Professional Documents
Culture Documents
Abstract
An emergency diesel generator (EDG) is the ultimate electric power supply source for the operation of emergency engineered safety
features when a nuclear power plant experiences a loss of off-site power (LOOP). If a loss of coolant accident (LOCA) with a
simultaneous LOOP occurs, the EDG should be in the state of a full power within 10 s, which is a prescribed regulatory requirement in
the technical specifications (TS) of the Optimized Power Reactor-1000 (OPR-1000).
Recently, the US nuclear regulatory commission (NRC) has been preparing a new risk-informed emergency core cooling system
(ECCS) rule called 10 CFR 50.46. The new rule redefines the size for the design basis LOCA and it relaxes some of the requirements such
as the single failure criteria, simultaneous LOOP, and the methods of analysis. The revision of the ECCS rule will provide flexibility for
plant changes if the plant risks are checked and balanced with the specified criteria.
The present study performed a quantitative analysis of the plant risk impact due to the EDG starting time extension given that the new
rule will be applied to OPR-1000. The thermal-hydraulic analysis and OPR-1000 probabilistic safety assessment (PSA) model were
combined to estimate the whole plant risk impact. Also, sensitivity analyses were implemented for the important uncertainty parameters.
r 2006 Elsevier Ltd. All rights reserved.
Keywords: EDG starting time; ECCS rule; LOOP; LOCA; PSA; Risk impact
0951-8320/$ - see front matter r 2006 Elsevier Ltd. All rights reserved.
doi:10.1016/j.ress.2006.07.004
ARTICLE IN PRESS
962 H.-G. Lim et al. / Reliability Engineering and System Safety 92 (2007) 961–970
It was well known that a sudden start-up of an EDG EDG is automatically increased by opening a governor
may increase the EDG failure probability in real accident valve.
situations in addition to the test-induced degradations In the surveillance test procedures of the EDG [6], there
during a surveillance test. If the EDG starting time is exist two main time consuming steps to prevent a
extended to a certain value, the plant risk will be changed mechanical failure of the EDG. One is an idling operation
mainly due to (1) the increase of risk by immitigable LOCA of the EDG at the startup and the other is a load
and (2) the decrease of risk by the availability improvement sequencing. The test procedure guideline requires that the
of the EDG. EDG should be started by the ‘‘idle mode’’ by which the
Under the condition that the ECCS rule in Korea will be EDG should reach the rated speed in about 2 min. In a
revised based on the new US 10 CFR 50.46, a risk impact similar manner, when the EDG is synchronized to the
due to the EDG starting time extension is analyzed in the electric power line, the guideline also requires that the
present study. power of the EDG should be slowly increased to prevent a
This paper is composed of seven sections. In Section 2, thermal shock to the components in addition to a
the LOCA break size that cannot be mitigable under the malfunctioning of the load sequencing.
condition of an extended EDG starting time is obtained We have interviewed two plant operators relevant to the
from the thermal hydraulic analysis. Section 3 discusses the EDG surveillance test to estimate the appropriate EDG
frequency of the immitigable LOCA and the probability of starting time. One of them said that 3–5 min is needed to
a LOOP given a LOCA. In Section 4, the effect of the EDG safely startup the EDG while the other estimated 5–10 min
starting time extension on its failure probability is as the safe EDG starting time.
discussed in a qualitative manner. Finally, all the risk Based on the surveillance test procedures and the
changes due to the EDG starting time extension are interviews with the plant personnel, we estimated that the
calculated in Section 5 with the sensitivity analysis for the proper EDG starting time would be within 10 min. We
important uncertainty parameters given in Section 6. expect that the optimal and reliable EDG starting time can
be estimated if a subsequent rigorous analysis for the EDG
starting procedures is performed.
2. Determination of an immitigable LOCA break size
2.2. T/H analysis for an estimation of the critical pipe break
The extension of the EDG starting time causes the safety
size
injection (SI) to the RCS to be delayed because the electric
power supply to the SI is interrupted to start up the EDG.
Thermal/Hydraulic analysis was performed to investi-
In this section, thermal-hydraulic analysis for the RCS is
gate the reactor transient behaviors given that the EDG
performed to determine the immitigable LOCA break size
starting time is to be extended. From this analysis, the
for an extension of the EDG starting time. The extension
largest pipe break size of a LOCA that the OPR-1000
of the EDG starting time is estimated based on the OPR-
ECCS can mitigate is determined.
1000 periodic surveillance test procedure [6] and interviews
MARS, which was developed by KAERI (Korea Atomic
with the operators.
Energy Research Institute) was used as the best-estimate
T/H system analysis code [7]. The applicability of the
2.1. Estimations of a feasible EDG starting time extension MARS code has been verified by a comparison with the
RELAP5/MOD3.3 [8] verification and validation report
OPR-1000 has three EDGs for the prevention of a [9]. As core damage criteria, the 1204 1C (2200 1F) of the
station black out (SBO) accident. Two of the EDGs are for peak cladding temperature described in 10 CFR 50.46 was
a back-up for the two trains of the electric power supply used. This value has also been widely used as the core
system and the other is for an alternate alternating current damage criterion in a NPP probabilistic safety assessment
(AAC) back-up. In Korea, one AAC back-up EDG is (PSA). Since a cold leg break has severer impacts for a core
shared with all the nuclear power plant (NPP) units in a damage [10], the present study used the cold leg break as
single site. the representative break locations.
The present OPR-1000 technical specification (TS) Fig. 1 shows the calculation results for the reactor core
requires the EDG to start within 10 s to prevent a guillotine hottest channel cladding temperature for 10 min of the
break LOCA (GBLOCA) with a simultaneous loss of off- EDG starting time. As shown in Fig. 1, if the break size is
site power (LOOP). GBLOCA with a simultaneous LOOP larger than 0.4826 m (19 in), the ECCS of OPR-1000
is one of the design basis accidents (DBA) of OPR-1000. cannot mitigate the core damage. On the other hand, if
When an accident condition such as a LOCA/LOOP the break size is smaller than 18 in, the ECCS has the
occurs, the EDG will be automatically started to reach the capability of mitigating the core damage with the
rated speed by a loss of voltage signal (LOVS). After that, temperature margin of about 200 1C.
the plant control system (PCS) distributes the electric Also, we performed a sensitivity study for the critical
power to the safety-related systems, so called a load pipe break size according the EDG starting time. Fig. 2
sequencing. During the load sequencing, the power of the shows the reactor peak cladding temperature of a
ARTICLE IN PRESS
H.-G. Lim et al. / Reliability Engineering and System Safety 92 (2007) 961–970 963
2000
200
0
0 250 500 750 1000 1250
Time (sec)
Fig. 1. Reactor core hottest cladding temperatures according to pipe break sizes.
2000
Ratio of Break Diameter to Cold leg Diameter
4 min
1400 5 min 1.2 cold leg guilotine break
1200 6 min
1000 1.0
800
400
200 0.6
0
0 250 500 750 1000 1250
0 2 4 6 8 10 12
Time (sec)
EDG Starting Time(minute)
Fig. 2. Peak cladding temperature for the EDG starting time assuming
GBLOCA. Fig. 3. Critical pipe break size according to the change of the EDG
starting time.
GBLOCA as a function of the EDG starting time. From LOCA. Since the OPR-1000 PSA model does not deal with
the results, the current OPR-1000 DBA may be prevented double initiating events and there have not been any OPR-
if the EDG is started within 5 min. Fig. 3 also shows 1000 specific estimations of a LOCA frequency and a
the critical pipe break size as a function of the EDG LOOP probability, we utilized generic estimation results.
starting time. As shown in Fig. 3, the critical pipe break The following two sections describe the details of each
size is shown to exponentially decrease for the EDG information selection.
starting time.
3.1. LOCA frequency distribution
3. LOCA frequency and the probability of a loop given a
LOCA There have been several studies on the estimations of a
pipe break failure frequency [11–13]. The first systematic
To estimate a CDF increase by an immitigable LOCA, study on a piping failure in the nuclear industry was
we need information on the LOCA frequency as a function performed in WASH-1400. At that time, the combined
of the pipe break size and the LOOP probability given a years of reactor service experiences were less than 200 yr.
ARTICLE IN PRESS
964 H.-G. Lim et al. / Reliability Engineering and System Safety 92 (2007) 961–970
0.1
25 yr
40 yr
0.01
Cumulative Frequency(/yr)
1E-3
1.35X10-7
1E-4
5.0X10-8
1E-5
1E-6
1E-7
1E-9
1 10 100
-1
Reciprocality of Diameter(m )
Therefore, the pipe LOCA frequencies were based on operation years of 25 and 40 yr, the frequencies of an
experiences from other industries, that is, data from a naval immitigable break size for a 10 min EDG starting time
nuclear reactors’ experience, experimental reactors, United records 5.0E-8/yr and 1.35E-7/yr, respectively.
Kingdom military information, commercial power plants,
and the oil and gas transmission pipeline industry. The next 3.2. Simultaneous LOOP given a LOCA
NRC-sponsored evaluation of the pipe break LOCA
frequencies was carried out within Appendix J of There have been several studies to estimate the condi-
NUREG/CR-5750. The authors evaluated the nuclear tional probability of consequential LOOP following a
piping failures in this study and separate frequencies were reactor trip [15–17]. The first study for estimating a LOOP
determined for the BWR and PWR reactors, respectively. is contained within NUREG/CR-6538. Recently, EPRI
In the same time period as the NUREG/CR-5750 and USNRC independently performed a study for an
evaluation, the Swedish Nuclear Inspectorate (SKI) in- estimation of the probability of a LOOP given a LOCA.
itiated an effort to develop an international piping failure EPRI used an expert elicitation process based on service
database. Unfortunately, these estimates are not sufficient history data while USNRC used a systematic approach
to estimate the immitigable break size LOCA frequency based on the fault tree method. USNRC categorized the
because they do not discriminate among breaks with causes of a LOOP into two factors. One is by a plant-
effective diameters greater than 6 in. centered factor and the other is by that of an electric grid
Recently, the NRC has finished a study on new instability.
estimations of the LOCA frequencies by using an expert Table 1 shows a comparison of the EPRI and USNRC
elicitation process [14]. It was aimed at providing a results. As shown in Table 1, the LOOP probability
technical basis for the new ECCS rule (10 CFR 50.46). estimations of USNRC are much larger than those of
Service history data and the insights from the probabilistic EPRI. It is partially due to the fact that the probability of
fracture mechanics (PFM) with the knowledge of a plant an electric grid instability was conservatively determined by
design, operation and material performance were consoli- using the LOOP probability by a plant-centered factor.
dated to provide the LOCA frequency as a function of the USNRC used bounding values of the LOOP probability by
break size. a plant-centered factor as the LOOP probability by an
The present study used these results for the frequency electric grid instability. They accounted for this approach
estimation of an immitigable LOCA break size. Fig. 4 by stating that the relevant phenomenon for a grid
shows the estimation result for an immitigable LOCA size instability was not clearly understood, so called an
according to the years of a NPP operation for a PWR. epistemic uncertainty.
Since the NUREG-1829 estimated the LOCA frequencies In Korea, such a quantitative analysis for the LOOP
cumulatively for the break size, the results of NUREG- probability given a LOCA has not been performed as yet.
1829 were rescaled with a reciprocal of the break diameter However, it is expected that the effect of a grid instability
shown in Fig. 4. As shown in Fig. 4, for two reactor on the LOOP probability in Korea would be comparatively
ARTICLE IN PRESS
H.-G. Lim et al. / Reliability Engineering and System Safety 92 (2007) 961–970 965
Table 1
Generic conditional probability of LOOP given a LOCA
5% Mean 95%
Table 2
The causes of EDG failure to start [18]
A test An accident
lower than that in US. The electric grid in Korea is From Eq. (1), the failure probability caused by demand,
composed of lots of electric power stations including p, is expected to be relevant to an extension of the EDG
nuclear-electric, thermo-electric, hydro-electric, etc. When starting time because a failure by a demand shock will be
a NPP is tripped, the effect of the trip of a NPP on the reduced when the EDG starting time is prolonged to
electric grid is considered to be insignificant. certain values. Vessely used 9.89E-3 for the probability
In the present study, since there was no study for a assessment as a default value. However, it is not easy to
Korean-specific LOOP probability, the results of USNRC estimate what portions of the value will be reduced.
were used as the representative LOOP probability given a Therefore, a risk change by a reduction of the probability
LOCA for the OPR-1000. by a demand shock is estimated as a function of the EDG
unavailability in the next section.
4. The effect of the starting time on the EDG failure
probability 5. Estimation of the OPR-1000 CDF changes
Although the EDG failure probability is expected to be As explained in the previous sections, the CDF changes
reduced when we extend its starting time, quantitative due to an EDG starting time extension occur from two
estimations for the EDG failure probability as a function aspects. One is that the CDF increase by the appearance of
of the starting time are not clearly known. Therefore, an immitigable LOCA and the other is the CDF decrease
qualitative considerations are discussed in this section. by an improvement of the EDG availability. The following
To examine the effect of the test intervals of an EDG, sections describe each risk impact.
Vessely et al. classified an EDG unavailability for a failure
to start into five causes [18]. Table 2 shows the details of the 5.1. CDF increase by immitigable LOCA
causes. The total accident unavailability of an EDG is then
expressed by the following equation by using the first order The CDF increase by an immitigable LOCA can be
approximation [19,20]: estimated quantitatively by using the results in Sections 2
and 3. Since an immitigable LOCA may contribute to a
QEDG ¼ a2 lT þ p þ wd þ cd=T þ l0 t0 d=T, (1)
CDF under the simultaneous LOOP, a CDF by immitig-
where l is the standby failure rate, w the maintenance able LOCA can be given as follows:
frequency, c the probability of a maintenance, p the failure
CDFBLOCA=LOOP ¼ f BLOCA PðLOOPjLOCAÞ, (2)
probability per demand, l0 the operating failure rate, d the
average down time, t0 the average test time, T the EDG where CDFBLOCAL/LOOP is the core damage frequency of
mission time, a2 ¼ 1=2 if the average probability from an immitigable LOCA, fBLOCA the frequency of an
undetected failures is to be included in the accident un- immitigable LOCA and P(LOOPjLOCA) the probability
availability and a2 ¼ 1 if the maximum probability from of a LOOP given a LOCA.
undetected failures is to be included in the accident Fig. 7 shows the CDF increase by an immitigable LOCA
unavailability. as a function of the EDG starting time. The frequencies of
ARTICLE IN PRESS
966 H.-G. Lim et al. / Reliability Engineering and System Safety 92 (2007) 961–970
ccf
an immitigable LOCA were evaluated by using the results where ðcm j Þi1 i2 im is the frequency by the part of MCSs with
of the critical pipe break sizes for each EDG starting time which simultaneous mj independent EDG failure events
as shown in Fig. 3. The power supply mode of OPR-1000 and j CCF of EDGs result in a core damage, Fj=i1 imj the
during a normal operation corresponds to the first case of probability of the fraction of the MCSs which j, EDG,
the NRC evaluation, that is, ‘‘Main generator through an CCF events are included.Fj=i1 imj can be written as the
auxiliary transformer’’ in Table 1. If this LOOP probability following Eq. (7) with the constraint in Eq. (8)
is used, the mean value of CDFBLOCAL/LOOP at 10 min of X n Xn
an EDG starting time records 5.256E-10 and 1.3272E-9 for Fj=i1 ...imj ¼ ðQk1 Þimjþ1 ...imjþk
1
imjþ1 ¼1 im ¼1
the 25 and 40 yr plant operations, respectively. imjþ1 ai1 imj im ai1 im1
X
l
To investigate a risk impact due to an improvement of kh ¼ j; 2pkh pj, (8)
the EDG availability, we should know the relation between h¼1
a NPPs’ whole CDF and the EDG failure probability. P
where S h ¼ hi¼1 kh , ðQkh ÞimjþS mjþS is the CCF prob-
When the CDF of a NPP is quantified from its fault tree in ability of kh number of EDGs.
h1 h
a PSA model, the Minimal Cut Sets (MCS) can be To evaluate Eqs. (6) and (7), a method of treating CCF
classified according to the number of EDG failure events. events should be determined. The PSA for OPR-1000 uses
For a plant, which has ‘‘N’’ EDGs, the CDF of that plant the alpha factor model [21,22] for treating a CCF event.
can be expressed by the following equation in view of the With the staggered testing scheme for the EDG, the kth
EDG failure events if the rare event approximation is CCF probability is given as follows [26]:
applied: ak h
X
n ðQkh Þik þ1ik ¼ Qt , (9)
h1 h
m1 C kh 1
CDFT ¼ CSðmÞ, (3)
m¼0 where Qt is the total EDG failure probability, akh the ratio
of the probability of failure events involving kh component
where CS(m) means the core damage frequency of a set of failures in a common cause group over the total probability
MCSs which have m numbers of EDG failure events. The of all the failure events.
CS(m) can be further subdivided according to the causes of By inserting Eq. (9) into Eqs. (6) and (7), it is easily seen
the EDG failure events. The EDG may fail by two causes, that the total CDF in Eq. (3) is expressed as Nth order
that is, an independent failure or a common cause failure polynomials of Qt.
(CCF). Accordingly, CS(m) can be expressed as follows: Since OPR-1000 has three EDGs and the PSA model for
X
m OPR-1000 treats these three EDGs as a single CCF group,
CSðmÞ ¼ ðF m ÞCCF ðjÞ, (4) Eq. (4) can be written by using Eqs. (7)–(9) as follows:
j¼0
ja1
X 3
ccf 0 a1
CSð1Þ ¼ ðc1 Þi1 Qt , (10)
where (Fm)CCF(j) is the core damage frequency of a set of i ¼1 2C0
1
MCSs which have m numbers of EDG failure events in "
which j CCF events are included. When j equal 0, that is, 3 X
X 3 2 #
a1 a2
no CCF event is involved in a set of MCSs, the following CSð2Þ ¼ ðcccf 0
2 Þi1 i2 Qt þ ðcccf
2 Þ
2
Qt ,
i1 ¼1 i2 ¼1 2C0 2C1
equation is obtained: i2 4i1
X
n X
n X
n (11)
F CCFm ð0Þ ¼ ðcccf
m Þi1 i2 im ðQ1 Þi1 ðQ1 Þi2 ðQ1 Þim ,
0
i1 ¼1 i2 ¼1 im ¼1
X
3 X
3 X
3 3
i2 4i1 im 4im1 a1
CSð3Þ ¼ ðcccf 0
3 Þi1 i2 i3 Qt
(5) i1 ¼1 i2 ¼1 i3 ¼1 2C0
i2 4i1 im 4im1
Table 3
Highest 10 MCSs relevant to EDG failure to start
where Table 4
Numeric values of the coefficients
a1 X 3
a2 X 3 X 3
a3 ccf 3
d1 ¼ ðcccf
1
0
Þi þ ðcccf
2 Þþ
2
ðc3 Þ, Coefficient Value
C
2 0 i ¼1
1
C
2 1 i ¼1 i2 ¼1 2C2
1 1
i2 4i1
CS(0) 3.69E06
2 X
3 X
a1 3
a1 a2 X 3 X 3 X 3 Qt,BASE 4.49E02
d2 ¼ ðcccf 0
2 Þi 1 i 2 þ ðcccf
3 Þi 1 i 2 ,
2
a1 0.9627733
2C0 i1 ¼1 i2 ¼1 2 C 0 2 C 1 i ¼1 i2 ¼1 im ¼1 a2 0.0202
1
i2 4i1 i2 4i1 im 4im1
3 X a3 0.0168
a1 3 X 3 X 3
d1 2.25E05
d3 ¼ ðcccf
3 Þi 1 i 2 i 3 .
0
d2 1.17E04
2C0 i ¼1 i2 ¼1 i3 ¼1
1
i2 4i1 im 4im1 d3 1.20E03
CDFBASE 5.05E6
The coefficient di in Eq. (13) can be obtained from the
fault tree quantification results, that is, the MCSs of the
NPP. All the MCSs are classified according to their number 1E-5
of EDG failure events and their types of failures. As an
9E-6 Constant alpha factor(ΔQt)
OPR-1000 Core Damage Frequency(/yr)
7E-6
d 3 ¼ ðF 3 ÞCCF ð0Þ=ðQt Þ3 . (14) Current CDF
QBASE = 4.49E-2
6E-6
For a quantification of Eq. (13), the present study used CDFBASE = 5.05E-6
the KIRAP code [23], which was developed by KAERI and
5E-6
uses FTREX [24] as the quantification engine in the
KIRAP code. Under the truncation limit of 1.0E-11 for the
MCSs, KIRAP shows over 4000 MCSs, which include the 4E-6
EDG failure events. Table 3 shows several of the MCSs,
which have the largest failure frequencies in OPR-1000.
The LOOP is the initiating event for these MCSs. Table 4 3E-6
0.00 0.02 0.04 0.06 0.08
also shows the coefficients for Eq. (6). The alpha factors in
EDG Unavailability due to failure to start
Table 4 which are used in the OPR-1000 PSA model are
referenced from NUREG-5497 [25]. Fig. 5. OPR-1000 CDFtot as a function of EDG probability of failure to
Fig. 5 shows the overall OPR-1000 CDF as a function of start.
the EDG failure probability. For the default values of an
EDG failure to start probability, the OPR-1000 has 5.05E- where DCDFEEDG is the amount of CDF decrease by an
6 as a base NPP CDF. EDG availability improvement for the EDG failure to start
To obtain the risk impact due to an improvement of the events, QBASE the base EDG probability of a failure to
EDG availability, the CDF change can be given as start.
DCDFEEDG ¼ ðCDFð0Þ þ d 1 Qt;BASE þ d 2 Q2t;BASE þ d 3 Q3t;BASE Þ Fig. 6 shows a comparison of the CDF changes by an
EDG availability improvement and an immitigable LOCA.
ðCDFð0Þ þ d 1 Qt þ d 2 Q2t þ d 3 Q3t Þ, ð15Þ As shown in Fig. 6, the effect of a CDF decrease can be
ARTICLE IN PRESS
968 H.-G. Lim et al. / Reliability Engineering and System Safety 92 (2007) 961–970
1E-6 1E-8
25Yr(NRC LOOP Pr)
ΔCDFEEDG(Constant α factor) 40Yr(NRC LOOP Pr)
CDFBLOCA/LOOP at 40 years 25Yr(EPRI LOOP Pr)
1E-7 CDFBLOCA/LOOP at 25 years 40Yr(EPRI LOOP Pr)
1E-9
CDFBLOCA/LOOP
CDFBLOCA/LOOP
ΔCDFEEDG
1E-8 95 percentile
Mean P(LOOP/LOCA)
1E-10
1E-9
5 percentile
1E-10 1E-11
0.0 1.0x10-3 2.0x10-3 3.0x10-3 4.0x10-3 5.0x10-3
6 8 10 12
EDG Availability Increase(QBASE-Qnew)
EDG Starting Time(Min)
Fig. 6. OPR-1000 CDF changes due to EDG starting time extension. Fig. 7. The CDF increase effect according to the EDG starting time and
Pr(LOOP|LOCA).
larger than a CDF increase if the EDG availability is 6.2. Effect of the CCF on CDF
improved slightly.
If as expected, the EDG availability will be improved by
6. Sensitivity analysis an extension of the EDG starting time, the CDF decrease
effect will vary with the types of an EDG failure events. If
As a pilot study of option 3, the present quantification the CCF of the EDG is decreased by an extension of the
results can have large uncertainties in the estimations of EDG starting time, the entire plant risk will be reduced
their parameters. The candidates of the dominant uncer- more effectively than that of an independent EDG failure
tainty parameters in the present study are assumed to be probability.
those for a feasible extension of the EDG starting time, This section investigates the effect of the EDG starting
availability reduction effect by the EDG starting time time extension on a CCF. The following EDG availability
extension, LOOP probability, and so forth. improvement cases were assumed for the CDF decrease
In this section, two sensitivity analyses are performed to quantification:
investigate the effect of the parameters on the plant risks.
(1) independent EDG failure probability;
6.1. Effect of the EDG extended starting time and (2) double EDG CCF;
P(LOOP|LOCA) on CDFBLOCA|LOOP (3) triple EDG CCF;
(4) total EDG failure probability with constant alpha
As described in Section 2, the feasible EDG starting time factor
extension can has large uncertainties because a rigorous
analysis has not yet been implemented. When the EDG To perform such a sensitivity analysis, the change of a
starting time is changed, the LOCA break size, which basic parameter should be converted into an alpha factor
cannot be mitigated with the present ECCS is changed (see because the present OPR-1000 PSA model uses the alpha
Fig. 3). factor model.
Using the pipe break frequency estimations of NRC [14], By assuming the basic parameter of the k EDGs CCF
the frequencies of the critical pipe diameter can be probability, Qk, is reduced to Q0 k, and the new total failure
evaluated and thereby the immitigable LOCA frequency probability and the alpha factor can be represented as
can be expressed as a function of the EDG starting time. follows:
Finally, by multiplying the simultaneous LOOP probabil-
ity, P(LOOP|LOCA), with the immitigable LOCA size X
3
Q0t ¼ 2 C i1 Qi þ 2 C k1 Q0k ; k ¼ 1; 2; 3, (16)
frequency, the CDF increase in Eq. (2) can be expressed as i¼1
a function of the EDG starting time. Fig. 7 shows the iak
1E-10
This work was performed under the Long-term Nuclear
0.0 -4
4.0x10 8.0x10 -4
1.2x10 -3
1.6x10 -3
2.0x10 -3 R&D Program sponsored by the Ministry of Science and
Unavailability Reduction(ΔQk) Technology.
[16] Martinez-Guridi G, et al. Evaluation of LOCA with delayed LOOP conference on structural mechanics in reactor technology. Lausanne,
and LOOP with delayed LOCA accident scenarios. NUREG/CR- Switzerland, 1987.
6538, BNL-NUREG-52528. Brookhaven National Laboratory, 1997. [22] Mosleh A, Fleming KN, Parry GW, Paula HM, Worledge DH,
[17] USNRC. Technical work to support possible Rulemaking for a risk- Rasmuson DM. Procedures for treating common cause failures in
informed alternative to 10 CFR 50.46/GDC 35, Appendix G, Revision safety and reliability studies. NUREG/CR-4780, USNRC, 1988.
1, Memorandum, US Nuclear Regulatory Commission, 2002. [23] Han SH. PC-workstation based level 1 PRA code package-KIRAP.
[18] Vesely WE, DeMoss GM, Lofgren EV, Ginzburg T, Samanta P, Reliab Eng Syst Safe 1990;30:313–22.
Boccio J. Evaluation of diesel unavailability and risk effective surveillance [24] Jung WS, Han SH, Ha JJ. A fast BDD algorithm for large coherent
test intervals, NUREG/CR-4810(BNL-NUREG-52022), 1987. fault trees analysis. Reliab Eng Syst Safe 2004;83(3):369–74.
[19] Barlow RE, Prochan F. Mathematical theory of reliability. New [25] Marshall FM, Rasmuson DM, Mosleh A. Common-cause parameter
York: Wiley; 1965. estimations, NUREG/CR-5497. Idaho Falls, ID: Idaho National
[20] Gnedenko BV, et al. Mathematical methods of reliability Theory. Engineering and Environmental Laboratory; 1998.
New York: Academic Press; 1969. [26] Mosleh A, Rasmuson DM, Marshall FM. Guidelines on modeling
[21] Mosleh A, Siu NO. A multi-parameter, event-based common-cause common-cause failures in probabilistic risk assessment. NUREG/
failure model, Paper M7/3. In: Proceedings of the ninth international CR-5485, USNRC, 1998.