You are on page 1of 6

6Q-SB-NC

30-VL-NC
Cover Page.doc

SALALAH AMMONIA PROJECT

SLI Project No. : 645295


Purchase Order No. : 645295-C50001

MPEI INSTALLATION

HYDROSTATIC TEST PROCEDURE

VDR Code: Q07

INCO Engineering, Manufacturing, Trading & Civil


INCO-INE398-185 01
HYDROSTATIC TEST PROCEDURE 9/16/2019

Salalah 1000 T/D Ammonia Plant


Saber ALaamri
9/29/2019 645295-C50001-0185 02

01 2019-09-16 SATHIASEELAN TARIK KURTKAYA SARPER SAKA ISSUED FOR REVIEW

A 2019-07-03 SATHIASEELAN TARIK KURTKAYA SARPER SAKA ISSUED FOR REVIEW

REV DATE PREPARED REVIEWED APPROVED DESCRIPTION

CONTRACTOR: VENDOR :

Page 1 of 06
SLI Doc. No. : 645295-C50001-0185_02

Rev 01 Date: 2019-09-16


INCO Doc. No : INCO-INE398-185
SALALAH AMMONIA PROJECT

VDR CODE : Q07


HYDROSTATIC TEST PROCEDURE PAGE : 2 OF 5
DOCUMENT NO : INCO-INE398-185 REV : 01

TABLE OF CONTENTS

1. SCOPE

2. REFERENCE

3. TESTING APPARATUS

4. SAFETY PRECAUTIONS

5. TEST MEDIUM

6. TEST PACKAGE PREPARATION

7. PREPARATION

8. ACCEPTANCE CRITERIA

9. REPORTS
SALALAH AMMONIA PROJECT

VDR CODE : Q07


HYDROSTATIC TEST PROCEDURE PAGE : 3 OF 5
DOCUMENT NO : INCO-INE398-185 REV : 01

1. SCOPE
This Project Standard and Specification specifies pressure and leak test procedure and
acceptance criteria of Steel piping works to perform minimum quality level.

2. REFERENCE

Throughout this Standard the following dated and undated standards/codes are referred to.
These referenced documents shall, to the extent specified herein, form a part of this standard.
For dated references, the edition cited applies. The applicability of changes in dated references
that occur after the cited date shall be mutually agreed upon by the Company and the
Contractor. For undated references, the latest edition of the referenced documents (including
any supplements and amendments) applies.

ASME B31.3 - Process Piping

ASME SECTION.IX - Welding and Brazing Qualifications

645295-0000-46EF-0001 - Specification Piping Fabrication,


Installation and Testing

645295-0000-46EF-0005 - Construction/installation
Specification welding & NDE

645295-0000-46EL-0002 - Line List

645295-C50001-0002 - Project Quality Plan

3. TESTING APPARATUS

Test pump, hose and fittings connections, test medium, a calibrated pressure gauge to
monitoring test pressure, pressure recorder may be used to record variable of test pressure,
torch flash for visual inspection of leakage. The pressure gauges and recorder shall be calibrated
within 12 months, range of pressure gauge shall not be less than 1.5 times and not more than 4
times.

4. SAFETYPRECAUTIONS

Display suitable warnings on the equipment and in the testing areas.


To confirm bolting materials are corrected and met specifications.
Test pump shall constantly attend by experience operator during testing.
SALALAH AMMONIA PROJECT

VDR CODE : Q07


HYDROSTATIC TEST PROCEDURE PAGE : 4 OF 5
DOCUMENT NO : INCO-INE398-185 REV : 01

Pressure gauges to be monitored by operator during the test.


5. TEST MEDIUM
Test medium shall be clean potable water. Note that chloride content in water shall be less than
250 ppm for carbon steel components and chloride content in water shall be less than 50 ppm
for stainless steel components, Water certificate will be provided.

6. TEST PACKAGE PREPARATION


Notification will be sent for the line walk down and the test package...
The test package shall be submitted for approval include a minimum:
1. A list of all piping spools or equipment,
2. GA drawings, P&ID drawings or Isometric drawings,
3. Drawing markup with battery limits,
4. Line History Sheet,
5. NDE Reports,
6. NCR/CAR closed,
7. Punch List,
8. PMI report and FerriteTest Report (if SS/AS),
9. Hardness Test Report,
10. PWHT chart (if applicable),
11. Bolting/Torqueing Report (if Final Bolting)
12. Test pressure,
13. Test medium,
14. Pressure gauges, pressure recorder, thermal temperature,
15. Pressure test certificate sample,
16. Calibrated certificates,
17. Water analysis certificate

7. PREPARATION
1. All examinations and stress relieving activities have to complete before testing.
2. All raised face of flanges and thread end shall be inspected in good condition and make sure
no damaged or deformation.
3. All connections by bolting, threading shall be tightened and sealed by its nut.
4. One pressure gauge shall install at a higher point, other pressure gauge(s) shall install at
nearly location for monitoring and control by operator.
5. Barricade must be limited at the testing area with display signboard with “KEEP AWAY
HYDROTEST IN PROGRESS”.
6. Hydrostatic tests will perform by operator under supervision of Supervisor and QC inspector.
7. The test pressure shall not less than 1.5 times of the design pressure.
8. A minimum holding time of test pressure shall at latest 10 minutes.
9. Temperature measurement of test medium may be recorded during the test.
10. The QC inspector shall monitor the testing process and verify that there is no leakage or may
be visual distortion during or upon completion of test.
11. Upon completion of the test, test medium shall be drained and unbolt flange joint.
SALALAH AMMONIA PROJECT

VDR CODE : Q07


HYDROSTATIC TEST PROCEDURE PAGE : 5 OF 5
DOCUMENT NO : INCO-INE398-185 REV : 01

12. All raised face of flange and thread ends shall be properly protected in good condition.
13. All internal pipe spools shall clean and flush with pressurized water, then drying out by dried
air
8. ACCEPTANCE CRITERIA

1. Pressure tests are successful if no leaks, no cracks and no deformations found.


2. If leakage found on products or product welds, their location shall be recorded/marked in
drawing and forward the report to QC Engineer for investigation before re-testing.
3. If leakage found on flanged joints, threaded joints shall rectify before re-starting test.

9. REPORTS
The completion of test package includes:

1. Client’s job number / project number,


2. Job number,
3. Duration of hydrostatic test,
4. Pressure gauge and recorder,
5. Calibration certificate of instruments,
6. Date of test,
7. Tag name or piping spool number,
8. Test medium,
9. Test pressure,
10. Test temperature,
11. Test results,
SALALAH AMMONIA PROJECT

PROJECT NO : 645295

INCO Engineering, Manufacturing, Trading &

Date :
Civil Contracting Co LLC
REPORT No:
PRESSURE TEST REPORT

PAGE : 01/01

HYDROSTATIC  PNEUMATIC

Project SAL AL AH AMMONIA PROJECT DWG No./TP No.

Client/Title SAL AL AH METHANOL COMPANY Equipment No./Piping

Manufacturer's Serial
Job No. INE-398
No.

Code of Construction ASME B31.3 Procedure No.

Equipment Name. Chart Recorder, Pressure Guage, Manifold Area

SPECIFICATION
Test Pressure Barg Test Medium

Design Pressure Barg Metal Temperature °C

Position of Equipment /Piping HORIZONTAL VERTICAL 

TEST GAUGES

POSITION / L OCATION Manifold Top Remarks

ID (TAG No.)

RANGE

CAL IBRATION DATE

CAL IBRATION DUE

CAL IBRATION CERTIFICATE

TEST RESULT :

No leakages were found during the hydrotest. No distortions were noted at the time of test.

Hence found acceptable.

IN CO Engineering Co. SLI SMC


Signature
Name
Designation
Date

You might also like