Third Party Inspection for Power Cable

The Third Party Inspection for Power Cable provides you with information about the power cable
test and power cable inspection in the manufacturing shop.

You may need to review this article along with the following article:

This content guides you through all the necessary stages in the production of the power cables,
including the raw material, final inspection, preservation and packing, and dispatch to site.

You need to take this point into account: this article is written for a typical power cable and might
not be detailed for special cases.

This content may be useful for second party inspectors, power cable manufacturer quality control
personnel, engineering companies, and purchasers, as well.

All power cable inspection and testing is done against the approved drawings, purchase order
specifications, purchasers or company standards, and within the practices and rules of the
country, state or province and any government decrees, laws, ordinance or regulation as may
apply.

The applicable codes and specifications for a power cable that is under the construction process
is:

 Design code
 Purchase order specification
 Purchaser's standards
 Approved drawings

the applicable codes and standards may be based on any international standards. This content
is general and can be useful for all recognized standards.

Required Documents for Third Party Inspector Review:

The list of documents normally is agreed upon in the Pre-Inspection meeting, which is held several
weeks before the actual commencement of the inspection work. The parties that participate in
this meeting are the manufacturer, purchaser and third party inspection agency representatives.

This is already explained in the Inspection and Test Plan for Power Cable article.

These are the list of documents that are normally agreed upon to be presented to the inspector:

 Power Cable Purchase Order or Contract


 Power Cable Quality Control Plan
 Power Cable Data Sheet
 Power Cable Approved Drawings
 Power Cable Fittings Drawings and/or Parts Lists
 Power Cable Material/parts Certificates
 Power Cable Special Procedures
 Power Cable Special Qualifications
 Power Cable Calibration Records for Testing and Measuring Equipment
 Power Cable Preparation and Painting/Finishing Procedure (for ancillaries)
 Preservation, packing and Shipping Procedure
 Power Cable Packing List

Third Party Inspection for Power Cable - Material Inspection

The first actual inspection work in the power cable is the raw materials inspection.

The original or authenticated copies of mill certificates of material normally are available at the
manufacturer's premises.

The third party inspector examines these certificates for compliance with specifications, and
where appropriate, drawings.

The review includes checks on:

 Maker’s name and location


 Certificate number, grade
 Heat or cast number
 Chemical composition

Then the inspector witnesses the materials identification on the certificates against the materials
marking. It is also necessary to check these with the power cable drawing datasheet, material
list and other specifications as appropriate.

Visual inspection for surface finish and probable defects is done and dimensional compliance
with specification need to be controlled, as well.

When the third party inspector carries out the material inspection, then provides the inspection
visit report (IVR), the report contains the following items:

 Confirmation of satisfactory document review


 Record of the endorsement of certification reviewed/witnessed
 Record of all non-conformities
 Record of any tests witnessed and the result

Third Party Inspection for Power Cable - Construction Check

When the power cable raw material inspection is carried out, and the results were satisfactory or
non-conformities were closed by remedial action, then the power cable manufacturer will start
fabrication.

The third party inspector checks the following points on the power cable, based on the
inspection and test plan (ITP), which has already been agreed upon between the purchaser and
the power cable manufacturer.

The inspection scope is determined in the ITP. Some purchasers prefer to have stringent
controls and assign the TPI for more “hold or witness points” for inspection and test activities,
and some others prefer less “hold or witness points” and assign the TPI much more work in the
“review document.”
This depends in the inspection budget, which purchasers assign for inspection. Much more
inspection will have a much larger cost and less risk, and conversely, less inspection will have
less cost but more risks.

The third party inspector checks the following items in the power cable casing inspection process:

 Check of paint using specified color swatch, measure thickness, if specified


 Check of name plate
 Check of outline dimensions, interface dimensions
 Power Cable General Arrangement Check

If the third party inspector is not in the hold or witness point in the ITP for this inspection stage,
then he/she will review the power cable manufacturer quality control report in his/her coming visit
or on the final inspection day.

Third Party Inspection for Power Cable - Configuration

Third party inspector checks the power cable configuration in accordance to drawing and
datasheets. Following items is taken in account:

 Cable type
 Number of conductors
 Conductor size
 Conductor color coding
 Insulation type and size
 Fillers
 Water stoppers
 Armour
 Shield
 Outer diameter
 Other specified elements/dimensions
 Cable identification

Third Party Inspection for Power Cable - Drum

For cable already drummed the third party inspector controls following items:

 Labelling
 Sealing
 Lagging
 Drum quantity
 Conformance of quantity listings on drums to documented declarations

Third party inspection for Power Cable - Conductor Resistance Test

The third party inspector witnesses the measurement which is done

by “Kelvin’s Double Bridge” or “Wheatstone Bridge” and checks the result against acceptance
criteria specified in the purchase order.
Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Withstand Voltage Test

The AC and DC withstand voltage test is witnessed by third party inspector for each length of
completed cable as below:

 AC Withstand Voltage Test:

The test voltage is applied between the conductor or conductors and metallic shield, metallic
armour, or water. The duration is 5 minutes and the test would be acceptable if withstand the
specified test voltage.

 DC Withstand Voltage Test (ICEA only):

All cables rated 5001 volts and above is tested by the DC withstand voltage test and would be
acceptable if withstand specified test voltage

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Insulation Resistance Test

The insulation resistance test is measured after the completed cable AC voltage test or before
any DC voltage test and witnessed by third party inspector.

Reading of the insulation resistance is taken for one minute and obtained value would be
acceptable if they are above the specified value in the requirement.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Discharge Test

The partial discharge test is made prior to the AC voltage test as per the appropriate test method
specified in the code and standard. The AC test voltage is applied between conductor and the
metallic component of insulation shield

If the existence of discharge is not evident after the voltage has been raised to a value 20% above
the specified minimum extinction value, the cable is considered to have met the requirements.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Tensile Strength and Elongation Test
Physical tests are made at room temperature and the test specimens are kept at room
temperature for not less than 30 minutes prior to the test.

The specimen is stretched until it breaks. Elongation at rupture is determined simultaneously with
the test for tensile strength and on the same specimen.

The tensile strength is calculated on the area of the unstretched specimens. The percentage of
elongation at rupture is divided by the original gauge length and multiplied by 100. They would be
acceptable if meet the requirements.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Aging Test

The test specimens are heated at the required temperature for the specified period in air oven or
immersed in oil hot oil.

The kind of oil, temperature and duration is in accordance of applicable standards.

Physical tests on both the aged and unaged specimens are made at the same time and the result
of the test would be acceptable if comply with the requirement

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Heat Shock Test

Samples of the cables are wound around a mandrel, held firmly in place and subjected to the
specified temperature for 1 hour. Diameter of mandrel is specified in the standard.

The test specimen would be acceptable if show no cracks visible to the normal unaided eye.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Heat Distortion Test

The test is made in accordance with appropriate method specified in the standard (ICEA). The
test would be acceptable if obtained value is not exceeding the maximum percentage of unaged
value specified in ICEA.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Flame Resistance Test


Flame resisting test is made in accordance with respective code, standard. (IEC, IEEE) and after
the test, the test would be acceptable if specimens meet the requirement of applicable code,
standard.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection
stage, then he/she will review the power cable manufacturer quality control report in his/her
coming visit or on the final inspection day.

Third Party Inspection for Power Cable - Reporting

The third party inspector provides an Inspection Visit Report (IVR) after each visit, as well as a
final report summarizing the activities carried out during the power cable production in accordance
with the contract requirements and circulated within the time limits specified in the contract.

The report is in the format required by the client and clearly indicates final acceptance or rejection
of the power cable.

Third Party Inspection for Power Cable - Release Note

When required by the contract or purchase order, a release note is issued by the third party
inspection agency and given to the manufacturer when the power cables have been accepted.

Third Party Inspection for Power Cable - Packing and Marking

The following points are checked by the third party pre-shipment inspector:

 Drum marking and tagging.


 Cable end secured.
 The reel is lagged or covered with suitable material to provide physical protection for the
cables during transit.
 Cable end sealed against moisture.
 Verify that the packing materials conform to specifications and accepted practice for the
mode of transport.
 Check protection against humidity, abrasion, distortion and other damage.
 Check shipping marks with marking instructions and record. Check handling marks.