You are on page 1of 7

30 Good Rules

for Connection Design


By Carol Drucker, S.E.

Practical tips for designing economical, fabricator- and erector-friendly steel connections

hen working on a steel ➜ At infill beams that support a rela- cators/erectors keep at least a ¼” differ-

W construction project, the


Structural Engineer of
Record (SER) can create
an economical structure
that is fabricator and erector friendly, es-
pecially with good communication and
tively small area.
➜ At beams with axial load.
At relatively short beams, the UDL
method usually gives overly conserva-
tive shear loads, and an upper-limit shear
load or the actual beam shear load
ence between bolt sizes to prevent uncer-
tainty.

5. Avoid different grade bolts with the


same diameter.

teamwork on the project design and con-


struction teams.
should be given.
Below are some recommendations for
6. Use bolted connections instead of
field-welded connections.
If the fabricator designs the connec- cost-effective connection design that also Bolted connections are quicker to erect
tions, sealed calculations usually need to could reduce problems in the field: and less costly. Welded connection delays
be submitted to the SER for review. Also, result from the absence of a qualified
the load criteria need to be given on the
contract documents. For moment and ax- 1. At bolted flange-plated connections,
the flange plate should not be the
same width as the beam flange.
welder or welding platforms, or cold
windy weather.
ially loaded connections, the actual de-
sign load or a percentage of the
member’s capacity is given. For shear
Allow at least a ½” difference on each side
of the flange plate at bolted flange-plated
7. Try to use fillet welds instead of par-
tial-penetration or full-penetration
welds.
connections, one of three methods (or a connections. If bolt holes misalign in the
combination) is used: field, there will be a sufficient shelf di- Fillet welds are less expensive, since no
➜ The actual beam shear loads are given. mension to place longitudinal fillet welds base-metal preparation is needed. Also,
➜ A beam shear-load schedule for differ- to compensate for the missing bolts. partial- and full-penetration welds usually
ent beam depths are given. require more weld metal and inspection.
➜ The SER specifies that the shear load
will be determined based on a per- 2. Use oversized holes in beam moment
and brace connections.
8. Limit the maximum fillet weld size to
5
/16” (especially in the field).
centage of the beam’s uniform distrib- At flange-plated moment connections or
utive load capacity (UDL). brace connections with slip-critical bolts, This is the maximum-size weld that can
If a beam shear-load schedule or a oversized bolt holes are often preferred be completed in a single pass using the
percentage of UDL is given, the actual over standard bolt holes. Although stan- shielded-metal arc-welding (SMAW)
criteria specified by the SER should sat- dard holes give a greater bolt capacity, process. Smaller, longer welds are pre-
isfy the required loading. However, the oversized holes permit more erection tol- ferred over larger, shorter welds.
criteria should not be so conservative as erance and reduce field problems. Typi-
to unnecessarily create the need for ex-
cessive typical shear connections (more
cally, oversized holes are used in the
detail material and standard holes in the
9. Avoid overhead welding.
than two vertical rows of bolts or more main member. The preferred welding positions are flat
than full-depth connections). and horizontal. Overhead welding is diffi-
For the most economical structure, it
is preferred that shear loads be given on 3. Group similar connections rather than
have several different connections.
cult, costly and generally yields lower-
quality welds. For single-pass SMAW fillet
drawings for every beam. There are also Connections on a project should be as welds, it can take four times as long as
conditions where a beam shear-load uniform as possible to save fabrication welding in the flat or horizontal position.
schedule or the UDL method do not time and reduce the possibility of errors.
apply and actual loads should be given:
➜ At beams with concentrated loads
4. Limit the number of bolt diameters to
one size (a maximum of three sizes if
10. Use full-penetration welds only
when necessary.
near the beam end. Full-penetration welds cost more than
➜ At beams sized for serviceability re- necessary). partial-penetration or fillet welds due to
quirements rather than strength re- This reduces field errors as well as fabri- increased material preparation, testing
quirements. cation errors with drill lines that have requirements, weld-metal volume and
manually changed spindles. Some fabri- material distortion. Use fillet welds (pro-

May 2004 • Modern Steel Construction


connections.

16. Specify slip-critical bolts only


when necessary.
Slip-critical bolts are not always needed at
moment and brace connections, and bear-
ing bolts might be acceptable in standard
holes. The RCSC (Research Council on
Structural Connections) Specification,
Section 4.3 gives criteria for slip-critical
joints, which are more costly than bearing
joints due to additional installation, in-
spection and faying-surface preparation.
Also, more or larger bolts are needed for
reduced bolt strength. In certain condi-
tions, fabricators/erectors might prefer
slip-critical bolts for oversized holes and
greater erection tolerance.
If slip-critical joints and bolts are
needed, the steel detailer must indicate
them on the erection and shop drawings.
The detailer should indicate masking re-
quirements in the bolt-hole area to keep
the faying surface free of coatings from
inadvertent overspray of unqualified
paint.

Use shear plate connections at beam-to-column flange-plated moment connections (see tip 20). 17. Allow bearing bolts at the shear
connection of flange-welded mo-
ment connected beams.
vided that the fabricator does not deter- essary. Excessive connections increase At directly welded moment connections
mine them excessively large) or partial- construction cost and the possibility of or flange-plated moment connections
penetration welds when joint strength is problems in the field. Over-welding can welded to the supported beam, bearing
adequate for the applied load. Full-pene- damage the steel. bolts can be used in the beam-web shear
tration welds at HSS members are diffi- connection. Since the flange weld and the
cult due to the need for backing bars.
13. Specify only prequalified welds.
web bolts are not on the same faying sur-
face, the web bolts do not need to be slip-

11. Consider finishing to bear.


The welding procedure specification
(WPS) for a weld not American Welding
critical. (See AISC’s LRFD Specification
Commentary, Section J1.9). Also, since
For connections with high compressive Society (AWS) prequalified must be the web bolts will be installed prior to the
loads, it could be more economical to fin- tested. To avoid the cost, time and confu- completion of the flange weld, the web
ish the steel to bear and provide AISC’s sion of qualification, use only prequali- bolts should be in bearing.
minimum-required weld size instead of fied welds.
transferring the compressive force 18. Limit the maximum bolt diameter
to 11/8” diameter.
through large fillet or groove welds.
When steel is to be finished to bear, it 14. Minimize weld volume at full- and
partial-penetration welds. Bolts with diameters greater than 11/8”
must be indicated on the connection de- The weld configuration with the least weld are difficult to tighten, not commonly
tail. The detail also should call for the volume is the most economical. For weld used, and costly. ASTM A490 bolts
beam flanges to be square to the beam configurations with double-sided prepara- greater than 1” diameter have a disad-
web. In detailing, stiffeners might need to tion, consider the additional cost of mate- vantage in slip-critical connections with
be longer than d-2tf for beam overrun in rial preparation, since it could offset the oversized or slotted holes. Hardened
depth and variation in beam-flange cost savings of less weld metal. For full- washers with a 5/16” minimum thickness
thickness. Per AISC Specification Section penetration welds, it is economical to prep (standard washers are 5/32” thick) are re-
M, gaps not exceeding 1/16” are permitted one side of plates with a thickness less than quired to cover oversized and short-slot-
in bearing connections. 1” and to prep both sides of plates with a ted holes in outer plies. See RCSC
thickness greater than or equal to 1”. Specification Section 6.2.

12. Avoid excessive connections.


15. Provide proper clearance for
bolted and welded connections. 19. Avoid slotted holes in plates
thicker than the bolt diameter.
Connections should be designed to ac-
tual load requirements. The SER should AISC’s LRFD Manual of Steel Construction, Slots in thick plates are hard to punch
not specify that connections be designed 3rd Edition, Parts 7 and 8, give the neces- and must be flame-cut, which is difficult
for the members’ full capacity if not nec- sary clearances for bolted and welded and costly. Standard holes or oversized

Modern Steel Construction • May 2004


holes are preferred.

20. Use shear plate connections at


beam-to-column flange-plated
moment connections.
If flange plates need to be welded to a
column flange, a shear-plate connection
is preferred. Since the column needs to be
positioned in the shop for the flange-
plate welds, the shear plate can be readily
welded.
At fully restrained moment connec-
tions, a typical shear-plate connection
can be designed for shear only (and ec-
centricity in the shear connection can be
ignored). The joint rotation is considered
resisted by the flange connections.

21. Use double-angle connections at


directly welded beam-to-column
moment connections.
To avoid double-cutting the beam, dou-
ble-angle connections (bolted to the col-
umn) are preferred over shear-plate
connections at directly welded moment
connections. At directly welded moment
connections, the beam flange typically is
set back ¼” from the face of the column
flange for welding purposes. If a shear- Consider bolted HSS bracing connections (see tip 29).
plate connection is used, the beam web
needs to be set back ½” to clear the shear- nections and how to evaluate them. Face-
plate welds, and the beam needs to be
double-cut. However, for double-angle
mounted single-angle connections are
also economical shear connections to HSS
26. Clearly show column stiffener and
doubler requirements.

connections, the beam-web set-back can The SER should check columns for stiff-
columns. eners and doublers, and if possible, in-
be reduced to permit a single beam cut.
crease column sizes to eliminate required

22. Allow for field adjustment in one


direction only at bolted connec-
25. At beam-to-HSS column moment
connections, use direct moment
connections when possible.
column reinforcement (especially dou-
blers). If the fabricator is responsible for
tions. checking the columns, the actual beam
Moment connections in which the beam’s dead, live and wind moments are needed
If slotted holes are needed at a bolted flanges or flange plates are welded di-
connection for field adjustment, the ad- at the time of bidding to determine the
rectly to the face of the HSS column are required reinforcing or alternate column
justment should be in only one direction. the most economical moment connection
This permits adjustment in one direction sizes.
to an HSS column. It is preferred over Sometimes typical details on the SER’s
while the adjustment in the other direc- cut-out plate (doughnut) or through-
tion is made. structural drawings can include prob-
plate connections. If the resistance of the lems, such as:
direct moment connection is insufficient,
23. Cope or block beams instead of
cutting flush and grinding smooth. then a cut-out connection is preferred to
an expensive through-plate connection.
1. Stiffeners might be provided unneces-
sarily.
2. It is unclear if the stiffener material is
It is less costly to cope or block a beam. If The limit states for direct moment
the beam flange must be cut flush, then Grade 36 or Grade 50.
connections are given in the HSS Specifi- 3. The stiffener weld size is not given.
specify grinding smooth only when cation in AISC’s LRFD Manual of Steel
needed. 4. The full-penetration field welds could
Construction, 3rd Edition. They include be excessive.
effective flange width, and yielding, crip-
24. For shear-plate connections to
HSS columns, use face-mounted
single-plate connections instead
pling, and punching shear and buckling
of the side walls. The HSS Specification
5. It is unclear if the SER checked if col-
umn doublers are needed.
If no information is shown on the con-
of through-plate connections. does not include the limit state for yield- tract documents, it might be assumed in-
ing of the HSS face given in equations (5- correctly that no column reinforcing is
Avoid through-plate shear connections, 2) and (5-3) in AISC’s HSS Connections
which cost more than face-mounted sin- needed.
Manual. Based on conversations with
gle-plate connections. AISC’s Hollow AISC, this limit state was omitted due to
Structural Sections Connections Manual limited testing and does not need to be
discusses face-mounted single-plate con- considered.

May 2004 • Modern Steel Construction


Cope or block beams instead of cutting flush and grinding smooth (see tip 23).

27. For simple shear connections,


allow the fabricator to choose the
AISC standard shear connection
30. Whether using ASD or LRFD, con-
sider information in AISC’s LRFD
Manual that can simplify connec-
that is most economical for their tion design and increase connec-
shop. tion capacity.
Each fabricator has a preference for a 1. Appendix J gives the fillet-weld
standard shear connection, based on strength-increase equation for welds
shop equipment, ease of erection and loaded at an angle relative to the lon-
specified shear reactions. Usually, any gitudinal axis of the weld.
AISC standard shear connection is ac- 2. Eccentrically loaded bolt-group and
ceptable. Concerns about shear-plate weld-group tables for loads applied at
connections or single-angle connections an angle from the vertical position. ★
at laterally unbraced beams are due to
the low torsional resistance of these con- Carol Drucker, S.E, P. E. is a principal at
nections. However, most beams are later- Drucker Zajdel Structural Engineers in
ally braced due to the attachment of Naperville, IL. She can be reached at
metal deck or perpendicular beams. carol@dzse.com.

28. At W-shape brace connections,


connect only the brace flanges to
the gusset plate.
For more information on connec-
tion design, see the article “57
For ease of erection and fabrication, it is Tips for Reducing Connection
preferred that only W-shape flanges con- Costs” by Victor Shneur, P.E., in
nect to the gusset plate. If the gusset plate the July 2003 issue of Modern
and the web of the brace are not the same Steel Construction (available on-
thickness, then filler plates are necessary line at www.modernsteel.com).
at the web connection. If the web needs Also, check out AISC’s new
to be connected, connect it on one side so Detailing Cards, available by call-
the brace can be erected easily from it. If ing 800.644.2400 or by visiting
only the brace flanges are connected, the www.aisc.org/bookstore for $30
section must be checked for shear lag. for AISC members ($60 for non-
members). AISC Detailing Cards

29. Consider bolted HSS brace con-


nections.
are a quick and handy reference
for the shape, gage, and strength
HSS braces commonly are shown slotted properties of steel sections and
and welded to the gusset plate. To elimi- connectors.
nate the need to field-weld the HSS
brace, the HSS brace can be bolted to the
gusset plate. A welded tee end or a slot-
ted HSS/gusset-plate connection could
be used. Design procedures for both con-
nections are in AISC’s HSS Connection
Manual. To eliminate connection eccen-
tricity, side plates also can be used.

Modern Steel Construction • May 2004


Tips for Reducing
57 Connection Costs
Victor Shneur, P.E.

A little planning goes a long way, especially with respect to steel connections.
These helpful tips should help you keep bolts from driving you nuts, and welds
from torching your temper.

onnections can be expen- tions. Drawings that don’t show actual sive—and sometimes impossi-

C sive, and they can take a lot


of effort to create during
the design and construc-
tion process. How can you
save time and money—and make
everybody’s work easier when work-
ing with connections on fast–track
end reactions can lead to costly and un-
safe connections.

4. Always provide complete load


paths (including transfer forces)
where there are axial forces. Keep load
paths simple.
Favor factored end reactions
ble—copes in the W8.
■ Favor W12 and W14 sections for
typical gravity columns. The dis-
tance between flanges makes web
connections easier.
■ Consider using heavier member sizes
to eliminate stiffeners (see Tip 18).
schedules? Here are some general
guidelines for structural engineers for
5.
(ASD).
(LRFD) over service end reactions ■ Provide adequate flange width at
perimeter members. Provide beams
the design of economical bolted and Provide details that clearly repre- that frame slab openings to support
welded connections for columns,
beams and braces.
6. sent the design intent. They will
eliminate misunderstandings and save
deck and pour stops, and to weld
studs.
Communication is key. Develop a time. Use A36 steel for connection
1. working design-build team for
fast-track projects—with the fabricator 7. Use standard AISC connections
when possible.
12. angles, and plates for typical
connections.
and erector on board. The main bene- Don’t be excessively conser- Specify readily available an-
fits are:
■ Design requirements can be con-
8. vative—connections need to with-
stand only design loads.
13. chor rods. Often, the rods are
delivered in a rush immediately after
veyed accurately. Simplify as much as possible. For the contract has been awarded and be-
■ Everyone’s expertise can be utilized.
■ Detailing can start quickly.
9. example, make column-base de-
tails symmetrical, use the same spacing
fore communication has been estab-
lished between fabricator and engineer.
■ Duplication of work can be avoided. for expansion anchors and minimize When possible, use standard
■ “Revise and Resubmit” on ap-
provals is avoided.
the number of sizes of slab edge clo-
sures/pour-stops. This expedites the
14. tolerances established by
ASTM A6/A6M, the AISC Code of Stan-
■ All parts work together without fabrication and erection process and dard Practice for Steel Buildings and
“surprises.” greatly reduces the number of possible Bridges (www.aisc.org/code), and
■ Paperwork is minimized. mistakes—and repair costs. AWS. Tighter tolerances will increase
■ Your best chance for cost savings. Check structural drawings for costs and construction time substan-
■ Good working environment.
Connection approvals should
10. constructability issues.
Review the member sizes for
tially.
Avoid overly restrictive specifi-
2. occur in a timely manner. Detail-
ers need connections immediately for
11. connection economy:
■ Preferably, a supporting beam should
15. cations.
Don’t “over-specify” details—
fast-track project delivery. Make ap-
proval comments clear. Confusing
have at least the same depth as the
supported beam.
16. you might not be aware of fab-
rication/erection procedures, required
notes cause misinterpretation and ■ Don’t frame W8 beams into the clearances, etc.
more paperwork. webs of heavy W-shapes or plate

3. Engineers should always provide


all end reactions, including shear,
girders. The thick flanges of the
heavier shapes will require exces-
17.

Moment connections:
Eliminate when possible. For exam-
moment, torsion and axial end reac- ple, you can use a cantilever at the

Modern Steel Construction • July 2003


Least Weight Isn’t Heavier Columns Specify ASTM A36
Always Least Cost Minimize Stiffeners Connection Material
roof in lieu of two moment connec- ■ Complete each released area as Never use bolts with the same
tions to the column.
■ Provide actual moments/moment
much as possible.
■ Size members conservatively.
31. diameter but different
strengths on a job—it can lead to mis-
envelopes and vertical end reac- ■ Consider using field-welded con- takes.
tions. nections for openings. Use short-slotted holes in out-
■ Favor extended end-plate moment
connections. Refer to AISC Design
■ Immediately inform fabricator of
the areas of possible substantial re-
32. standing legs of connection an-
gles, end plates and single-plate
Guide 4: Extended End-Plate Moment visions. connections.
Connections for design information. Provide for tolerances—use When loads are large, consider
■ Shop weld short cantilevers.
■ Moment connections to HSS
23. oversized, short-slotted, and
long-slotted holes in bolted connec-
33. larger diameter bolts and/or
ASTM A490 bolts.
columns are usually very expensive. tions, and leave extra space for welded ■ Bolt material cost is roughly propor-
Stiffeners can complicate con- connections. tional to strength.
18. nections for framing beams.
■ Specify only when required. 24. Make embedded plates a min-
imum 6” to 8” larger than re-
■ Higher strength bolts save in con-
nection material, hole making, and
■ Wherever possible, use partial- quired for connections. Field fixes for installation cost.
depth stiffeners. embedded plates that are mislocated Consider excluding bolt
■ AISC’s SteelToolTM Clean Columns
v3.1 can help avoid column stiffen-
are time and money consuming.
Clearly identify all changes
34. threads (X-bolts) for:
■ Heavily loaded connections where
ers. It’s available
www.aisc.org/steeltools.
at 25.
drawings.
and revisions on design typical bolt size doesn’t give enough
capacity.
■ Refer to AISC Design Guide 13: Wide- When shop or field errors re- ■ Shop assembled trusses.
Flange Column Stiffening at Moment
Connections for designing and speci-
26. quire correction:
■ Request an as-built report. It clearly
■ Connections when outer plies are
3
/8” thick or larger.
fying stiffeners. shows the problem and eliminates Use slip-critical connections

19. Favor one-sided shear connec-


tions (single-angle and single-
misunderstanding and misinterpre-
tation.
35. for:
■ Bracing connections with oversized
plate), but avoid expensive through- ■ Discuss possible solutions with fab- or slotted holes.
plate connections at HSS columns. ricator or erector. ■ Field-assembled trusses with over-
Rule of thumb: The more ■ Keep in mind: labor is expensive, sized holes.
20. pieces there are in a connection
detail, the more expensive it is to fabri-
material is relatively inexpensive.
■ As a rule of thumb, fast decisions
■ Members with short/long-slotted
holes when force applies parallel to
cate and erect. and approvals are required to con- the slots.
Give some thought to the de- tinue the work. ■ Built-up compression members.
21. sign of column splices:
■ Do not specify to “develop the full
■ Remember that not every error re-
quires correction.
■ Cyclic loads.
Where fully pretensioned bolts
bending strength of the smaller
shaft.” This is not always necessary. 27. Wherever possible, specify
bearing joints. It makes the
36. are needed, permit the use of
any of the four methods approved by
■ Use field-bolted column splices for most economical use of bolts, elimi- RCSC and AISC:
moderate uplift forces. nates masking or a special paint sys- ■ Turn-of-nut.
■ Minimize the number of splices, es- tem, and reduces installation and ■ Calibrated wrench.
pecially for HSS columns. Some- inspection requirements. ■ Twist-off-type tension-control bolt.
times it is more economical to Use snug-tightened joints as ■ Direct-tension-indicator.
extend the lower shaft for another
level than to add a splice.
28. much as possible.
Favor ¾”-diameter A325 bolts 37. Mechanically galvanized
ASTM A325 bolts provide ex-
■ For W-column splices with PJP or
CJP welds at flanges, favor web
29. for typical structures.
Try to limit bolt diameters to
cellent corrosion resistance and require
a minimum overtapping of nuts and
channel(s) over temporary flange
lugs wherever possible. This will
30. 1” or smaller. Larger diameters
require special equipment, larger spac-
easier pretensioning.
Keep your bolt holes as ra-
make detailing, fabrication and
erection easier.
ing and edge distance, and special 5/16”-
thick washers (ASTM F436) for fully
38. tional as possible:
■ Don’t use different hole sizes in the
Design-build projects require pretensioned ASTM A490 bolts. same member. It leads to mistakes
22. extra attention:

July 2003 • Modern Steel Construction


Keep Bolt Holes Member Reactions Single-Pass Fillets
One Size Per Piece Simplify Detailing Are Cost-Effective

and slows fabrication because shop hydrogen process: “Minimum weld


re-tooling is required for the piece. size is dependent upon the thinner of
■ Don’t specify slots in material the two parts joined.” Favor Fillet Welds
thicker than bolt diameter plus 1/8”.
The AISC Specification doesn’t allow 44. Use intermittent fillet welds
when possible.
Over Groove Welds
punching holes in such material, Use AISC Specification Appen-
and it is difficult to make slots. A
good alternative would be to use
45. dix J2.4 for fillet welds. This al-
lows an increase in strength of the fillet
oversized holes. weld based on direction of the force. Slip-Critical Joints
■ Use the same oversized holes in all Note: Per AISC it is also acceptable for ex-
plies if it is possible. tended end-plate moment connections. Only When Needed
■ Use long-slotted holes in girts and Favor fillet welds over groove
any members that must be field-
aligned to tolerances other than
46. welds. Groove welds are usu-
ally more time consuming.
standard steel framing tolerance (for Favor PJP welds over CJP
example, curtain wall connections).
Correctly apply AISC require-
47. welds.
Allow full-strength connec-
39. ments for fillers:
■ Fillers in slip-critical joints are not
48. tions in lieu of CJP welds in
statically loaded structures. Fillet
required to be developed. welds up to ¾” are more economical.
■ Fillers up to ¼” thick can be used in Specify effective throat size or
bearing joints without reduction in
strength.
49. required strength for welds.
Allow the use of groove-
■ Fillers up to ¾” thick don’t have to be
developed if the design shear strength
50. welded joints with a prepara-
tion that minimizes weld metal
of the bolts is multiplied by the factor volume.
[1 - 0.4(t – 0.25)], where t is the total
thickness of the fillers up to ¾”.
■ Fillers over ¾” must be developed
51. Leave weld access holes open.
Inspect critical CJP welds with
by bolts or welds, in or outside of
the joint.
52. Ultrasonic Testing (UT).
Avoid the “weld-all-around”

40. Leave extra holes open. In al-


most all cases they don’t need
53. symbol. It is expensive, and in
a lot of cases it’s not required—and
to be filled, and filling takes a lot of sometimes it’s even prohibited.
time (think labor costs), especially for Avoid shop welding on galva-
thick members. 54. nized surfaces.
Layout welds to reduce re-
41.

Avoid over-welding.
The weld doesn’t need to be
55. straint, especially for large
welds. This lowers the possibility of
stronger than base metal in any lamellar tearing.
case. Favor horizontal and flat posi-
■ Excessive welding can cause serious
problems (distortion, cracking, etc.).
56. tions. Let gravity work for you.
Try to minimize field-welded
This can lead to expensive repairs or
even rejections.
57. connections and favor field-
bolted connections. ★
■ Weld connection elements for actual
forces. Victor Shneur, P.E. is a chief engineer
Use single-pass fillet welds with LeJeune Steel Company in Minneapo-
42. where possible. A 3/8” fillet
weld requires 44% more material and
lis, MN. He is a member of the AISC Com-
mittee on Manuals and Textbooks. This
100% more labor, but it is only 20% article was adapted from the paper Mr.
stronger than a 5/16” fillet weld. Shneur submitted for the 2003 NASCC,
Use AWS D1.1 rules for mini- “How to reduce the cost of common struc-
43. mum weld size. Per AWS
D1.1/D1.1M:2002, Table 5.8, for low-
tural steel connections.”

Modern Steel Construction • July 2003

You might also like