INSPECTION TEST PLAN JUNE 2021

PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

PROJECT : TP-212112-Oil & Gas New Main Warehouse, Brega, Area 1


OWNER : SIRTE OIL COMPANY

Projects Dept. : For Production, Manufacturing of Oil & Gas

CONTRACTOR : Tareq Asia for Construction Co.

CONTRACT No. : 99984-320-418

Page 1 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

CONTENTS

1. INTRODUCTION 4
2. CONFLICTING REQUIREMENTS 4
3. SCOPE OF WORK 4
3.1 Civil Works......................................................................................................................................4
3.2 Architectural Works........................................................................................................................5
3.3 Electrical Works..............................................................................................................................5
3.4 Communication Systems Works.....................................................................................................5
3.5 Fire & Gas Alarm And Fire Protection Works.................................................................................5
3.6 HVAC Works....................................................................................................................................5
3.7 Equipment’s Works........................................................................................................................6
3.8 Furniture Works..............................................................................................................................6
3.9 Warehouse Racks Works...............................................................................................................6
3.10 Demobilization..............................................................................................................................6
4. Pre-Fabricated Precast Concrete Structure 6
5. Reference Standards 7
6. Submittals 7
7. Products 8
8. Execution 9
8.1 Forms.............................................................................................................................................9
8.2 Placing Reinforcement....................................................................................................................9
8.3 Installing Embedded Items.............................................................................................................9
8.4 Preparing Form Surfaces................................................................................................................9
8.5 Concrete Placements......................................................................................................................9
8.6 Finishing..........................................................................................................................................9
8.7 General Reinforced Concrete Construction.................................................................................10
9. Architectural Works 10
9.1 Shop Drawing and As built Drawing.............................................................................................10
10. Sewer System 11
10.1 Cold and Hot Water System.......................................................................................................11
10.2 Plumbing Fixtures.......................................................................................................................11

Page 2 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

10.3 Water System & Plumbing.........................................................................................................11


11. HVAC Work 11
11.1 Codes & Standards......................................................................................................................12
11.2 Design Requirements..................................................................................................................12
11.3 Commissioning Start Up.............................................................................................................12
12. Communication and Fire Alarm System 13
13. Electrical Work 13
13.1 Electrical Systems & Equipment.................................................................................................14
13.2 Electrical Specification................................................................................................................14
13.3 Codes & Standards.....................................................................................................................14
13.3 Drawings.....................................................................................................................................14
13.4 Material & Equipment................................................................................................................15
13.5 Installation..................................................................................................................................15
14. Codes & Standards 16
15. Approved Drawings 18
16. Inspection And Test Plan Requirement 18
17. INSPECTION LEVEL DEFINITION 19
17.1 Spot Witness (SW)......................................................................................................................19
17.2 Witness Point (W)......................................................................................................................19
17.3 Hold Point (H).............................................................................................................................19
17.4 Approval (A)................................................................................................................................19
17.5 Review and Comment ( R ).........................................................................................................19
17.6 Verification (D)............................................................................................................................19
18. COORDINATION 20
19. Important Notes 20
20. Acknowledgement 21

Page 3 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

1. INTRODUCTION

ITP is the minimum requirement of the activities for quality control and inspection of the field construction
work. This Inspection and Testing Plan outline the extent of witness inspection and its reporting.

2. CONFLICTING REQUIREMENTS

Should conflicts exist between this specification and other documents, the following order of precedence
shall govern:

 Scope of Work
 Data Sheets
 This Specification
 Other Company Specification
 Other Referenced Publications
 Approved for Construction Drawings
 Vendor’s Code

3. SCOPE OF WORK

General Description : “TP-212112 (EPC) OIL&GAS MAIN WAREHOUSE AREA-1,Brega.

The New Building will be located on the same site of the previous main warehouse as shown on the site
development plan, comprising a site area of approximately 8500 sq. mts, divided into 4 bays.

3.1 Civil Works

 Cutting, Demolition & Removal Work


 Excavation, Backfilling & Compaction Work
 CAST IN-SITU CONCRETE Works
 PRECAST CONCRETE ELEMENTS Installation
 Masonry Works
 Plastering Work
 Sanitary Plumbing Sewer System Works
 Water Supply And Distribution System
 External Work
 ROOFING Works

3.2 Architectural Works

Page 4 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

 Protective Coating
 Wall Finishes And Painting
 Ceramic Tiling Works
 Doors
 Windows
 Ceiling System
 Floor Finish
 Toilets And Wash Area Fixtures
 Miscellaneous works

3.3 Electrical Works

 Internal Electrical System


 Panel board Work / Transformers
 External Electrical System

3.4 Communication Systems Works

 Surveillance/Security Camera (CCTV) System


 Telephone Network Installation
 Data Network (It) Network
 Intercom System
 Fiber Optic Routing
 Tie-In, Testing And Commissioning

3.5 Fire & Gas Alarm And Fire Protection Works

 Wet & Dry Fire Hydrants


 Fire Water Lines & Sprinkler System
 Fire & Gas Detection And Alarm System
 Testing And Commissioning

3.6 HVAC Works

 Split Units Air Conditioning


 Exhauster Roof Ventilators
 Sand Traps & Multi-Leaf Dampers
 Commissioning Spares
 Pre-Commissioning Of HVAC System
 Commissioning Of HVAC System

3.7 Equipment’s Works

 Overhead Crane

Page 5 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

 It Equipment
 Office Equipment’s
 Testing And Commissioning

3.8 Furniture Works

 Offices
 Communication Room
 Stationary Area
 Tea Rooms
 Praying Room
 Shipping And Bonded Custom Area
 Wash Room
 Receiving And Issuing Area

3.9 Warehouse Racks Works

 Hanging Racks
 Heavy Duty Racks
 Protective Barriers

3.10 Demobilization

 Dismantling And Removing


 Cleaning Site Area , Laydown Area , Store Area And Handover

4. Pre-Fabricated Precast Concrete Structure

Prefabricated precast concrete structure includes the following:

 Exterior Wall
 Interior Wall
 Roof Slab
 Interior Finishes ( where applicable )

5. Reference Standards

A) American Concrete Institute (ACI)

 ACI 117 , Standard Specification For Concrete Construction and Materials.


 ACI 301 , Structural Concrete for Building.

Page 6 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

 ACI 304 , Measuring, Mixing Transporting and Placing Concrete.


 ACI 309, Consolidation of Concrete
 ACI 318 , Building Code Requirements for Reinforced Concrete.

B) American Society Testing and Materials (ASTM)

 ASTM A36, Carbon Structural Steel


 ASTM A82, Steel Wire For Concrete Reinforcement
 ASTM A108 Steel Bars
 ASTM A153 ,Zinc Coating on Iron
 ASTM A497 Welded Deformed Steel Wire Fabric for Concrete Reinforcement
 ASTM A615 Deformed Steel Wire Fabric for Concrete Reinforcement
 ASTM C33 Concrete Aggregates
 ASTM C150, Portland Cement
 ASTM C494 Chemical Admixture for Concrete
 ASTM C618, Coal Fly Ash for use as a mineral admixture in concrete.

C) American Welding Society (AWS)

 AWS D1.1 Structural Welding Code – Steel


 AWS D1.4 Structural Welding Code Reinforcing Steel

D) Concrete Reinforcing Steel Institute (CRSI):CRSI Manual of Standard Practice

E) Precast/Pre-stressed Concrete Institute (PCI)

 PCI MNL-116
 PCI MNL-20
 PCI MNL-123 Manual Design Connections for Precast.
 PCI MNL -124 Design For Fire Resistance of Precast.
 PCI MNL-127 Recommended Practice For Erection of Precast.

6. Submittals

A) Product Date : Manufactures Catalogue cut sheet, published specification and material description for each
component that is incorporated in the pre-fabricated precast concrete structure and other request by SOC.

B) Shop Drawing :

 Fabrication Drawing needs to attached for all components including placing concrete reinforcement
detailing bending and placing concrete reinforcement in compliance with ACI318 and CRSI Manual
Standards practice.
 Elevation Section and Dimension for all precast units including anchors, inserts and embedded cast-in
place items.
 Mechanical, Electrical and plumbing layouts indicating location for all respective equipment’s.
 Drawing and structural calculation shall be signed and sealed by professionals engineers.

C) Quality Assurance :

Page 7 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

 Precast Concrete Structure Manufacture Shall Perform work in compliance with applicable
requirements of ACI318, and PCI MNL-116,PCI20,PCI-123,PCI-124, and PCI MNL-127.
 Design Standards Comply with ACI318 and the design recommendation of PCI MNL 120.
 Quality Control Standard for manufacturing procedure and testing comply with PCI MNL 116
 Comply with camber and dimension tolerance of ACI 318 and PCI MNL 135.
 Welding Quality Procedure and personnel according to AWA D1.1 “Structural Welding Code Steel” and
AWS D1.4 “Structural Welding Code-reinforcing Steel.
 Fire Resistance indicated structural precast concrete units whose fire resistance meets the prescriptive
requirements of the governing code or has been calculated according to ACI 216.1/TMS 0216.1.

7. Products

 General : Prefabricated precast concrete structure consisting of four, five or six sided units.
Coordinate installation of hollow metal door and window frames , electrical, plumbing,
fixtures.
 Form Materials
 Reinforcing Materials : Rebar ASTM A615 and OR ASTM A706.
 Welded Wire Fabric : ASTM A497
 Structural Material : For Structural Beam ASTM A992 , For Structural Tubing ASTM A500 Gr.B ,
For Angles/Flat ASTM A36.
i. Portland Cement : ASTM C150 TYPE I
ii. Fine Aggregates in accordance with ASTM C 33
iii. Aggregates in accordance with ASTM C 330
iv. Water should be portable
v. Concrete Admixture that contain no more than 0.1 percent chloride ions.
vi. Water Reducing Materials : ASTM C 494 , Type F&G
vii. Basics of Design : Pro-Mix Co. , Propel Excel 25
viii. Additional Manufacture:
 Pro-mix Co.
 Euclid Chemical
 Grace & Co
 Sika Corp.

ix. High-Range Water Reducing Admixture ASTM C 494 TYPE E.

 Related Material: Liquid type membrane forming curing compound with ASTM C 309, TYPE 1
Class.
i. Products : As per Scope of work.
ii. Epoxy Adhesive : ASTM C 881, two component gel epoxy suitable for use on dry or
damp surface.
iii. Basic of Design : Sika Hi-Mod 31
iv. Additional Manufactures : As per Scope of Work
v. Roof Joint Epoxy : ASTM C 881

Page 8 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

vi. Basis of Design : Prairie Epoxy 7095

8. Execution

8.1 Forms

Maintain formwork construction tolerance and surface irregularities comply with ACI 318 and PCI MNL-116 .

8.2 Placing Reinforcement

Comply with ACI 318 , PCI MNL -116 and CSRI: Manual of Standard Practice for “Placing Reinforcing Bars”.

8.3 Installing Embedded Items

Comply with PCI MNL-123 Manual of Design for Connection for precast.

8.4 Preparing Form Surfaces

Coat Contact surfaces of forms with an approved, nonresidue low-VOC , form-coating compound before
placing reinforcement.

8.5 Concrete Placements

Inspection : Before placing Concrete, Inspect and complete form work installation, reinforcing steel and items
to be embedded or cast in.

General : Comply with ACI 304 “ Guide for Measuring, Mixing Transporting and Placing Concrete” and PCI
MNL-116 “Manual for Quality Control for plants and Production of Precast.

8.6 Finishing

 Smooth-Formed Finish
 Non-Formed Finish

8.7 General Reinforced Concrete Construction

 Columns, Beams, and Roof Slab


 Concrete Materials ( Internal Offices and Stationery Office )
 Exterior Walls
 Interior walls
 Toilet partitions concrete block walls
 Masonry work
 All blocks units shall have the following criteria:

Page 9 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

I. Minimum Compressive Strength


Average of 3 units – 4.8 Mpa (700psi)
Individual unit - 4.1 Mpa (600psi)

9. Architectural Works

 Furnishing and Equipment


 Floor Finish
 Wall finish & Painting
 Ceiling
 Exterior & Interior Doors
 Hardware
 Exterior Windows
 Interior Windows
 Overhead Roll-up Door
 Curtains
 Brackets
 Hoods
 Locking
 Built – up roofing

Note : The Contractor will submit all those material submittals , Datasheet for Architectural work accordingly
for approvals prior to fix or install.

9.1 Shop Drawing and As built Drawing

 Contractor will submit 3 sets of shop drawing for the above work and manufacture product data
brochure to company prior to purchase . ( reference : Same as Scope of Work )
 Contractor will submit as built drawing ( Mylar and Electronic File) as per scope of work.

10. Sewer System

 Manholes, Valve pits shall be constructed in fair faced structural reinforced concrete.
 Sewer and waste pipes shall be UPVC pipe schedule 40 with minimum slopes of 2% for 100 mm
diameter sewers and 1% for 150mm Diameter pipe sewers.

10.1 Cold and Hot Water System

 Piping materials for cold and hot water system shall be CPVC SH80, Socket weld and fittings
conforming to ASTM Standard 2846-69T.
 Other pipes, valves and fittings as per the Scope of work.

Page 10 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

10.2 Plumbing Fixtures

 Water Closet
 Urinals
 Hand Wash Basin
 Washroom Accessories

All as per Scope of Work.

10.3 Water System & Plumbing

Drainage and freshwater service all system shall be in accordance with the National Plumbing Code (USA) or
its equivalent. Plumbing shall include the following system:

 Fresh Water
 Hot Water
 Fire Water
 Sanitary and sewer

Contractor Need to Submit Shop drawing for approval prior to start work.

The Contractor will submit the “Method of Statement for piping works” If required.

11. HVAC Work

The Specification covers the requirements of HVAC System, designed to maintain and control the
temperature, relative humidity , air filtration and ventilation for normal operation of the operating personnel.

11.1 Codes & Standards

The Design is based on the following codes and standards as appropriate. All materials and equipment used
shall also be designed and manufactured with relevant standards, codes & specification.

International Codes & Standards

 ASHRAE – American Society Of Heating Refrigerating & Air Conditioning For Engineers.
 SCS – Standard Construction Specification For SOC
 GES- General Engineering Specification For NOC
 SMICNA- Sheet Metal & Air Conditioning Contractor National Association
 DWI142 – Specification For Sheet Metal Ductwork, Low & Medium Pressure Air System
 ASME- American Society Of Mechanical Engineer

Page 11 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

 HVCA– Heating & Ventilation Contractors Association


 CIBSE- Chartered Institution Of Buildings Service Engineers
 ANSI – American National Standard Institute
 NEC- National Electric Code
 UBC- Uniform Building Code

Sirte Oil Company Construction Specification

SPEC. NO. REV. TITLE


CS2000 0 Installation Of A/C Units
CS2001 0 Balancing Of A/C Units
CS2002 0 Duct Work And Air Outlets
CS2003 0 Installation Of Fans
CS2004 0 Installation Of Freon
Refrigeration System
CS2005 0 Installation Of Hot & Cold Lines

11.2 Design Requirements

 Splits Units
 Ventilation System

11.3 Commissioning Start Up

 Commissioning Spares
 Commissioning of HVAC System

Note : The Contractor will submit all those material submittals , Datasheet for Architectural work accordingly
for approvals prior to fix or install.

Contractor Shall Submit the Shop Drawing, Method of Statement accordingly. The Commissioning work shall
be as same as scope of work.

12. Communication and Fire Alarm System

This scope of work shall be interpreted together with the attached drawings SK-05 TO SK-17 as given in Scope
of Work.

 Data Network/fiber Optic Cable and Installation works


 Telephone System
 Fire Detection and Alarm System
 Surveillance /Security Camera (CCTV)System
 Intercom System

Page 12 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

 Power System
 Code & Standards : As per Scope of work
 Vendor List
 Attached Drawing : Refer to Drawing SK-00 TO SK-17

13. Electrical Work

Contractor Shall Provide all the electrical material as per scope of work, the method statement should follow
for the installation procedure. Contractor will submit material data sheets and submittals for the materials for
approvals prior to purchase.

Area Classification : The New Warehouse location is classified as NON-HAZARDOUS.

However, outdoor materials and equipment shall meet with NEMA Weatherproof definition, where materials
shall be specified as splash-proof.

Electrical Drawings : The following drawings are included with this specification for :

Drawing No. Drawing Title


LD2-1-94 Local Facilitates 2 one Line Diagram
ES-16-3-1 to ES-16-5-10 SOC Standard Engineering Drawings

Electrical Supply : Contractor Shall ensure that all supplied materials for the project is compatible with SOC
Area-1 Electrical System.

Voltage Rating 12/208V , 480V/277V , 480 3-PHASE + Neutral


Frequency Rating 60Hz 3-PHASE + Neutral

13.1 Electrical Systems & Equipment

All Equipment shall be tropicalized. Nameplates and mounting screws for all motors, transformers and
electrical equipment shall be corrosion resistant stainless steel.

 Motors
 480V and 120/208V Distribution Panel boards & Lighting Transformers
 Surge Arresters
 Wiring & Cable System
 Lighting
 Grounding System

Page 13 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

13.2 Electrical Specification

These Specification are intended to provide a complete and functioning electrical installation.

Contractor Shall provide all labor, supervision, construction equipment, tools and miscellaneous material to
carry out the work.

13.3 Codes & Standards

The Electrical installation and all materials and equipment incorporated into the installation shall comply with
the following codes & standards,…

 NFPA 70 National Electrical Codes (NEC)


 NEMA Standards
 ANSI Standards
 UL Standards

13.3 Drawings

Drawing Issues : Drawing marked for Bid only , preliminary only. The electrical drawings indicate the general
location and route to be followed by conduits.

Deviations: All deviation from drawing or specification must be approved by company.

As built : Three complete sets of detailed as build drawings, calculation, data sheets, certification, design , and
test records certified by professional engineers experienced in the design shall be supplied to company at
completion of construction works.

13.4 Material & Equipment

All Electrical Materials Used Shall Be New And High Quality, Manufactured to IEC/ANSI/NEMA Standards And
Have Approvals.

Panel Boards : Low Voltage lightening panel boards shall be 225A (minimum),42x circuit complete with main
breaker. ( as per SOW )

Lighting Fixture : Due to poor efficiency and a short life, the use of incandescent lamps shall be minimized.

Conductors : All power conductors shall have 90 degree cross linked polythene insulation.

Cable Trays and Fittings : Cable Trays and Fittings shall be hot dip galvanized , epoxy coated.

Conduits & Fittings : All above ground conduits shall be rigid steel, hot dip galvanized, epoxy coated.

Conduits & Tray support : Support channel shall be compatible with the tray material.

Page 14 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

Junction boxes & terminals : Junction boxes for outdoor areas shall be weatherproof NEMA 4X,complete with
jack panel, hinged door and drain fittings.

Grounding Electrodes and Inspection Pits : Grounding Rods shall be 19mm diameter by 3050 long copper clad
ground rod.

13.5 Installation

All electrical material installation shall be as per standards and scope of work only. The list of the installation
are :

 Lighting
 Control Station
 Wall Mounted Equipment
 Cable trays
 Surface Raceway
 Conduits
 Cable Sealing
 Wall penetrations
 Tray Supports
 Cable Trenches
 Armored Cables
 Wiring
 Grounding
 Lightening Protection

Note : Testing shall be done as per scope of work.

14. Codes & Standards

The Contractor shall conform to the following codes and standards for all following works.

Civil Codes

AMERICAN CONCRETE INSTITUTE (ACI)

UNIFORM BUILDING CODE (UBC)

Specification No. Specification title


ACI301 Specification for structural concrete for buildings
ACI304 Recommended practice for measuring, mixing,
transporting and placing concrete
ACI305 Hot weather concreting
ACI308 Standard practice for curing concrete
ACI309 Standard practice for consolidation of concrete
ACI318 Building Code requirements for reinforced Concrete
ACI347 Recommended practice for concrete form work

Page 15 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

ACI201.2R Guide to durable of concrete


ACI212.1R Admixture for concrete
UBC Uniform Building Code-USA

AMERICAN SOCIETY FOR TESTING AND MATERIALS ( ASTM )

Specification No. Specification Title


ASTM A307 Carbon Steel externally threaded standards fastener
ASTM A615 Deformed and plain billet-steel bars for concrete
reinforcement
ASTM A36 Masonry anchors
ASTM A153 Hot dipped galvanized material
ASTM C31 Concrete test specimens
ASTM C33 Concrete aggregates
ASTM C39 Compressive strength of cylindrical concrete
specimens
ASTM C94 Ready mix concrete
ASTM C143 Portland cement
ASTM C150 Sampling freshly mixed concrete
ASTM C172 Sampling freshly mixed concrete
ASTM C494 Chemical Admixture For concrete

Page 16 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

Page 17 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

15. Approved Drawings

Contractor shall complete their work with approved drawing, some of the drawing is approved by company
and remaining contractor submitted to the company for approval.

16. Inspection And Test Plan Requirement

 CONTRACTOR shall prepare and execute all inspection and test. They shall conform to the above
mentioned codes, standards, and project specifications.
 CONTRACTOR shall provide all inspection equipment for inspection activities s. These activities are to
assure themselves that adequate inspection personnel and back up equipment are in place in order to
expedite their activities speedily so as not to impact on the construction schedule.
 CONTRACTOR shall prepare check sheets and inspection reports for carrying out the required quality
control checks according to particular discipline work activities. All inspection and test reports forms
shall be specific to the activity and items inspected.
 CONTRACTOR shall also prepare a detailed inspection and test plan indicating inspection levels (spot
witness, witness, hold point, etc.), based on COMPANY definitions herein. The test inspection plan
shall include witness/attendance requirements by COMPANY.
 CONTRACTOR shall generate, maintain, documented, and collate the inspection records, which is done
by them or by its Vendor/Subcontractors. The system employed shall insure full tractability of records
including back up in accordance to COMPANY requirements. CONTRACTOR shall submit the originals
of all inspection data and other related documents to COMPANY, as required by the contract terms.

Page 18 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

17. INSPECTION LEVEL DEFINITION

17.1 Spot Witness (SW)

Spot witness inspection is a point during construction activities where measurement, witnessing of work or
inspection normally takes places. Formal written notification is not required, although oral or informal memo
will normally be given. If the discipline inspector does not inspect the work at this point, the work may
continue. However inspection data must be recorded, and the CONTRACTOR is fully responsible to ensure that
this is done before continuing the next work step.

17.2 Witness Point (W)

A witness point is a point in a construction activity where inspection must take place.
CONTRACTOR/COMPANY QC Group shall be formally notified in writing of the inspection 24 hours in advance
notice is for most accurate schedule) and will normally attend the inspection. Nevertheless, CONTRACTOR
needs to include schedule of inspections in weekly meetings. On a case by case basis, the inspection
witnessing may be waived. In this case, inspection may proceed without attendance. However, inspection data
must be recorded and submitted for review and approval. All waivers will be given in writing prior to
inspection execution (jointly approved by CONTRACTOR and COMPANY).

17.3 Hold Point (H)

A Hold Point is a point in a construction activity where formal written notification is given of an inspection (24
hours in advance notice is for most accurate schedule) and work shall not proceed until the inspection is
performed. Nevertheless, CONTRACTOR needs to include schedule of inspections in weekly meetings.
Mandatory attendance is required.

17.4 Approval (A)

A document or drawing, which is to be submitted for approval prior to proceed the activity.

17.5 Review and Comment ( R )

A document or drawing, which is to be submitted for review/ comments.

17.6 Verification (D)

A document or drawing, which shall be submitted to COMPANY for report/ comments.

Page 19 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

18. COORDINATION

Quality Control and Inspection by CONTRACTOR

For the items marked with “ SW “ and “ W “ under column “CONTRACTOR”, the quality control and inspection
will be conducted by CONTRACTOR at their own responsibility. However, COMPANY shall have the right to
inspect any works done by CONTRACTOR or Vendor at any time (except for “ W ”, a written notification from
CONTRACTOR is required).

Inspection Hold Point

For item marked with “ H “ under column of COMPANY and CONTRACTOR, CONTRACTOR shall notify
COMPANY in writing of the inspection scheduled date and time. Witnessing shall be jointly performed by
CONTRACTOR and COMPANY. CONTRACTOR cannot proceed the next work step activity until the inspection
and measurement or test has been witnessed and approved by all attending parties.

Notification of Inspection

CONTRACTOR shall give a written notification to COMPANY for attending the inspection/testing.

Document Approval

For item marked with “ A “ under column “COMPANY”, CONTRACTOR shall submit documents, drawing, etc.
to COMPANY. For item marked with “ A “ under column “CONTRACTOR”, Vendor shall submit documents,
drawing, etc. to CONTRACTOR for approval. Inspection shall not be conducted before COMPANY approves the
required documents.

Document Review

For item marked with “ R “ under column “COMPANY”, CONTRACTOR will submit documents, drawing, etc. to
COMPANY for review / comment. For item marked with “ R “ under column “CONTRACTOR”, Vendor shall
submit documents, drawing, etc. to CONTRACTOR for review / comment.

Document Verification

For item marked with “ D “ under column “COMPANY”, CONTRACTOR shall submit documents, drawing, etc.
to COMPANY for a report and/ or comments (if required). CONTRACTOR shall accommodate COMPANY’s
comments (if any). For item marked with “ D “ under column “CONTRACTOR”, Vendor shall submit documents,
drawing, etc. to CONTRACTOR for verification and review and or report.

19. Important Notes

 This ITP Consist the quality procedure and codes of standards as per scope of work
 Data Sheet for all type of material contractor shall submit accordingly for approvals.
 Contractor will follow method of statement for each activity.
 Contractor will submit request inspection format form for each activity to company for approvals.

Page 20 of 21
INSPECTION TEST PLAN JUNE 2021
PROCEDURE
TAREQ ASIA Oil & Gas New Main Warehouse, Brega,
Construction Co. Area 1
REV-0

20. Acknowledgement

Project Manager Date

Site Manager Date

MEP Manager Date

QA/QC Manager Date

Safety Manager Date

Page 21 of 21