You are on page 1of 16

DOCUMENT NO: MSCL-SEC-I&C-ITP-001

DOC REVISION: B
OWNER: SEC
CONTRACTOR: MSCL
Completion of Work for NWC Water Pipeline Network Supplying Water to PP11, PP12 & PP13 from NWC Dhurma
PROJECT:
Pumping Station (CONTRACTNO: 4400015651)
LOCATION `RIYADH, DHURMA REGION – PP11, PP12 & PP13

I&C INSPECTION AND TEST PLAN –


NWC DHURMA PUMP STATION, PP11, PP12, PP13

B 8-June-2022 ISSUED FOR APPROVAL


A 4-ApR-2022 ISSUED FOR APPROVAL
ALI AHMED JAN ZAHEER ULLAH KHAN NIAZI
QA/QC ENGINEER TEAM LEADER (QHSE)
REV DATE OF ISSUE PURPOSE OF ISSUE (PROJECTS MANAGER) (DEPARTMENTAL MANAGER)
PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 1 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
TABLE OF CONTENTS
S. Location/
ACTIVITY TITLE SHEET
NO. Plant
1 LEGENDS 3
2 INTRODUCTION 4
3 A NWC – Material Inspection for I&C PANEL, SCADA HMI and Instrumentation at NWC Pump Station Control Room 5
4 B Dhurma Installation of I&C panel, Instrumentation and SCADA HMI at NWC Dhurma Pump Station 6
5 C Pump Station Pre-Commissioning of I&C panel, Instrumentation and SCADA HMI at NWC Dhurma Pump Station 7
6 D Material Inspection for I&C and Instrumentation at Power Plant PP11 8
Power Plant
7 E Installation of I&C Local PLC Panel, Instrumentation at Power Plant PP11 9
11/ RTU11
8 F Pre-Commissioning of I&C Local PLC panel and Instrumentation at Power Plant 11 10
9 G Material Inspection for I&C and Instrumentation at Power Plant PP12 11
Power Plant
10 H Installation of I&C Local PLC Panel, Instrumentation at Power Plant PP12 12
12
11 I Pre-Commissioning of I&C Local PLC panel and Instrumentation at Power Plant 12 13
12 J Material Inspection for I&C and Instrumentation at Power Plant PP13 14
Power Plant
13 K Installation of I&C Local PLC Panel, Instrumentation at Power Plant PP13 15
13
14 L Pre-Commissioning of I&C Local PLC panel and Instrumentation at Power Plant 13 16

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 2 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
1. LEGENDS

1.1 LEGEND - GENERAL

SEC SAUDI ELECTRICITY CO


MSCL MARINE SERVICES CO LTD

1.2 LEGEND –SURVEILLANCE AND DOCUMENTATION CODES

CODE ACTIVITY DESCRIPTION


H HOLD. ACTIVITY 100% WITNESSED. Action performed for all materials or equipment, which is witnessed by SEC. The activity cannot proceed
without witnessing. MSCL shall notify SEC formally in advance prior to the schedule. MSCL will notify SEC in advance 24 hours prior to
inspection.
W WITNESSING OPTIONAL. MSCL shall notify SEC formally in advance. SEC reserves the right to witness the test. If the test is conducted on the
notified date, MSCL may proceed with the subsequent phase, even if SEC did not witness the test. MSCL will notify SEC in advance 24 hours prior
to inspection.
R REVIEW OF RECORDS. Material certificates, statement of compliance and reports of inspection and tests conducted shall be reviewed to assess
their conformance with the project requirements as per applicable Procedures, Specifications, Code and Standards defined in the Purchase
Order.
RA REVIEW AND APPROVAL OF TECHNICAL DOCUMENTS/DRAWINGS BEFORE COMMENCEMENT OF ACTUAL WORK. The technical
documents/drawings shall be reviewed and approved before commencement of actual work.

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 3 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
2. INTRODUCTION
The purpose of this document is to provide the inspection test plan for the supplied equipment and their related site installation and testing activities.

The scope will cover the following cabinets.

Item
Location Location Tag Cabinet Tag
No
1 NWC –DHURMA PUMP STATION PS PS-CRA-33-GH-001
2 POWER PLANT 11 (RTU11) PP11 PP11-CRA-33-GH-002
3 POWER PLANT 12 PP12 PP12-CRA-33-GH-003
4 POWER PLANT 13 PP13 PP13-CRA-33-GH-004
5 NWC – DHURMA PUMP STATION PS PS-BLA-33-GW-001 (VALVE PANEL-3)
6 POWER PLANT 11 (RTU11) PP11 PP11-BLA-33-GW-002 (VALVE PANEL - 4)

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 4 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
A Material inspection for I&C Panel, SCADA HMI, Instrumentation at NWC Dhurma PS
ACTIVITY REFERENCE TYPE OF INTERVENTION
ACTIVITY ITP Number ITP Checklist No ACCEPTANCE CRITERIA
NO DOCUMENTS MSCL WSP SEC
Supply of Main PLC, Installation of
RFIM, ITP Checklist and test
A.1 new PLC Rack and IO modules and BOM, Datasheet MSCL-SEC-I&C-ITP-001 NWCI&C-1QC-001A H W R/A
procedures
Marshalling

RFIM, ITP Checklist and test


A.2 Supply of SCADA Workstation HMI BOM, Datasheet MSCL-SEC-I&C-ITP-001 NWCI&C-1QC-001B H W R/A
procedures

RFIM, ITP Checklist and test


A.3 Supply of Pressure Transmitters BOM, Datasheet MSCL-SEC-I&C-ITP-001 NWCI&C-1QC-001C H W R/A
procedures

RFIM, ITP Checklist and test


A.4 Supply of Valve Panel 3 BOM, Datasheet MSCL-SEC-I&C-ITP-001 NWCI&C-1QC-001D H W R/A
procedures
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 5 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
B Installation of I&C Panel and Instrumentation at NWC Dhurma PS
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Checklist No ACCEPTANCE CRITERIA
NO MSCL WSP SEC
Installation of Main PLC
Control System modification
in existing panel, Control room Layout dwg, RFIW, ITP Checklist and Sat
B.1 MSCL-SEC-I&C-ITP-001 NWCI&C-2QC-002A H W W
Installation of new PLC rack Interconnection and Procedures
and IO modules and
Marshalling
Control room Layout RFIW, ITP Checklist and Sat
B.2 Installation of SCADA HMI MSCL-SEC-I&C-ITP-001 NWCI&C-2QC-002B H W W
location Drawing Procedures
Instrument Hookup and
Installation of Pressure RFIW, ITP Checklist and Sat
B.3 Instrument location MSCL-SEC-I&C-ITP-001 NWCI&C-2QC-002C H W W
Transmitters Procedures
drawings
Cabinet location Layout
Installation of Valve RFIW, ITP Checklist and Sat
B.4 dwg, Interconnection and MSCL-SEC-I&C-ITP-001 NWCI&C-2QC-002D H W W
Panel - 3 Procedures
power distribution Drawings

FO Cable Repair from NWC FO survey report, Method RFIW, ITP Checklist and Sat
B.5 MSCL-SEC-I&C-ITP-001 NWCI&C-2QC-002E H W W
PS to PP11 and Testing statement Procedures

Cable route dwg,


Instrument and Control RFIW, ITP Checklist and Sat
B.6 Interconnection dwg, MSCL-SEC-I&C-ITP-001 NWCI&C-2QC-002F H W W
Cable laying Procedures
IO List
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 6 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
C Pre-Commissioning I&C Panel, Equipment and Instrumentation at NWC Dhurma PS
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC
Energization of Main PLC RFIW, ITP Checklist and Sat
C.1 power distribution Drawings MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-003A H W W
Control Panel Procedures

Energization of Network RFIW, ITP Checklist and Sat


C.2 power distribution Drawings MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-003B H W W
Panel Procedures

Energization of Valve RFIW, ITP Checklist and Sat


C.3 power distribution Drawings MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-003C H W W
Panel -3 Procedures

Energization of SCADA HMI RFIW, ITP Checklist and Sat


C.4 power distribution Drawings MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-003D H W W
Workstation Procedures

I&C Loop check, Pre-Testing RFIW, ITP Checklist and Sat


C.5 Loop Check List MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-003E H W W
and commissioning Procedures

Fiber Optic Communication Network Architecture,


RFIW, ITP Checklist and Sat
C.6 Test between NWC PS and Method Statement, OTDR MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-002F H W W
Procedures
RTU11 Report

Communication Test of
C.7 RFIW, ITP Checklist and Sat
Main PLC with PP11, PP!2 Network Architecture MSCL-SEC-I&C-ITP-001 NWCI&C-3QC-002G H W W
Procedures
and PP13 Local PLC
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 7 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
D Material inspection for I&C Panel, SCADA HMI, Instrumentation at PP11 (RTU11)
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC
Supply of Local PLC Control RFIM, ITP Checklist and test
D.1 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP11I&C-1QC-001A H W R/A
Panel PP11 (RTU11) procedures

Supply of Pressure RFIM, ITP Checklist and test


D.2 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP11I&C-1QC-001B H W R/A
Transmitter procedures

RFIM, ITP Checklist and test


D.3 Supply of Valve Panel 4 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP11I&C-1QC-001C H W R/A
procedures
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 8 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
E Installation of I&C Panel and Instrumentation at Power Plant 11 (RTU11)
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC
Control room Layout dwg,
Installation of Supply of RFIW, ITP Checklist and Sat
E.1 Interconnection and MSCL-SEC-I&C-ITP-001 PP11I&C-2QC-002A H W W
local PLC Control Panel Procedures
power distribution Drawings
Instrument Hookup and
Installation of Pressure RFIW, ITP Checklist and Sat
E.2 Instrument location MSCL-SEC-I&C-ITP-001 PP11I&C-2QC-002B H W W
Transmitter Procedures
drawings
Cabinet location Layout
RFIW, ITP Checklist and Sat
E.3 Installation of Valve Panel -4 dwg, Interconnection and MSCL-SEC-I&C-ITP-001 PP11I&C-2QC-002C H W W
Procedures
power distribution Drawings
Cable route dwg,
Instrument and Control RFIW, ITP Checklist and Sat
E.4 Interconnection dwg, MSCL-SEC-I&C-ITP-001 PP11I&C-2QC-002D H W W
Cable Laying Procedures
IO List
FO Cable Splicing for Main
FO Cable termination RFIW, ITP Checklist and Sat
E.5 FO Cable, PP12 and PP13 in MSCL-SEC-I&C-ITP-001 PP11I&C-2QC-002E H W W
drawing Procedures
existing network cabinet
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 9 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
F Pre-Commissioning of I&C Panel and Instrumentation at Power Plant 11 (RTU11)
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC

Energization of Local PLC RFIW, ITP Checklist and Sat


F.1 power distribution Drawings MSCL-SEC-I&C-ITP-001 PP11I&C-3QC-003A H W W
Control Panel Procedures

Energization of Network RFIW, ITP Checklist and Sat


F.2 power distribution Drawings MSCL-SEC-I&C-ITP-001 PP11I&C-3QC-003B H W W
Panel Procedures

Energization of Valve Panel- RFIW, ITP Checklist and Sat


F.3 power distribution Drawings MSCL-SEC-I&C-ITP-001 PP11I&C-3QC-003C H W W
4 Procedures

I&C Loop check, Pre-Testing RFIW, ITP Checklist and Sat


F.4 Loop Check List MSCL-SEC-I&C-ITP-001 PP11I&C-3QC-003D H W W
and commissioning Procedures

Fiber Optic Communication


RFIW, ITP Checklist and Sat
F.5 Test between RTU11 and Network Architecture MSCL-SEC-I&C-ITP-001 PP11I&C-3QC-003E H W W
Procedures
PP12
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 10 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
G Material inspection for I&C Panel, SCADA HMI, Instrumentation at PP12
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC

Supply of Local PLC Control RFIM, ITP Checklist and test


G.1 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP12I&C-1QC-001A H W R/A
Panel PP12 procedures

Supply of Pressure RFIM, ITP Checklist and test


G.2 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP12I&C-1QC-001B H W R/A
Transmitter procedures

RFIM, ITP Checklist and test


G.3 Supply of Flow Transmitter BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP12I&C-1QC-001C H W R/A
procedures

Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review


MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 11 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
H Installation of I&C Panel and Instrumentation at Power Plant 12
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC

Installation of Supply of Control room Layout dwg, RFIW, ITP Checklist and Sat
H.1 MSCL-SEC-I&C-ITP-001 PP12I&C-2QC-002A H W W
local PLC Control Panel Interconnection Procedures

Instrument Hookup and


Installation of Pressure RFIW, ITP Checklist and Sat
H.2 instrument location MSCL-SEC-I&C-ITP-001 PP12I&C-2QC-002B H W W
Transmitter Procedures
drawings

Instrument Hookup and


Installation of Flow RFIW, ITP Checklist and Sat
H.3 instrument location MSCL-SEC-I&C-ITP-001 PP12I&C-2QC-002C H W W
Transmitter Procedures
drawings

Cable route dwg,


Instrument and Control RFIW, ITP Checklist and Sat
H.4 Interconnection dwg, MSCL-SEC-I&C-ITP-001 PP12I&C-2QC-002D H W W
Cable Laying Procedures
IO List

FO Patch Cord laying from


Cable route dwg, RFIW, ITP Checklist and Sat
H.5 existing Patch panel to Local MSCL-SEC-I&C-ITP-001 PP12I&C-2QC-002E H W W
Interconnection dwg, Procedures
PLC Panel PP12
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 12 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
I Pre-Commissioning of I&C Panel and Instrumentation at Power Plant 12
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC

Energization of Local PLC RFIW, ITP Checklist and Sat


I.1 Power distribution dwg MSCL-SEC-I&C-ITP-001 PP12I&C-3QC-003A H W W
Control Panel Procedures

I&C Loop check, Pre-Testing RFIW, ITP Checklist and Sat


I.2 Loop Check List MSCL-SEC-I&C-ITP-001 PP12I&C-3QC-003B H W W
and commissioning Procedures

Fiber Optic Communication


Network architecture RFIW, ITP Checklist and Sat
I.3 Test between PP12 and MSCL-SEC-I&C-ITP-001 PP12I&C-3QC-003C H W W
Interconnection dwg Procedures
RTU11
Communication Test of
PP12 Local PLC with NWC RFIW, ITP Checklist and Sat
I.4 Network architecture MSCL-SEC-I&C-ITP-001 PP12I&C-3QC-003D H W W
Dhurma Pump station Main Procedures
PLC
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 13 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
J Material inspection for I&C Panel, SCADA HMI, Instrumentation at PP13
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC

Supply of Local PLC Control RFIM, ITP Checklist and test


J.1 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP13I&C-1QC-001A H W R/A
Panel PP13 procedures

Supply of Pressure RFIM, ITP Checklist and test


J.2 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP13I&C-1QC-001B H W R/A
Transmitter procedures

RFIM, ITP Checklist and test


J.3 Supply of Patch Panel BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP13I&C-1QC-001C H W R/A
procedures

Supply of Fiber Optic Cable RFIM, ITP Checklist and test


J.4 BOM, Datasheet MSCL-SEC-I&C-ITP-001 PP13I&C-1QC-001D H W R/A
5000m procedures

Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review


MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 14 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
K Installation of I&C Panel and Instrumentation at Power Plant 13
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC
Cabinet Layout dwg,
Installation of local PLC RFIW, ITP Checklist and Sat
K.1 Interconnection MSCL-SEC-I&C-ITP-001 PP13I&C-2QC-002A H W W
Control Panel Procedures
Drawings
Instrument Hookup and
Installation of Pressure RFIW, ITP Checklist and Sat
K.2 instrument location MSCL-SEC-I&C-ITP-001 PP13I&C-2QC-002B H W W
Transmitters Procedures
drawings
Cable route dwg,
Instrument and Control RFIW, ITP Checklist and Sat
K.3 Interconnection dwg, MSCL-SEC-I&C-ITP-001 PP13I&C-2QC-002C H W W
Cable Laying Procedures
IO List
Cable route dwg,
FO Cable Laying from RTU11 RFIW, ITP Checklist and Sat
K.4 Interconnection dwg, MSCL-SEC-I&C-ITP-001 PP13I&C-2QC-002D H W W
to PP13 Procedures
Method statement
FO Cable Splicing at PP13
Patch Panel and Patch Cord RFIW, ITP Checklist and Sat
K.5 FO Interconnection dwg MSCL-SEC-I&C-ITP-001 PP13I&C-2QC-002E H W W
laying from Patch panel to Procedures
Local PLC Cabinet

RFIW, ITP Checklist and Sat


K.6 Installation of Patch Panel Cabinet Layout dwg, MSCL-SEC-I&C-ITP-001 PP13I&C-2QC-002G H W W
Procedures

Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review


MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 15 of 24 Doc. No. MSCL-SEC-I&C-ITP-001
L Pre-Commissioning of I&C Panel and Instrumentation at Power Plant 13
ACTIVITY TYPE OF INTERVENTION
ACTIVITY REFERENCE DOCUMENTS ITP Number ITP Check List No ACCEPTANCE CRITERIA
NO MSCL WSP SEC
Energization of Local PLC RFIW, ITP Checklist and Sat
L.1 Power Distribution Dwg MSCL-SEC-I&C-ITP-001 PP13I&C-3QC-003A H W W
Control Panel Procedures

I&C Loop check, Pre-Testing RFIW, ITP Checklist and Sat


L.2 Loop Check List MSCL-SEC-I&C-ITP-001 PP13I&C-3QC-003B H W W
and commissioning Procedures

Fiber Optic Communication


RFIW, ITP Checklist and Sat
L.3 Test between PP13 and Network architecture dwg MSCL-SEC-I&C-ITP-001 PP13I&C-3QC-003C H W W
Procedures
RTU11
Legends: H- Hold Point, W- Witness Point, A-Approval, R-Review
MSCL/Contractor, WSP-Consultant/SEC - Saudi Electricity Company

Document Name I&C INSPECTION AND TEST PLAN


Customer NWC/Saudi Electric Company Page 16 of 24 Doc. No. MSCL-SEC-I&C-ITP-001