You are on page 1of 2

Pre-commissioning Checklist

Information to be provided to the commissioning engineer prior to order completion.

Following mackwell receiving this document two weeks notice will be needed before the site visit.

Please be aware that once a system is configured any Mackwell devices contained therein will perform a full
commission cycle.

SITE ADDRESS / DETAILS: ENGINEER:

COMPANY:

CONTACT DETAILS:

DATE:

ITEM DESCRIPTION YES NO N/A

1 Installation

1.1 Are all emergency control gears manufactured by Mackwell Ltd. (or its affiliated companies or
partners)?

1.2 Are all emergency luminaires / exit signs installed to the relevant requirements, standards
and codes of practice for emergency lighting installations (e.g. EN 1838, BS 5266-1)?

1.3 Are all emergency luminaires / exit signs powered from the unswitched mains supply?

1.4 Do all emergency luminaires / exit signs have batteries connected and are charging or are
fully charged (flashing or steady green LED indication)?

1.5 Are all emergency luminaires / exit signs connected to an N-light control panel DALI loop?

Does the specification of DALI cable meet the requirements for mains rated cable?
1.6

Maximum length of any single DALI loop < 300m?


1.7

NLIGHT001 Rev1 mackwell.com Page | 1


ITEM DESCRIPTION YES NO N/A

Does the specification of DALI cable meet the following conductor cross-sectional area?

0.5mm2 for line length < 100m


1.8 0.75mm2 for line length < 150m
1.0mm2 for line length < 200m
1.5mm2 for line length < 300m

Is measured voltage drop <2V between farthest communicating devices on each DALI line?
1.9

1.10 Maximum of 64 devices per DALI loop?

2 Identification of Emergency Luminaires / Exit Signs

Is there a copy of the building plan available to the commissioning engineer showing the
2.1
position of all emergency luminaires / exit signs?

Have all emergency devices had their GTIN / serial number and location name recorded on
2.2
the building plan or device location record sheet?

In case of "NO" to item 2.2, are GTIN / serial number labels attached to an external visible
2.3
surface of the luminaire / exit sign?

Test Schedule and Grouping Information

Important Note: the following information should be determined and agreed between the building owner / occupier and
3
responsible maintenance engineer. Groupings and test schedules should be configured to be compliant with the relevant
requirements for automatic testing of emergency lighting systems (e.g. to ensure that adjacent emergency luminaires do not
enter test or re-charge periods at the same time).

Have emergency luminaires / exit signs been planned into a grouping scheme suitable for the
3.2
application of automatically scheduled testing?

Has a testing schedule for the groups been defined and agreed with the building owner /
3.3
occupier?

4 Site Safety

Will commissioning engineers need any personal protective equipment that is not provided
4.1
on site? Provide details below

Date Time Location

Will commissioning engineers need to complete a site induction and what time will this take
4.2
place?

If there are any issues found with the installation is there an electrician/maintenance engineer
4.3
on site to assist with rectification?

NLIGHT001 Rev1 mackwell.com Page | 2

You might also like