A4, A5, A6
J3, J9
Parapet 4.565x0.23x1.0x19.5 20.474
2.5x0.23x1.0x19.5 11.212
Roof Tiling 01x4.565x3.665x0.05x19.5 16.312
01x4.565x1.165x0.05x19.5
Mud Phuska 01x4.565x(3.665+1.165)x0.10x19.2 42.334
Roof Slab 04x4.565x(3.665+1.165)x0.15x25.0 330.734
Roof Beams 04x3.665x0.23x0.65x25.0 54.791
Flooring 04x2.615x2.283x0.025x19.2 11.462
(B/ballast) 04x2.615x2.283x0.075x19.2 34.387
Lime Concrete
s/s brickwork 04x2.615x0.23x2.95x19.5 138.393
04x2.283x0.23x2.95x19.5 120.823
Below Plinth
Brickwork 01x2.615x0.23x0.85x19.5 9.97
01x2.283x0.23x0.85x19.5 8.70
Beam 01x2.615x0.23x0.65x25.0 9.77
01x2.283x0.23x0.65x25.0 8.532
Live Load
At Ground Floor 2x2.615x2.283 11.94KN
1st Floor 90% of 11.94 10.75
2nd Floor 80% of 11.94 9.55
3rd Floor 70% of 11.94 8.36
40.6KN
Total for one column=590.6KN