Project Title: - Dismantling of existing walls and Supply, Installation Gypsum walls and other scope as
agreed for Office in Al Idrisi Tower – Amir Sultan Road Jeddah
Herewith this service contract declares that the Party – A has sub-contract the following table scope of
work to Party – B.
S Description QTY Total Amount
N
01 Gypsum Walls Dismantling a Waste removal from the site Lot
02 Construction and Assembling of Gypsum wall partition with material 6
supply. Material should be water and fire proof.
03 Supply and Installation of Walls Corner Cornish for all office. Lot
04 Repairing all Damaged parts of the office and complete painting. As per Lot
29,500.00 SAR
site situation.
05 Wooden windows and doors wood bordering with material supply Lot
06 Washrooms and Kitchens Floor Tiling with material supply Lot
07 Washroom Seat and Basin Installation Lot
08 Gypsum rooms insulation for sound proof. Lot
Total Amount: - Twenty-Nine Thousand Five Hundred (Saudi Riyals Only) 29,500.00 SAR
GENERAL TERMS: -
a- Party – A mentioned the required scope of work in the above table along with the price.
b- The given scope of work is in lumpsum price. Any conflict between the both parties the scope
will be calculated on progress percentages work completed at site according to the current
market price.
c- Party – B agreed to finish the work within 25 days from the date of this contract.
Party – A Hail Towers Est. For Contracting Party – B Zeeshan Abdul Ghafoor
Representative Usman Nadeem
Signature Signature
Date Date
This is certifying that the below mentioned payments has been paid to Zeeshan Abdul Ghafoor
for the Service Agreement No # HT-2021-MW-01
SN Description Date
01 Advance Payment 5000.00 SAR
02 Progressive Payment 5000.00 SAR
03 Progressive Payment 8000.00 SAR
04 Progressive Payment 5000.00 SAR
Total Amount Received 23,000.00 SAR
Party – A Hail Towers Est. For Contracting Party – B Zeeshan Abdul Ghafoor
Representative Usman Nadeem
Signature Signature