
To collect samples for laboratory analysis, dedicated sample connections are required;
sample points shall not be located in dead ends of piping.
6.0 GENERAL:
Pipes of sizes 80 mm NPS and above shall be shop fabricated as per the drawings and
pipes of sizes 50 mm NPS and below shall, in general, be field routed.
6.2 Accessibility:
For accessibility requirement of Valves & Instruments for the plant refer Annexure-H
of this specification.
6.3.1 All Piping entering and leaving a plot area shall be grouped together as far as
practicable. Inside plot piping shall be routed on overhead pipe bridges wherever
possible.
SHEET: 11 of 32
6.3.3 Fire fighting water lines, if installed above ground shall not run along pipe bridges
and pipe racks but as practical along roads.
6.3.4 The elevations of overhead piping shall be as specified by the site requirements but
never be less than
6.3.5 The minimum horizontal clearance shall be 0.75 M for access ways and walkways,
however the minimum clearance shall be 0.9 M for frequently used main passages.
- Drainage or Sewerage.
- Fire water lines.
6.3.8 The load on the pipes should be equalized for lines crossings railroads / railways and
traffic roads by means of pipe sleeves or a culvert. The pipes shall be kept centrally in
the sleeves by distance pieces welded to the pipe or fixed to the sheeting if the line is
insulated.
6.3.9 As far as practical, piping shall run at the different elevations designated for north-
south and east-west banks and shall change elevation at change in direction.
6.3.10 Sleeves or holes through walls, floors of buildings shall have a size permitting the
passage of a flange of the relevant pipe size to facilitate the installation of fabricated
piping and to permit insulation work.
Relief valve discharging steam, air directly to atmosphere shall be equipped with
drain or suitably piped to prevent accumulation of liquid at valve outlet.
Relief valve discharge piping shall be taken to safe location as per following
SHEET: 12 of 32
Inlet and outlet piping of pressure relief valve shall be adequately supported to take
care of the thrust induced by the relief valve during popping.
In general, the Pipes shall be laid at grade level on sleepers at 300mm higher from
grade level. Pipes at crossing of roads shall be by pipe-way bridges in general. Pipes
sleeves may be considered where one or two pipes are to cross the road.
Piping systems shall have sufficiently flexibility to allow for thermal expansion and
contraction so as to prevent
Loops and offsets shall provide for flexibility in piping systems, especially for
noxious or hazardous fluids, Expansion joints shall be considered when limited space
will not give sufficient flexibility. Expansion joints shall be used only with adequate
guided and anchors. Loops and offsets shall be used in preference to bellow type
expansion joints wherever possible.
Horizontal piping expansion loops on pipe bridges shall have vertical offset to stay
clear of adjacent piping and any thermally expanded piping shall be anchored at the
plot limit.
Pipe stress / flexibility analysis shall be executed with program: CEASAR II from
COADE
7.1 Thermal insulation shall be provided for all piping and equipment with surface
operating temperatures of 60°C or above for one or more of the following reasons:
SHEET: 13 of 32
a) Conserve heat
ii) For sizes 400 mm and above: In order to meet the sizes above
400mm, (Including insulation thickness) lightly resin bonded mattress
confirming to ASTM C547 class III shall be applied in addition to the
Rock wool preformed pipe sections.
iii) The physical requirement of bulk density and chloride content,
thermal conductivity and PH value of the material shall be as follows:
7.4 Aluminum cladding shall be used as a weather protection over insulation unless
otherwise specified and shall conform to ASTM - B - 209 - 1060 Temper H-14.
8.0 PAINTING:
8.1 Painting of pipe work shall be as per the painting specification. The procedures for
painting of insulated and non-insulated pipes, the colour codes, the method of
painting, etc. shall comply with the guidelines specified in the painting specification.
SHEET: 14 of 32
9.1 General:
The complete CPP piping shall mainly consist of following systems; viz. Boiler
feed pump suction piping, boiler feed pump discharge piping, boiler feed pump
recirculating piping, main steam piping, auxiliary steam piping, extraction steam
piping, condensate piping, Raw Water piping, DM Plant piping, fire water piping,
boiler blow down, vents, drains, etc. and low pressure utility piping.
A common suction line from deaerator/ feed water storage tank shall be provided
with branching off lines to individual boiler feed pumps. The common suction line
of BFP’s shall be designed for rated flow of the operating BFP’s + minimum
recirculation flow of the standby BFP and the branch off line shall be designed for
the rated flow of the pump.
The discharge of boiler feed pumps shall be connected to the common discharge
header. From the discharge header feed water piping shall be routed to the steam
generator through, hp heater and feed water control stations. The feed water control
station shall have 1 x 100% and 1 x 40% control valves having flexibility in
operating the Boiler at varying load conditions. Feed water required for super
heater attemperation of the steam generators and other desuperheaters for auxiliary
steam in the power plant shall be tapped from the discharge headers of BFP’s.
Separate recirculation line for each boiler feed pump shall be provided from the
non-return-cum modulating recirulation valves (Automatic Recirculation Valves)
with necessary isolation valves and pressure break down orifices and shall be
connected to the deaerator. Though the pressure reduction is achieved mainly
through the recirculation valve, the upstream of the pressure break down orifice
located near deaerator shall be kept 3 to 4 kg/cm2 above the deaerator pressure so as
to avoid flashing of water in the recirculation line thereby avoiding water hammer
and vibrations in the recirculation lines.
9.5 Main Steam Piping, Auxiliary Steam Piping and Extraction Steam Piping:
The main steam lines constitute the most important piping in a power plant and the
main steam piping from the boiler is connected to the turbine with adequate
expansion loop(s) to take care of the thermal expansions & to obtain adequate
flexibility so as not to exceed allowable reactions on boiler & turbine connections.
SHEET: 15 of 32
Three separate extraction piping will be provided from the turbine to the H.P.
Heater, Deaerator and L.P. Heater to supply the steam. In order to meet the
transient condition, separate tap off will be provided from the main steam line to the
Deaerator extraction line through the Desuper Heater. Another tap off will be
provided in the main steam line to meet the steam requirement of turbine gland
steam ejector system.
The common suction line from condenser hot well shall be connected to individual
condensate extraction pumps through branch lines and expansion joints. The piping
shall be sized for the maximum flow to the condenser under various modes of plant
operation.
The discharge from the condensate pumps shall be connected and fed to the
deaerator through ejector, gland steam condenser, drain cooler and L.P heater. A
tapping shall be provided for supplying spray water to turbine exhaust hood to
control the temperature. At the condensate outlet of GSC a minimum recirculation
line shall be taken and this will be directly connected to condenser to control the
level of the condenser.
Blow down piping shall connect the drains from boiler drum, super heaters, bottom
ring headers, etc. with the blow down tank. Pressure breakdown orifices shall be
provided before the blow down tank nozzle. Some high-pressure steam line drains
from different piping and equipment are connected to flash tank while others shall
be let off to the plant drains.
1. Make-up water
2. Instrument air
3. Service air
4. D.M.water
5. Fuel oil-HSD
6. Service and potable water
7. Cooling water
8. Auxiliary cooling water
REV.NO DATE DESCRIPTION PREPD CHKD APPD
A Issued for Approval
DOC.NO:
SHEET: 16 of 32
9. Raw water
Makeup water for the power plant shall be supplied from raw water reservoir. From
the raw water reservoir, raw water shall be pumped for cooling tower make up, the
DM plant requirement, air-conditioning ventilation system and service/drinking
water.
The instrument air shall be supplied through pipes from the common compressor
house located in the power plant. The header shall be run throughout the power
plant to meet all instrument requirements. Tapping for control valves in the
deaerator area, feed water control station etc., and for other instruments shall be
made from the header at all the nearest points.
The service air shall be supplied from the compressor house through service air
pipes. The header shall be routed through out the power plant. Tappings shall be
made from this header for various plant locations in Boiler area. STG building, coal
handling plant area as per the distribution list given in Compressed Air DBR.
9.9.4 DM Water:
The DM water piping from DM plant to the DM water storage tank and from the
storage tank to deaereator and other areas of requirement such as initial filling for
condenser hot well, H.P. and L.P. Dosing system will be routed through suitably
sized pipeline.
9.9.5 HSD:
Fuel oil pipeline shall be routed from the storage tank to boiler through transfer
pumps.
Potable water pipe lines shall be routed separately throughout the power plant. The
material of potable water pipe shall be carbon steel conforming to IS: 1239 black
and galvanized.
The cooling water system shall be supplying cooling water to the condensers of the
steam turbine generators of the power plant.
SHEET: 17 of 32
The common supply header and return header shall be buried along the T.G.
building for the turbine condenser. The buried piping shall be provided with
suitable external coating and wrapping.
The butterfly valves shall conform to API 609 or AWWA C504 standards and
flanged type and shall be of cast steel body and disc with nitrile rubber seating.
The auxiliary cooling water header shall be routed along with the main cooling
water piping. From the header branch lines for lube oil coolers, generator air
coolers, ash handling system compressors and plant air compressor and sample
coolers etc. The return piping shall be routed to cooling tower inlet header. The
material of construction shall be same as that of cooling water piping.
All piping to the coolers shall be provided with isolation valves of gate type at inlet
and globe valve, at outlet.
Raw water piping shall be routed from the existing raw water Reservoir (UMI) to
the proposed CPP raw water reservoir.
The Raw water piping shall be buried at 1.5 m below the ground. The material of
piping shall be carbon steel as per IS: 3589 ERW pipes. The buried piping shall be
provided with suitable external coating and wrapping.
Firewater piping shall involve piping for the fire hydrant system and high velocity
water spray systems.
Fire hydrant piping shall be routed from the fire water pumps to various hydrant
valve locations, the yard piping mainly being buried piping with suitable wrapping
and coating. The hydrant piping shall be ring main type (close loop system) so that
leakage/breakage at one location would not render the total system non-operational.
Suitable isolation valves, drains connected at all low points shall be provided.
SHEET: 18 of 32
Following parameters for each service have been considered to arrive at optimum
line size:
c) Recommended velocity
d) Pressure at source and receiver ie., available pressure drop through the lines
including fittings, valves and specialities such as strainers, flow elements etc.
For pumps, in addition to friction losses, static head is also considered while
estimating total pressure head required.
ANNEXURE - A
REV.NO DATE DESCRIPTION PREPD CHKD APPD
A Issued for Approval
DOC.NO:
SHEET: 19 of 32
SHEET: 20 of 32
ANNEXURE - B
SEAMLESS PIPES
ASTM A106 Gr.B 0.30 Max. 427
ASTM A335 Gr.P1 0.10 - 0.20 468
ASTM A335 Gr.P11 0.15 Max. 570
ASTM A335 Gr.P22 0.15 Max. 600
ASTM A312 Gr.TP304 0.08 Max. -200 to 500
ASTM A312 Gr.TP304L 0.035 Max. -200 to 500
WELDED PIPES
ASTM A672 Gr.B60 0.30 Max. -46 to 300
API 5L Gr.B (ERW ; E = 0.85) 0.20 Max. 230
ASTM A312 Gr.TP304 0.08 Max. -200 to 500
ASTM A312 Gr.TP304L 0.035 Max. -200 to 500
FITTINGS
ASTM A234 Gr.WPB 0.30 Max. 427
ASTM A234 Gr.WP1 0.10 - 0.20 468
ASTM A234 Gr.WP11 0.15 Max. 570
ASTM A234 Gr.WP22 0.15 Max. 600
ASTM A403 Gr.WP304 0.08 Max. -200 to 500
ASTM A403 Gr.WP304L 0.035 Max. -200 to 500
FORGINGS
ASTM A105 0.35 Max. 427
ASTM A182 Gr.F1 0.28 Max. 468
ASTM A182 Gr.F11 Cl.1 0.10 - 0.20 570
ASTM A182 Gr.F22 Cl.1 0.15 Max. 600
ASTM A182 Gr.F304 0.08 Max. -200 to 500
ASTM A182 Gr.F304L 0.035 Max. -200 to 500
SHEET: 21 of 32
CASTINGS
ASTM A216 Gr.WCB 0.30 Max. 427
ASTM A217 Gr.WC1 0.25 Max. 468
ASTM A217 Gr.WC6 0.20 Max. 570
ASTM A217 Gr.WC9 0.18 Max. 600
ASTM A351 Gr.CF8 0.08 Max. -105 to 538
BOLTS
ASTM A193 Gr.B7 0.37 - 0.49 427
ASTM A193 Gr.B16 0.36 - 0.44 566
NUTS
ASTM A194 Gr.2H 0.4 Min. 427
ASTM A194 Gr.7 0.37 - 0.49 566
PLATES
ASTM A515 Gr.60 0.30 Max. 450
ASTM A516 Gr.60 0.30 Max. -46 to 300
ASTM A387 Gr.11 Cl.1 0.10 -0.20 570
ASTM A387 Gr.22 Cl.1 0.15 Max. 600
ASTM A240 Gr.304 0.08 Max. -200 to 500
ASTM A240 Gr.304L 0.035 Max. -200 to 500
SHEET: 22 of 32
ANNEXURE - C
SHEET: 23 of 32
SHEET: 24 of 32
ANNEXURE - D
TEMP. Up to 101 151 201 251 301 351 401 451 501
°C 100 to to to to to to to to to
150 200 250 300 350 400 450 500 550
Pipe Dia Insulation Thickness (mm)
15 mm (1/2”) 25 25 25 35 45 50 60 70 85 95
20 mm (3/4”) 25 25 30 35 45 55 65 75 90 100
25 mm (1”) 25 25 30 40 45 60 70 80 90 105
32 mm (1 ¼”) 25 25 30 40 50 60 70 85 95 110
40 mm (1 ½”) 25 25 30 40 50 60 75 85 100 115
50 mm (2”) 25 25 30 45 55 65 80 90 105 120
65 mm (2 ½”) 25 25 35 45 55 70 80 95 110 125
80 mm (3”) 25 25 35 45 60 70 85 100 115 130
100 mm (4”) 25 25 35 50 60 75 90 105 120 140
125 mm (5”) 25 25 35 50 65 75 90 110 125 145
150 mm (6”) 25 25 35 50 65 80 95 115 130 150
200 mm (8”) 25 25 40 50 65 85 100 120 140 160
250 mm (10”) 25 25 40 55 70 85 105 125 145 165
300 mm (12”) 25 25 40 55 70 90 105 125 150 170
350 mm (14”) 25 25 40 55 70 90 110 130 150 175
400 mm (16”) 25 25 40 55 75 90 110 130 155 180
450 mm (18") 25 25 40 55 75 90 110 135 155 180
500 mm (20") 25 25 40 55 75 95 115 135 160 185
550 mm (22") 25 25 40 55 75 95 115 135 160 185
600 mm (24”) 25 25 40 55 75 95 115 140 165 190
ANNEXURE - E
SHEET: 25 of 32
• The design loads for hangers & supports shall include the weight of pipe, the weight of
insulation and the weight of medium transported or the medium used for testing,
whichever is heavier. All components of hanger or support assembly shall be designed
for the above design load and the self-weight of hanger/support assembly.
• Design and manufacture of hanger components including springs shall generally confirm
to MSS - SP58, MSS-SP69 and MSS-SP89.
• The materials used in the construction of hangers, supports and accessories shall be the
most suitable for the service intended.
• Material of lugs and welded attachment to pipes and pipe clamps shall be compatible
with parent pipe. However, welded pipe attachments shall be minimised.
• The hangers shall be provided with suitable linkages to permit swing. The angle of
inclination shall not exceed 4° from the vertical plane.
• The diameter of hanger rods for piping, 50mm NPS and smaller, shall not be less than
10mm.
• Bolted pipe clamps, used with rod hangers, for pipe 50 mm NPS and smaller, shall have
a minimum thickness of 6mm.
• Springs, for spring hangers, shall be of helical compression type and shall be provided
with means to prevent misalignment, buckling and eccentric loading and with stops to
prevent excessive travel.
• Where variable spring hangers are specified, the units selected shall have support
variation of not more than 25% through its total travel range.
• Constant spring hangers shall be specified where pipe thermal vertical movements
exceed 40 mm.
• Constant support hangers shall have a field load adjustment range of +10% of the
operating load specified. The total travel of the unit selected shall be the calculated travel
of plus 20% to take care of possible discrepancies. Constant support hangers shall have
support variation of not more than 6% throughout the total travel range.
• All rigid / spring hangers shall provide a means of vertical adjustment after erection.
SHEET: 26 of 32
• The threads on threaded parts such as hanger rods, nuts and turnbuckles shall conform to
applicable codes for the coarse-thread series with a “medium” class fit or equivalent.
• All anchors shall be designed for rigid fastening to the structure either directly or through
a bracket. Anchors and guides shall be capable of withstanding the moments and forces
imposed by thermal expansion.
• Pipe supports shall be designed such that a minimum amount of heat will be transferred
to the structure.
• Stainless steel shim plates are required between stainless steel pipe and carbon steel
supports.
• The maximum allowable deflection of supports due to the design loads in the direction of
the restraints shall be 3mm.
• Shear lugs shall be provided for friction type clamped support on riser pipes. Friction
type clamped supports shall not be normally used on a vertical riser for critical systems.
• The hanger shall be offset 1/2 of the thermal movement in cold position if swing angle of
the rod is in excess of 5 degrees, but not exceeding 10 degrees.
• Suitable locking devices shall be used at all threaded connections of the hanger
assembly.
• Each half assembly of a riser support shall be capable of supporting the entire load.
• Overall rod length shall not be greater than 6m without proper evaluation.
Rigid Restraints:
• Restraints fabricated out of structural steel shall have a clearance of 1.5mm in direction
of the restrained movement except in the downward direction.
• Anchors shall only be used where full constraint of piping against three deflections and
three rotations are required.
• Dependence on friction straps or bolted joints shall be avoided, to the extent possible,
especially in pipes, where design temperature exceeds 120°.
ANNEXURE - F
REV.NO DATE DESCRIPTION PREPD CHKD APPD
A Issued for Approval
DOC.NO:
SHEET: 27 of 32
This criteria is established for piping flexibility analysis to be performed during piping
design work for the plant.
Stress analysis of piping systems shall be performed in compliance with ANSI B31.1
∗ Temperature :
∗ Computer Software :
The computer pipe stress analysis shall be carried out using CAESAR - II ver. 3.24
computer software.
(i) Pipe diameters of 80mm to 200mm with design temp. greater than 60°
(ii) Pipe diameter 250 mm & larger
SHEET: 28 of 32
Any closed vessel exceeding 22.75 litres (five gallons) in capacity, which is used
exclusively for generating steam under pressure and include any mounting or other
fittings attached to such vessels, which is wholly or partly under pressure when
steam is shut off.
Piping:
Any pipe or connected fitting wholly or partly under pressure through which feed-
water passes directly to a boiler.
Material Certificates:
1. Any item part of steam piping i.e. pipes, valves, fittings, traps, safety valves must
have material certificates, countersigned by the local boiler inspector.
SHEET: 29 of 32
Drawings:
1. Prior to fabrication of any items i.e. Boiler, fabricated pipe work which are
coming under the purview of the boiler drawings shall be submitted before
construction to the Chief Boiler Inspector of the State where the plants /
equipment / Pipe line will be installed.
2. The Chief Inspector shall after examination of the drawings and particulars shall
inform the proposers whether he is satisfied with the design and fitness of the
parts for the intended pressure and if not, what modification is necessary therein
with respect to design, material etc.
SHEET: 30 of 32
ANNEXURE - H
Note: 1) Center line of Block valves located above 2.0 meter from the operating floor
which are required for normal operation shall be provided with portable platform
or chain for operation of valves.
SHEET: 31 of 32
ANNEXURE - I
A. STEAM
4.Superheated steam from 7.1 to 3.5 kg/cm2 (g) 20-35 30-45 35-55
SHEET: 32 of 32
B. Water
Average Velocity
Meter / second
Firewater lines 0.6. to 0.9
Feed water suction lines 1.0 to 2.5
Feed water discharge lines 2.5 to 5.0
Auxiliary cooling water (suction) 0.6 to 1.5
Auxiliary cooling water (discharge) 0.9 to 2.5
Condensate delivery lines 0.9 to 2.2
Condensate suction lines 0.4 to 0.7
Main cooling water lines (discharge) 0.9 to 2.5
Main cooling water lines (suction) 0.6 to 1.2
Viscous fuel oil 0.6 to 0.9
Gases 25 to 30