We followed up the ICT strategy plan by having discussions with various departments and SBUs,
documenting their ICT requirements that will assist in accomplishing their separate objectives. This report
will be a summary of various departmental plans in conjunction with ICT. The report also includes the
sequencing of the ICT Strategy’s Action Plans. Considerations such as the availability of budgeted funds,
urgency of the need as well as the business case for each entity were made.
HR – ICT Strategy
A lot of opportunities exist for digitization and automation of several of HR’s manual and routine tasks.
1. The focus will be on exploring digitization opportunities available with the current HR Management
System.
2. Streamlining the recruitment and selection processes and the performance management system
through the introduction of off-the-shelf software and tailor-made solutions.
3. Integration of HR Management system with SAP.
Note:
To achieve the goals above, the ICT department requires the below human resources:
1. 1 x systems/network administrator,
2. 2 x Helpdesk technicians.
ICT Strategy Action Plans Sequence
For easy reference. We approached this in 3 ways: what should be achieved by the 3 rd quarter of 2021,
what should be achieved by end of 2021, and then 2022 and beyond.
By End of 2021
Activity BDG Dept Start Due
Network
Introduce a Proxy Server. TBD CMI Oct 2021 Dec 2021
Introduce SD-WAN. TBD CMI Oct 2021 Dec 2021
Introduce Network Authentication. TBD CMI Oct 2021 Dec 2021
SOPs Dec 2021
Review all SOPs and SLAs. N/A CMI Oct 2021 Dec 2021
IT Infrastructure Dec 2021
Review Current ICT Infrastructure. N/A CMI Oct 2021 Dec 2021
Expand the WWB IQ feature use. TBD WWB Oct 2021 Dec 2021
Automation Dec 2021
Automate of ICT Routine Tasks. TBD CMI Oct 2021 Dec 2021
Introduce Online Leave Application TBD HR Oct 2021 Dec 2021
System.
Digitize HR Processes. TBD HR Oct 2021 Dec 2021
Introduce an Online Transport TBD CMI Oct 2021 Dec 2021
Requisition System.
Communication
Improve/increase use of the Intranet. TDB CMI Oct 2021 Dec 2021
Roll out the Call-Centre service to all TDB Depts Oct 2021 Dec 2021
programs.
Introduce eBooks on the WWB TDB WWB Oct 2021 Dec 2021
website.
Implement Customer Data Collection TBD Depts Oct 2021 Dec 2021
for all entities.
Introduce a Project Management Tool. TBD CMI Oct 2021 Dec 2021
Training
SAP Training. TBD CMI Oct 2021 Dec 2021
By end of 2022
Activity BDG Dept Start Due
Upgrade the LAN to CAT 6 TBD CMI Jan 2022 Dec 2022
Install of Managed Switches. TBD CMI Jan 2022 Dec 2022
Install the Basement to Server room Fibre. TBD CMI Jan 2022 Dec 2022
Complete upgrade of the Wireless LAN. TBD CMI Jan 2022 Dec 2022
Install a Fire Suppression System in the server room TBD CMI Jan 2022 Dec 2022
Complete automation/digitization of HR Tasks. TBD HR Jan 2022 Dec 2022
Install Video Conferencing Kits. TBD Functen Jan 2022 Dec 2022
Upgrade the CCTV System. TBD CMI Jan 2022 Dec 2022
ICT Certification and Upskilling Training TBD CMI Jan 2022 Dec 2022
Introduce a Cloud Storage solution. TBD CMe, CMI Jan 2022 Dec 2022
Develop the WWB IQ Application. TBD WWB Jan 2022 Dec 2022