CONSTRUCTION BULLETIN
DAAA NO. 02-2007
(PHASE 1 and 2)
ALUMINUM WORKS
DATE : NOVEMBER 19, 2007
ATTTENTION : AUST-PHILS ALUMINUM INT’L., INC./
NEW GOLDEN CITY BUILDERS
FROM : GLORIO O. CORTEZ, JR.
SUBJECT : MEZZA RESIDENCES
For W-6 for Towers 3 and 4 Follow 1.55 m as shown in revised window
since pre-cast was already installed at 16th –
succeeding levels.
Deductive to Aluminum and Glazing works.
See attached DAAA Request for Approval
A-20.
NOTE:
Contractor is required to submit above mentioned requirement of Designer 3 to 4 days upon receipt of this
Construction Bulletin.
PREPARED BY: APPROVED BY: RECEIVED BY: COPY FURNISHED TO:
Name:_____________ Name:_______________
BUTCH NARVADEZ GLORIO O. CORTEZ, JR Company:__________ Company: SMDC
Project Resident Manager Date:______________ Date:________________
RONALD S. CREDO
SHEILA DE CASTRO
/conversion/tmp/activity_task_scratch/528506682.doc
JOSE MICHAEL HERNAL
/conversion/tmp/activity_task_scratch/528506682.doc