Objective:
To ensure no water spillage /dripping during heavy rain from Drainage system (safety no hindrance in production)
Scope of work :
All drainage system will be replaced with new drainage system.
Total 13 Drainage system (Main 5 drainage system and 8 Branches)
12x15x12 (inches)
24 Gauge / 0.5 mm
Selection Of Contractor:
M/s Z.M Engineering selected based on following.
M/s Z.M Engineering is a sub-contractor of M/s Izhar Steel (most of PEB structure in AIP is done by M/s Izhar
steel.
Z.M Engineering is Specifically working on Maintenance / Installation of PEB structure.
M/s Z.m has good experience of rain in Panjab (Station in Lahore)
Other Contractor:
Warranty:
Time Line: