Professional Documents
Culture Documents
QUALITY COSTS
By Kent Davis, 1 W. B. Ledbetter, 2 Fellow, ASCE,
and James L. Burati, Jr., 3 Member, ASCE
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 07/06/14. Copyright ASCE. For personal use only; all rights reserved.
INTRODUCTION
385
Basic Premises
In view of these facts, the Quality Management Task Force of the CII has
undertaken the development and field trial of a quality performance tracking
system (QPTS). The QPTS is defined (Burati and Farrington 1987) as: "A
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 07/06/14. Copyright ASCE. For personal use only; all rights reserved.
Quality-Related Activities
In the global sense, one could argue that all activities related to the suc-
cessful completion of a project involve quality. While philosophically this
argument may be correct, there are certain aspects of quality that merit spe-
cial attention in a tracking system. These aspects include quality assurance,
quality control, and quality management, which might be considered the
inputs to the quality system, and quality-related failures, the negative outputs
of the system. The quality-related failures are called deviations.
Quality assurance (QA) is sometimes used as an all-encompassing term
387
Deviation Description
The major issue in the development of the QPTS was how to handle de-
viations. The writers have proposed nine important questions that should be
answered in connection with a deviation. Each of these questions has a num-
ber of possible answers, as shown in Fig. 1. A tracking system designed to
answer all these questions would involve thousands of combinations. To limit
the initial effort, only a portion of these combinations was considered in the
initial system. Fig. 1 also shows whether the information is tracked by the
current QPTS (Q), the usual cost tracking system (W), or is not tracked (N).
The following discussion expands each question in Fig. 1 and explains its
relationship to the QPTS.
Which Task?
The complete question is "Which specific tasks were involved in the de-
viation?" This information is vital if corrective action is to be taken to pre-
vent future occurrences. This information is captured by the usual cost cod-
ing and need not be tracked separately by the QPTS, provided relevant costs
are assigned to the task responsible for the deviation. For example, if un-
derground piping were improperly installed, requiring removal and replace-
ment of a concrete slab, the cost of the concrete rework should be charged
against the piping task.
Who Affected?
The complete question is "Which phase of the project incurred the quality
costs due to the deviation?" Deviations can result in quality costs affecting
any of the seven phases shown under this question in Fig. 1. To limit the
scope of the current effort, the QPTS has been restricted to design, con-
389
\ ^'•Disposal
\ 4
WHAT CLASS ?
Imperfection w w w WHEN DETECTED
Nonconformance
Defect -^Preplanning
Design
""Procurement
Construction
Start-Up
"^•Operation
"'Disposal
WHAT RESPONSE ?
Rework
-''Accept
WHO CAUSED ?
•
' Owner
WHAT TYPE ? Designer
QM INVOLVED ? Vendor
Error
Change Transporter
Prior QM input
Constructor
QA/QC Rework
What Costs?
The primary question is "What is the cost of the particular deviation?" A
companion question is "What measurable costs are caused by deviations in
general?" Although these costs are normally captured by existing systems,
they may not be distinguishable from the normal cost of performing work.
The QPTS captures these costs and adds information about them.
In addition to the direct costs associated with deviations, there are indirect
costs. The QPTS, in combination with the usual cost-tracking system, can
390
$100,000.
Impact is an additional element that may be associated with design or
construction deviations. A deviation-caused delay or disruption in one ac-
tivity may have a detrimental effect on another activity resulting in additional
costs, i.e., an impact. While all deviation-related impact costs are a part of
quality costs, the current QPTS does not track impact costs.
Liability costs may be considered to be deviation costs (Besterfield 1979).
This includes some legal costs, the costs of certain types of insurance, and,
under some circumstances, liquidated or actual damage payments. These costs
are generally available from existing cost-tracking systems and are not tracked
by the current QPTS. The determination of what portion of liability costs
should be classified as deviation costs is not addressed herein.
Warranty costs are also properly included as part of the costs of deviations
(Besterfield 1979). The consideration of such costs is also outside of the
scope of the current QPTS.
When Detected?
The complete question is "During which phase of the project was the de-
viation discovered?" Obviously, early detection of deviations is better than
late detection (Schrader 1986). Further, the ability to detect deviations in-
ternally is a measure of the effectiveness of the appraisal effort. Information
about when deviations are detected may lead to improved approaches to quality
management.
The QPTS is designed to identify detection times for design, construction,
and start-up. To limit the scope of this work, consideration of deviation
detections during pre-planning, procurement, operation, and disposal is not
currently included.
Who Caused?
The complete question is "Who caused the deviation, and why?" A de-
viation by any of the participants of the project may cause quality costs for
that participant or for others. "Cause" need not have the connotation of
"blame." For example, a decision to proceed with a detailed design without
complete vendor, information may be considered the best approach even though
it is suspected that some design rework will result. In many cases, however,
the attachment of blame to a deviation is inevitable and appropriate. This
question is closely tied to the previous question of "Which Task?" Whenever
a deviation occurs and rework results, the task causing that rework should
be charged the total cost, regardless of what other tasks were affected.
At times, determining the cause of deviations will be difficult. Respon-
sibility may be shared or unclear. The current QPTS identifies five causes:
owner, designer, vendor, transporter, and constructor. Once the cause has
been determined, management can take the necessary next step to determine
the underlying reason, e.g., haste, fatigue, or faulty communication. This
consideration is outside of the scope of the current QPTS.
391
tions may lead to repeat work for quality management personnel. (The term
"repeat" is used instead of "rework" for this situation.) The cost of repeat
work must be considered a deviation cost rather than an ordinary quality
management cost. The QPTS provides answers to both of these questions.
What Type?
The complete question is "Did the deviation result as the consequence of
an error or a change?" A change is defined as (Burati and Farrington 1987):
"a directed action altering the currently established requirements. Changes
may encompass design, fabrication, construction, etc. and materially affect
the approved requirements, the basis of design, the existing scope of the
contract plans and specifications, or operating capability of the facility.
It is a matter of semantics whether a change is a deviation, but changes
are so costly to construction projects that they are addressed by the QPTS.
The QPTS, which tracks the costs involved with changes only when the
changes result in rework, is not intended to replace the change-control mech-
anism. Although the owner is involved in approving a change, the QPTS
provides for the possibility of change initiation coming from the other project
participants.
What Response?
The complete question is "What is done in response to the deviation?"
Typically, a deviation results in rework. Thus, the response to a design de-
viation is to redesign, and the response to a construction deviation is to
rebuild. All the extra costs involved are deviation costs. As has been stated,
the ordinary cost system captures these costs, while the QPTS identifies them
as rework and provides descriptive information. Occasionally an owner may
accept some "below-specification" work rather than demand rework. In ef-
fect, the acceptance of such work is a negotiated change in the project re-
quirements. This situation is not addressed by the current QPTS.
What Class?
The complete question is "Should the deviation be classified as an im-
perfection, nonconformance, or defect?" The classification of a deviation
refers to its degree of severity (Freund 1985). The class of deviation is in-
cluded here for completeness, but it is not included in the current QPTS
because of the limited value of tracking imperfections and the practical dif-
ficulties in distinguishing between nonconformances and defects.
Deviation Categories
The foregoing description illustrates some of the complexities of tracking
deviation costs. Referring to Fig. 1, it can be seen that the QPTS supple-
ments the usual cost-coding system by characterizing rework by type, cause,
and time of detection. While there are several thousand possible combina-
tions, only a relatively small number is required to properly track the cost
392
Owner Change X X X
Designer Error X X X
Designer Change X X X
Vendor Error X X X
Vendor Change X X X
Transporter Error — X X
Constructor Error — X X
Constructor Change — X X
Other Change X X X
393
Feasibility study
Contractor/subcontractor evaluation
Quality orientation activities
Personnel qualification/testing
Personnel training
Formal design check/review *
Formal drafting check/review *
Formal check/review of other documents *
Constructibility review *
Materials inspections/tests *
Inspection *
Quality status documentation
Post-project review
"When repeated, the cost of these activities become deviation costs.
Cost and schedule control systems vary from one firm to another, with
those used for construction tending to be more extensive than those used for
design. Those most compatible with the QPTS use a work-breakdown struc-
ture (WBS) system. A QPTS/WBS cost-coding system involves two parts:
the usual WBS portion and the quality cost portion. For example, on a cost-
coding system in which the QPTS has simply been added, a designer might
code his or her time: xxx-yyy-zzz-QM.
The code QM indicates that a designer is performing some quality man-
agement function (e.g., a formal design review). The xxx-yyy-zzz portion
would be the usual WBS code. Another approach would be to place the
QPTS codes into existing cost-coding schemes by utilizing unused fields and
numbers. Both approaches were accomplished on actual cost-coding schemes
for design (Diekmann and Thrush 1986) and for construction (Neil 1983).
Detailed analyses of these schemes demonstrate the ease of integrating the
QPTS into existing cost-coding structures (Davis 1987). It is clear that QPTS
coding can supplement existing WBS coding. Since coding systems vary,
the integration of the QPTS must be accomplished on a case-by-case basis.
The writers believe that many WBS cost-coding systems can absorb QPTS
coding very readily.
Some quality costs require frequent, perhaps even daily, tracking. These
are listed in Appendix I. Fortunately, continual record keeping of such in-
394
The QPTS has been introduced on five projects ranging in size from about
$5,000,000 to about $170,000,000. Three of the projects include both design
and construction. The firms involved introduced the QPTS by defining spe-
cific work packages to be tracked (generally combined into major disciplines
such as civil, electrical, etc.). The only problem with the application was
in forcing each work package into the same discipline, whether it be the
design or the construction phase. A design organization may categorize a
work item in a different discipline than the construction company building
the item. This had to be overcome by utilizing consistent discipline defini-
tions throughout all project phases. The results of the field trials will be
made available after their conclusion. Preliminary results indicate that the
desired information is being tracked. This is illustrated in Tables 3 and 4,
which consist of information obtained from computer printouts during the
design phase of one project. Note the additional categories introduced by
the participating firm. The QPTS is designed to be dynamic and adaptable
to specific needs. Table 3 indicates that quality management activity hours
are being tracked by specific activity (e.g., design check/review) and dis-
cipline (e.g., structural). Table 4 indicates that design rework times are being
tracked by cause (e.g., client) and discipline (e.g., structural). Using this
information and overall times charged to the project by discipline, time per-
395
CONCLUSIONS
396
RECOMMENDATIONS
Much more work needs to be done, both in terms of the continuing field
trials and further quality-related studies. The surface has only been scratched
in terms of understanding the true cost of quality in the design and construc-
tion of engineered projects. The QPTS needs further refinement optimization
to make it truly effective, especially in the area of accurately tracking the
"true" causes of deviations. Companies need to use the system on a number
of projects to develop their particular cost of quality relationships and to
reach the optimum point where these costs are minimized. Finally, of course,
the QPTS must be expanded and adapted to include other critical phases of
projects, from conception through disposal.
ACKNOWLEDGMENTS
The work reported herein was sponsored by the Construction Industry In-
stitute of the University of Texas at Austin and under the direct supervision
of the Quality Management Task Force. The writers wish to acknowledge
the outstanding guidance and support of the task force in conducting the
research program.
The statements made herein are solely those of the writers and are not
necessarily those of the Construction Industry Institute or the Quality Man-
agement Task Force.
Personnel Times
• By salary or wage scale.
• By QM activity or rework category.
• By design discipline or construction activity.
Equipment Times
• By hourly or daily rate.
• By Qm activity or rework category.
• By design discipline or construction activity.
Materials
• By cost.
• By QM activity or rework category.
• By design discipline or construction activity.
ACI Committee 121. (1985). "Quality assurance systems for concrete construction."
Am. Conor. Inst. J., 82(4), 537-543.
397
398
399
400