Week day HARADH&HAWIYAH FIELD GAS COMPRESSION Daily Checklist Boom Truck

Translation PROJECT
S S M T W T F
1.1 Equipment No. Date From: To:
1.2
1.3 3. Boom 1. Cabin
3.1 Pivots & Connections 1.1 Cleanliness/Housekeeping
1.4 3.2 Lever operational & Labelled 1.2 Seat Condition & Seat belt
3.3 Hook / Safety Latch 1.3 Rear View Mirrors
1.5 3.4 Wire rope / Drum 1.4
1.5
Levers / Pedals
Window glasses
1.6 Windscreen & Wipers / Washers
1.6 1.7 Operation Manual
1.8 Fire Extinguisher with colour
1.7 code/Tag

1.8
2.1
2.2
4. Hydraulics
3.1 4.1 Cylinders free from leaks
4.2 Hoses Condition
3.2 4.3 Connections (check for leaks)
4.4 Out Rigger jacks with pads
3.3
3.4
4.1
4.2
4.3
4.4
2. Lights
5.1 2.1 Front & Tail lights
2.2 Reverse & Break Light
5.2
5. Wheels
6.1 5.1 Tyres / Wheels
5.2 Brakes
6.2 6. Warning
6.3 Devices
6.1 Horn 7. Others
6.2 Reverse Alarm 7.1 Exhaust
7.1 7.2 Engine Guarding

7.2 Checks performed by Equipment Operator Verification by Field Supervisor:


initial Instructions: Indicate every day with “O” if ok, “N” if not ok, “----” if not applicable.