Materials Cost

Footing
Cement 11 bags 200 2200
Sand 1.1 cu.m 600 660
G3/4 1.1 cu.m 1400 1540

Column
Cement 17 bags 200 3400
Sand 0.9 cu.m 600 540
G3/4 1.8 cu.m 1400 2520

CHB Laying
CHB 6" 57 x 10 570 x 14 = 7980

Plaster
Cement 20 bags 200 4000
Sand 1 cu.m 600 600

Mortar
Cement 40 bags 200 8000
Sand 3 cu.m 600 1800

Summary
Cement 88 bags x 200 = 17600
Sand 6 cu.m x 600 = 3600
G3/4 2.9 cu.m x 1400 = 4060
CHB 6" 570 pcs x 14 = 7980
33240

Steel Reinforcement
12mm
15 pcs x 213.12 = 3196.8
6m
10mm
48 pcs x 147.84 = 7096.32
6m
Total 43533.12

Labor Cost
Laborers 10 x 600 x 14 = 84000
Foreman 1x 1000 x 14 = 14000