Piping Design Specifications
Piping Design Specifications
This article provides you with a example piping design specification that is used in the
industrial plant engineering and construction work.
1. GENERAL
1.1. SCOPE
1.1.1. This specification covers general and detailed design and layout requirements for
all process and utility piping systems and supplements the requirements of the codes
under which the piping systems are to be designed, for industrial plant engineering and
construction work.
1.1.2. All process and utility piping shall be designed based on the requirements of this
specification.
In the case of a part of this specification is not applicable due to specific requirements of
Client, local code, etc., supplementary paragraphs may be added to the end of
specification, after OWNER’s approval.
1.1.3. This specification shall be applied to all piping systems indicated on piping &
instrument flow diagram (P&ID) and plot plan, except for following:
b) Piping line running after first block valve (or fitting) of piping system connected to
instrumentation, except for control valves, safety valves and orifice flanges.
d) Piping line running after first block valve of piping system connected to steam tracing,
tracers and instrument air consumers.
1.1.9. Requirement of thermal insulation for hot lines shall be considered in accordance
with “Engineering Specification for Thermal insulation (Hot)”.
Design specification and inspection of piping shall be in accordance with the following
Codes and Standards.
For piping material codes, referred to “Engineering Specification for Piping Material“.
1.2.2. RELEVANT ENGINEERING SPECIFICATIONS
The relevant engineering specifications are as follow and all specification shall be of the
latest revision.
1.3. UNITS
Unless otherwise specified, Metric Units (Kg, mm, Kg.m, Kg/cm2) shall be applied as
the measurement system for drawings and documents to be submitted. However,
nominal sizes of piping components shall be in accordance with Inch system (NPS).
2.1.1. Piping arrangement drawings shall generally be drawn to a scale of 1/33-1/3 for
process areas (1/50 may be used for pipe rack area) and 1/100 and 1/200 for offsite
areas. For clarification purposes offsite drawings may be drawn to a scale of 1/50.
b) A key plan should appear above the title block to identify the location of the drawing
relative to remaining part of the plot.
2.2.1. Fully dimensioned Isometric drawing with bills of material shall be prepared for 2"
& larger piping for Carbon Steel and 1-1/2" & larger piping for Stainless Steel lines.
a) Material class.
c) Line designation.
2.2.4. Unless otherwise specified, centerline of pipe elevation shall be applied for pipe
elevation in the Isometric drawings.
2.3.2. Tracer routing shall be shown on the reproducible copy of the piping arrangement
drawing, together with the block valve numbers of the tracer feed and return.
2.4.2. Location of all supports together with support designation and number shall be
indicated on Piping Arrangement Drawings for pipe rack, pipe way and offsite areas.
2.4.3. Location together with support designation and number of all supports shall be
indicated on Isometric drawings for areas other than clause 2.4.2 above.
3.1.1. Piping shall be designed to maintain its lifetime during whole span of life of the
plant.
3.1.2. Design pressures and temperatures, allowable stresses, joint efficiencies and
other design conditions shall be used as a basis for wall thickness calculation and the
material selection.
3.2.1. Pressure Temperature Ratings have been established for certain piping
components.
3.2.2. Flange Ratings shall be determined, based on ASME B16.5 or ASME B16.47-B.
Where a line with a lower rating connected to a pipe or equipment with a higher rating,
such line shall be rated at the higher rating (and shall be the same material as the line
of the higher rating) to and including the first block valve or, when double block valves
are used, to and including the second block valve. Block valves on both sides of a
control valve and the by pass valve shall be rated at the same specification of the line
with the higher rating. The class breaking shall be indicated in the P&IDs and piping
Isometric drawings.
3.4.1. Allowable stresses which specified in ASME B31.1-1998 edition or ASME B31.3-
1999 edition (which ever is applicable), shall be used in design calculations.
4.1. GENERAL
4.1.1. Piping shall be designed for the most severe coincidental conditions of pressure
and temperature, arrived on the basis of the following considerations:
4.1.3. All pipelines shall be routed for the convenience of installation, operation, and
maintenance of the pipeline, equipment and instruments.
4.1.4. All lines inside battery limits, except drain lines, sewer lines and other special use
lines shall be run side by side on overhead pipe supports or on sleepers. The use of
pipe trenches within units shall be avoided as much as possible.
4.1.5. Buried piping shall be kept at a sufficient distance from electrical cables for power
and lighting, and from instrument signal cables. They shall also be run in concrete
trenches only under the pipe rack. Above ground lines which have to buried partially
(passing roads, etc.) shall be run in pipe sleeves, tunnels, culverts or bridges.
4.1.6. Unless otherwise specified, bottom of pipe (BOP) elevation shall be applied for
pipe elevation.
4.1.7. Bottoms of hot and cold insulated lines, which are run on overhead supports,
shall generally be supported with steel shoes and cradles respectively.
4.1.8. Un-insulated lines shall not be supported on steel shoes and cradles, and shall
generally be carried at a common elevation of bottom of piping. Insulated lines shall be
carried at a common elevation of bottom of shoes and cradles. The lines, which are run
on overhead supports, shall generally be changed in its elevation when there is a
change in direction. Intersecting main pipe runs, shall be routed at different levels to
facilitate changing direction and/or crossing of lines.
4.1.9. Large piping (18" and larger) of thin wall shall be supported by adequate
methods, to reduce local stresses at the supporting point.
4.1.10. Lines carrying molten solids or service fluids of high viscosity, or those lines so
indicated on the applicable P&IDs, shall be designed to have a continuous slope and
drain into a vessel. The shortest and most direct layout possible shall be provided for
lines in which gravity flow is required, especially, when the line fluid is subject to
solidification or when the available differential pressure is small.
4.1.11. Concrete trenches must be adequately drained into a liquid sealed drainage
system and must be covered with grating, except near plant access or at road crossing,
etc., where the type of covering shall be as per Civil Engineering details.
Notes : * Elevations are measured from H.P.P.EL (high point paving elevation EL.= 0
for each terrace)
4.1.13. In general, all major process lines should be carried on overhead pipe ways or
sleeper pipe ways.
All lines in process type areas shall preferably run, side by side on over head pipe rack
to common supporting elevations for bottom of pipe. Hot lines on pipe rack shall be
grouped and expansion loops shall be nested together, the number of expansion loops
shall be kept to a minimum. Lines, handling corrosive fluids shall be run under piping
handling non-corrosive fluids, and shall not, where possible, be run overhead across
walkways or normal passages for personnel. Piping shall run on sleepers in tank areas.
4.1.14. Overhead pipe ways and sleeper pipe ways shall have one 10% spare space for
each layer at middle as one continuous space and also future load shall be considered
on 10% spare space.
Consideration shall be given to space allocated for instrument and electrical cable trays
in the pipe racks and sleepers.
4.1.15. All branched piping from utility header (steam, steam cond., water, air, nitrogen,
fuel gas, fuel oil and etc.) shall be taken from the top of the header to prevent plugging
however, water branch piping of 2” and larger may be taken from the bottom of the
header.
4.1.16. All valve pit shall be equipped with non-slip metal plate cover.
4.1.17. Line blinds 10” and larger shall be provided with jack scews.
4.1.18. Access platform with ladder or stairs shall be considered in piping design
specification for access to equipment, valves, instruments and etc., for operation and
maintenance in accordance with section 8 of this specification.
4.1.19. Vent and drain hookup, sample points with or without sample cooler and
pressure instrument points, etc., shall be designed in accordance with the relevant
piping standards.
4.1.21. Material of construction of each piping system with specific operating condition,
shall Conform to the service classifications and pipe classes in accordance to
“Engineering Specification for Piping Material”.
4.1.22. Cold pulling of pipes for alignment during construction or other purposes is not
permitted.
4.1.23. When reducers are used, the maximum reduction shall not be greater than 2
nominal line sizes per reducers.
4.1.24. Change in line sizes, shall be made by Eccentric or Concentric reducers and
swages. Bushing and reducing elbows, are not permitted except for instrument piping
and sewers.
4.1.25. Unions shall only be used, when permitted by the particular piping classes.
4.1.26. Supports and/or anchors shall be provided close to changes indirection of lines,
branch lines and, close to valves.
4.1.27. In general piping shall be designed for zero expansion at the battery limits.
4.1.28. In general, all piping leaving the plant battery limits shall be designed for a
closed valve at the battery limit when defined in P&IDs.
4.1.29. When discharging to a closed collector system, the discharge line shall be
sloped downwards to the header and the header connection shall be made on the
topside of the header line, so that the flow direction angle between the axes of the outlet
line and the header is 45°.
When a collector system includes a knockout drum and flare, the headers shall be
slopped to the knockout drum with a falling gradient of minimum 2/1000.
4.1.30. Where a common header used to vent lighter than air gases to atmosphere, the
header shall slope upwards to the relieving stack or pipe. Discharge lines carrying air
and steam slop upwards and discharge in upward direction.
The minimum clearances below the bottoms of pipe (BOP) other than pass ways shall
be as follows:
a) At grade.……………………………………………………. 250 mm
b) Medium and large pumps (more than 3.75 KW) ………… 900 mm clear aisle
plus 1000 mm
Note: these requirements are not applied to the inside of packaged equipment
assembled on the skid.
(1) The minimum clearances around control panels shall generally be as follows:
(3) The minimum clearance between the lowest points of all flanges or insulation of lines
running in trenches shall be 75 mm above the floor of the trench.
(4) The minimum free distance above a control valve and minimum clearance under the
control valve, shall be in accordance to ISA PR4.2
(5) Impact wrench clearance shall be provided at any equipment flange.
(6) Underground pipe risers shall be terminated 500 mm aboveground, unless otherwise
specified.
4.3.1. To permit ready access for the removal or maintenance of a pipeline, under
operating conditions, a minimum side clearance of 25 mm shall be provided between
parallel lines outside of insulation or between flange and pipe (insulation). Thermal
expansion movements shall be taken into consideration in determining the minimum
side clearances.
4.3.2. The minimum center to center distance between hand wheels of valves shall be
determined take operability of the valve into consideration.
4.3.3. To determine the distance between pipe and others such as wall of the trench,
edge of pipe rack and etc., access for removal or maintenance for the pipe shall be
considered.
4.4.1. General
(a) Valves shall preferably be installed so that the centerline of the hand wheel shall not
be more than 1800mm above the pavement or platform levels.
(b) In case of the centerline of the hand wheel is more than 1800mm above the
pavement or platform levels, the valve accessibility shall be provided in accordance with
section 8, of this specification.
(c) Frequently operated valves, which can not be operate from grade or platform levels,
shall be equipped with remote operation device such as chain wheel or extension stem
to permit ease of operation.
(d) For valves, which operated with remote operating chain device, Chains shall hang
to within 900mm of the operating level and Spark proof chain shall be used.
(e) Valves in trenches, pit, etc., which can not be operate from a platform, shall be
provided with a stem extension, if required.
(f) Valves requiring extension stem or chain operate device, shall be noted in piping
drawings, such valves shall be specified on Isometric drawings for decision.
(g) Valves in piping arrangements shall be designed so that they do not obstruct
walkways, platforms, pass ways, etc., and yet accessible for operation.
(h) Valves at towers shall be located directly against or close to the tower nozzles
unless physical interference would prevent proper operation of the valves. Valves shall
preferably not be located inside vessel skirts.
(i) All valve outlet ends, in process services, which do not connect to a piping system,
shall be provided with a blind flange or a screwed cap/plug assembly, unless otherwise
indicated on the P&IDs.
(j) Manually operated valves, which are used in conjunction with locally mounted flow
indicators, etc., shall be placed at the same operating level and located where the
instrument can be readily observed.
(k) Valves, whose type and number are shown on the applicable P&IDs, shall be
installed on the suitable places to permit proper and safe operation of the unit.
(l) Under any condition, Valves shall not be installed with their stems below horizontal.
(m) Hand wheels of valves shall never be made of a light alloy that could melt in case of
fire.
(n) Double block and bleed valve system shall be provided only where necessary to
avoid product contamination or hazardous condition, as shown on the P&IDs.
(p) Check valves shall be suitable for installation in vertical lines with flow upward as
well as for installation in horizontal lines. They shall be used in cases where reversal of
flow may occur.
(q) All ball and plug valves shall have the ball or plug stem and lever electro statically
grounded to valve body.
(r) All gate and globe valves shall have back seat, except for 2” and smaller, inside
screw rising stem (ISRS) type valves such as bronze valves.
(s) For check, globe and any directional valves, which are insulated or coated, the
direction of flow through the valves shall be suitably marked on insulation.
c) Drain shall be installed before or behind the control valve as shown on P&IDs.
d) By pass valve and block valve shall be installed within 1800mm from floor or
platform.
f) Control valves and safety relief valves and relevant isolating valve and bypass valve,
if any, shall be located close to the platform, or on the grade for maintenance.
a) Safety relief valves shall be provided to the extent shown on P&IDs and UFDs.
c) Safety relief valves, which are not connected to flare or other disposal systems, shall
have the pipe extending at least 3000 mm above any platform or working area within a
12M radius of the point of gas discharge.
e) A 10 mm minimum weep hole shall be provided at the low point of the discharge
piping when discharging to atmosphere. Drain piping shall be provided in discharge
piping when necessary.
f) Safety relief valves shall generally have a minimum length of piping between the
protected line or equipment and the valve inlet.
g) Discharge lines from relief valves shall have a minimum use of elbows and shall be
supported and braced to prevent movement of the line due to reaction forces of the
discharge flow.
h) Safety and relief valves shall be installed with their springs in a vertical position. Any
thermal relief valves shall also be installed only with their springs in a vertical position.
I) Relief valve inlet and discharge piping shall be designed to avoid moments and forces
on the valve body.
j) Outlet piping of safety and relief valves (including flare lines) shall be designed to
prevent excessive stresses in the line resulting from larger rapid temperature changes
or from uneven temperature distribution.
a) Flanged joints.
d) Threaded joints.
4.5.2. The joint type shall be selected according to reliability, maintainability and
economy, except when limited by specific note.
4.5.3. Bolts with nut and gasket shall be used for all flanged joints, in accordance with
related pipe class of “Engineering Specification for piping Material”.
4.5.4. For piping components, joint type shall be considered in accordance with
“Engineering Specification for Piping Material”.
4.5.5. Field weld joints in alloy steel piping, shall be avoided as far as practicable, where
heat treatment is required after welding.
4.5.6. Welded carbon and alloy steel pipe shall be stress relieved when required by
ANSI B.31.3.
Welding on of attachments such as clips, brackets, etc. after stress relieving is not
permitted.
4.5.7. Threaded joints shall be used only in moderate service conditions, and
connection to instrumentation and shall not be used in corrosive, flammable and toxic
services. Unless otherwise specified, pipe thread shall be in accordance with NPT as
per “Engineering Specification for Piping Material”.
4.5.8. Threaded joints shall be made with 1” width ”PTFE” jointing tape for design
temperatures 200°C and below, and for Above 200°C, threaded joints shall be seal
welded with a full strength fillet weld.
4.5.9. All threaded joints except for instrument connection, irrespective of pressure and
temperature on lines carrying corrosive flameable and toxic fluid shall be seal welded
with a full strength fillet weld.
4.5.10.End connections for fittings shall be as indicated on the particular pipe classes in
accordance with “Engineering Specification for Piping Material”.
4.5.11. For Butt Welded joints, Pipe wall thickness shall be as indicated in the individual
pipe classes. Where a heavier pipe wall thickness is used than required by the
individual line classes, the inside of the end connection of heavier pipe or fitting shall be
machined to an inside diameter equal to the end connection of the lighter pipe or fitting
with a taper 1:4.
When in a piping class, a minimum wall thickness is indicated the wall thickness shall
be checked for the actual design conditions of the line.
When a line is subjected to full vacuum, care shall be taken that the correct wall
thickness is noted on the P&IDs or line list, If the wall deviated from the one, in the pipe
class.
4.6.3. Type of branch connections shall be selected in accordance with related pipe
class branch table, in “Engineering Specification for Piping Material”.
4.6.4. The required reinforcement shall be designed in accordance with the ANSI B31.3
4.6.5. If the wall thickness of the pipe is insufficient to sustain the pressure and thermal
stress, branch connection shall be provided with reinforcement according to
“Engineering Specification for Piping Material.”
4.6.6. Stub in connections shall be designed so that the angle of intersection between
the branch and the run is 90° unless required for process or flow reasons, and shall not
be less than 45°.
4.7.1. Vent other than indicated in P&IDs shall be provided at high points of piping of 2”
and larger in accordance with the following:
a) ¾” blank off for alloy and stainless steel piping required for hydrostatic testing
purposes.
b) ¾” threaded plugged for carbon steel piping required for hydrostatic testing purposes.
(To be seal welded after testing).
4.7.2. Drains other than indicated in P&IDs shall be provided at low points of all piping in
accordance with the following:
b) ¾” gate valve with threaded plug or screwed cap for threaded/socket welded type
valve.
4.7.3. Vent and drain arrangement in accordance with working pressure of the line shall
be mentioned and showed on the piping standard drawing.
4.7.4. Where lines are heavily insulated, vents and drains shall be provided with
sufficiently long nipple that they will project outside the insulation.
4.7.5. Vents and drains shall be 3/4" NPS, unless otherwise specified in P&IDs.
4.7.6. Vents and drains shall be readily accessible. The discharge end of all drain and
vent lines shall be so located and directed so as not to be a hazard to personnel.
4.8.1. Sample points shall not be located in dead ends of piping. They shall be easily
accessible, preferably at ground level if a part of the piping is at ground level. Sample
lines shall be as short as possible and shall not exceed 8 m in length.
4.8.3. Connections for sampling shall generally be of 3/4" couplings, unless otherwise
specified in P&IDs.
4.8.4. The sample connection shall generally be located in vertical line. When pipe is in
a horizontal or inclined plane, the sample connection shall generally be located at the
side of the pipe unless otherwise indicated on the P&IDs.
4.8.5. Type of sample connection, necessity of cooler, type of block valve and etc., shall
be in accordance with the P&IDs requirement.
5.1. GENERAL
5.1.1. This piping shall be arranged so that full access is provided for maintenance, e.g.
by cranes and trucks, and that removal or replacement of equipment can be done with a
minimum dismantling of piping.
5.1.2. Special notes for piping shown on P&IDs shall be considered as mandatory
requirements, and it shall be reflected in piping design specification.
5.1.3. Piping for pumping out equipment is a part of the process piping and shall be
provided as indicated on the P&IDs.
Pump-out piping shall be designed with a minimum possible additional piping, not
regularly required for normal start-up or operation of the process units and utilizing
process pumps.
5.1.4. Where equipment may be removed for maintenance, piping shall be supported so
that temporary supports are not required upon such removal.
5.1.5. The piping should be supported in a manner to keep forces and moments on
equipment within allowable amounts.
5.1.7. Suction and discharge lines on rotating equipment shall be supported as close as
possible to the equipment nozzles and shall be relieved of excessive piping strain by the
use of proper pipe supports.
5.2.1. Suction lines to pumps shall generally be designed to avoid pockets. Horizontal
suction lines from towers shall generally be designed to avoid pockets caused by
thermal expansion of vertical lines. Pump-suction Lines shall be as direct as possible to
avoid collection of vapor or gas when pocket is anticipated due to piping elongation in
critical services.
5.2.2. The discharge line from centrifugal pumps shall be provided with a check valve
between the pump and the block valve. For vertical discharge pumps, the check valve
shall be located in the vertical line whenever practical. Discharge valves shall have the
size as indicated on the P&IDs. Reducer shall be provided, if the pump nozzle is not the
same size as the discharge valves.
5.2.3. Suction and discharge lines of pumps shall be drained through drains located at
the low point of the pump casing whenever possible. Provisions shall be made for
draining suction and discharge lines. Suction lines may be drained through pump
casing.
5.2.4. Sealing oil systems and cooling water piping for gland, shall be furnished in
accordance with the pump vendor's recommendations. All fluids from pump drain shall
be drained in accordance with P&IDs requirement. Gland and seal oil pumping shall be
designed in accordance with relevant standard.
5.2.5. Reducers, when required in the horizontal run of a pump suction line, shall be
eccentric type and installed with the flat portion on top (top flat).
5.2.6. To avoid Cavitation in horizontal centrifugal pumps of the double suction type, the
suction line shall be arranged so that equal flow distribution to both impeller entrances,
is warranted.
5.2.7. Break flanges shall be provided, when necessary, for pumps, in order to install
temporary strainers.
5.2.8. Where necessary, provisions as spool pieces shall be made in order to facilitate
removal of internal elements, housing sections and strainers.
5.2.9. Piping shall be arranged to provide full access to all pumps, and to permit pump
removal or replacement with the minimum dismantling of the piping.
Piping shall be arranged so they do not hamper removal of pumps (especially barrel
type).
5.2.10. Thermal expansion, vibration, fabrication and erection tolerance shall be taken
into consideration, so that excessive forces and moments are not developed at the
pump casing and nozzles.
5.3.1. Generally, piping at columns should drop or rise immediately upon leaving the
nozzle and run parallel and as close as practicable to the column itself. However, for
ease of supports a number of lines can be grouped together and run parallel in one
plane.
5.3.2. For ease of operation and maintenance, columns and vessels, which are grouped
together, should have their platforms at the same elevation with interconnecting
walkways.
The nozzle for level controlling instruments shall be oriented within an angle not
exceeding 60° against the fluid inlet nozzle.
5.3.4. Drain valves on tanks and towers are to be located close to the equipment nozzle
in order to avoid water pockets, which would freeze during the winter.
5.3.5. Davit or trolly beam shall be provided on vessel over 9m high where the weight of
removable internals and/or external equipment, such as relief valves, is greater than
50Kg.
5.4. HEAT EXCHANGER PIPING - PIPING DESIGN SPECIFICATION
5.4.1. Piping shall be arranged so that they do not hamper removal of shell and channel
covers and the withdrawal of the tube bundle. It may be necessary to provide for a
pipe spool, elbow or other removable pipe piece, other than the block valve, adjacent to
the channel cover. Piping shall be so arranged as to permit removal of shell cover,
channel and channel cover with minimum dismantling of piping.
5.4.2. For inlet piping to Air Fin Cooler, symmetrical piping arrangement consisting of
multiple cascading headers shall be taken to equalize the flow to each bundle, in
accordance with the requirement of P&IDs.
5.4.3. Pockets in exchanger piping shall be provided with low point drains to avoid
freezing.
5.4.4. Enough clearance shall be provided around channel and shell flanges to permit
tightening of studs with, impact wrench during maintenance.
5.5.3. The piping shall be so designed as to permit maintenance and dismantling of the
machine with the minimum interference with piping.
5.5.6. Suction lines to gas compressors shall be designed to prevent entrained liquid
from getting into the compressors.
5.5.7. Pipe supports shall not be combined with the compressor and other foundation.
The compressor foundation shall not be combined with the compressor house
foundation. Pipe racks shall not be connected to the compressor house.
5.5.8. Requirements for removal of mill scale, etc., by chemical cleaning for compressor
piping, shall be reviewed for each individual case and indicated on the P&IDs. Where
chemical cleaning is specified, the piping design specification shall be such that this is
feasible.
5.6.1. Piping for this type of equipment shall be flexible. Refer to related specification for
piping stress analysis.
5.6.2. Design shall allow for sufficient space below turbine inlets to permit the use of a
blow down.
5.7.1. Piping at the burners, etc., shall be arranged so that it does not hamper
insertion/removal of lighting torches and burner guns. Furthermore, piping shall not
obstruct observation windows, access doors, header box covers, etc.
5.7.2. Main fuel gas block valves for each furnace shall be located 15 meters away from
the furnace it services.
5.7.3. Smothering steam lines, shall be grouped and manifold in a remote location at
least 9m from the heater and accessible from grade.
5.8.1. All piping in the system supplying sealing fluid to equipment mechanical seals
shall be furnished in accordance with the equipment vendor's recommendations.
5.9.1. Local pressure gages and pressure transmitters shall be rigidly supported on the
lines to which they are connected.
5.10.1. Sufficient distance shall be kept from tank nozzle to the first pipe support to
prevent damaging of the pipe by tank settling.
5.10.2. In general, piping within tank dikes shall be routed in the shortest possible
distance to the pipe-ways with adequate allowance for expansion and settling of tank
without crossing trough other dike-in areas.
5.10.3. Process operational valve manifold shall be located outside dike area, as much
as possible.
5.10.4. Tank farm piping shall be routed outside dike area as much as possible.
6.1.1. The steam supply for space and protective heating shall be connected to a
source that will not be shut off during unit or equipment shutdown.
6.1.2. In steam piping a steam trap shall be installed at each expansion loop, low points,
the upstream side of venturi meters, and any place condensate can accumulate and for
NPS 3” & larger, a condensate pot or drip leg (NPS 3”) shall be installed together with a
steam trap.
6.1.3. When locating steam traps upstream of venturi meters or any instrument where
the upstream or downstream piping is critical, the instrument engineer shall be
contacted to indicate the minimum distance the drain valve can be located.
6.1.4. Steam piping systems shall be supplied to the extent shown on the steam flow
diagrams and normally shall include systems for the distribution of steam required for
process operations, steam turbines, service steam and for steam tracing.
6.1.5. Steam trap hookup will be indicated in the piping design standard drawings.
Traps inside unit battery limit shall generally discharge to a condensate return system or
sewer.
Outside battery limit the traps shall discharge to a suitable location, such as ditch, or as
defined on the P&IDs.
6.1.6. All branch connections from steam and condensate headers shall be taken off the
top of the header with suitable valve.
6.1.7. In general steam exhaust line from reciprocating and centrifugal equipment,
connected to a header, shall have a single block valve as per P&IDs.
6.1.8. Single block and check valves shall be provided adjacent to the point of injection
of steam into any process stream as shown by flow diagrams.
6.1.9. All steam lines shall be designed to avoid unnecessary traps. Where traps can
not be avoided, steam traps with drains shall be designed into the piping to remove
condensate.
6.1.10. Block valves shall be provided near the header of each branch to all steam and
steam condensate Consumers.
6.1.11. Condensate lines from different coils or system shall not collect in the same trap,
but each system shall have its own trap(s).
6.1.12. All clean condensate shall run to a knockout drum, oil contaminated condensate
shall be piped up to oily water sewerage system.
6.2.1. Water lines connected to process lines or equipment where back flow may occur
shall be fitted with a check valve as shown on P&IDs.
6.2.2. Potable water shall be used for safety showers and eye bath. Safety showers and
eye bath shall be provided in accordance with P&IDs and shall be in accessible
location.
They shall also be in accordance to relevant NFPA code and related Engineering
Specification.
6.2.3. Cooling water piping shall preferably be designed to prevent draining exchangers
if water failure occurs. All exchangers shall remain full of water.
6.2.4. Main lines for drinking water, cooling water, fire water and sewer should be
underground piping.
6.3.2. All air and nitrogen branch lines shall take off from the top of horizontal mains.
Every take-off point from headers to instruments shall be furnished with a block valve,
close to the header.
6.3.3. Instrument air sub-header shall have shutoff valve closed to the main air header.
6.3.4. Size of tapping branch from instrument air header for instrument air consumers
shall conform to the following:
6.3.5 Instrument air shall not be used for any other purpose.
a) Hose station shall be provided at ground level so that all equipment can be covered
within the redius of 15m by using 20 m hose.
d) Hose station shall be provided at each Tie-in valves platform so that all valves can be
covered within the redius of 15m by using 20 m hose.
e) Hose station shall be provided at reactor top and bottom platforms so that top and
bottom nozzles can be covered within the redius of 15m by using 20 m hose.
2) The hose connections shall generally be provided with 3/4" valves and hose
connectors unless otherwise specified on P&IDs.
3) Supplied utilities shall be arranged in the order of N2 (if required), air, water and
steam from the left in operation side.
4) Steam trap shall not be required at dead end of steam connection, unless otherwise
specified by P&IDs.
5) Utilities for hose stations could be taken from any header of related area.Block valve
at take-off point from utility header shall not be provided unless otherwise specified by
P&IDs.
6) All nitrogen supply lines at utility stations shall be provided with special and different
design to prevent the accidental connection to a nitrogen line when compressed air is
required.The elevation of hose coupling and valve for nitrogen service shall be located
lower than that for other services.
7) All ground level hose station shall be provided with a steam and water mixing line to
make hot water as specified by UDDs.
8) Unless otherwise specified, general concept for hose station supplied service shall
be as follows:
Emergency showers with eye wash fountains shall be provided in areas where
operating personnel are subject to hazardous sprays or spills such as acid, caustic, etc.
in accordance with P&IDs.
6.5.2. Equipment drains shall be collected to drain system in accordance with P&IDs.
6.5.3. Oily sewer systems shall be properly trapped and sealed at manholes and
sumps.
6.5.4. Oily sewer shall be drained separate from rainwater and non oily sewer.
6.5.5. All sewer branches shall be connected to main at an angle of 60° or less.
All Piping material and components shall be selected based on items specified on
Engineering Specification for Piping Materials.
All piping items which are not coverd by Engineering Specification for Piping Material
shall be considered as Piping Special Item.
All piping special items shall be defined by tag number and listed in Piping Special Item
List.
7.1.2. The minimum pipe size shall be 4" for the buried main sewer lines, and 2" for
other buried lines.
7.1.3. Pipe size 1 ¼”, 2 ½”, 3 ½”, 5”, 7”, 9”, 22” and 26” shall not be used, except for
connection to the equipment.
In general, flanged fittings shall not be used. However, when required, it shall be in
accordance with ASME /ANSI B16.5 & ASME/ANSI B 16.47-B.
7.3.1. Elbows shall generally be used to change the direction of piping, however factory
bends and miters may be used in place of elbows.
7.3.2. In general, directional changes in piping arrangements shall be 45°, 90° and 180°
turns, other turns are subject to OWNER’s approval.
7.3.3. Miter may be used, only when specified in relavant piping class in accordant with
“Engineering Specification for Piping Material.”
7.3.4. The radius of bend shall be generally be 5 time the nominal outside diameter,
unless otherwise indicated on the P&IDs.
Short radius welding elbows (R=OD) shall be used where required for clearance
purpose and shall be indicated on piping drawings as SR.
b) Ferrous Alloy and Non Ferrous Alloy pipe: 3/4" and smaller.
7.4. FLANGES - PIPING DESIGN SPECIFICATION
7.4.1. Flanges of 24" and smaller shall be consistent with ASME B16.5, and flanges of
26" through 60" shall be in accordance with ASME B16.47 series B.
7.4.2. The use of flanges in piping shall be limited to connections at flanged equipment
(instrument equipment) and valves.
b) Where plastics, non metallic, cast iron or lining piping systems cannot be welded or
otherwise joined except by flanges.
7.4.3. Welding neck type flanges shall be used for 2” and larger piping.
7.4.4. Flange faces shall be serrated finish in accordance with ASME B16.5.
7.4.6. In general, the bolt holes of all flanges shall be straddled in vertical centerline for
horizontal piping and shall be straddled in plant north-south line for vertical piping.
7.5.1. Temporary conical strainers or wire nets for the purpose of flushing shall be
provided in suction lines of pumps and compressors, if it has no permanent strainers.
7.5.2. Any other type of strainer or filter requirement shall be in accordance with the
relevant P&IDs.
7.5.4. Duplex type basket strainers shall be used where shut down is not permitted, and
specified in the P&IDs.
7.5.5. The strainers shall be provided with connections for easy removal and servicing.
7.6.2. The valves for which by-pass are to be furnished, shall be indicated on the
P&IDs.
7.6.3. If the P&IDs require a valve body by-pass, the by-pass size shall be as follows:
a) Material specification of the by-pass line shall be same as the material specification
of the run pipe line unless otherwise specified.
1) The top platforms of the structure is located 10 m and over above the ground and
also the floor, has an area of 50 m2 and larger.
3) Platforms for equipment, which require frequent opening and/or closing of some part
once or more per day.
4) The elevated platforms more than 1.5 m height on which a sample nozzle requiring
sampling once or more per day.
3) Platform height is 1.5 m and lower even though frequent operation is required.
1) When the platform has more than 20 m traveling from a main access ladder or stair,
an escape ladder shall be provided. Dead end way shall also be restricted within 20 m.
2) Access ladders for walkway on the pipe rack shall be required at intervals of a
maximum of 60m in process plant area (on-site) and a maximum of 100 m in off-site.
For each of the above, a crossover access way to another platform or floor may be
planned in place of a ladder or stair.
https://www.inspection-for-industry.com/piping-design-specification.html