Recreation and Wellness Intranet Project

WBS Text [Draft Version]


1.0 Initiating
1.1 Assign project manager
1.2 Prepare business case
1.3 Prepare project charter
1.4 Identify key stakeholders
2.0 Planning
2.1 Hold project initiation meeting
2.2 Prepare scope statement
2.3 Prepare WBS
2.4. Prepare milestones list
2.5 Prepare project cost model
2.5.1 Project cost model estimate
2.5.2 Project cost model baseline
2.6 Prepare project variances, estimates and values
2.7 Identify quality standards/requirements
2.8 Identify progress measurement variables
3.0 Executing
3.1 Prepare list of programs
3.1.1 List of recreational programs
3.1.2 List of health programs and courses
3.2 User inputs
3.3 Intranet add-on content
3.3.1 Course/programs descriptions
3.3.2 Application form
3.3.3 Search options
3.3.4 User profile template
3.4 Intranet add-on design
3.5 Intranet add-on construction
3.6 Intranet add-on testing
3.7 Intranet add-on announcement
3.8 Intranet add-on roll-out
3.9 Project benefits measurement
4.0 Controlling
4.1 Weekly status reports
5.0 Closing
5.1 Prepare final project report
5.2 Prepare final project presentation
5.3 Lessons learned