Blind Probe
Note:
- All stages based on Well Program of Exploitation Department (Exhibit-1)
- Basis of calculation time is taken from the standardization work time WOWS
Department.(Selected Performance Measure – Exhibit-2)
Total Cost to be paid by Pertamina to the implementation of tubing test are 27.47
hours /24 hours x 11,275 = $ 12,903.60
Page 2 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
MID TERM MM5009 – STRATEGIC DECISION MAKING AND NEGOTIATION
Lecturer : Mrs. Santi Novani Ph.D
Student Name : HASBI ASIDIK [NIM. 29120131]
1 Long duration tubing test activity USD 12,905.18 USD 12,905.18 68% 68%
2 Waiting for checklist USD 2,255.00 USD 15,160.18 12% 80%
3 Waiting for daylight to bleed off well USD 1,879.17 USD 17,039.34 10% 90%
4 Waiting for services company USD 1,879.17 USD 18,918.51 10% 100%
Value Total USD 18,918.51
Our discussion result among the team member conclude that Long Duration of Tubing Test is
our first priority.
1.3 DETERMINATION OF PREVENTION TOPIC
Based on pareto table above, problem number 1 have the highest score/priority. Based on the
exist problem source, therefor WOWS Jatibarang will solve the problem, with topic “COST
REDUCTION OF RENTAL RIG BY TUBING TEST PLUG INSTALATION ON
PRODUCTION PIPELINE AND FRACTURING PIPELINE IN PERTAMINA EP
ASSET 3 JATIBARANG FIELD”
Page 3 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
INDIVIDUAL ASSIGNMENT MM5009 – DECISION MAKING
Lecturer : Mrs.
Student Name : HASBI ASIDIK [NIM. 29120131]
- Tubing test job using blind probe will Make Improvement by making new tools - Test tubing will be effective and
experience repetitive stages for about 20 that will finish the tubing test job effective efficient
times repetitive and efficient as : - The completion will finish be faster
- Tubing test job using plug & prong will - No repetition stages - Work planning taget will reached faster
QUALITY faces another fishing plug job. - No fishing jobs
Tubing test pipe test that needs a lot of Suppers tubing test cost as much as US Increase company profit
time will cost US $ 12,905.00 (27,47 $ 3,288.5 ( 7 jam / 24 jam x US $
jam / 24 jam x US $ 11,275.00) and fuel 11,275.00)
COST cost 1.373,5 liter (same as US $ (POOH String takes about 7 hours )
1,373.50)
Repetitiive stages on tubing test job will Tubing test job will reduce about 7 hours Doing tubing test job simultaneously
DELIVERY takes 27,47 hours with RIH Production Packer/Fracturing
Packer
SAFETY & There's well kick while disconecnt the Theres No more the well kick by Increase zero accident achivement
ENVIRON tubing eliminating POOH stages while tubing
MENT test job
The crew rig will be bored because doing Making the crew fell comfortable while Worker work ethic will increase
the same job over & over again & worry work
MORALE
because theres a little kick while
disconnect the tubing connection
Page 4 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
MID TERM MM5009 – STRATEGIC DECISION MAKING AND NEGOTIATION
Lecturer : Mrs. Santi Novani Ph.D
Student Name : HASBI ASIDIK [NIM. 29120131]
Environment Method
No bullhead from
string, but have from
annulus Using Blind
Probe
Using blind
probe & prong
Connect &
disconnect while
closing tubing test
It takes time to kill the
well if kick happens while
doing tubing test
Page 5 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
INDIVIDUAL ASSIGNMENT MM5009 – DECISION MAKING
Lecturer : Mrs.
Student Name : HASBI ASIDIK [NIM. 29120131]
TOOLS
USD 22,550.00 USD 22,550.00 51% 51%
1 (Conventional)
METHODE
(Blind probe and USD 12,905.18 USD 35,455.18 29% 81%
2 plug prong)
ENVIRONMENT
Dominant Causes Alternative Strengths Weakneses Conclusion
(Blind probe and USD 5,637.50 USD 41,092.68 13% 94%
3 plug prong)
-No repetitive stages
MATERIAL
USD 1,879.17 USD 42,971.84 4% 98%
4 (Not standard) - Tubing test finish faster
PEOPLE - Cheaper cost ( cost to created
USD 939.58 USD 43,911.43 2% 100%
5 (OutBurst CF) tools Rp. 6.500.000)
Cumulative Value USD 43,911.43 - For the natural flow wells
completion time to do well under -Can be applied on
1. Substitute old
pressure balance within the ESP and TCP well
with test plug
string, so the work does not need complation First Alternatif is
STEP 4. PREVENTION PLAN to do the job swab choose, because
PLAN - Prevent wett pull job tubing test plug is :
-As safety device while dismatle - More eff ective
BOP - More effi cient
4.1 PREVENTION
Tubing test not ALTERNATIVES - Insert plug that had fallen in the - More economic
eff ective & effi cient well will be destroyed - Safer
- The material won't
interfere the
production
- Drop bar will be
performance
2. Substitute old became debris on
- Easy to sett
tools with glass the well
- Faster fabrication process
disk - Hard to accive the
material
Page 6 of 15
Page 7 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
INDIVIDUAL ASSIGNMENT MM5009 – DECISION MAKING
Lecturer : Mrs.
Student Name : HASBI ASIDIK [NIM. 29120131]
Step of
Period Where Who Documentation Result
Activity
01 -31
Selection of Test
December
Problem WOWS Supervisor Tubing problems that
2019
Identification Office are not effective and
efficient
Tool Design
- Drawing 1st Weeks WOWS Drawing Design been
Supervisor
- Dimension January 2020 Office made and Fix
- Material Type
The Material are:
- Plug (AISI 4140)
Material 1st Weeks of At Rig WS - Shear Pin (Solid bar
Selection January 2020 Location Engineer (bronze))
- Seal ( O Ring Seal
Rubber High Temp )
Turning
Fabrication / 2nd Weeks A tool created was
Machine Supervisor
Created Tools January 2020 appropriate design
Workshop
Page 8 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
MID TERM MM5009 – STRATEGIC DECISION MAKING AND NEGOTIATION
Lecturer : Mrs. Santi Novani Ph.D
Student Name : HASBI ASIDIK [NIM. 29120131]
Successfully Test
At location
Implementation 2nd Weeks WS Appropriate with
and Workshop Step job in…..
and inspection January 2020 WO-WS
Engineer Engineering
Calculation
1st location
3st Weeks Success application
at well CMB-
Application in January 4th- tools
24and Supervisor Next step at…..
well December
continue at
2020
another Well
Conclusion: The Implementation of Tubing Test with New Tools “Tubing Test Plug” Can
Be Done Simultaneously With Running In Hole Of Production Packer / Packer Fracturing,
therefore time duration of Completion Well is shorter than before.
6.2 DIFFERENT EVALUATION OF TIMES, RIG COST, DIESEL FUEL AND GAIN
PRODUCTION
Work Stages Before Improvement (Exhibit-10)
Page 10 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
MID TERM MM5009 – STRATEGIC DECISION MAKING AND NEGOTIATION
Lecturer : Mrs. Santi Novani Ph.D
Student Name : HASBI ASIDIK [NIM. 29120131]
COST
Time (min)
NO DETAIL OF ACTIVITY Rig cost (USD) Fuel (liter ) Fuel (USD) Gain Production (bbl)
USD 11,275.0 USD 1.0
1. Prepare test tubing job 60.0 USD 469.8 50 USD 50.0 0.83
Make up Connection Tubing Test Plug at tool joint tubing atau drill pipe
2. tighteen with recommended torque
USD 2,512.3 267 4.46
320.9 USD 267.4
RIH Tubing test plug with Fracturing / production packer to Well
3. L/U circulating head and release plug 30.0 USD 234.9 25 USD 25.0 0.42
Total time and cost each depth at 2000 mtr 410.9 USD 3,217.0 342.39 USD 342.4 5.71
20.5 USD 160.8 17.12 USD 17.1 0.29
Total time and cost
Page 11 ofeach15100 mtr (After Improvement)
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
INDIVIDUAL ASSIGNMENT MM5009 – DECISION MAKING
Lecturer : Mrs.
Student Name : HASBI ASIDIK [NIM. 29120131]
Total Savings The Obtained From Job Well That Use Tubing Test Plug In Years 2014-
2015
COST
TIME (min)
COMPARISON RIG COST (USD) FUEL (litres) FUEL (USD) GAIN PROD (bbl)
USD 11,275.0 USD 1.0
Total of time and cost each 100 mtr (Before Improvement) 82.4 USD 645.2 68.7 USD 68.7 1.1
Total of time and cost each 100 mtr (After Improvement) 20.5 USD 160.8 17.1 USD 17.1 0.3
COST REDUCTION OF TEST TUBING JOB AT 100 METERS 61.9 USD 484.3 51.5 USD 51.5 0.9
Page 12 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
MID TERM MM5009 – STRATEGIC DECISION MAKING AND NEGOTIATION
Lecturer : Mrs. Santi Novani Ph.D
Student Name : HASBI ASIDIK [NIM. 29120131]
No repetitive stages
The timing of the test Tubing in 1 wells Time for tubing test job at 1 well (2000 m
(depth of 2000 meters) fell as much as 7 depth): :
DELIVERY 295%
hours (eliminating the process of re-pull - Old tool : 27.47 hours
circuit) - New tool : 6.85 hours
(Time reduced by 20.62 hours)
MORALE Creating a sense of comfort in working Worker feel comfortable and safe -
Page 13 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
INDIVIDUAL ASSIGNMENT MM5009 – DECISION MAKING
Lecturer : Mrs.
Student Name : HASBI ASIDIK [NIM. 29120131]
For well with potention flowing and well gas can be done underbalance pressure in string so that eliminate swab job
3
and unloading with coil tubing
4 Lifetime Rig Equipment not corroded by outburst cf when of the test tubing job
Page 14 of 15
INSTITUT TEKNOLOGI BANDUNG
SCHOOL OF BUSSINESS AND MANAGEMENT
MASTER OF BUSSINESS ADMINISTRATION PROGRAM
MID TERM MM5009 – STRATEGIC DECISION MAKING AND NEGOTIATION
Lecturer : Mrs. Santi Novani Ph.D
Student Name : HASBI ASIDIK [NIM. 29120131]
Page 15 of 15