Installation of New Rain Water Drainage System In CIF

Objective:
To ensure no water spillage /dripping during heavy rain from Drainage system (safety no hindrance in production)

Scope of work :
 All drainage system will be replaced with new drainage system.
 Total 13 Drainage system (Main 5 drainage system and 8 Branches)

Size And Material:

 12x15x12 (inches)
 24 Gauge / 0.5 mm

Selection Of Contractor:
M/s Z.M Engineering selected based on following.

 M/s Z.M Engineering is a sub-contractor of M/s Izhar Steel (most of PEB structure in AIP is done by M/s Izhar
steel.
 Z.M Engineering is Specifically working on Maintenance / Installation of PEB structure.
 M/s Z.m has good experience of rain in Panjab (Station in Lahore)

Other Contractor:

 M/s Projexive (General works of fabrication)

Warranty:

 No water spillage from drainage system during heavy rain

Time Line:

Two month after P.O