1 INTRODUTION
This procedure is for the Static Load Testing of the 250mm diameter Mircopile at IMPROVEMENT WORKS
TO SG. SEBAB AT KAMPUNG KEMUNTING, BINTULU DIVISION, SARAWAK. Each test pile is to be
tested to to testing load as specified ie two times working load.
3 KENTLEDGE SYSTEM
The kentledge system will be provided by concrete block with a total weight of about 15% heavier than the
test load requirement of the about package.
The test arrangement is show diagrammatrically in the sketch attached.
a. Test beams ( Providing a platform for the reaction counter weight and the jack )
b. Hydraulic jack.
c. Survey leveling instrument
d. Dial gauges
e. Scale rule
f. Temporary bench mark ( TBM )
4 METHOD OF LOADING
The test load shall be applied by mean of a jack. The load will be measured using a calibrated pressure
gauge in the hydraulic system. The hydraulic jack will be carefully aligned so that the load applied is co-axial
with the test pile.
6 TEST PROGRAMME
CRP and Maintained Load Tests will be conducted on the test pile as proposed in Appendix 1.
7 TEST RESULTS
A copy of field test data and field results will submitted upon the completion of the Static Load Test.
A full engineering report on the Static Load Test will be submitted within two weeks from the completion of
the tests.
1 The maintained load test shall be carried out in Two (2) cycle of the loading. The full test shall be 25% of the
working load increment of twice the working load repectively. Each cycle shall consist of a loading and
unloading stage with the following load increments :-
2 Dial gauge and datum reading shall be taken immediately before and after application of each load
increment. The reading shall be taken at 2, 5, 10, 20, 30, 45 and 60 minutes. If beyond that the time reading
shall be recorded at every 1 hour. The rate of change in the settlement shall reduced to less than
0.25mm/hour before the next stage of load increment or decrement can be applied.
3 The test load shall be applied by means of a single hydraulic pump. Load / Settlement - Time and Load -
Settlement graphs shall be plot.
Test loading shall be generally in accordance with BS8004 for maintaned loads. Increamental loads shall be
as follows :-
IMPROVEMENT WORKS TO SG. SEBAB AT KAMPUNG KEMUNTING, BINTULU DIVISION, SARAWAK. Revised 24.2.2021.xlsx /
Statement for Mircopile 2
Static Load Testing of the 250mm diameter Mircopile at IMPROVEMENT WORKS TO SG. SEBAB AT
KAMPUNG KEMUNTING, BINTULU DIVISION, SARAWAK.
Working load 550 kN Pressure Gauge with Model No. : EN 837-1 ( Wika )
Test Load 1100 kN Cylinder Capacity ( Tons ) : 520
Hydraulic jack Model HDA5006
Effective Area 113.13 sq inch for 1 jacks . ( 113.13 sq inch per jack )
No. of jack used : 1 no.
CONTENT RATE OF PENETRATION ( CRP )
% Test Load, Applied Load, kN Working Load psi Period of Remark
Test
1100kN (1no.jack) Observation
0 0 0 -
10.0 55 109
20.0 110 219
30.0 165 328
40.0 220 437
50.0 275 546
60.0 330 656
Data observation is
70.0 385 765 continuous throughout
Constant Rate of 80.0 440 874 loading cycle - Allow
at least 15 minutes
Penetration Test 90.0 495 984 before the next CRP
(CRP 1, CRP 2, 100.0 550 1093 cycle. ( Dial Gauge
CRP 3) 120.0 660 1312 shall not be reset to
zero between every
140.0 770 1530 CRP cycle )
160.0 880 1749
180.0 990 1967
200.0 1100 2186
150.0 825 1639
100.0 550 1093
50.0 275 546
0.0 0 0 15 mins
MAINTAINED LOAD TEST
0 0 0 -
25.0 138 273 1 hour
50.0 275 546 1 hour
75.0 413 820 1 hour
1st Cycle 100.0 550 1093 24 hours
Reading shall be taken
75.0 413 820 1 hour at 2, 5, 10, 20, 30, 45
50.0 275 546 1 hour and 60 minutes. If
25.0 138 273 1 hour beyond that the time
reading shall be
0.0 0 0 1 hour recorded at every 1
25.0 138 273 1 hour hour, The rate of
settlement shall not
50.0 275 546 1 hour exceed 0.25mm per
75.0 413 820 1 hour hour. - Maintained
Period - During the
100.0 550 1093 1 hour first hours - 2, 5, 10,
125.0 688 1366 1 hour 20, 30, 45 and 60
150.0 825 1639 1 hour minutes. After then
2nd Cycle recorded at intervals
175.0 963 1913 1 hour of one(1) hours.
200.0 1100 2186 48 hours
150.0 825 1639 1 hour
100.0 550 1093 1 hour
50.0 275 546 1 hour
0.0 0 0 1 hour
IMPROVEMENT WORKS TO SG. SEBAB AT KAMPUNG KEMUNTING, BINTULU DIVISION, SARAWAK. Revised 24.2.2021.xlsx /
Statement for Mircopile 3
METHOD STATEMENT
OF
AT
SARAWAK.
No.3, Lot 74, 1ST FLOOR, LORONG SUNGAI MAONG ULU NO.3,
JALAN TUN AHMAD ZAIDI ADRUCE, 93150 KUCHING,
SARAWAK, MALAYSIA.
Tel / Fax : 6082-252758, H/P : 019-8892758, 013-9234413
E-mail address : advancedgeotest@yahoo.com