Professional Documents
Culture Documents
NRP - Non Technical Summary
NRP - Non Technical Summary
January 2021
Contents
1. INTRODUCTION....................................................................................................................................................................... 4
Purpose and Content of the Non-Technical Summary (NTS) ..................................................................................... 4
Project Background..................................................................................................................................................................... 4
Main aims of the project ........................................................................................................................................................... 6
Regulatory Context and Standards ....................................................................................................................................... 6
Environmental Impact Assessments ..................................................................................................................................... 7
2. PROJECT DESCRIPTION......................................................................................................................................................... 8
Process Description..................................................................................................................................................................... 8
Assessment of Alternative Sites ............................................................................................................................................. 9
Environmental Measures Incorporated in Al Zour Refinery ...................................................................................... 10
Air Emissions Abatement ................................................................................................................................................... 10
Wastewater Treatment, Reuse and Disposal .............................................................................................................. 10
Solid Waste Strategy ............................................................................................................................................................ 11
Noise Control and Abatement ......................................................................................................................................... 11
Odour Abatement ................................................................................................................................................................. 11
Environmental Stewardship ............................................................................................................................................... 12
Monitoring ............................................................................................................................................................................... 12
3. BASELINE CONDITION ........................................................................................................................................................ 13
Environmental Baseline Study............................................................................................................................................... 13
4. NOISE ......................................................................................................................................................................................... 15
Noise Studies and Monitoring .............................................................................................................................................. 15
5. AIR QUALITY............................................................................................................................................................................ 16
Air Emissions Studies and Monitoring ............................................................................................................................... 16
6. MARINE AND COASTAL ENVIRONMENT..................................................................................................................... 17
Marine and Coastal Environment ........................................................................................................................................ 17
7. SOLID WASTES ....................................................................................................................................................................... 20
Non-Hazardous Solid Waste Generation, Handling & Disposal.............................................................................. 20
Hazardous Waste Generation, Storage and Handling ................................................................................................. 20
8. HAZARDOUS MATERIALS .................................................................................................................................................. 22
It is important to note that this NTS does not, and is not intended to, convey all the information
relating to the aspects and impacts of the Project. Its intention is to present key information,
describe the main findings and conclusions, enabling the reader to understand the significant
environmental effects of the Project without needing to refer to the detailed assessments.
Project Background
Kuwait Integrated Petroleum Industries Company (KIPIC) is building a world class Refinery, the Al-
Zour Refinery Project. Al Zour Refinery will encompass all the activities and facilities required to
upgrade up to 615,000 barrels per calendar day of Kuwait crude oil to produce high value products
and fuel oil. The Refinery construction started in October 2015, the actual progress of the
engineering, procurement, and construction (EPC) phase is 95.71%. The first Oil in the Refinery is
projected for 2021.
KIPIC has divided the ZOR into five discrete packages including: Package 1 – Main Process Units,
Package 2 – Support Process Units, Package 3 – Utilities and Offsites, Package 4 – Tank Farm and
Package 5 – Marine and Export Facilities.
The project was divided into five packages, in addition to the contract to rehabilitate the Al-Zour
refinery land, the five project packages were distributed to four global joint ventures.
Amec (Wood) was awarded the front-end engineering design (FEED) and project management
consultancy (PMC) contract for the refinery. The first package (major manufacturing units) is
implemented by the alliance that includes the following companies Spanish Tecnicas Reunidas,
Chinese Sinopec and Hanwha South Korea. The second and third packages (support and
infrastructure services units) includes Fluor British Company, South Korean Hyundai and Daewoo
also South Korean. The fourth package (tank farm) includes the Italian Saipem and the Indian
Essar. For the fifth package (marine export facilities), the Joint Venture is South Korean Hyundai,
• Decision No. 2 of 2015 for conducting Environment and Social Impact Assessment Study
(ESIAS).
• Decision No. 5 of 2016 Executive Regulations on Chemicals Management.
• Decision No. 6 of 2017 for Management of Hazardous, Medical, Municipal, Solid and
Sludge Waste.
• Decision No. 8 of 2017 on the executive regulations for protection of external environment
from pollution.
• Decision No. 12 of 2017 for Protection of Sea and Coastal Environment from Pollution
Decision No. 3 of 2020 on Executive Regulations concerning the Occupational Safety of
Employees in all Establishments
For environmental guidelines not been developed yet for the state of Kuwait, accepted
international standards are used (e.g. Canadian Soil Quality Guidelines for Environmental and
human health).
In addition to KEPA Environmental legislation, the project is in compliance with KIPIC’s HSE
guidelines, Project Procedures and EIA requirements and procedures.
The major process units are the Crude Distillation Units, Naphtha, Diesel and Kerosene
Hydrotreatment Units, Atmospheric Residue Desulphurization Units and Heavy Oil Cooling Unit.
Support Units include the Sulphur Recovery Unit, which remove sulphur as a saleable product
from acid gas streams received from the upstream process units. After recovering part of it,
virtually all the remaining H2S is converted in SO2 by the Tail Gas Treating Units before being
discharge to atmosphere. Other support units are the Hydrogen Production Unit, Hydrogen
Compression Unit, Hydrogen Recovery Unit, Saturated Gas Unit, Sour Water Stripper Unit and
Amine Generation Unit.
Supporting facilities include low pressure, high pressure and gas flare systems, a wastewater
treatment unit for various categories of industrial wastewater, stormwater and sanitary sewage,
utility boilers, cooling water system, tankage, and marine terminals for both solid and liquid
products.
Assessment of Alternative Sites
Four Practicable Alternative Locations were studied for Al Zour and their environmental benefits
Study focused on the following four locations:
1. Ras Al-Sabiyah
2. Shuaiba
3. Umm Al Heman
4. Az Zour
Weight Linear Summation Method (WLSM) was used to compare alternatives because it provides
a structural basis on which comparison can be made. A conceptual model was developed involving
the following four major issues: Air Quality, Marine Environment, Geology and Spatial
Environment.
Az Zour Area was considered the most suitable site. This is based on the availability of adequate
space to accommodate all requirements for the Al Zour Refinery, less impact on ambient air
quality for residential communities, and less potential impact to the marine environment, Sabiyah.
Az Zour is also suitable for any future expansion of the Refinery.
• Using mufflers and silencers for construction equipment, with vendors to target maximum
equipment noise at 85 dB(A) at 1 metre distance.
• Providing high noise sources with sound-reducing enclosures, acoustical insulation,
silencers, or other engineering methods to minimize noise.
• Including a hearing protection programme for personnel within the Al Zour Refinery overall
HSE Management Programme.
• Conducting periodic noise monitoring surveys around individual process units and Refinery
fence line.
Odour Abatement
Principal environmental measures regarding odour abatement at the Al Zour Refinery include:
• A strategy to address odour nuisance conditions via the Al Zour Refinery EMS.
• Focusing particularly on noxious odours and gas emissions from the wastewater treatment
facilities, process and support units, laboratory, chemicals neutralization, sewerage.
• Using bulk containers to minimize emissions during drum unloading.
Environmental Stewardship
Principal environmental stewardship measures at the Al Zour Refinery include:
Monitoring
Principal environmental measures regarding air, water and groundwater monitoring include:
• Using Continuous Emission Monitoring Systems (CEMS) for main pollutants from stacks,
providing readouts in the control room
• Applying area monitoring for hazardous pollutants such as H2S, and providing for ongoing
ambient air quality monitoring
• Analyzing the sulphur content of fuel-oil or fuel-gas for the Al Zour Refinery. Use of LIMS
(Laboratory information management system)
• Providing in-line sampling at all wastewater discharge points
• Implementing groundwater monitoring wells at both upgradient and downgradient
locations around the process units, tank farms and Refinery fence line.
An environmental philosophy was developed and used in the design of the Al Zour Refinery. The
environmental philosophy is consistent with the stated goal of safeguarding the environment of
Kuwait as well as with KPC HSSE Vision.
• Land use
• Water use
• Demography and socioeconomics
• Geology
• Seismic characteristics
• Hydrology (surface and ground)
• Terrestrial and aquatic ecology
• Coastal and marine environments
• Air Quality
• Meteorology
• Noise Monitoring and Measuring
The project site itself is a relatively undeveloped zone. The existing site consists of desert sand,
sabkhas and sparse vegetation. Although much of the immediate surrounding area is
undeveloped, the industrial plants of the Texaco Refinery and Al Zour Power station are located
very close to the boundaries of the Refinery to the east and south respectively.
There is a low population density in the general area of the site. Prior to construction starting
there was village settlement located within the northeast portion of the Al Zour Refinery site.
Private chalets are located to the north of the Refinery along Bnaider beach and to the South
Khiran Area.
The demographic and socio-economic survey revealed that commercial and residential buildings
in the village on site (i.e. non-industrial buildings) were generally in a poor state of repair. The
village was relocated as part of the Refinery development, and compensation has been agreed.
The housing development (Al Khiran) that was under construction to the south of Az Zour power
station has been growing to a mega planned community, the development incorporates many
kilometres of waterways connecting with the Al Khiran estuary, broad canals were excavated into
lowlands, and the spoil was used to build up the land for residential development.
The geology of the site comprises Undifferential Ghar and Fars formation. The dominant sediment
type in Al-Zour area are Calcareous sandstone, oolitic sand, fine sandy limestone and clayey sand.
The Refinery area is characterized by shallow ground water with water close to the surface. There
are no major fresh water sources or sewage discharges in the Az Zour coastal area. The soil and
groundwater investigation did not identify any significant contamination in underlying soils or
groundwater.
The terrestrial ecology survey concluded that the project area is typical of much of Kuwait. Flora
and fauna were identified and recorded as part of the assessment. The project area is not
considered as sensitive from an ecological perspective as in the northern region of Kuwait (e.g.
Subiyah).
The coastal survey showed that the area is covered with coarse to finely grained and medium
sand. Finely grained sediments are found in the north-eastern corner of the study area. In general,
the grain size of the sediment becomes finer offshore. Coral has been identified offshore.
Water quality analyses during the coastal survey revealed that all parameters were within KEPA
limits for both surface marine and bottom marine waters, except Total Suspended Solid (TSS)
which is recorded to be slightly higher than KEPA sea water criteria, this is expected to be due to
the temporary or local conditions prevailing in the nearby coastal regions.
Ambient air quality monitoring was conducted at several locations around the proposed site, there
was no violation of KEPA ambient air quality standards observed at the place and time samples
were collected. The measured pollutant concentrations reflect the meteorological conditions at
the time of sampling. It is expected that concentrations for some of the air pollutants sampled,
particularly sulphur dioxide (SO2), could have been significantly higher had meteorological
conditions placed passive samplers directly in the path of the power plant’s emissions. This is
confirmed with reference to other studies because baseline sulphur dioxide levels are known to
be high in the Az Zour area, and in fact, throughout much of Kuwait.
Baseline noise measurements were taken at a variety of locations around the perimeter of the
planned Refinery site. Monitoring was conducted during both day and night time and the
measurements indicate compliance with the applicable KEPA noise criteria.
The main purpose of the Noise study was to evaluate the potential community noise impact due
to the noise emissions from Al Zour Refinery.
In the original EIA (2006) a noise prediction program was performed using SOUNDPLAN 6.2. Noise
prediction were simulated for construction, normal operating conditions and start up and shut
down with full flaring. The noise impact during construction and normal operation were predicted
to be lower than the most stringent noise requirement promulgated by Kuwait regulatory
authorities. In start-up and shutdown situation, even the results are over the regulated limits,
equipment liability and redundancy ensure that large flare releases scenarios will be both
extremely rare and of short duration, a plant wide power failure, very conservative scenario, that
represent the maximum design load case for the flare system. The Refinery will be operated so
the units start up and showdown events are controlled, and shutdown do not occur
simultaneously, thus minimizing loads to the flare system.
In 2013 a noise modelling study was performed using CUSTIC 2.0 software to estimate the
dispersion of noise in the air. Noise modelling was carried out to study the general noise levels
for two seasons (summer and winter), for the Refinery which will be operated in Al-Zour area.
Major noise sources in the Refinery were identified from plot plan provided by KIPIC. These
sources were placed, scaled and geo referenced on bitmap loaded into the program.
The results of the model show borderline and adjacent areas at the Refinery site compliance with
environmental noise limits. In general, the results of the model indicate that the noise levels in
most areas of the Al Zour Refinery and its surrounding are less than the allowable limit of Kuwait
EPA standards.
As part of the Construction Quarterly Monitorings, the trend of Equivalent Noise Levels in different
locations over the Al Zour Refinery fulfil the KEPA Community Noise limits for Industrial and
Commercial Areas (Decision 8 of 2017 Appendix 1 - Table 5).
It is considered that the modelling results demonstrate that the air quality impacts associated with
the Al Zour Refinery at Az Zour are acceptable for the Al Zour Refinery will provide LSFO (i.e. 1%
weight Sulphur) to replace the up to 4% weight Sulphur content fuel oil that is currently available
and being used by the electric power generation industry in Kuwait. This will help enable the
power industry to satisfy the KEPA ambient air quality criteria for SOx criteria both in the Az Zour
area as well as in other parts of country.
Al Zour Refinery emissions, considered both in isolation and when also considering emissions
from the power station (including the power station extension), satisfy SOx and NO2 criteria at the
Al Zour Refinery site fence for both normal and maximum emission cases. Al Zour Refinery
emissions during emergency flare scenario, during upset conditions and on site from the tank
farms areas satisfy relevant criteria.
In 2013 an assessment methodology for the air dispersion modelling was performed that follows
the guidance specified by the US-EPA guideline on Air Quality Models using the CALPUFF Air
dispersion model. The different scenarios showed that in Al Zour normal operation the
parameters Ground Level Concentration (GLC) are below the KEPA limits, Operation of Al Zour
with Az Zour Power Plant showed that the GLC exceeded the KEPA limit mainly from the emissions
of Az Zour Power Plant (Al Zour Contribution to GLC is only 9.4%), Acid Flares scenario showed
KEPA limit fulfilment with adequate design and in Multipoint Ground Flares, since the emissions
from ground flares are mainly during emergency situations the GLC’s were also compared to
occupational exposure limit of KEPA and were found to meet the occupational limit.
As part of the Construction Quarterly Monitoring, the trend for Ambient Air Data shows
compliance with KEPA regulations. Specific parameters like Particulate Matter, Non-Methane
Hydrocarbons, Sulphur Dioxide and Nitrogen Monoxide present exceedances in certain
monitoring performed, these parameters were impacted by weather condition and emissions from
Al Zour Power Plant (Decision 8 of 2017 - Tables 1 (a) and 1 (b)).
Specialized marine site investigation was performed to undertake an extensive series of metocean,
geotechnical and geophysical surveys on the marine environment including, sedimentation
modelling studies, wave, wind, and current modelling.
Several Environmental Documents were prepared and submitted to KEPA including Marine study
to support Environmental Impact Statement, Environmental Impact Assessment Offshore Borrow
Areas and Environmental assessment of dredged material disposal and development of Dredging
management plan. Also, Environmental Studies where prepared for the Marine Outfall, Barge Dock
and Heavy Haul Road, Solids Handling Pier and Small Boat Harbour, and Soil Remediation
Baseline Water quality analyses undertaken revealed all the measured parameters are within KEPA
limits for both surface marine and bottom marine waters, except total suspended solid which is
recorded to be slightly higher than K-EPA sea water criteria due to the temporary or local
conditions prevailing in the nearby coastal regions.
The creation of increased suspended sediment concentrations within the water column is just an
inevitable consequence of the aggregate dredging process. However, mitigation measures were
in place to minimize this change to the physical environment. These mitigation measures focused
on either seeking to reduce the increase in suspended sediment and minimising the area affected
by the increase (see Figure 5 Silt Sea Curtains). Meteorological conditions were monitored using
a Meteorological monitoring station installed on a temporary jetty. The measured parameters are
Temperature, Barometric Pressure, Humidity, Wind Direction, Wind Speed, Tide level.
The sea water monitoring works are carried out by 7 environmental monitoring buoys deployed
on the sea (see figure 4); the locations were approved by KEPA. The parameters measured by the
sensors on the buoy were Turbidity, Dissolved Oxygen, pH, Salinity, Conductivity and Water
temperature. Every buoy had its own built data logger, kept in the main body of the buoy in a
waterproof canister, the buoy recorded data on a time interval of every 15 mins, the data was
transmitted to a receiving server with the help of the local internet. The buoys maintenance was
done every 2 – 3 weeks during summer and every 4 – 5 weeks during winter.
During Construction, all physical parameters nutrients and heavy metals in seawater were
generally within the prescribed standards of KEPA decision No 12 of 2017, Table 1, Seawater
Quality Guidelines. The results of sediment analysis are compared with Consensus Based Sediment
Quality Guidelines (CBSQG) developed by Contaminated Sediment Standing Team of Wisconsin
Department of Natural Resources, published in 2003 (CCME, 1999) for heavy metals in sediments.
Generally, the heavy metal concentrations except Nickel and Chromium all other are within
prescribed standards. Exceedances of Nickel, Chromium and Arsenic concentration in marine
(bottom) sediments are due to variations in natural background levels and not related to project
activity. Exceedances of Nickel and Chromium were also recorded in previous studies, these levels
as representative of natural variability rather than an anthropogenic source of pollution.
The Benthic studies showed moderate abundance of benthic community. The phytoplankton
community showed relatively common biomass per cubic meter in the study area, while
zooplankton community, on the other hand, showed frequent biomass. The phytoplankton results
indicated that the phytoplankton communities have improved and showed higher values
compared to baseline data. The macro epi-benthic communities were surveyed show Mollusca,
Polychaeta, Chordata, and Echinodermata as the most abundant marine phyla, followed by
Cindaria and Crustacea. Porifera and Bryozoa showed the lowest abundance. The fish community
Liquid wastes such as sewage from toilets, and solid wastes: domestic garbage including food
wastes, paper and cardboard, plastics, other packaging, and medical wastes during construction
were collected and returned to the Al Zour Refinery to be transported by KEPA authorized waste
management companies. The Operational wastes like oil rags, machinery maintenance remains,
broken parts, packaging also will be collected and transported to Al Zour Refinery within the waste
management system.
The following criteria for handling and disposing of non-hazardous solid waste were
implemented:
• Non-hazardous solid waste was segregated as much as possible to optimise the amount
of material that can reused or recycled.
• Containers for storing various non-hazardous wastes were selected for the specific service
intended and equipped with tightly fitting lids.
• Rubbish chutes and waste receiving areas were designed to prevent the spread of fire or
discharge of airborne pollutants or odours. The chutes and storage areas were maintained
free of debris and cleaned and disinfected on a regular basis. Bulk containers were readily
accessible to collection vehicles.
• Permanent waste was transported and disposed by KEPA approved third parties.
Wastes are not transferred outside the site unless it is removed by an approved of Environment
Public Authority Waste Company. Temporary storage in an environment friendly way was
observed. Any contractor that produces hazardous wastes due to its activity do not deal with any
waste carriers or storage, treatment, or elimination sites, which do not have an identification
number from Environment Public Authority and necessary licenses from concerned authorities.
Wastes are transferred to special sites determined by concerned authorities in the state.
The Refinery is under an EMS that include a waste management plan. The waste management
plan did incorporate the existing KIPIC waste management procedures and practices. The waste
management plan is to ensure that appropriate waste management practices are followed in
accordance with relevant prevailing national laws, regulations, and requirements regarding the
protection and preservation of the environment. In addition, the waste management is review
periodically by personnel working within the area of the Al Zour Refinery where waste is generated
Any hazardous waste generated such as un-used paints, thinners, oils, greases, acids, or corrosives
have been collected in an appropriate storage location and placed in sealed drums prior to offsite
disposal to a KEPA approved facility. Care was taken not to mix potentially incompatible materials.
Firefighting, safety, and spill control equipment is be readily available, should an accidental
discharge of hazardous material occur.
In compliance with KEPA Decision No. 6 of 2017, KIPIC’s waste management plans and EPC waste
management procedures, all the waste generated during construction activities were segregated
and disposed of in approved KEPA disposal locations. The details of waste generation are
submitted to KEPA in Environmental Monitoring Quarterly Reports.
During the operations phase, Safety Data Sheets (SDSs) will be made available at the guardhouse,
administration building, control room building, and chemical storage warehouse building.
During construction, all hazardous material is stored and managed appropriately in storages
located within each EPC Contractor controlled area. Materials within these areas are stored
according to compatibility and all flammable materials are segregated and stored appropriately.
All hazardous materials are contained within temporary or permanent secondary containment to
prevent a release to soil or groundwater. Bunded areas have impermeable floors and bunds,
including the chemical storage warehouse.
During operation, the Al Zour Refinery will fully incorporate and comply with all KEPA HSE criteria
including that for handling, treatment, storage, and disposal of hazardous materials. The
appropriate handling and danger placards are displayed wherever hazardous chemical materials
are handled, transported, or stored. Storage of hazardous chemicals were in accordance with the
provisions of the KEPA regulations and KIPIC Guidelines.
Hazardous materials storage during operation of the Al Zour Refinery will either be in fixed tanks
(at various bunded locations on the site), in a compressed gas cylinder storage area or in a
Chemical Storage Warehouse. The Chemical Storage Warehouse is likely to contain hazardous
materials in bottles, pails, drums, bags, or similar containers.
The design, construction and operation of this warehouse will be in accordance with KEPA
licensing requirements as specified under Article No. 18 and the United Nations Classification
System for separation of hazardous chemical materials. Category 1 explosive materials are not
envisaged for the Al Zour Refinery. Typical safety features included in the Chemical Storage
Warehouse includes firewalls to separate materials that are combustible, flammable, corrosive, or
toxic including acids and alkalis. The Chemical Storage Warehouse floor has a chemical resistant
coating, and impermeable kerbing will be used to provide secondary containment where needed.
The Al Zour Refinery design incorporate best environmental engineering practices such as Best
Available Control Technology (BACT) to avoid, prevent or mitigate the discharge of all harmful
emissions to meet (or exceed) applicable KEPA environmental standards. KIPIC proceed based on
zero liquid discharge (ZLD) for the Al Zour Refinery.
KEPA requires that all discharges to sea be 500 meters or more offshore. Although an outfall
pipeline for offshore discharge will be provided as part of the Al Zour Refinery design, it will not
exist during the early construction phase. Throughout the construction period no wastewater
effluents have been discharged to the environment (either to land or sea) without first having
been analyzed to verify compliance with all applicable KEPA discharge criteria. If sample analysis
indicates that the water in the retention pond(s) is not of acceptable quality for discharge it is
pumped back to the packaged wastewater treatment or collected via vacuum truck for transport
to an appropriate wastewater treatment facility.
An overall peak workforce of more than 60,000 construction staff (divided into four separate EPC
contractor camps) was working in the Al Zour Refinery.
Wastewater effluents are generated on a short-term basis because of the various construction
activities associated with building the Al Zour Refinery, and its scheduled start-up and
maintenance activities. These include sanitary wastewater, wash-down water, stormwater, water
from groundwater de-watering activities, and wastewater from hydrostatic testing activities (i.e.,
from asset-integrity testing of pipelines and Storage Tanks etc). Hydrostatic test water with low
levels of a proprietary biocide and corrosion inhibitors is collected or treated in the Refinery to
ensure compliance with applicable KEPA discharge criteria.
The size of the manpower required to construct the Refinery implies that a large fleet of vehicles
to access the Refinery site every day. The study undertook the design of the optimum
transportation system that ensures that during construction and operation, people and goods
move to or inside the Refinery safely and without delays.
An iteration process followed consisting on the design of a series of mitigation options and their
consequent evaluation. The mitigation options capacity was analyzed to evaluate the different
alternatives based on levels of service, construction costs and constructability. Based on this
evaluation, a preferred alternative was identified.
The study recommended a 4-lane access road that will extend south from the north end of the
laydown area, span over Route 40 on a temporary bridge and over Road 270 on a roundabout
interchange and continue parallel to Route 40 to reach the roundabout that leads to the future
Route 40 interchange #6. During construction, EPC access were processed via dedicated access
roads that intersect the proposed Refinery access road at either small roundabouts or T-
intersections. This alternative included the construction of a permanent bridge on Al Zour Power
Station Road and a utility overpass.
During the operational stage, while the bridge over Route 40 and access to the laydown will be
removed, the temporary bridges over Road 270 could remain and used to provide alternative
access to Route 40NB through an intersection North of Interchange # 5. Also, a new link from the
Refinery Access Road to the proposed Interchange #5 on Route 40 could be added to provide
access to the Refinery from Route 40 SB bypassing Road 270.
In 2000, all the occupants of the Az Zour village were served notice to vacate the village and they
had two years to clear the property. Each household was given rights to a new plot in the Al Khiran
city that will be built west of the highway, and agreed financial compensation, which was settled.
This approach to compensation follows the precedent set by the expansion for the power station
for taking and using land for industrial use in this concession area. As such, the greatest social
impact has already occurred before the start of construction. KIPIC was not involved in the
relocation of the village North of Al Zour Refinery.
The overall economic impact is positive, as this is one of the reasons for the development. As such,
the focus is on the impact on local populations and other associated issues.
Several Social welfare procedures have been developed by KIPIC to manage Social aspects
including:
• KIPIC Environment & Social Guidelines for Contractors (KIPIC/HSE/ENCSR/19/1515)
• KIPIC Environmental and Social Audit Guidelines (KIPIC/HSE/ENCSR/20/1513)
• Environment and Social External Complaint Recording & Tracking Procedure for
Contractors (KIPIC/HSE/ENCSR/20/1517)
• Social Incident Reporting and Investigation Procedure for Contractors
(KIPIC/HSE/ENCSR/20/1518)
• Social Counselling Procedure for Contractors (KIPIC/HSE/ENCSR/20/1519)
The area is dominated by a large oil-fired electricity-generating power station, Al Zour, with twin
stacks (192 m high). This power station is being expanded to double in capacity. Al Zour power
stations are adjacent to the Al Zour Refinery and to the south east of the project area. Adjacent
and east of the Al Zour Refinery is a Texaco oil storage facility and associated pipeline and small
port facilities, with beach chalets located on the coast side. Further houses are located northwest
The nature and scale of the Al Zour Refinery is partly compatible with the site context due to the
adjacent power-plant (due for expansion) and near-by oil storage facility. The height and scale of
the proposed structures are also compatible with surrounding industrial structures although the
size of the Al Zour Refinery will be larger and emphasize the industrial character after construction.
Receptors at long distance will consider the proposed Refinery in context with the existing
industrial developments adjacent to the site. The proposed project is set in context with adjacent
industrial areas where the visual environment is dominated by the Al Zour power station and oil
storage facility, both to the east. Local observers will be potential visually impacted by the new
development, although the village was relocated prior to development of the Refinery. The impact
of the Refinery on the desert landscape surrounding the site is minimised due to the development
being adjacent to the Al Zour power station and industrial areas to the east. Impacts on landscape
character are therefore minimised.
During construction, different monitoring wells were built to extract groundwater both on site
and laydown area, the water analyzed do not show important variations compared to the
groundwater baseline.
In addition, during operation a groundwater monitoring well system will be installed around the
process and tank farm areas will provide a further means for monitoring contamination at the Al
Zour Refinery Site. These wells shall be located so that representative samples of the groundwater
that may be impacted by operation of the proposed facility can be obtained. Placement of the
wells will include a minimum of one up-gradient location and two down-gradient locations. The
tank farm area shall be regarded as a single unit. A minimum of two up-gradient and five
downgradient groundwater monitoring wells will be installed along the perimeter of the tank
farm. Down gradient wells will be located no more than 500 meters apart.
• Prevention and mitigation: to eliminate or reduce the chances or lessen the effects of an
emergency, for example, by adopting safe design, operating and maintenance practices.
• Emergency plans: written procedures and guidelines on how to respond efficiently and
effectively, with the right resources and trained personnel, should an emergency occur.
• Response: activities immediately following the alert or disaster.
• Restoration: returning all used and affected systems and services to normality as soon as
practicable after the emergency has been resolved and any adverse impacts mitigated.
KIPIC has developed and implemented a Major Incident Procedure Plan (MIPP) for its refineries.
The MIPP provides a procedural framework for responding to emergency incidents such as fire
and flammable or toxic releases and has been approved by the appropriate Kuwaiti authorities.
KIPIC MIPP, the principal features of which have been described above, has enabled a similarly
stringent Emergency Response Plan to be implemented for the Al Zour Refinery, and ensures that
KIPIC will apply a unified and collective KIPIC approach to responding to emergencies at all its
installations - including the Al Zour Refinery eventually - and other associated facilities (eg oil
terminals). Such an Emergency Response Plan (based on KIPIC’s MIPP) for the Al Zour Refinery.
There are likely to be three project stages which decommissioning of the Al Zour Refinery will go
through: pre-decommissioning consents and contracts; decommissioning activity obligations; and
post-decommissioning responsibilities. Specific environmental-related decommissioning and
closure objectives associated with the Al Zour Refinery are predicated around meeting all Kuwaiti
legal and regulatory requirements (including KEPA criteria), and mitigating any impacts
(environmental, public health, safety, social) within the impact vicinity of the site.
Elements such as these in establishing an ongoing DCMP for the Al Zour Refinery, will send a
robust signal that post-closure, the Al Zour Refinery will be optimally decommissioned, prior to
handover back to the state or private use.
KIPIC is working on an EMS, in line with the requirements of ISO14001, that will be similarly
implemented for the Al Zour Refinery. As a tried and tested system, it will provide the same
structured approach for the optimum management of environmental issues at the Al Zour
Refinery. The principal mechanism by which this will be done is through KIPIC Manual.
As part of the HSE Management System, KIPIC has developed specific procedures related to
Environmental and Health including:
Safety Integrity Level (SIL) classification and verifications have been specifically carried out of
safety critical systems taking into consideration system redundancy in identifying minimum
performance requirements for Project development. These were assessed in the form of
probability of failure on demand.
FWDA (Firewater Demand Assessment) throughout process units have been carried out to identify
firewater requirements during a fire hazard for extinguishing and cooling purposes of process
inventory and load bearing structure, manned facilities etc. and in sizing firewater pumps and
firewater tanks. This was followed by Hydraulic Analyses (HA) in establishing velocity and pressure
profiles through the firewater network and at each delivery point in compliance to Project Design
Engineering Specs and Codes such as SHELL DEP and NFPA. Buildings fire safety has been
extensively addressed with safety design measures rigorously applied for detection, prevention,
control, and mitigation of building fires.
Petroleum refineries are complex facilities with hundreds of thousands of sources of air pollutants
including greenhouse gases (GHG), the vast emissions of these atmospheric pollutants pose a
great concern to global communities due to their contributions towards global warming, the
primary GHG emitted by the petroleum refining industry are carbon dioxide (CO2) and methane
(CH4). In addition to the combustion-related sources (e.g., process heaters and boilers), there are
certain processes, such as hydrogen production units, and sulphur recovery plants, which have
significant process emissions of CO2. Methane emissions arise from process equipment leaks and
crude oil storage tanks. Flaring of waste gas also contributes to the overall CO2 and CH4 emissions
at the refinery.
In Al Zour Refinery proven and efficient design measures were incorporated as per industry and
operating practices to minimize the generation and release of greenhouse gases (GHGs). In
operation GHG emissions will be reported annually.