Professional Documents
Culture Documents
Signature
Filename
Description
Signature
Filename
Description
Signature
Filename
Description
Signature
Contents
Page
1 Key Considerations 3
1.1 Clients Requirements 3
1.2 External Influences 4
1.3 Internal Considerations 5
1.4 Buildability 6
1.5 Building Form 7
3 Loads 32
3.1 Dead Loading 32
3.2 Typical imposed loading 34
3.3 Imposed loads on barriers 35
3.4 Fire 36
3.5 Horizontal Loads 37
3.6 Snow Loads 39
3.7 Seismic Loads 41
3.8 References 44
4 Stability 45
4.1 Checklist 45
4.2 Load Paths 46
4.3 Horizontal Stability Systems 47
4.4 Vertical Stability 48
4.5 P∆ Sway effects 50
4.6 Braced and unbraced vertical stability systems 50
4.7 Shear Walls 51
4.8 Moment Frames 52
4.9 Stability serviceability performance criteria 52
4.10 References 53
5 Reinforced Concrete 54
5.1 Reinforced Concrete Beams 54
5.2 Concrete floor slabs 57
5.3 Columns 62
5.4 Reference 64
6 Prestressed Concrete 65
6.1 Advantages of prestressed concrete 65
6.2 Basics 65
6.3 Tendon parameters 68
6.4 Design considerations 70
6.5 References 72
7 Non-composite steelwork 73
7.1 Rules of thumb 73
7.2 Columns 78
7.3 Struts and ties 78
7.4 Portal frames 79
7.5 Element stiffness 82
7.6 Connections 83
7.7 Fire protection 83
7.8 Corrosion protection 84
7.9 References 85
9 Timber 90
9.1 Rules of thumb 90
9.2 Materials 90
9.3 Material Strengths 91
9.4 Timber Element Sizes (domestic) 92
9.5 References 93
10 Masonry 94
10.1 Joints 94
10.2 Vertical load resistance 95
10.3 Lateral loading 97
10.4 Stability 102
10.5 Internal Non-Loadbearing Masonry Walls 103
10.6 Reinforced masonry 104
10.7 References 104
Appendices
Appendix A
Useful Design Data
Introduction
This publication is intended to be used, as the title suggests, as a
structural concept design guide. It should be readily available both in and
out of the office environment.
This document is for distribution only within the Ove Arup
Partnership. It is not intended for and should not be relied upon
by any third party.
The term concept design represents a preliminary stage in the overall
design process whereby the basic principles, spatial and cost parameters
of the structural design can be understood by all parties involved. To
attain this level of design it is expected that the engineer will utilise
preliminary sizing, rules of thumb, informed judgement and appropriate
assumptions. The concept design will take account of an appropriate level
of risk, representing an adequate basis for the development of the design
and final construction detailing, from which the established basic principles,
spatial and cost parameters will be maintained within an appropriate and
acceptable margin of error.
This guide aims to gather useful facts, figures and hyperlinks for use in the
development of a sound structural concept design. It should be used in
this context and where necessary or appropriate supplemented with
additional reference material.
Given the nature of this guide there may be instances whereby the
information given is not appropriate for a particular application. The
engineer should always rely on their own skill and judgement when using any
guide for design. We intend that this guide continues to evolve to suit the
collective needs of the users and as such we ask that you feed back any
suggestions in relation to further editions. Please send any constructive
thoughts in relation to suggestions, corrections, or future content to
UKMEA-CDG@arup.com
- Chris Carroll
1 Key Considerations
What do we know
and what is unknown?
Financial constraints,
budget, fee?
What have we
agreed to do?
Key drivers?
Do we need to deal
with external bodies? What are the ground
NR, LUL, Water conditions?
Authority etc.?
What is the
architect’s vision?
Site services,
External adjacencies,
tunnels, existing
Influences basements and
foundations
What is the
programme? Does it
What is the affect our design on
performance how it is built?
requirements of the What can we
building? challenge?
Is there anything
special about the Have we done this
building? Is additional before?
research required?
Have we reviewed
the load paths
Can we simplify the horizontally and
concept design to vertically?
avoid unnecessary What are the
secondary effects risks and
on the structure? opportunities?
How can we improve
on previous
examples?
How can we
rationalise the
design?
1.4 Buildability
How will it be
External built and
maintained?
Influences
Is there any
lead in items?
What temporary
works will be
required and how
practical is this?
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Ribbed floor Medium structural depth Harder to adapt for
Relatively lightweight changes once constructed;
Offices Good flexibility for holes not flexible to penetration
Retail between ribs through ribs
Reasonably adaptable, Propping required, (table
6m to 9m span within configuration of system with formers)
ribs, throughout design Detail at top of partitions
(until cast) difficult
Reasonably adaptable for Slow reinforcement fixing
fixing of cladding Difficult to provide larger
No downstands make aid holes adjacent to columns
services distribution Services cannot be secured
No additional fire to ribbed soffits
protection required to Cost of fire stopping/sound
structure insulation at wall heads
Medium site lead – in Complexity of cantilever
time construction adjacent to
existing building
Slower reinforcement fixing
and formwork stripping
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Coffered floor Medium structural depth Harder to adapt for
Relatively lightweight changes once constructed
Offices Good flexibility for, Propping required (table
holes within pots system with formers)
7m to 10m span Reasonably adaptable Slower reinforcement fixing
for changes prior to and formwork stripping
concreting Larger number of
Reasonably adaptable reinforcement bar works
for fixing of cladding Difficult to provide holes
No downstands for easy adjacent to columns
services distribution Services cannot easily to
No additional fire secured to rib soffits
protection required to Cost of fire stopping/
structure sound insulation at wall
Medium site lead-in time heads
Reasonably simple
cantilever construction
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Omnidec (lattice Medium speed of Harder to adapt for
plank) precast hybrid construction changes once
floor Relatively lightweight constructed.
Reasonable easy to Propping required
Car Parks modify for changes prior Order (lead-in) period for
Houses to concreting precast units
Reasonably adaptable for Slow reinforcement fixing
6m to 8m span fixing of cladding to spine beams
No additional fire Complicated formwork
protection required to along spine beams
structure Difficult to provide larger
Medium site lead-in time holes adjacent to columns
Minimum formwork Complexity of cantilever
Can substitute insitu slab construction adjacent to
for precast units at existing building
service hole locations Precast units require
Flat soffit for easy placement by crane
services distribution Variable soffit surface
quality
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Hollow core precast Medium speed of Harder to adapt for
floor construction changes once constructed
Lightweight Propping required (at
Car Parks Reasonably adaptable for spine beams only)
fixing of cladding Order (lead in) period for
6m to 8m span Flat soffit for easy hollow core precast units
services distribution Difficult to provide large
No additional fire holes in beams adjacent to
protection required to columns
structure Complexity of cantilever
Medium site lead-in time construction adjacent to
Minimum formwork existing buildings
Can join with in-situ Complicated reinforcement
topping or through- detailing in spine beams,
depth joints to form slow to fix
diaphragm Complicated formwork
along spine beams
Differential tolerance of
precamber
Precast units require
placement by crane
Variable soffit surface
quality
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Precast planks and Provides large column- Deep structural zone
composite topping on free areas May need to haunch
prestressed beams Relatively quick to prestressed beams to
construct reduce overall structural
Car Parks depth on grid lines
Relatively heavy structure
14m to 16m span Precambering may be
required
Susceptible to vibration
Susceptible to differential
load cases (common in car
parks)
Precast units require
placement by crane
Low point-point resistance
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Precast planks on Lightweight (smaller Downstand beams restrict
steelwork foundations) services distribution
Fast construction Longer lead-in
Retail Least requirement for Most expensive for
Schools ‘wet’ trades cladding fixings and
supports and least
4m to 9m span buildable
(Although precast Greatest structural depth
planks become thicker Flexibility for future
and heavier as the services penetrations not
span increases) good
Difficult to modify before
and after construction
Precast units require
placement by crane
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Composite slab Lightweight (smaller Downstand beams restrict
foundations) services distribution
Offices Easy to fix services to Medium lead-in
Retail slab soft More expensive cladding
Reasonable easy to fixings and supports with
modify before reduced buildability
Up to 12m span (with construction Greater structural depth
secondary beams) Decking can be part of (and greater height of
steelwork contract and cladding)
avoids temporary Propping required
formwork Fire protection require to
Fast construction structure
Could utilise slimdek Susceptible to vibration
system to reduce Complexity of Cantilever
structural depth construction adjacent to
building
Steelwork requires
placement by crane
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Composite slab with Longer spans / larger Large openings (in girders)
cellular plate girder column free areas may require stiffeners
Reduced floor to floor Deflection may become
Car Parks height through critical at mid-spans (may
Offices integration of structure need to consider
Retail and services precambering)
Cellular girders are not
10m to 20m span good for point loads
Typically secondary
beams spacing 2.4m
to 3m
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Composite slab with Taper (or haunch) Increased fabrication
tapered or haunched provides zone for costs for haunched order
plate girder services in zone or Greater midspan
minimum moment deflections to consider,
Offices with longer Larger column-free floor may require precambering
clear spans area
Reduced overall floor to
10m to 20m span floor height through
Typical secondary integration of
spacing 2.4m to 3.0m structure/services
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Precast Planks and Composite Reduced overall Increased
Topping on Steelwork with Ledger structural depth fabrication costs
Angles Fast construction Poor flexibility for
Fewer ‘wet’ trades future services
Retail penetrations
Schools Difficult to modify
Car Parks before and after
construction
with composite topping 9m span
without topping 6m span
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Slimflor system – Minimum structural depth Perceived as expensive
precast units and for steel Tends to produce
structural topping heavier structural steel
tonnage
Offices
Propped: 9m span
Unpropped: 7m span
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Slimdek system – Flat soffit Heavier overall
Composite slab Composite action without structure than
shear studs traditional decking
Offices Decking can be Perceived to be
Residential unpropped up to 5.5m expensive
Hotels (dependent upon slab
weight
Propped: 9m span Partial integration with
Unpropped: 5.5m span services can be achieved
using holes through
beams
Floor Type,
Typical Uses Advantages Disadvantages
And Spans
Precast plank with Better acoustic properties on Limited number of
concrete topping beam line than standard ‘I’ standard sized beams.
on Deltabeam beam
Offices
5m to 10m span
If settlements become
excessive deep foundation
might be required. Cyclic
loading may cause larger
settlements.
Spread footings may
settle excessively or
require use of low bearing
pressures. Any later
disturbance to the sand by
vibration, groundwater
changes or seismic loading
for example may cause
large settlements.
Consider mat (raft)
foundations or consider
compacting sand by
vibroflotation or other
method then use spread
footings.
Driven / CFA piles could be
used. Driven piles would
densify the sand.
Deep foundation
penetrating through fill are
appropriate. With piles or
piers consider stopping in
upper zone of sand layer to
limit consolidation of clay
layer. Also consider
replacing poor fill with new
imported, compacted, fill,
then use spread footings in
the new fill. Calculate
settlements due to
consolidation of clay under
complete load of new
structures.
Offices & retail 6.0, 7.2, 9.0, 10.5, 12, 15m grids
Some retail outlets 5.5m or 11m grids (to suit shop units)
Car parks (7.5 or 7.2) x (15 to 16m) grids (see section 2.5)
Approx.
Coaches 12.00 - 4.00 - -
13.5m
2.5.5 Headroom
Recommended minimum height: 2.050m through the building.
If motor caravans are to be used, allow approx. 2.300m.
Check if there are any specific access requirements e.g. emergency
vehicles.
2.6 References
1. Ove Arup & Partners, Building Services Concept Design Guide
http://www.steelconstruction.info/Engineering_students%E2%80%99_guide_to_multi-
storey_buildings
4. ISTRUCTE, Design Recommendations for Multi-Storey and Underground Car Parks (Fourth
edition), 2011
3 Loads
3.1.1 General
In the absence of specific details, use the following:
Services:
Nominal 0.25
HVAC 0.4
External walling:
Curtain walling and glazing 0.5 on elevation
Cavity walls (lightweight block/brick) 3.5 to 5.5 on elevation
3.1.2.2 Cladding
Cladding Arrangement Dead Load on Elevation (kN/m2)
Cladding sheeting and fixings 0.5
Steel wall framing only 0.25 - 0.4
Framing + brick panels and windows 2.4
Framing + steel sheeting 0.75
Windows, industrial type 0.25
Patent glazing: single 0.3
double 0.55
Doors: industrial wood 0.4
Lath + plaster + studding 0.5
Plate glass / 25mm thick 0.65
3.1.2.3 Walls
3.1.3 Roofs
Description Dead load on plan (kN/m2)
(Assuming flat)
Bitumen roofing felts (3 layers
0.29
including chipping)
Ceiling tray/panels 0.25
Asphalt (19mm, 25mm) 0.41, 0.58
Tiles (clay laid to 100mm gauge) 0.62 to 0.70
Concrete tiles interlocking 0.48 to 0.55
C – Areas Areas with tables, etc. (Schools, cafes, restaurants, 2.0 to 3.0 3.0 to 4.0
where people receptions)
may
congregate Areas with fixed seats. (Churches, theatres or 3.0 to 4.0 2.5 to 7.0
(with the cinemas, lecture halls) (4.0)
exception of
areas defined Areas without obstacles for moving people 3.0 to 5.0 4.0 to 7.0
under (Museums, hotels, hospitals)
category A, B
Areas susceptible to large crowds (Concert halls, 5.0 to 7.5 3.5 to 4.5
and D)
sports halls Inc. stands)
Corridors & Hallways (residential / public institutions 3.0 / 4.0 / 5.0 4.5
& hotels / trolleys & wheeled vehicles)
Stairs & Landings (residential / institutions & hotels) 3.0 / 4.0 4.0
Walkways (600mm wide / regular two-way traffic / 3.0 / 5.0 / 7.5 2.0 / 3.6 / 4.5
high density including escape routes)
Dance halls, gymnasia, stages / Drill halls (EC 5.0 / 7.5 3.6 / 4.5
category: Areas with possible physical activities)
δc 10 mm 100 mm
Note: where δb = 0 use F = 150 kN for mass of vehicle = 2500 kg.
The mass of 1500kg is taken as being more representative of the vehicle
population than the extreme value of 2500kg.
3.4 Fire
Minimum Periods of Fire Resistance
Purpose group of building Minimum periods (minutes) for elements of structure in a:
Basement storey Ground or upper storey
Depth (m) of a lowest Height (m) of top floor above ground, in a building or
basement separated part of a building
More than Not more Not more Not more Not more More than
10 than 10 than 5 than 18 than 30 30
1.Residential (Domestic)
a. Flats and maisonettes 90 60 30* 60**┼ 90** 120**
Not
b. and c. Dwelling houses Not relevant 30* 30* 60@ Not relevant
relevant
2.Residential
a. Institutional (oe) 90 60 30* 60 90 120#
b. Other residential 90 60 30* 60 90 120#
3.Office
Not
a. Not sprinklered 90 60 30* 60 90
permitted
b. Sprinklered (2) 60 60 30* 30* 60 120#
6. Industrial:
Not
a. Not sprinklered 120 90 60 90 120
permitted
b. Sprinklered 90 60 30* 60 90 120#
Single storey buildings are subject to the periods under the heading *not more than 5*. If they have basement
storeys are subject to the period appropriate to their depth
$ The floor over a basement (or is there is more than 1 basement, the floor over the topmost basement
should meet the provisions for the ground and upper storeys if that period is higher.
* Increase to a minimum of 60 minutes for compartment walls separating buildings.
** Reduced to 30 minutes to any floor within a maisonette, but not if the floor contributes to the
support of the building.
ce Multi-storey hospitals designed in accordance with the NHS Firecode document should have a minimum
60 minute standard.
# Reduced to 90 minutes for elements not forming part of the structural frame.
+ Increased to 30 minutes for elements protecting the means of escape
┼ Refer to paragraph 8.10 regarding the acceptability of 30 minutes in flat conversions from “The
building regulations 2000: Fire safety”
@ 30 minutes in the case of three-storey dwelling houses, increased to 60 minutes minimum for
compartment walls separating buildings.
NOTE 1 This map is intended for sites in the United Kingdom, Isle of Man and Channel Islands only.
NOTE 2 The isopleths in the Irish Republic are shown for purposes of interpolation only.
2 0.40
3 0.50
4 0.60
5 0.70
6.5 0.85
Shape Coefficient µ1
Angle of Pitch a 0o ≤ a ≤ 15o 15o ≤ a ≤ 30o 30o ≤ a ≤ 60o a ≥ 60o
Flat Roof 0.8
Choose simple structures with clear load paths, avoiding poor connectivity
between the diaphragm and lateral resisting system. For example, avoid
remote cores or large voids near walls.
Ensure that diaphragms remain elastic beyond yield of the vertical system.
Permit damage only in inherently non-critical elements (for Life Safety). For
example, damage in beams rather than columns.
Coupled Shear Walls Similar to cantilever walls, but Large foundation forces
the yielding is controlled to Ductile detailing required for
occur within coupling beams the coupling beams may have
linking the walls, rather than at constructability challenges
the base of the wall
Timber frame with sheathed panel Very good performance, Height limitations (generally
shear walls lightweight four stories or less)
Relatively easy to construct
Steel moment frame with Sliding A Moment Frame, but uses May give higher accelerations
Hinge Joints friction rather than steel thus not low damage for non-
yielding to dissipate energy. structural systems
Thus a low damage detail for
the structure
Supplemental Dampers Not a lateral system, but may Damping components need to
be used to enhance be designed to
performance displace/deform enough for
Higher than Life Safety them to be effective
performance is possible May not be effective for very
stiff structures (or use
geometric amplification
devices)
3.7.3 Foundations
3.8 References
1. BS EN 1991-1-1:2002 Eurocode 1: Actions on Structures – Part 1-1: General actions –
Densities, self-weight, imposed loads for buildings, (2010)
3. ISTRUCTE, Manual for the design of steelwork building structures to Eurocode 3 (2010)
4. ISTRUCTE, Manual for the design of concrete building structures to Eurocode 2 (2010)
5. Tata Steel Construction, Comflor Brochure, Composite floor decking February 2013
11. PEER (Pacific Earthquake Engineering Research) Centre Report No 2010/05 “Guidelines
for Performance-Based Seismic Design of Tall Buildings”
4 Stability
The following information has been sourced from the IStructE, Stability of
Buildings series.
4.1 Checklist
Consideration Checked
Are minimum and maximum gravity load cases considered?
Actions – Are wind, soil, ground surcharge and hydrostatic lateral forces considered?
applied:
Are accidental and extreme actions including impact, fire and earthquakes
considered?
Will actions result from the restraint of arches, domes, catenaries, nets?
Will actions result from the restraint of post tensioning and other elastic
strains?
Second-order
Is the structure sway sensitive / do P∆ effects need to be considered?
P∆ effects:
Combination of Are all governing combinations for all elements / failure mechanisms
actions: evaluated?
Are movements understood and quantified?
Accommodating Are corresponding forces (actions and reactions) allowed for throughout the
movement: load path?
Are all parts of the structure adequately served by load paths to ensure
stability, noting load paths and movement joints are irreconcilable?
How many independent structures exist; is each one stable?
How are forces transferred from the substructure into the soil?
Are the interfaces of the above six line items each adequate?
Are there any aspects of the structure, small or large, that do not follow the
normal pattern? Do these have suitable load paths of resistance?
Consideration Checked
Is the structure braced, unbraced, or a hybrid?
Braced or
unbraced Are effective lengths correctly determined, taking account of relative
stiffnesses and joint rotations where necessary?
Is the structure in static equilibrium: rotational and linear?
Design – Are all elements and connections adequate to transfer the design actions?
Stability,
strength, Are deflections, rotations and the natural frequency each within permissible
service and bounds?
robustness
Is the structure deemed robust in the event of failure to any of the stability
structures? Doe the design safeguard against progressive collapse?
Is the disposition of the stability system, and are all design assumptions
communicated to the contractor?
Are all parties clear and in agreement on their responsibility?
Will the new structure provide support to, or act on existing structures?
✓ X ⦰ ✓ ✓ X
Unstable Restrained Unstable
between
systems
✓ to ⦰ ✓ to ⦰ ✓ ✓ ⊠ ⊠
Depending on Depending on But slab No No
building plan building plan movement may redundancy redundancy
shape, shape, cause minor
dimensions dimensions axis bending
and scale and scale of the stability
system
✓ ✓ ✓ ✓ ✓ ✓ to ⦰
But slab Depending on
movement may building plan
cause minor shape,
axis bending dimensions
of the stability and scale
system
✓ ✓ ⦰ ⊠ ✓ ⊠
Restrained Failure at a Failure at a
between corner would corner would
systems impact on impact on
two systems two systems
leaving only leaving only
two intact two intact
✓ to ⦰ ✓ to ⦰ ✓ ⊠ ⊠ ⊠
Depending on Depending on Single No No
building plan building plan concentrated redundancy. redundancy.
shape, shape, system The core is a The core is a
dimensions dimensions key element key element
and scale and scale
✓ ✓ to ⦰ ✓ ⊠ ⊠ ⊠
Depending on Single No No
building plan concentrated redundancy. redundancy.
shape, system The core is a The core is a
dimensions key element key element
and scale
✓ ⦰ ✓ ⊠ ⊠ ⊠
Large lever Single No No
arm between concentrated redundancy. redundancy.
the centres of system The core is a The core is a
stiffness and key element key element
mass
✓ ✓ ⦰ ✓ ✓ ✓ to ⦰
Restrained Large lever
between arm between
systems the centres of
stiffness and
mass
✓ Denotes inherently good performance
Legend
⦰ Denotes unwelcome characteristics that may or may not be critical (depending on the plan
geometry) and may be alleviated via careful detailing
⊠ Denotes instability in the even that a single stability system fails. Design parameters for the
stability elements must be justified based on an assessment of risk.
X Denotes inadequate performance.
Where:
L is the overall height of the wall
b is the overall length of the wall on plan
Notes
a) These are guide ratios only; they are not rules and design solutions may fall outside
the ranges given.
b) Ratios are derived for wall sections without dominant openings.
c) The performance of any specific structure at any nominated ratio will depend on the
loading which is usually a function of the tributary load area and / or building mass.
L>H/6 t = H / 100
L<H/6 t = H / 75
Where:
H is the overall height of the wall
L is the overall length of the wall on plan
t is the thickness of the wall
See 5.3.3 for minimum thicknesses.
4.10 References
1. ISTRUCTE, Stability of Buildings, Parts 1 and 2: General philosophy and framed bracing,
2014.
5 Reinforced Concrete
Shear
vmin ≈ 0.4 MPa, vmax ≈ 5 MPa
700
200 kN/m 100 kN/m
600
Beam depth, mm
25 kN/m
500
400
300
200
4 6 8 10 12
Span, m
700
400 kN/m
600
Beam depth, mm
500
200 kN/m
400
50 kN/m
300
200
4 6 8 10 12
Span, m
600
500
25 kN/m
400
300
200
4 5 6 7 8 9 10 11 12
Span, m
200 kN/m
800
700
600
Beam depth, mm
400 kN/m
500
100 kN/m
400
50 kN/m
300
200
6 8 10 12 14
Span, m
RC flat slabs
RC troughed slabs
PT flat slabs
450
Slab depth, mm
400
7.5 kPa
350
10.0 kPa
300
250
200
2.5 kPa
150
100
4 6 8 10 12
Span, m
650
600
500
10.0 kPa
450
2.5 kPa
400
250
200
6 7 8 9 10 11 12
Span, m
10.0 kPa
400
350
5.0 kPa
300
250
2.5 kPa
200
150
100
4 6 8 10 12
Span, m
100
90
Total ultimate load (kPa)
80 600
70
500
60
400
50
300
40
30
20
250
10
200
0
20 40 60 80 100 120
Floor area (m²)
100
90
Total ultimate load (kPa)
600
80
70
500
60
50 400
40
30
20
300
10
250 200
0
20 40 60 80 100 120
Floor area (m²)
100
600
80
Total ultimate load (kPa)
500
60
400
40
300
20
250 200
0
20 40 60 80 100 120
Floor area (m²)
100
90
600
Total ultimate load (kPa)
80
70
500
60
400
50
40
30
20
300
10
250 200
0
20 40 60 80 100 120
Floor area (m²)
5.3 Columns
Initial rule of thumb for columns to EC2 – assume they are slender and
design for the additional moments. As a guide, for columns with an
effective height of 12 times the minimum dimension, bending moment will
increase by 50% for an axial stress of 10MPa and by 100% for an axial
stress of 15MPa.
700
Square columns size ( mm)
2.0%
600
0.20%
500 1.0%
3.0% 4.0%
400
300
200
0 2000 4000 6000 8000 10000
Ultimate axial load NEd (kN)
5.3.3 Walls
At least 200mm thick (usually 300mm) for normal loads; if less than
1000mm high then 150mm thick is usually allowable.
For sizing of walls with axial loading refer to the column sizing table
For sizing of walls for shear forces an approximate rule of thumb =
Internal walls: Thickness > Height / 15 (unrestrained at top)
Thickness > Height / 30 (restrained at top)
5.4 Reference
1. BRITISH STANDARDS INSTITUTION. BS EN 1992-1-1:2004 Eurocode 2: Design of
concrete structures: General rules and rules for buildings, 2004
5. ISTRUCTE, Standard method of detailing structural concrete: a manual for best practice.
3rd edition, (2006)
9. CIRIA C660, Early-age thermal crack control in concrete. 2014 reprint (2007)
10. THE CONCRETE CENTRE, How to Design Concrete Structures using Eurocode 2, 2011.
6 Prestressed Concrete
6.2 Basics
6.2.2 Definitions
Prestressed concrete = compressive stresses are introduced into the
concrete member (in the absence of applied actions) either by pre-
tensioning or post-tensioning of high strength steel strands.
Pre-tensioning = the Strands are tensioned before the concrete is cast
around them. Once the concrete has cured the strand is released placing
the concrete into compression.
Post-tensioning = compressive stress is introduced into the concrete via
the tendon being stressed after the concrete is cast. The tendons can be
either bonded or unbonded
Bonded = the ducts containing unstressed strands are placed within the
slab, after the concrete is cast the strands are stressed and the duct is
grouted up. The strand is therefore bonded to the concrete over the full
length of the tendon.
Unbonded = the ducts containing unstressed strands are placed within the
slab, after the concrete is cast the strands are stressed and anchored.
The compressive stress applied to the tendon is transmitted to the
concrete via the anchorages only, the strands of unbonded tendons are
generally covered with grease and encased in a plastic sheath.
Strand = a strand consists of a series of wires wrapped together
Tendon = a single strand or a series of strands contained within a
duct/sheath including end anchorages.
Flat Tendon = tendon carrying typically up to 4 or 5 strands side by side.
Strands are stressed individually.
Multistrand tendon = tendon in a circular duct containing typically up to
37 strands. The strands are stressed together.
Sheath/Duct = casing for the strands typically used in the post-tensioning
condition.
Anchorage = the ends of the tendon that the compressive stress is
applied to (live end) and the end that is fixed to the structure with no load
applied (dead end).
Transfer = the time at which the stress is transmitted to the concrete.
Losses = the components that should be taken into consideration of the
design of prestressed slab system. These are split into short term (friction
losses, anchor draw-in, elastic shortening of the structure) and long term
(shrinkage of concrete, creep of concrete including the effect of the
prestress, relaxation of steel tendon).
Typically in the UK bonded post-tensioned tendons are used. Unbonded
post-tensioned tendons may be used in roof decks and car parks when
exposure class is XD1, XD2, XD3, XS1, XS2, and XS3.
5.0 36
10.0 30
5.0 40
10.0 36
5.0 40 22
10.0 36 18
5.0 38 16
10.0 34 13
Vibration – The following additional check should be made for normal office
conditions if no further vibration checks are carried out: either the floor
has at least four panels and is at least 250mm thick or the floor has at
least eight panels and is at least 200mm thick.
All panels assumed to be square.
Span/depth ratios not affected by column head.
The values of span/depth ratio can vary according to the width of the
beam.
For ribbed and coffered slab span to depth ratios refer to Table 1 of [1].
These graphs have been reproduced from Technical Report 43, Concrete
Society.
6.5 References
1. CONCRETE SOCIETY, Technical Report 43, 2nd Edition, 2005.
5. BRITISH STANDARDS INSTITUTION, BS 5896:1980 High tensile steel wire and strand for
the prestressing of concrete
7 Non-composite steelwork
Source: [1]
Secondary
Beam Beam Size Beam Size Beam Size Beam Size Beam Size
Span O/A O/A O/A O/A O/A
Dia Spacing Dia Spacing Dia Spacing Dia Spacing Dia Spacing
Depth Depth Depth Depth Depth
457 x 191 x67 610 x 229 x 125 762 x 267 x 173 914 x 305 x 201 914 x 305 x 253
6
400 600 627 500 750 828 700 1000 1078 700 1000 1219 700 1000 1235
610 x 229 x 101 762 x 267 x 147 914 x 305 x 201 914 x 305 x 289
9
500 750 819 500 750 970 700 1000 1219 700 1000 1243
610 x 229 x 113 838 x 292 x 194 914 x 305 x 289
12
500 750 824 700 1000 1157 700 1000 1243
686 x 254 x 125 914 x 305 x 253
15
550 750 934 700 1000 1235
762 x 267 x 173 914 x 305 x 289
18
700 1000 1078 700 1000 1243
Assumptions
1. Secondary beam spacing 3m
2. 150mm thick concrete slab of normal weight concrete
3. All beams grade S355
4. Beams laterally restrained by concrete slab
7.2 Columns
Preliminary design based on a concentric axial load.
For top storey:
Preliminary design axial load =
Total axial load + 4(difference in Y-Y axis load) + 2(difference in X-X axis load)
For intermediate storey:
Prelim. design axial load =
Total axial load + 2(difference in Y-Y axis load) + 1(difference in X-X axis load)
Element Limit
• Cantilever L/180
• Beam supporting plaster or brittle finish L/360
• Beams supporting masonry L/500
• Other beams L/200
• Crane beams L/500
• Columns (per storey) H/300
• Columns (per storey with movement-sensitive cladding) H/500
• Portal frames: lateral at eaves H/100 – H/300 *
• Portal frames: vertical at apex L/250 – L/500 *
7.6 Connections
7.6.1 Bolted
Assume S275 fittings
Simple connections – use grade 8.8, 20mm diameter bolts
o Fin plates, t = 8mm for UB’s < 457mm deep
Partial depth end plates , t = 10mm for UB’s > 457mm deep
Web cleats.
Environment
External Externally exposed steelwork (Where maintenance is difficult) E-1
Externally exposed steelwork (Default for external conditions –
E-2
urban, rural, industrial locations)
Internal Controlled (e.g. office) I-1
Controlled (e.g. office) with requirement for decorative finish I-2
Cavity and perimeter I-3
Uncontrolled (e.g. warehouses) I-4
Specials (e.g. swimming pools kitchens) I-5
Epoxy MIO
Barrier - - -
125 µm (Shop)
7.9 References
1. ISTRUCTE/ICE Manual for the design of steelwork building structures Aug 2008
2. ISTRUCTE Manual to EC3, 2010
3. COBB F., Structural Engineers Pocket Book 2nd edition, 2009
4. BRITISH STANDARD INSTITUTION. BS EN 10025-2: 2004: Hot rolled products
of structural steels.
5. BRITISH STANDARD INSTITUTION. UK National Annex to BS EN 1993-1-1:2005:
Design of steel structures.
6. Westok CELLBEAM, https://www.kloecknermetalsuk.com/westok/
7. TATA Steel
8. ‘The Blue Book’
Slimfloor - 4.5 to 9 20 -
Slimdek - 5 to 7 - -
𝐿𝑠𝑒𝑐𝑜𝑛𝑑𝑎𝑟𝑦 4
=
𝐿𝑝𝑟𝑖𝑚𝑎𝑟𝑦 3
Studs should also be placed so that there is not less than 20mm between
the edge of stud and the edge of the flange
Lateral restraint to the compression flange may normally be assumed to be
provided by decking which spans perpendicularly onto the top flange and is
fixed down (e.g. by through-deck welding of shear studs). In other cases,
the steel beams should be checked for lateral torsional buckling.
8.3 References
1. SCI/ TATA, Comflor Design Software v9.0
2. SCI, P355 Design of composite beams with large web openings, 2011
3. ISTRUCTE, Manual to Eurocode 3, 2010
4. BRITISH STANDARD INSTITUTION, BS EN 1994: Design of composite steel and
concrete structures.
9 Timber
ALL THE INFORMATION IN THIS SECTION APPLIES TO SOFTWOOD IN DRY
LOCATIONS. THIS DESIGN GUIDE APPLIES TO STRUCTURES DESIGNED
TO EN 1995-1-1 [1]
9.2 Materials
Glue laminated timber (Glulam)
Widths up to 240mm, depths up to 2,400mm
Length – limited only by the question of transport to avoid connections
which are expensive and govern member size. It is common to transport
lengths up to 40m subject to local restrictions near the site.
There is a limited range of straight stock sizes. Most members
(straight/curved) are specially fabricated. Initial proportions of cross
section should be limited to less than 1:5 to prevent LTB.
Minimum economic radius is about 8m, down to 4m is possible but at
significant extra cost.
9.3.2 Glulam
Two standardised glulam grades are available (see table below). Higher
grades are significantly more expensive.
Characteristic strengths from EN14080 [2].
GL
24 19.2 24 2.5 3.5 11500 9600 420 385
24h
GL
28 19.5 24 2.5 3.5 12500 10800 420 390
28c
9.4.1 Joists
Size of joists Floors Flat Roofs
(mm)
(planed on 2 faces) LL = 1.5kN/m2 (inc. partitions) LL = 0.75kN/m2
9.4.2 Rafters
C16 C24
9.4.3 Purlins
Maximum purlin spans for roof pitch between 22.5o and 30o.
C16 C24
1500 1800 2100 2400 2700 1500 1800 2100 2400 2700
47x200 2.38 2.23 2.10 1.97 1.85 2.49 2.33 2.20 2.10 2.00
47×225 2.68 2.50 2.36 2.20 2.07 2.80 2.62 2.47 2.35 2.25
63×175 2.32 2.17 2.05 1.95 1.87 2.42 2.27 2.15 2.04 1.96
63×200 2.64 2.48 2.34 2.23 2.13 2.76 2.59 2.45 2.33 2.24
63x225 2.97 2.78 2.63 2.51 2.40 3.10 2.91 2.75 2.62 2.51
9.5 References
1. BRITISH STANDARD INSTITUTION.BS EN 1995-1-1:2004 Eurocode 5: Design
of timber structures. General – Common rules and rules for buildings,2004
5. TRADA (Peter Ross, Patrick Hislop, Hugh Mansfield-Williams and Adrian Young).
Concise illustrated guide to timber connections
6. ARUP 2015 SGN 08 Timber floor systems for commercial buildings: scheme
design.
7. ARUP 2015 SGN 09 Timber composite floors: Procedural guidance
10 Masonry
Masonry is the generic term used to describe the matrix of clay, concrete,
stone or calcium silicate units (bricks or blocks) with cement or lime based
mortars.
Masonry construction is widely used throughout the world and extensively
used in the construction of low to medium rise buildings or for infill panels
to framed construction.
The following section provides guidance for the concept design of masonry
with the following limitations:
Masonry in existing structures is excluded. The strength / capacity of
existing masonry construction requires a knowledge / estimation of the
materials and geometry of the sections. The following values should not be
used for existing masonry construction.
Reinforced masonry is excluded. The vertical and lateral bending strength
of masonry can be improved using reinforcement within the mortar joints or
through the units. This requires more detailed calculations and is therefore
beyond the scope of this Concept Design Guide.
Geometric sections. Diaphragm, fin and other forms of buttressed wall
construction require specific calculations and are therefore excluded.
In the UK we are often asked to provide limited advice on non-load-bearing
masonry construction to our Architectural colleagues. Further guidance
including typical responsibilities is provided in 2015 NST 07 Masonry
Specification: advice to architects.
10.1 Joints
Movement joints can be considered for a number of reasons, all associated
with mitigating cracking. The following should be considered:
Thermal loads
Creep and shrinkage
Over restraint
Dimensional or support irregularities
Guidance is given in the national annex and PD6697, and some examples
are given in the table below. This varies from the previous guidance given in
BS 5628 (comparison values from BS 5628 are given in brackets).
Where:
𝑓𝑥𝑑 is the design flexural strength appropriate to the plane of bending
Z is the thickness of the wall
fd is the design compressive strength of the masonry
For detailed calculations, refer to BS EN 1996-1-1 section 6.3 and Arup
spreadsheet Masonry panel design 16.
ULS capacities for walls and piers for a range of support conditions are
given in the charts below, which assume:
Simply supported, with lateral load only
Walls do not form part of the stability system, therefore γM = 2.4
20N brickwork with M4 mortar, E = 1000fk, ρ = 1800kg/m3
7.3N blockwork with M4 mortar, E =1000fk, ρ = 1500kg/m3
Unit group 1, unit category I, class of execution control 2
NOTE: for cavity walls, if ties can transmit load then the capacity of the
separate leaves can be calculated and added together.
10.4 Stability
The stability system should resist loads in two orthogonal directions, as
well as any twisting forces due to asymmetry of applied loading or building
geometry.
In loadbearing masonry construction stability is provided by either:
Cellular construction - low to medium rise construction where the
internal and external walls form stiff cellular boxes used to resist lateral
loads. The internal and external walls tend to be loadbearing and
provide the vertical and lateral resistance.
Cross wall construction - long narrow building forms, such as terraced
housing, where strong lines of continuous construction are spaced at
regular centres.
Spine wall construction - stiff masonry elements located at key
locations throughout a building. These may be location at lift or stair
cores, gable walls or specific internal walls which are continuous to
foundation level.
Geometrical sections use stiff section shapes to created stable
structural elements; such as fin and diaphragm walls.
Wind Zone Max. ratio of height (above later restraint): Max. ratio of height (above
actual thickness d.p.c.†): actual thickness
1 8.5 6.4
2 7.5 5.6
3 6.5 4.9
4 6.0 4.5
2. Applicable only in areas with many windbreaks (cities, towns, woodland, etc.) –
elsewhere calculate wind forces and design as gravity wall or to BS 5628 Part 1.
Note: This graph only applied where significant internal wind pressure
cannot occur.
Graph has been reproduced from BS5628 Part 3, figure 6.
10.7 References
1. BRITISH STANDARDS INSTITUTION. BS EN 1996-1-1:2005 Eurocode 6: Design
of masonry structures. General rules for reinforced and unreinforced masonry
structures.
13. ISTRUCTE Manual for the design of plain masonry in building structures to
Eurocode 6, 2008.
11.1 Introduction
This chapter is for the initial sizing of foundations and retaining walls.
Horizontal loads on foundations have not been expressly covered in this
Concept Design Guide. This chapter should only be treated as a starting
point.
You should not use this chapter if you are carrying out a detailed design.
Please contact one of our many geotechnical engineers for further
guidance and assistance, your local contact can be found here.
Within this chapter the allowable capacity of the footings and piles are
calculated and these should be compared back to the unfactored loads
unless noted otherwise.
For further information on the characteristic weight density for soils refer
to BS 8004 [2]
For further information on the characteristic weight density for soils refer
to BS 8004 [2]
The above table and charts should only be used up to scheme design; they
are not suitable for detailed design.
Table based on Table 1 of BS 8004 [2]
Factor of safety assumed to be 2.5
Width of footings to be ≥ 1m
Ground water level assumed to be below the base of foundation
Bearing pressures halved in the presence of groundwater
Strip footings susceptible to long term consolidation
Settlement limited to 25mm
Detailed calculations should be carried out to determine settlement
Where:
W = self-weight of the footing
N = applied axial load
M = applied axial load
H = applied horizontal load
R = resultant vertical reaction on soil
e = eccentricity from centre of footing to resultant reaction
x = distance from centre of footing to applied loads
B = width of footing
L = length of footing into the page
For overturning not to be critical the resultant force should be within the
middle third of the footing, i.e. , -B/6 ≤ e ≤ B/6.
Source: [4]
700
Allowable base pile capacity (kN)
600
500
300 dia
CuNcAb/γb
100
0
50 150 250
Undrained shear strength Cu (kN/m²)
See CIRIA Report 181 [5] for further guidance on the design of piled foundations in weak
rock
Pile shaft skin friction capacity (kN Pile base capacity (kN per m²)
SPT ‘N’ per m²)
Blows Unfactored Factor of Allowable qs Unfactored Factor of Allowable qb
safety γ safety γ
10 35 2 18 2500 5 500
15 70 2 35 3750 4 940
20 105 2 53 5000 3 1670
25 170 2 85 6250 3 2090
30 250 2 125 7500 3 2500
35 250 2 125 7750 3 2590
≥40 250 2 125 8000 3 2670
Source: [3]
2 𝐹𝑡 = 𝑃𝑙/2𝑑
3 𝐹𝑡 = 2𝑃𝑙/9𝑑
𝐹𝑡 = 𝑃𝑙/4𝑑
4 Force in longitudinal and transverse
direction 𝐹𝑡 = 𝑃𝑙/2𝑑
Note: piles are usually at a minimum spacing of 3*diameter of pile. For larger pilecaps
bending theory should be used.
Limited working space King post or sheet Sheet pile wall and King post or sheet
pile as temporary dewatering pile as temporary
support. Secant piled wall support.
Contiguous piled wall Diaphragm wall Contiguous piled wall
Diaphragm wall Diaphragm wall
Soil nailing Soil nailing
Limited working space Contiguous piled wall Secant bored piled Contiguous piled wall
and special controls Diaphragm wall wall Diaphragm wall
on ground movements Diaphragm wall
* Working space available to allow the ground to be battered back during wall construction
Source: [1]
11.8 Contamination
Contaminated soil can affect the durability of foundations. Remedial and
protective measures include:
Excavation and removal of the hazard
Treatment or stabilisation of the contaminated soil
11.9 References
1. COBB, F. Structural Engineer's Pocket Book. Elesevier Ltd, 2009
9. CONCRETE CENTRE, Concrete Basements, Guidance on the design and construction of in-
situ concrete basement structures
11. TOMLINSON & WOODWARD, Pile design and construction practice, 5th Edition
12.1.2 Reinforcement
Typically for water resistant walls:
B16 @ 200 c/c in both faces and in both directions, or
B12 @ 150 c/c in both faces and in both directions
This is only a general guide to what might typically be expected and actual
reinforcement diameter and spacing will be based on limiting crack width
for thermal effects and flexure.
Generally bar spacing in the range of 100mm minimum to 200mm maximum
with bar diameters typically of 10 to 20 mm diameter. Smaller bars at
closer centres are generally better than larger bars at greater centres.
Initial guide only - May be reviewed for particular cases and construction
method.
Larger pours possible with appropriate controls and methods.
Thorough preparation of the joint is required prior to concreting.
Where a membrane is used below slab ensure lap zones are properly
protected until slab is poured
12.8 References
1. BRITISH STANDARDS INSTITUTION. BS 8102:2009 Code of practice for protection
of below ground structures against water from the ground, 2009
5. CONCRETE CENTRE, Concrete basements Guidance on the design and construction of in-
situ basement structures, 2012
8. http://networks.intranet.arup.com/materials/technical/concrete/waterproofing_admixtures/
10. ICE. “Water, water everywhere “ICE Forensic Journal, November 2013
11. ARUP, 2015 SGN 06, Top down construction of deep basements: an introduction
Load/Span Tables
Minimum 100mm bearing support
Self-weight has been accounted for in the tables
Concrete grade C25/30 (Cube 30N/mm2)
Minimum reinforcement should meet / exceed 0.1% gross cross sectional area.
This should be increased if:
o Slab is propped during construction
o Required to control cracking
o There are moving loads
Total applied load referred to in the table is a working load (live load, finishes,
ceilings, services, partitions). Ultimate load divided by 1.6. Self-weight already
accounted for so should not be included.
Deflection
o At construction stage - limited to 30mm or span divided by 130,
whichever is smaller
o At composite stage – maximum ratio of slab span to slab depth is 35 for
NWC and 30 for LWC
For propped construction, supports should be in place until concrete has
achieved 75% of its 28 day cub strength (often available after 7 days)
Normal Weight concrete. Unpropped Load/Span Tables (Steel 450N/mm2)
Span Type Slab Min Gauge – 1.00mm Gauge – 1.2mm
(Support Depth Mesh Total Applied Load (kN/m2) SLS Total Applied Load (kN/m2) SLS
Condition) (mm) Size 6.0 8.0 10.0 12.0 6.0 8.0 10.0 12.0
Span (m)
SINGLE 100 A142 3.30 3.22 3.00 3.50 3.32 3.05 3.00
150 A142 2.94 3.00 3.12
200 A193 2.94
2.70 2.87
A252 2.94
2.70
2.53
250 2.69
2.94
2.70
2.53
MULTIPLE 100 A142 3.56 3.50 3.40 3.66 3.50 3.41
2.70
2.53
3.50
150 A142 3.39 3.78
2.53
3.39
200 A193 3.07 3.42
A252 3.39
3.07
250 2.8 3.13
3.39
3.07
Fire Resistance
Load/Span Tables
Minimum 100mm bearing support
Self-weight has been accounted for in the tables
Concrete grade C25/30 (Cube 30N/mm2)
Minimum reinforcement should meet / exceed 0.1% gross cross sectional area.
This should be increased if:
o Slab is propped during construction
o Required to control cracking
o There are moving loads
Total applied load referred to in the table is a working load (live load, finishes,
ceilings, services, partitions). Ultimate load divided by 1.6. Self-weight already
accounted for so should not be included.
Deflection
o At construction stage - limited to that stipulated in BS 5950: Part 4: 1994
o At composite stage – maximum ratio of slab span to slab depth is 35 for
NWC and 30 for LWC
For propped construction, supports should be in place until concrete has
achieved 75% of its 28 day cub strength (often available after 7 days)
Where ★ appears, the addition of props gives no further spanning benefit in these
cases
Fire Resistance
BS 8110:1997
Up to 2 hour fire resistance
Type ‘A’ Finished soffit
Service Class 3 – limiting
crack width of 0.1mm
Lifting hooks
Increased speed of erection
Suitable Applications
Hospitals Car Parks
Schools Office buildings
Retail Leisure & Hotels
The table below is based upon 50 or 75mm structural topping of C30/37 concrete
(minimum grade).
Overall Characteristic service loads kN/m²
Self
structural Unit
Wt 0.75 1.5 2.0 2.5 3.0 4.0 5.0 10.0 15.0
depth depth
kN/m² Effective span in metres
mm
200 150 3.6 8.25 8.25 8.1 7.9 7.7 7.4 7.1 5.8 4.9
250 200 4.2 10.4 9.9 9.7 9.4 9.2 8.8 8.4 7.0 6.0
300 250 4.5 11.7 11.2 10.9 10.6 10.4 9.9 9.5 7.8 6.8
375 300 5.8 14.5 14.0 13.7 13.5 13.2 12.7 12.3 10.7 8.8
425 350 6.2 16.0 15.5 15.2 14.9 14.6 14.1 13.7 11.9 10.0
475 400 6.6 17.1 16.5 16.2 15.9 15.6 15.1 14.6 12.7 10.7
525 450 7.2 18.5 17.9 17.6 17.3 17.0 16.4 15.9 13.9 11.7
Note: Spans indicated in the table allow for characteristic service load (live load) plus self-weight plus 1.5 kN/m²
for finishes.
Composite Profiles
Structural Concept Design Guide
The values provided in the table are a range for each span as a guidance to determine the
zone required. Refer to Metsec Technical Manual for more information.
Z-section Sleeved Purlin System
Span Section Range Weight Total Working Load Deflection Ultimate U.D.L. in kN/span
(m) (kg/m) SLS (kN) Span/360 Uplift based on no anti
sag rods (U.N.O.)
142.Z.13 to 2.84 to 7.81 to 3.84 to 8.25 to
5.0
202.Z.15 4.09 17.41 9.91 11.39
172.Z.13 to 3.25 to 8.85 to 4.33 to 7.33 to
6.0
232.Z.16 4.73 18.55 10.19 10.28
202.Z.15 to 4.09 to 10.80 to 5.26 to 7.03 to
7.0
262.Z.18 5.72 21.61 11.20 9.56
232.Z.14 to 4.15 to 10.67 to 5.17 to 16.84* to
8.0
262.Z.20 6.34 19.71 9.61 26.78*
232.Z.20 to 5.87 to 12.01 to 5.75 to 26.35** to
9.0
302.Z.25 9.77 33.08 16.11 56.23**
262.Z.18 to 5.72 to 11.67 to 5.55 to 23.04** to
10.0
302.Z.25 9.77 27.14 13.09 50.61**
302.Z.18 to 7.10 to 16.48 to 7.86 to 26.4* to
11.0
342.Z.27 11.37 32.18 15.48 49.31*
302.Z.18 to 7.10 to 13.91 to 6.54 to 24.51* to
12.0
342.Z.30 12.58 30.12 14.32 51.33*
302.Z.20 to 7.87 to 13.12 to 6.06 to 27.23* to
13.0
342.Z.30 12.58 25.75 12.07 47.50*
342.Z.20 to 8.49 to 15.04 to 6.94 to 28.51** to
14.0
342.Z.30 12.58 22.20 10.24 53.48**
342.Z.23 to 9.73 to 14.94 to 6.75 to 33.71** to
15.0
342.Z.30 12.58 19.26 8.71 49.91**
The values provided in the table are a range for each span as a guidance to determine the
zone required. Refer to Metsec Technical Manual for more information.
Z-section Butt Purlin System
Span Section Range Weight Total Working Load Deflection Ultimate U.D.L. in kN/span
(m) (kg/m) SLS (kN) Span/360 Uplift based on no anti
sag rods (U.N.O.)
172.Z.13 to 3.25 to 6.93 ti 3.39 to 6.15 to
5.0
202.Z.16 4.35 12.40 6.09 9.23
202.Z.13 to 3.56 to 6.96 to 3.37 to 5.14 to
6.0
232.Z.18 5.30 13.29 6.49 9.22
232.Z.14 to 4.15 to 7.56 to 3.64 to 4.96 to
7.0
262.Z.20 6.34 14.34 6.95 9.04
262.Z.16 to 5.10 to 8.73 to 4.16 to 7.66* to
8.0
302.Z.20 7.87 18.89 9.14 27.43*
30.Z.18 to 7.10 to 13.29 to 6.33 to 17.79* to
9.0
302.Z.25 9.77 18.24 8.69 24.17*
302.Z.23 to 9.00 to 13.40 to 6.26 to 16.59* to
10.0
342.Z.27 11.37 21.28 6.78 21.74*
342.Z.20 to 8.49 to 12.95 to 6.01 to 12.43* to
11.0
342.Z.27 11.37 17.28 8.03 16.53*
342.Z.27 to 11.37 to 14.21 to 6.44 to 12.87* to
12.0
342.Z.30 12.58 15.71 7.12 14.22*
The values provided in the table are a range for each span as a guidance to determine the
zone required. Refer to Metsec Technical Manual for more information.
*The uniform pressure values and uniform suction values are the same for the information
shown in the table and are represented by a single value.
Structural Concept Design Guide
The values provided in the table are a range for each span as a guidance to determine the
zone required. Refer to Metsec Technical Manual for more information.
*The uniform pressure values and uniform suction values are the same for the information
shown in the table and are represented by a single value.
Structural Concept Design Guide
Non-Cracked Concrete
Cracked Concrete
The recommended loads provided in the table below is based on the following assumptions:
No edge distance and spacing influence
Minimum base material thickness
Steel failure
Concrete C20/25, fck,cube = 25 N/mm2
Hilti HIT-HY 200 with HIT-V 5.8 Resin Anchor – Recommended Loads
Anchor Size M8 M10 M12 M16 M20 M24 M27 M30
Non-Cracked Concrete
Tension Nrec (kN) 8.6 13.8 20.0 33.6 53.3 73.2 89.4 106.7
Shear Vrec (kN) 5.1 8.6 12.0 22.3 34.9 50.3 65.7 80.0
Cracked Concrete
Tension Nrec (kN) 7.2 10.1 16.8 24.0 38.0 52.2 63.7 76.1
Shear Vrec (kN) 5.1 8.6 12.0 22.3 34.9 50.3 65.7 80.0
Hilti HIT-HY 200 with HIT-V 5.8 Resin Anchor – Setting Parameters
Anchor Size M8 M10 M12 M16 M20 M24 M27 M30
Nominal diameter
d0 10 12 14 18 22 28 30 35
of drill bit
Minimum base hmin hef + 30
hef + 2 x d0
material thickness (mm) ≥ 100 mm
Effective hef 60 to 60 to 70 to 80 to 90 to 96 to 108 to 120 to
embedment depth (mm) 160 200 240 320 400 480 540 600
smin
Minimum spacing 40 50 60 75 90 115 120 140
(mm)
Minimum edge Cmin
40 45 45 50 55 60 75 80
distance (mm)
Structural Concept Design Guide
Main boom capacities (tonnes) – through full 360 circle slew – with outriggers fully extended
Boom length
Radius 10.07m
10.07m to 12.50m to 15.00m to 17.50m to 20.00m to 22.50m to
in fully
12.50m 15.00m 17.50m 20.00m 22.50m 24.57m
meters retracted
22.0 0.90
Structural Concept Design Guide
Consideration will be given to requirements other Depth of pattern ranging from 1.9 mm to
than standard sizes where they represent a 2.4 mm.
reasonable tonnage per size, i.e. in one length and *Thickness as measured through body of
one width. Lengths up to 10 meters can be supplied the plate.
for plate 6mm & over.
Ultimate load capacity (kN/m2) for plates simply supported on two sides, stressed to
275 N/mm2
Thickness on Span (mm)
plain
mm 600 800 1000 1200 1400 1600 1800 2000