Professional Documents
Culture Documents
This article was published in ASHRAE Journal, July 2015. Copyright 2015 ASHRAE. Posted at www.ashrae.org. This article may
not be copied and/or distributed electronically or in paper form without permission of ASHRAE. For more information about
ASHRAE Journal, visit www.ashrae.org.
Steven T. Taylor
VAV systems are the most common HVAC system for commercial buildings, but
design practices vary widely around the country and even among design firms in
a given area. Some of the variation is due to local construction practices and labor
costs, but most of the variation, in the author’s experience, is due simply to how
engineers are taught by their mentors in their early years of practice; design tech-
niques and rules-of-thumb are passed down through the generations like family
cooking recipes with little or no hard analysis of whether they are optimum from a
life-cycle cost perspective.
This month’s column compares various VAV box inlet
FIGURE 1 VAV sensor error under different inlet conditions for 8 in. inlet VAV box
and outlet duct design options including their impact (Figure 7 from RP-1353 Final Report3).
on first costs and pressure drop. It focuses on single duct
VAV reheat systems, but most of the principles apply 25
to other VAV system variations, such as dual duct and 20
VAV Airflow Reading Error (Percent)
32 A S H R A E J O U R N A L a s h r a e . o r g J U LY 2 0 1 5
COLUMN ENGINEER’S NOTEBOOK
TABLE 1
VAV box inlet ducts off rectangular main (based on 8 in. inlet box, 630 cfm, 1,500 fpm duct main velocity).
D 8f 8f 10f
Option
Application Note 1 1 1 2 2 2 3, 4 3, 4 3 4, 5 4, 5 5, 6
1. Not recommended
2. Recommended for most VAV boxes but not at low velocity main ducts or for “obviously critical” VAV boxes
3. Recommended when VAV box is at a 45° angle to main (not shown in option figure)
4. Recommended for “obviously critical” VAV boxes
5. Recommended at low velocity main ducts (see Figure 3)
6. Recommended for VAV boxes that are greater than about 15 ft from main
the critical zone will vary due to variations in internal 75 years. To get a 15-year payback, no more than 20%
loads, weather, sun angle, etc. It is possible for most of the potentially critical zones could be ducted using
systems that 50% or more of the zones can be the most Option D, but the designer would have to figure out in
critical at any given time (see Figures 6 through 8 in advance which zones are potentially critical. Option
Taylor & Stein4). This would require that the first cost C has similar economics: it is less expensive than
penalty of Options C or D would apply to many zones, Option D but not as efficient.
not just one. So instead of using Options C or D at all zones, they
For example, simulations of a 60,000 cfm (28 000 should be used in special cases only:
L/s) VAV system serving an Oakland office build- •• Use Option C for VAV boxes that are at a 45° angle
ing showed that adding 0.15 in. w.g. (38 Pa) to the to the duct main. This eliminates the cost and pressure
fan design pressure for Option B versus D increased drop of the 45° elbow shown in Table 1.
energy costs only a few hundred dollars per year. That •• Use either Option C (a bit less expensive) or D (a bit
would result in an excellent payback if one particular more efficient) for “obviously critical” zones. This will
zone was always the critical zone and Option D were require some engineering judgment on the part of the
only applied to it. But if all 70 zones in the system designer. Examples include zones that are a long dis-
were designed using Option D, the payback would be tance from the main or zones that are expected to be at
*Neither the ASHRAE Duct Fitting Database nor the SMACNA HVAC Systems Duct Design Manual includes this tap type. Pressure drop is estimated by author based on comparison of other similar fittings.
J U LY 2 0 1 5 a s h r a e . o r g A S H R A E J O U R N A L 33
COLUMN ENGINEER’S NOTEBOOK
high loads for many hours per year, FIGURE 2 VAV duct main design: “Start fast and end slow.”
such as those serving an equipment
room. 2,030 fpm 8f 8f 8f 10f DP = 0.25 in. 10f
•• Use Option D for zones tap- 0.232 in./100 ft
ping into low velocity mains. One
28 × 18 28 × 18 28 × 18 28 × 18 28 × 18
technique for sizing duct mains
is to “start fast and end slow,” as
shown in the top half of Figure 2. 8f 8f 8f 10f 10f
Rather than using conservative 1,370 fpm 8f 8f 1 in./100 ft 8f 8f DP = 0.24 in. 8f
duct design sizing techniques, 0.094 in./100 ft
such as a constant 0.1 in. w.g. per
100 ft friction rate (80 Pa per 100 42 × 18 34 × 18 28 × 18 20 × 18 16f
m) for duct mains, this technique
uses a higher starting velocity and 8f 8f 8f 8f 8f
friction rate and then keeps the
duct main the same size for long
distances, e.g., up to 60 ft (18 m). This results in FIGURE 3 Tap pressure drop vs. duct main velocity (from ASHRAE Duct Fitting Database).
lower first costs due to eliminated fittings but re-
sults in similar overall pressure drop. The pressure 1.2
drop of the taps to VAV boxes also benefits from 1 8 in. Conical Tap
Tap Pressure Drop, in. w.g.
the lower velocities at the end of the duct main, 10 in. Conical Tap
0.8 12 in. Conical Tap
but only to a point. As shown in Figure 3, when the 0.6
duct main velocity is much lower than the velocity
0.4
in the tap (less than about 60%), the pressure drop
0.2
through the tap starts to increase. So VAV boxes at
the end of the main should use Option D. 0
500 700 900 1,100 1,300 1,500 1,700 1,900 2,100
Note that none of the options includes a manual Duct Main Velocity (fpm)
volume (balancing) damper upstream of the VAV box.
They are never necessary in VAV systems with pressure
independent controls; the VAV box controls provide the inlet but also note that their VP sensors are in fact
continuous, dynamic self-balancing. designed to allow for poor inlet conditions that fre-
Note also that Option D shows a tapered reducer at quently occur due to space constraints.
the inlet to the box. Many engineers will include two
or three duct diameters of inlet-sized duct between VAV Box Discharge Duct Design
the reducer and the box to ensure that the velocity Table 2 shows options for discharge plenums from VAV
profile at the velocity pressure sensor is uniform. This boxes. Both applications with and without 1 in. (25 mm)
is unnecessary. As shown in Figure 1, the “oversized” duct liner are shown. Duct liner is not allowed for some
inlet resulted in the same VP accuracy as the straight occupancies (e.g., hospitals) and is discouraged due to
“hard” inlet. Furthermore, in the research project indoor air quality concerns in consistently humid cli-
upon which Figure 1 is based, the 10 × 8 reducer was mates, but it is still standard practice in many areas of
only 8 in. (200 mm) long, much more abrupt than the the country. The cost of liner is generally close to being
taper shown in Option D of Table 1. net first cost neutral with the same duct outside dimen-
Figure 1 also shows that even having a 90° elbow sions (OD) since the unlined duct must be externally
directly in front of the VAV box has little impact on insulated in the field.
VP sensor accuracy. VAV box manufacturer’s instal- Option B is the least expensive lined duct option.
lation instructions encourage using SMACNA’s rec- The OD of the discharge plenum matches the dimen-
ommended three duct diameters of straight duct at sion of the box outlet so that a simple “S and drive”
34 A S H R A E J O U R N A L a s h r a e . o r g J U LY 2 0 1 5
www.info.hotims.com/54430-12
COLUMN ENGINEER’S NOTEBOOK
TABLE 2 VAV box discharge ducts. Based on 8 in. inlet box, three 210 cfm diffuser taps.
14 × 12 1/2 OD
14 × 12 1/2
12 × 10 OD
14 × 12 OD
5 ft
12 × 10
Option
duct connection can be made without any fittings. larger box; in other words, the box in this example
This has the disadvantage of increasing plenum with an 8 in. (200 mm) inlet but the box/coil of a
velocity and the liner also creates an abrupt reduction standard 10 in. (250 mm) box costs the same as a
in free area right after the coil. To avoid those losses, standard 10 in. (250 mm) box. Care must be taken to
Option C includes a 1 in. (25 mm) flange around the make VAV box equipment schedules very clear of the
VAV box discharge so that the inside dimensions (ID) design intent since this is non-standard construction.
of the plenum matches the coil dimensions. (This For instance, include coil size in the schedule and
could also be a standard duct transition, but the include a note in the “Remarks” column noting the
flange is usually a bit less expensive and takes up less non-standard construction.
space.) Unfortunately, the flange is expensive when This oversized box/coil option is recommended with
shop fabricated and it is not available as an option and without duct liner. An option with a discharge
from most VAV box manufacturers. Its costs can be flange like Option C is also possible but it is not likely to
offset, however, if it avoids the need for shop fabri- be cost effective because the pressure drop of the over-
cated square-to-round taps to diffusers; the larger sized plenum is already low.
plenum height allows for larger standard diffuser One valuable side benefit of Options D and E is the
taps. improved waterside performance of the coil resulting
But a better option in any case is to oversize the from the increased heat transfer area: the coil leaving
heating coil by using the next-size-up box and coil water temperature with the oversized coil is about 10°F
instead of the box and coil that comes standard with to 15°F (5.5°C to 8°C) lower than for the standard coil.
the inlet size. In this case, the box and coil are for a This reduces flow rates, pump size, and pipe sizes, and
standard 10 in. (250 mm) VAV box but the damper can improve the efficiency of condensing boilers. It can
and velocity pressure sensor are still 8 in. (200 mm). also allow low temperature water systems, such as those
This is a “special” order from most VAV box manu- using condenser heat recovery, to work effectively with a
facturers but the cost is usually the same price as the two-row coil.
36 A S H R A E J O U R N A L a s h r a e . o r g J U LY 2 0 1 5
COLUMN ENGINEER’S NOTEBOOK
Option A
Option
10f
14 × 12 1/2 OD
A. Straight Tap B. Conical Tap C. Square-to-Round
Relative
Base $20 $80
First Cost Option B
Pressure Drop 0.01 0.00 0.00
(in. w.g.)
Application 1 2 2
Note 10f
2. Not recommended
J U LY 2 0 1 5 a s h r a e . o r g A S H R A E J O U R N A L 37
Taps to outlets should be near the that it loses the acoustical benefit of
end of the plenum to gain its full the discharge plenum. The plenum
acoustical benefits and to avoid is beneficial acoustically even if
“cushion head” losses. Straight unlined.
taps should be used; conical taps •• Option C is almost the opposite
have negligible pressure drop of Option B: it is composed of all
benefit but add to first costs and rectangular duct except for flex-
may not always fit into the side ible duct to diffusers. This is usually
of the plenum whose height is the most expensive design because
generally determined by the rectangular duct costs more than
VAV box dimensions. For diffus- round duct and it is less flexible to
ers close to the plenum, the tap making field changes, e.g., offsetting
should include a volume damper; to miss a sprinkler pipe or cable tray
a straight tap with damper is a requires one or two shop fabricated
standard off-the-shelf item. For fittings. In addition to the shop and
diffusers that are more remote material cost, there is usually an
from the plenum, a round branch added labor cost to deliver the mate-
duct is used with reducing wyes rials and possibly a time delay while
with volume dampers at each it is being fabricated.
diffuser. Some contractors will Option A is recommended for
find it more cost effective to duct almost all applications.
all diffusers independently from
the plenum since it eliminates Conclusions
fittings and gangs volume damp- This column summarizes various
ers in a central location for ease duct design options for VAV boxes,
of balancing. With this option, all both upstream and downstream
ductwork is round except for the and makes recommendations
discharge plenum. This lowers based on lowest estimated life-
costs not only because round duct cycle costs. The recommendations
costs less than rectangular duct, are generally practical and easy to
but also because it is easier to implement.
make coordination offsets in the
field. For instance, if the work- Acknowledgments
ers find a sprinkler line or cable The author would like to thank
tray in the way of a hard round Eddie Patterson and Todd Gottshall
duct run, adjustable elbows (with of Western Allied Mechanical for
sealed joints) can be easily insert- providing the cost estimates pre-
ed in the field. sented in this article.
•• Option B eliminates all rectan-
gular ductwork. This design is often References
favored by contractors that do not 1. ASHRAE. 2002. “ASHRAE Duct Fitting
Database,” version 6.00.04.
have coil-lines for fabricating rect- 2. SMACNA. 2006. HVAC Systems Duct
angular plenums. It increases the Design, 4th edition.
number of joints and fittings, but re- 3. Lui, et al. 2012. “ASHRAE RP-1353,
Stability and Accuracy of VAV Box Control at
ducing wyes and adjustable elbows Low Flows,” Final Report.
are easily obtained off-the-shelf. The 4. Taylor, S., J. Stein. 2004. “Sizing VAV
one big disadvantage of this design is boxes.” ASHRAE Journal (3).
www.info.hotims.com/54430-18
38 A S H R A E J O U R N A L a s h r a e . o r g J U LY 2 0 1 5
THE POTTORFF LINE OF MIAMI-DADE SEVERE DUTY LOUVERS
Pottorff supplied our EFD-637-MD louvers for the Memory Care facility in the
Oakmonte Villages Luxury Senior Retirement Community in Lake Mary, FL.
Pottorff Representative: ADE Engineered Solutions of Florida, Inc.
EFD-637-MD
ECV-645-MD
ECD-545-MD