TR-0750 Truss
Instructions for EAW KF750 Loudspeaker Truss
This TR-0750 suspension truss supports the Eastern Acoustic Works KF700 series touring speakers only. Do not use for
any other purpose.

Important:
Rigging loudspeakers requires experienced, trained professionals. Improperly
installed loudspeakers can result in property damage, personal injury,
death and/or liability to the installing contractor.

Due to the wide variety of overhead structures, materials and rigging


combinations, these instructions assume that the installing contractor will
exercise proper judgment in selecting the proper rigging location and rigging
equipment.

As a guide, the installation, when completed, should be capable of supporting


ten times the actual combined applied load.

Read these important instructions for the best rigging results. Do not
exceed the working load limit of 1520 lbs./690 Kg. Use only Grade 8
supplied hardware. This truss supports a maximum of 7 (seven)
KF750 speakers in a vertical column.
Figure 1

Step 1.
Attach the hoist ring to the center hole of the hoist bracket using a 3/4” nut and
a 3/4” washer (Figure 1). Torque the nut down to 100 foot pounds.

Step 2.
Lay the TR-0750 truss on a flat surface making sure the arrows of the “ This
End Up” labels point up.

Step 3.
Mounting position of the Hoist Ring Assembly on the truss module will be
determined by the center of gravity of the array. Figure 2

Attach the hoist ring assembly to the TR-0750 truss using


two 1/2” x 5-1/2” bolts, flat washers, lock washers and hex
nuts placing the lock washer in between the nut and the
flat washer. Tighten permanently (Figure 1).

Step 4. Array/Cluster Procedures


Before starting, be sure that all cables, speakers, and
fasteners in the suspension system are capable of
supporting five to ten times the gross weight of the system.

Single Cabinet application


Capture the hoist ring of the truss with suitable rigging
equipment (Figure 3). Be sure that all hardware, fasteners,
cables and lifting chains are fitted and secured before
hoisting the truss/speaker assembly.

When hoisting, lift entire system a short distance and check


each and every connection thoroughly before proceeding.

Figure 3 Figure 4
Single cabinet Application Two Cabinet Application

 2000 APC Incorporated, Signal Hill, CA 90806 USA (562) 424-1100


040301

Two Cabinet Array Application


Permanently bolt two truss/speaker assemblies together using the two side holes of the truss with a ¾” hex bolts and
washers. Capture the hoist ring of each truss with suitable cable or equivalent rigging equipment and bridle to a pear ring
or other suitable link (Figure 4). Be sure that all hardware, fasteners, cables and lifting chains are fitted and secured
before hoisting the truss/speaker array assembly.

When hoisting, lift entire system a


short distance and check each and
every connection thoroughly before
proceeding.

Three Cabinet Array Application


Permanently bolt three truss/speaker
assemblies together using the two side
holes of the truss with a ¾” hex bolt
and washers. Capture the hoist ring of
the two outside trusses with suitable
cable or equivalent rigging equipment
and bridle to a pear ring or other
suitable link (Figure 5). Be sure that all
hardware, fasteners, cables and lifting
chains are fitted and secured before
hoisting the truss/speaker array
assembly.
Figure 5: Figure 6:
When hoisting, lift entire system a Three Cabinet Application Four Cabinet Application
short distance and check each and
every connection thoroughly before proceeding.

Four Cabinet Array Application


Permanently bolt four truss/speaker assemblies together
using the two side holes of the truss with a ¾” hex bolt
and washers. Capture the hoist ring of the two left
trusses with suitable cable or equivalent rigging
equipment and bridle to a pear ring or other suitable link
(Figure 6).

Repeat procedure to the other two right trusses then


bridle the two bridles together using a pear ring or other
suitable link (Figure 6). Be sure that all hardware,
fasteners, cables, and lifting chains are fitted and secured
before hoisting the truss/speaker array assembly.

When hoisting, lift entire system a short distance and


check each and every connection thoroughly before
proceeding.

Five Cabinet Array Application


Permanently bolt five truss/speaker assemblies together
using the two side holes of the truss with a ¾” hex bolt
and washers. Capture the hoist ring of the three left
speakers with suitable cable or equivalent rigging Figure 7: Five Cabinet Application
equipment then bridle to a pear ring or other suitable link
(Figure 7).

Repeat procedure to the three right speakers (Figure 7). Be sure that all hardware, fasteners, cables and lifting chains are
fitted and secured before hoisting the truss/speaker array assembly.
When hoisting, lift entire system a short distance and check each and every connection thoroughly before proceeding.
 2000 APC Incorporated, Signal Hill, CA 90806 USA (562) 424-1100
040301

2-3025 Hardware Kit

Item #: Qty: Description Item #: Qty: Description


1 1 pc “U-Hanger” assembly. Flat blk. 6 2 pc 1/2” Split washer, Grade 8
2 1 pc Hoist Ring 2500 lbs. WLL 7 4 pc 1/2” Flat washer, Grade 8
3 1 pc 3/4-10” Hex nut, Grade 8 8 2 pc 1/2-13 Nyloc Hex nut, Grade 8
4 5 pc 3/4” Flat washer Grade 8 9 2 pc 3/4”-10 x 2.5” Hex bolt, Grade 8
5 2 pc 1/2-13 x 5.5” Hex bolt, Grade 8 10 2 pc 3/4”-10 Nyloc hex nut, Grade 8

 2000 APC Incorporated, Signal Hill, CA 90806 USA (562) 424-1100


TR-0750-LT Truss Bar
Instructions for EAW KF750 Loudspeaker Truss
Eyebolt Suspension

This TR-0750-LT suspension truss supports the Eastern Acoustic


Works KF700 series touring speakers only. Do not use for any
other purpose.

Important:
Rigging loudspeakers requires experienced, trained professionals.
Improperly installed loudspeakers can result in property
damage, personal injury, death and/or liability to the
installing contractor.

Due to the wide variety of overhead structures, materials and


rigging combinations, these instructions assume that the installing
contractor will exercise proper judgment in selecting the proper
rigging location and rigging equipment.

As a guide, the installation, when completed, should be capable of supporting between ten times the actual combined
applied load.

Read these important instructions for the best rigging results. Do not exceed the working load limit of 1025
lbs./466 Kg. Use only Grade 8 hardware. This truss supports a maximum of 5 KF750 speakers in a vertical
column.

Make sure that all of the following items are included before proceeding:
1 pc. TR-0750-LT truss
1 pc. Hardware Kit
Box contents:
1 pc. “U-Hanger” assembly 2 pcs. ½” Split lock washer,grd 8
1 pc. Hoist ring, 2500 lbs WLL 8 pcs. ½” Flat washer, grd 8
1 pc. ¾-10 Hex nut, grd 8 2 pcs. ½-13 Nylock hex nut, grd 8
5 pcs. ¾” Flat washer, grd 8 2 pcs. ½-13 x 5.5” Hex bolt, grd 8
2 pcs. ¾”-10 x 2.5” Hex bolt, grd 8 4 pcs. ½-13 Eyebolt
2 pcs. ¾”-10 Nylock hex nut, grd 8 Figure 1

Step 1. Attach speaker to truss bar


See fixed cable instruction that comes with the speaker or the attached TR-009-FC fixed
cable instruction sheet.

Step 2.
Place the TR-0750-LT truss on a flat surface making sure the arrows of the “ This End Up”
labels and the four threaded holes face upward.

Step 3.
Attach four 1/2-13 eyebolts and 1/2” washers to the four threaded holes of the truss (Figure
1). Tighten the eyebolts permanently.

Step 4. Array/Cluster Procedures


Before starting, be sure that all the rigging gear above the truss bar can support ten times
the actual gross weight of the suspended system (1025 lbs./466 kg.).

Figure 2
 2001 APC Incorporated, Signal Hill, CA 90806 USA (562) 424-1100 03/01/01
Single Cabinet application
Attach one end using suitable rigging gear such as aircraft cables, lifting chain or span sets to each eyebolt using a rated
shackle or other suitable rigging fasteners. Loop the unattached end of the rigging gear over the overhead rigging truss or
beam and attached back to the eyebolt. Repeat for other three eyebolt (Figure 3).

Lift the entire system a short distance and check all hardware, fasteners, and lifting gear in the system to
be sure they are fitted, aimed and secured thoroughly before proceeding.

Two or more Cabinet Array Application


Permanently bolt two truss/speaker assemblies together using the two
side holes of the truss with ¾-10 x 2.5” hex bolts, lock and flat washers
and nylock nut. Attach one end using suitable rigging gear such as
aircraft cables, lifting chain or span sets to each eyebolt using a rated
shackle or other suitable rigging fasteners. Loop the free end of the
gear to the overhead rigging truss or beam and closing the loop to the
other end of the gear (Figure 4 and 5).

Lift the entire system a short distance and check all hardware,
fasteners, and lifting gear in the system to be sure they are
fitted, aimed and secured thoroughly before proceeding.

Figure 3: Single Cabinet Application

Figure 4: Two Cabinet Application Figure 5: Three Cabinet Application

Allen Products Company Inc.


1635 E. Burnett Street
Signal Hill, CA 90806 USA
Tel: (562)Signal
 2001 APC Incorporated, 424-1100
Hill, CAFax: (562)
90806 USA 424-3520
(562) 424-1100 03/01/01
Web Page: www.allenproducts.com

You might also like