There are 4 processes A, B, C, and D in the ready queue for execution.

Process Total CPU Time

Process A 4ms

Process B 6ms

Process C 4ms

Process D 8ms

The processes enter in the ready queue in the sequence B, D, A, and C and are picked by the
dispatcher in the same order. Value of Time Slice is 2ms. The dispatcher picks a process from
Ready Queue and sends it to the processor for execution.

You are required to


Draw the ready queue for the above given processes.
Draw the step-wise pictorial diagram of the above given scenario in the context of
multiprogramming.