(ely Ny ttt Riyadh Public Transport
wg fe
RIYADH METRO
Package 3 (Lines 4, 5 & 6)
at King Abdulaziz Project for >
a
Inspection and Test Plan for Screed Application in Floors -
LINE 4
M3-CJV-ITP-EAR00-GEN-000003 AA
(Sub-Contractor Organization):
TS Author | Ghee [Ghee | Aneved
asian ovsiaion Destpaon Designation
bate & Sone Dale & Spine baie Sustee bai & Stare
GJV Organization: _ ee
Author Site Manager Line aalac Line Manager Project Manager
| Mohammad Ahmady Booun Hong Kiyeon Kwon Hoiyong Chung | Ignacio Gutierrez
cecomen | ote | aan | peste |fpetomn
MW bbed | biked) -
02-62. andy | \ 3-fab- (§ | aga ly 2
FAST Organization
[ Checked ei Reviewed Approved
Designation Designation Designation Designation
Date & Signature Date & Signature Date & Signature Date & SignatureRiyadh Metro Package 3 (Lies 4,58 6)
Inspection Test Plan for Applcaion of Coal Tar Epoxy Paint For Sanitary
‘Sewerage Manholes - Rev. AA
DOCUMENT CHANGE RECORD
| Date Change Description Author
AAI 01-02-2018 Creation ‘Mohammad Ahmady
AA 01-02-2018 First Submission to RAMPED ‘Mohammad Anmady
'MG-CJV-ITP-EAR00-GEN-000008 AA ‘01/02/2018 Page t oftINSPECTION CHECKLIST [gt ils.
Solin
CONCRETE SCREED PLACEMENT
Name of Prose Contactor
RIVADH METRO PROJECT PACKAGE 3 FAST Cu
Item Description: ‘Area/Unit:
Rateroce Drawing Naz Rev. [TP Nor Tatvy No,
Now
Schetdled Inspection Date & Tine: | RAMPED Inspocton | Gorvactornapesfon Lovet IA No
tev
a ACCEPTANCE CRITERIA rerenence | accept | nevect | WA
1 Surtace Preparation Inaction
Examine substrates (Oampratng / Waterprooting or condlons
attoctngpoformance of sree, Pro Spee
“ sen aot,
Proceed with appletion only aferunsetistectorycondions have been | “asi A
corrected
Verify that base slabs meet finish and surface profile requirements in Pro}, Spec.
12 | jslon 8 Secion'Cashin Place Concrete” secon 544,
2 Material Recelving inspection
Concrete Seroed shall be accepted ihe temperature isbolow 620. | _ Pro). Spee
21 | Conctle Screed temperature ht exceeds $2 shallbo acta.” | Sedton OSs,
Actual creed Temperature *c. Max. 20) Pan 301.4
Concrete Setod Stump shal be accepted as per approved Mix
ap | Boson 20s046mm ony Ave
Actual Slump: _ mm. 7
3 instalation inspection
arande porto proceed placing of concrete sree:
1. Verify the IRs of Damproofing for non-wet areas (If Reqired)
na Watorpovtng lr wo! ares ony, ite aoopted
31 spproved by FAST AMPED. sor
2. Discipline clearance form shall be signed by Site Engr. to
ensure tat the embeded ern ere complete and at
requledinspecions havo been performed.
fap | Check nstaled Angle bars (Galvanized Polycarbonate andi =
bord instucing lock-out as er Approved Shop drawing
sag | Suey or conoree sored op elevations has been conducted and is
Reporte wae accepted by FaevRampod
Place screed continuously in a single layer, tamping and consolidating Proj. Spec.
3.4 | toachieve tight contact with bonding surface. Do not permit cold joints | Section 03544,
for seams to develop within pour stp peaea
| — Proj. Spec.
a8 | screed sutac witha salghtadg and sttko oo content elevations. | Section 09564,
Pat!
Pei Spo,
28 | stipe euanes utomly whe ieee, secon Sosa,
ranaaoe
te ACCEPTANCE CRITERIA rerenence | accept | nevect | NA
'M3-C)V-FOR-GQAO0-M50-014182 Rev. AA
Page 1of2ae Fe
INSPECTION CHECKLIST
oo
eae
CONCRETE SCREED PLACEMENT
a7 | Bean iia foating wing bul oats to forma untorm and open- hth Sea
-7 | textured surtace plane tre of humps or hollows. len SE.
Finishing: Consolidate surlace with hand loat as soon as soreed.can | pao, Spec
4.7_| support equipment and operator. Re-saighion, cul down high spots, | scion dst,
And fil low spots. Repaat float passes and re-sraighioning until surface
is left with a uniform, smooth, granular texture. Petase
Hard Trowel Finish: Alte floating surace, apply ist trowel finish and
ag | consolidates scroedby power-driven trowel so na bisters develop, ee
Continuo trowoling passoo and ro-sraighton unl cufavo le amooth and | Selon O54
tuniform in texture.
Finish and measure surface so gap at ny point between soreed
tag | surlace and an unloveledtteestanding mong straightedge, resting | P'S,
an two high spots anc placed anywhore onthe surface, doos not aout:
exceed 6.4 mm,
Moisture Curing: Keap surfaces continuously moist for not lass than ee
aro | Seven days with water or absorptive cover, water saturated and kept | PL Spec.
Continuously wet. Cover sereed surfaces and edges with 200-mmlap | Seulon 09544,
over adjacent absorptive covers.
a Final Inspection
Comprossve Strength (28 Days) Tost Reports as peroquroment ot | pig, spo
a1 | ASTMC 109/C 109M. (C20, 10mm Aga.) ‘Section 63532
‘Actual Comp, Strength:___Mpa Pee
‘Compressive Strength (28 Days) Test Reports as per requiromont ot | pag, spec
42_| ASTMC 109/C 109M, (C20, 5mm Agg.) Sootion 03522
Actual Comp. Strength:, Mpa Peters
FEMARKS:
REFERENCE DOCUMENTS:
SUB-CONTRACTOR QA/QC/SITE RAMPED QA/ac
ACTORS FAST QAlac
NAME: NAME: NAME:
‘SIGNATURE SIGNATURE SIGNATURE:
DATE: DATE DATE:
M3-C]V-FOR-GQAO0-M50-014182 Rey. AA
Page 2012ITP - Inspection and Test Plan for Screed Application in Floors -
Document No:
M3-CIV-ITP-EAROO-GEN-000003
ly . Revision: aa] AA
SS f2 et REF: Method Statement : M3-CIV-MST-EARSF-GEN-000001 Pages: 2
7 ir es M3-GEG-MST-EAROO-ELS-000002
Yoana ataee , Date: 2-Feb-18
REF: Check List : M3-CIV-FOR-GQA00-M50-014182
: ‘ 3 4 5 e 7 8 M
Activity Description of : {Qc Form Verifying Record ips eve
No | Actvity/inspection item | !sPection andTesting Method | Reference Documents Accoptance Criteria Ret: ee Breet Pr] | bere Peale Pe ear [ee
1._|GENERAL REQUIREMENTS (ie Mix Design Approval-Materials Approval, etc.)
a. Approved MAR
lb. Approved IFC Shop a. Riyodh Metro Station ané Buildings Ja. Approved Method Statement |a-Technical Manager
Drawings Specication Section 03544 part2-__fb.ThirdParty Test Reports |b,aavacengineer _|eriorto work
1. fa. Concrete Mix Design Approval Ja. approval of Mi 1
i sale prigee Walt concrete Delvery Receipt Products, Clause 2.1 Screed fc. Approved Checklist # M3-CWVe.third Party commencement eee | aie
a. Approved Method Materalso3532 For-canoo.ms0.014182 —_|Representative
Statement
.Approved Method
ee gaa Statement a Riyadh Metto Station and Buildings Ja. Approved Checks #: M3-CVa.Technical Manager Ipc to york
1.2 _|o. Approved Drawings epee Ib. Approved IFC Shop Speciation Section 03sad part1- _|ron-caaoomsoo1sis2 —_|b.aavac engineer : nf ]er
7 Drawings General, Clause 1.1 Related Documents eamecrren
a. Delivery Receipt Ja. Approved Shop Drawings 2. Riyadh Metro Station and Buildings Rae ae
1.4 |awire mesh (applicable) —_b.Review af Receipt Ib. Approved MAR specication Section 03544 Part 2- amin BNE tach delvery | 4 | w | w
esamping Jc. astm 185 Products, clause 2.1 Screed Materials Sins Fa,
Representative
a.visual Inspection/Documents _Ja.FASTHSE plan Heath and Safety conditions as per asite Wse :
5 |1H5€ requirement/safety eh a.Documents a:continueus
es es approved FASTHSE plan Pe Representative En Sele ink
2._ [Execution of Screed Appli Floors
a.Approved Method a.Approved Checklist &:3-clv-
surface Preperation eveing _|?™8H8 Inspections statement a. Riyadh Metro station and Buildings |FOR-GQAOOMSO.014182 Ja. surveyor _b.aw/ac
aa” | Seen b-Survey Levels b. Approved Drawings specication ection 03544 Part 3- _b.survey Report Engineer csite [Before Pouring nH] ow |w
MEP Clearances Execution Clause 3.1. and 3.1.b Engineer
Installation inspection ;
| Approved checklist #m3-Cv-
Embedded items Angles- ; lAporoved MS / ; ste engineer/ac
22 eed taneertreae, eer |Mstallnspection estes Approved Ms / Shop Drawings or-caxoo-msocisea [Pere Prior to placement aw] fw
Jc Mcp clearance
Boards & Block-out
Page 1 of 2i ee b No: M3-CIV-ITP-EAROO-GEN-000003
ITP - Inspection and Test Plan for Screed Application in Floors - Line 4 ee
wy aoe ik
>» KS fa et REF; Method Statement ; M3-CJV-MST-EARSF-GEN-000001 Pages: 2
" 7 re ere M3-GEG-MST-EAROO-ELS-000002
YY rst et ata Date: 2-Feb-18
REF: Check List : M3-CJV-FOR-GQA00-IM50-014182
9
1 2 6
3 4 5 7 8 ion Level
Activity Description of ae ere ; QC Form/Verifying Record/ Inspeet
wi Aetiviy/inmecton tem | msPeetlon and Testing Method | Reference Documents Acceptance Criteria Ref: ens Responsible Person | inspection Frequeney. [TRAM ove
eo | (4
+Siump & Temperature
leach Delivery/Truck)
set of 3
la.witness- ‘Approved Mi fi
23 [recat rfenal ss esate " BS SACISOR \Specification Section 03544 Part 2 FOR-GQA00-M50.014182 aus M a ; H}| w lw] te
Prod le 1 Scree laterials fest Report Ie =) eee
IC. Approved MAR tS Canis he eee acta preet hespor Technician: Jeach subsequent 460 sq.
m, but not less than 6
samples for each
day's placement.
Ja.Witness-ASTM C 143 and ASTM |a.Approved Method ja. Riyadh Metro Station and Buildings |a.Approved Checklist #: M3-CIV-|a.QA/QC Engineer
24 Jeuring Jc 1064 statement Specification Section 03544 Part 2- | FOR-GCADO-Ms0-014182 [site Engineer specity as per Specs n}wls
fb, Aci 309n Products, Clause 2.1 Sereed Materials
a.a/aC Engineer
checking of screed level after a.Approved Checklist #: M3-CIV
la, Aproved SD a. Riyadh Metro Station and Bulldings bsite Engineer lon all carpet ane epoxy
A | dryness (only at carpet and epoxy}a. Visual Inspections w
2A |armness (only at carpet and enony|a.Visual Inspect b.Survey Report [Specification Section 03544 POR SSOADD MiE0-010182 [c.Site Supervisor floors WW H
foors)
jd.Surveyor
Ja.Approved ITP Ja. Riyadh Metro Station and Buildings —_|.Approved Checklist #: M3-CIV-|a.QA/QC Engineer
2.5. |Repair of Concrete Screed (itany) |a.Visual Inspections l>.Approved Materials for repairs [Specification Section 03544 Part 3- FoR-Gaaoo-ms0-014182 b.site Engineer [On all defective areas H] ow fw
Execution, Clause 3.6.A Repairs site Supervisor
Prepared By:
l= Hold point: Attendance required & signature on IR is @ must to proceed
following work Mohammad Ahmady - QA Engineer
IW = Witness point: Attendance expected & signature on IR is required, but
if the signatory is not present to sign at the time, follow on work may "
: Signature:
lproceed and the IR document(s) signed later. Revived By lapatires
Surveillance point: Random attendance, no signature is required on IR
lor its accompanying documentation. ohiannerad AWG OM Ene ear 9 VL e
IR = Review of record: It may be in addition to any of the other codes. CAA
[For any inspection level: | = Information/Report shall be provided by those Approved By: Signature:
|who are responsible for the Inspection.
“ Kiyeon Kwon —L4 QA/QC Manager
(*): To be specified case by case. E.g. Independent Laboratory
Page 2 of 2