Professional Documents
Culture Documents
For the initial risk assessment, the project manager and the team have
brainstormed and collaborated in identifying all possible risks within the current
known elements of the project. These identified risks will be reviewed in the
presence of Dr. Lipsett and Roger Marchand as early as their schedules allow
the review.
To ensure that the risk environment is being assessed sufficiently, Dr. Lipsett
will act as the risk management expert. Other risk-related inquiries will also be
made to the laboratory equipment experts (Roger Marchand and his team).
Doing Planned
Reviews
Identification of
Hazards
Risk Assessment/
Analysis
Yes
Yes
Can the Risk Be Is the Risk
Reduced? Acceptable?
No Yes
Is the Risk Acceptable?: Risks are deemed acceptable only once they have
been rated using a risk matrix (see Sections 9.1.2.1 and 9.1.2.2). Low level
risks are “acceptable,” without any further management involvement. Medium
level risks are “acceptable with certain conditions.” These risks must be closely
monitored, and the project manager must be present to ensure the risk is kept
under control. High level risks are “unacceptable” and any actions producing
such risks will be halted immediately.
Reduce the Risk: If the risk can be reduced, the necessary changes must be
implemented to decrease it (see Section 9.1.4). It is important to note that if a
change is made to reduce the risk present in a process or action, a full risk
analysis must be redone on the newly implemented process or action. This will
reveal possible new risks that may have been added to the project. (See
Sections 9.1.1 to 9.1.4)
Risks have been identified by the project manager and the team by
first reviewing the following project documentation:
Interviewing: Aside from the project team members, Dr. Lipsett has
been interviewed on his perception of possible risks.
All identified risks have been documented in the Risk Register. (See
Section 10). As any further risks become apparent, a full risk
analysis will be performed on each new risk, and the Risk Register
will be updated accordingly.
9.1.2 Qualitative Risk Analysis
Each identified risk has been assessed for the potential effects on
schedule, cost, and scope by the project manager and the project
team. Incident probabilities have been documented through
brainstorming between the project manager and project team, as
well as through interviewing Dr. Lipsett (See the Risk Register in
Section 10).
During the weekly risk assessments, any new risks that are identified will be
added to the risk register.
The Risk Owners consist of Dr. Lipsett, Roger Marchand, AICT and the
University of Alberta facilities. Any risk-related activities or processes relevant to
Dr. Lipsett or Roger Marchand will be supervised by them accordingly during
the time that the risk is present. If any incidents occur, these individuals are to
handle them according to the risk responses listed in the Risk Register. Any
incidents relevant to AICT or the University of Alberta facilities will be
documented and the corresponding departments will be contacted.
9.3 Budgeting
In the event of an incident, the Accident / Incident Report Form is to be filled out
and returned to the Risk Owner. In the event that the risk was previously
unforeseen, and there is no Risk Owner dedicated to the incident, this
correspondence is to be given directly to Dr. Lipsett. This form can be found in
Appendix 9.8.4.
All risks identified in the Risk Register have been assigned a Risk Owner. Any
actions, processes or events posing a risk to the project will be closely
monitored and dealt with accordingly by the Risk Owners in the event where the
risks are present. In the event that a risk was previously unforeseen, and there
is no Risk Owner dedicated to a risk, Dr. Lipsett will act as the designated Risk
Owner.