CONSTRUCTION BULLETIN
DAAA NO. 04-2008
(PHASE 2)
ALUMINUM WORKS
DATE : FEBRUARY 20, 2008
ATTTENTION : AUST-PHILS ALUMINUM INT’L., INC./
NEW GOLDEN CITY BUILDERS
FROM : GLORIO O. CORTEZ, JR.
SUBJECT : MEZZA RESIDENCES
ITEM REMARKS
Delete one operable panel for W4, W1, W6, W14 and W9. Refer to the attached keyplan for item that
will be affected by this Construction Bulletin.
See attached shopdrawing of the deleted
operable panel.
Attached is DAAA RFI No. A-05 (Phase 2)
for your reference.
NOTE:
Contractor is required to submit above mentioned requirement of Designer 3 to 4 days upon receipt of this
Construction Bulletin.
Name:_____________ Name:_______________
JOSE MICHAEL HERNAL GLORIO O. CORTEZ, JR Company:__________ Company: SMDC
Project Resident Manager Date:______________ Date:________________