You are on page 1of 14

Evaluation, selection and installation of

surface repair mortars at a dam site


J. Mirza and B. Durand
Hydro-Québec, Varannes, Quebec, Canada JOL 2PO

Received 31 August 1993; accepted 31 October 1993


Increasingly, large sums are being spent on the repairs and maintenance of concrete surfaces using
one or other of the hundreds of surface repair materials available on the market. Unfortunately,
however, information on these materials has always been scarce and manufacturers have been
unable to supply specific data on their products' resistance to harsh climatic conditions. The 5 year
project described in this paper was initiated in an aim to evaluate and select surface repair mortars
such as cementitious grouts, polymer-modified cement-based mortars containing styrene—
butadiene rubber (SBR) and acrylics, epoxy mortars, etc., and eventually to install them at different
dam sites in Quebec. About 40 mortars from different manufacturers were intensively tested for
their physico-mechanical and durability tests in the laboratory. Of these, 21 mortars were then
selected and installed on a small scale on the spillway of a Hydro-Québec dam. After careful analysis
of the laboratory data and periodic inspections of the products, the six best were selected and
recently installed on a large scale on two spillway aprons and their adjacent piers. The paper
presents some of the mortar evaluation and selection criteria, the small-scale installation and
inspection of 21 products and, specifically, the large-scale installation of
the selected mortars and their cost materials are being used without much
effectiveness. known about their essential properties,
especially at the low temperatures
Keywords: surface repair; mortars; generally found in northern areas. In order
to address this problem and evaluate
dams products for their physico-mechanical and
durability properties at low temperatures,
Hydro-Québec initiated a joint Canadian
Hundreds of surface repair materials are Electrical Association (CEA) project and
now available on the market. Despite the studied 40 mortars from different
excellent characteristics of some of these manufacturers.
materials, a number of drawbacks can be This paper summarizes the results of a 5
mentioned. First, data on essential year study which consists of laboratory
properties, such as the effect of curing studies (phase I), small-scale
conditions l , are very limited and rarely
published and, even when they do exist, the
values correspond to ambient temperatures
*Correspondence to Dr J. Mirza
which rarely correspond to harsh climatic
conditions. Second, small companies do
not always conduct their own tests because 0950-0618194101/0017-9 @ 1994 Butterworth-Heinemann Ltd

of budget restraints and use data provided field tests (phase Il), and large-scale field
by their customers, but only those for tests (phase Ill). The main objectives of
whom their products performed best. phase I were to modify and optimize the
Nevertheless, all manufacturers say their properties of repair materials which
products are excellent and none say their showed potential for improvement in a
products are poor. In fact, users purchase previous study2 , to formulate and possibly
from the manufacturer or supplier whose commercialize new repair materials with
products are readily available in their own the assistance of manufacturers, and to test
area, regardless of superiority claims. newly marketed products considered
Consequently, as more and more structures durable by engineers, consultants,
are ageing and deteriorating, surface repair manufacturers or other users. Products
showing a better performance than the

Construction and Building Materials 1994 Volume 8 Number l 17


Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 18

normal cement mortar (used as reference)


were then subjected to small-scale field
tests (phase Il). Only the best products
were ultimately employed on a large scale
in the field (phase Ill), which also
comprises an economic feasibility study.
These best products were then
recommended to utilities for the protection
of concrete hydraulic structures damaged
by abrasion—erosion.
The materials tested were mortars
designed to repair damaged concrete
surfaces while increasing their resistance to
in the case of eroded areas
less than 75 mm deep. Deeper areas should
be filled with a silica fume concrete prior
to coating the entire eroded area with the
repair mortar.
A total of 40 different mixes (Table l)
taken from 37 repair materials from 13
different manufacturers were selected for
this study. These materials may be grouped
into four categories: cement mortars,
including ordinary cement mortar, cement
mortar containing silica fume and
aluminous cement mortar; polymer-
modified cement-based mortars containing
styrene—butadiene rubber (SBR) and
acrylics; sand/epoxy mortars; and

Construction and Building Materials 1994 Volume 8 Number 1


Surface repair mortars at a dam site: J. Mirza and B. Durand

Description of the surface repair materials tested in the laboratory

Mixes Type of materials Description

Cl Cement mortars/cement grouts Type 10 cement + Ottawa sand (reference mortar)


Type 10 cement + Ottawa sand + superplasticizera
Type 10 cement + 6% silica fume + sand + superplasticizera
Type 10 cement + 9% silica fume + sand + superplasticizera
Type 10 cement + 12% silica fume + sand + superplasticizera Type 10 cement + 15% silica fume + sand +
superplasticizera Inorganic cements + additives + abrasion-resistant aggregates
Portland cement + fines + additives + non-shrinkage agent
Type 10 cement + graded sand + non-ferrous admixtures
CIO Cement and premixed sand + additives

Cll Cement and premixed sand + additives

C12 Cement and premixed sand + additives + fibres

C13 Type 1() cement + sand + gassing and flowing agent

C14 Aluminous cement + artificial aggregates

C15 Aluminous cement + bonding agent + artificial aggregates

R16 Styrene—butadiene rubber (SBR) Latex emulsion + premixed cement-based powder + additives
R17 cement-based mortars Latex emulsion + premixed cement-based powder + additives
R18 Same as RI 7 + glass-reinforced fibres

R19 Latex emulsion with water + premixed cement-based powder + additives b

R20 Latex emulsion + cement + graded aggregatesb

R21 Latex emulsion + cement + premixed graded aggregates

R22 Latex emulsion + Portland-cement-based ingredients

A23 Acrylic cement-based mortars Latex emulsion + premixed non-shrinkage cement-based powder + low-density silica fume
A24 Latex emulsion + premixed cement-based powder + additives

A25 Latex emulsion + premixed cement-based powder + additives

A26 Latex emulsion + premixed cement-based powder + additives

E27 Sand/epoxy mortars Resin + hardener + premixed graded aggregates


E28 Resin + hardener + graded sand

E29 Resin + hardener + graded aggregates

E30 Low-modulus resin + hardener + graded sandc

E31 High-modulus resin + hardener + graded sand c

E32 High-modulus resin + hardener + graded sand

E33 Low-modulus resin + hardener + graded sand

E34 Resinhardener + silica sandc


E35 Resinhardener + premixed graded aggregates
E36 Resinhardener + graded sand
E37 Resinhardener + graded sand
E38 Resinhardener + quartz aggregate
EE39 Emulsified epoxy mortars Resin hardener + sand + cement
EE40 Resin hardener + sand + cement

Construction and Building Materials 1994 Volume 8 Number l 19


"In-house mortar (with Ottawa sand, Illinois, USA)
Mortars fabricated with the manufacturer's assistance
c
Mortars selected and modified from our previous study
Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 20

emulsified epoxy mortars. A mix (Cl) in wet-cured specimens. However, the type
consisting of normal Portland cement with of curing seems to have more influence on
a water/cement ratio of 0.46 and the volume change for mortars containing
sand/cement ratio of 2.75 was used as a silica fume after bonding; in fact, there is
reference throughout the study. greater shrinkage under dry curing and
greater expansion under wet curing.
Substituting 6% and 12% silica fume for
Laboratory tests (phase I) normal Portland cement increased the
The above-mentioned mortars were mortar's compressive strength, although
subjected to various laboratory tests, increasing it to 15% showed no
such as bond strength, sion resistance, further advantage. The use of silica fume
shrinkage-expansion, compressive also seemed to have an added impact on
strength, coemcient of thermal expansion, the physical properties, i.e. it increases the
thermal compatibility with base concrete, concrete's bond strength and abrasion
nitrogen gas permeability, freeze—thaw resistance, which could be due to a
cycling, alkali and sulfate content and decrease in the water/cement ratio and to
nature of major crystalline minerals by X- the use of a superplasticizer. On the other
ray diffraction, etc. Table 2 summarizes hand, silica fume seems to cause more
some of the important test data from which shrinkage under dry curing as well as
the following conclusions, by category, are greater expansion under wet curing after
drawn. hardening compared with standard cement
A decrease from 0.46 (Cl) to 0.31 (C2) mortar, which could possibly be due to the
in the water/ cement ratio of a standard high dosage of superplasticizer used. There
Portland cement mortar with the use of a were no unusual variations in the thermal
superplasticizer increases its resistance to expansion coemcients and tests showed
abrasion and compression as well as its good thermal compatibility with the
bond strength with the substrate concrete substrate concrete. The use of
18
Table 2 Test data summary of the laboratory-tested products

Bond strength Drying shrinkage Comp. strength


28 day (MPA)28 day (MPa)
Coeff. of
Coeff. of Thermal Coeff. of
Product Dry Wet abrasion— Net Total Dry Wet thermal exp. compat. permeability
code cure cure erosion change change cure cure x 10-6 % disbond Kc (cm S"A ) X 1

22.3 15.3 1.32 0.097 0.123 31.9 29.0 10.2 35


10.8
15.1 26.2 2.06 -0.14 0.238 33.5 43.4 9.9 10
77.5
26.8 30.3 I .63 -0.214 0.180 45.9 51.1 9.9 5
3.2
29.9 45.4 I .42 0.166 0.226 46.8 53.8 9.8 0
29 39.8 1.95 -0.171 0.221 50.3 61.0 9.9
37.9 41.0 2.38 -0.16 0.229 49.4 61.1 10.1
44.9 3704 - 0.067 0.165 72.8 73.3 12.9 20
18.6
50.2 47.3 2.17 -0.076 0.163 79.6 73.5 10.9 100
1.9
24. I 43.7 3.28 -0.078 0.1 18 41.9 44.0 9.7 9.6
CIO 39.8 33.5 -0.123 0.174 52.1 70.9 9 10 1.5
34 62.3 2.36 O, 174 59 77.3 9.7 5 4.9
Cll -0.154

Construction and Building Materials 1994 Volume 8 Number 1


Surface repair mortars at a dam site: J. Mirza and B. Durand

C12 33.8 37.8 1.94 0.1 18 58.6 65.3 IOO 51.8


-0.105
C13 36.9 47.3 2.4 -0.089 0.125 48.8 52.1 95 9.4

C14 28.6 54.9 4.45 -0.02 0.050 82.1 95.1 5 9.9

50.4 64.8 3.23 -0.037 0.089 85.3 1 15.2 7.3 85 10.5


R16 34.7 36.4 2.51 -0.005 0.091 57.8 54.8 14 95 0.1
R17 34.1 26.4 2.57 0.086 0.433 48.1 46.5 1 1.5 95 1.6
R18 31.3 25.3 3.32 0.02 0.433 45.1 46.0 12.1 0.39

R19 49.9 37.7 3.3 - 0.001 62.6 61.5


R20 68.7 60.4 3.32 -0.143 0.171 85.9 80.5 7.741.9 R21 38.1 34.2 2.82 -0.179 0.201 53.2 7.92.4
R22 16.6 10.2 0.92 - 0.063 0.087 23.2 24.4 10.41.9
A23 16.5 20. 2.1 0.096 0.180 3 2 1 1.8 0.
4 5. 7.
6 3
A24 28.4 17. 2.6 - 0.092 0.163 5 5 1 1.7 1.
8 2. 0.
3 2
A25 32.8 32. 3.11 0.052 0.253 5 4 12.5 0 0.
6 5 4.
2
A26 33.6 35. 1.6 -0.015 0.193 4 2 12.4 70 0.
1 4 4. 7.
8 7
E27 2.6 3.97 0.094 0.619 5 18.7 90 >
5. 1000
8
E28 0.7 3.28 0.081 0.131 2 >
7. 1000
5
E29 3 1 .06? 5.4 0.131 0.128 4 23.1 10 18
4.
2
E30 3.4 1.8 0.165 0.295 3 > 10 0
8 6.
9
E31 4.4 2.68 0.135 0.279 3 >
0. 1000
2
E32 5.1 2.12 I .065 1.431 3 >
6. 1000
7
E33 4.2 4.81 0.316 0.337 3 >
7. 1000
7
E34 0.3 0.63 0.029 0.03 1
6
.
1
E35 18.3 5.22 0.07 0.071 6 20 184
8.
8
E36 10 3.17 0.033 0.106 4 22.4 > IO
0 OOO
E37 22.6 5.35 0.01 1 0.026 7 19.5 100 4
3.
8
EE39 7.2 1 0.87 -0.086 0.098 2 2
EE40 1.8 0. 1.
8. I 8
0 2 1
7. 4.

Construction and Building Materials 1994 Volume 8 Number l 21


Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 22

9 4
silica fume also resulted in a lower 3, as recommended by the manufacturers,
permeability. The use of silica fume can be while in the present study they were
optimized by using less superplasticizer, increased and varied from 6.4 to 10. This
another type of superplasticizer, or another lowered the coemcient of thermal
type of sand instead of Ottawa sand expansion by a factor of 2 but at the cost of
(Illinois, USA). The field tests considered a considerable decrease in bond strength.
these parameters and were performed The emulsified epoxy mortars (EE39
using such samples, i.e. the silica fume and EE40) do not seem to be a feasible
content was the same but the amount of alternative as a repair material, since they
superplasticizer was reduced. This demonstrated poor compressive strength,
approach could reduce the shrinkage in bond strength and abrasion resistance.
mixes C3 to The hydraulic cement mortars showed the
best perfor-
The manufactured cement grouts (C7 to Surface repair mortars used for field tests
C12) all demonstrated high compressive
Type of product Mixes
and bond strengths as well as high
resistance to abrasion. However, a few Ordinary cement mortars
grouts still showed variations in volume in Silica fume mortars
the shrinkage test after hardening and a Cement grouts C8, O, CIO, Cl l
higher coefficient of thermal expansion Aluminous cement mortars C14,
than for the standard cement mortar. Polymer-modified cement-based mortars:
Most of the polymer-modified cement- SBR RI 7, R19, R20, R21
Acrylics A24, A25
based mortars exhibited a higher resistance Sand/epoxy mortars E29, E35, E38
to compression and abrasion, as well as a a
Laboratory-tested in-house silica fume mortars which were
higher bond strength, than the standard
modified for field testing
cement mortar. However, considerable
variations in volume proved possible
during the hardening process and the
coemcient of thermal expansion of these mance (compressive and bond strength,
mortars was slightly higher than that for resistance to abrasion and shrinkage) under
the reference mortar. wet curing (dry curing can lead to
In general, polymer-modified cement- considerable shrinkage). Hence, an initial
based mortars demonstrated much lower wet curing period of at least 24 h is always
permeability than hydraulic cement required to ensure the cement is hydrated.
mortars containing no polymers. These Moreover, the shrinkage tests
mortars retain water seeping from the systematically showed that complete
underlying concrete, which causes immersion of hardened sand/epoxy
cracking and a premature debonding of the mortars during wet curing could lead to
repair product. Such products depend on much greater expansion, especially for
the choice of application site: if water can sand/epoxy mortars with high sand/epoxy
seep through from the underlying concrete, ratios ( < 5). This also warrants additional
then specific precautions must be taken to study so that we can verify and
drain this water away; otherwise, such comprehend the phenomenon.
mortars should be avoided. Almost all the repair materials having
Sand/epoxy mortars (E27 to E38) experienced considerable disbonding
demonstrated good abrasion resistance. during the thermal compatibility test had a
However, this type of product generally much higher coemcient of thermal
performed poorly in terms of bonding with expansion than standard cement mortars,
the substrate concrete, in addition to which stresses the importance of this
having a high expansion rate under wet factor.
curing and a high coemcient of thermal In general, the Portland cement mortars
expansion. In the previous study 2 , the and grouts showed very satisfactory
sand/epoxy ratios were generally close to results, as did the mortars with silica fume

Construction and Building Materials 1994 Volume 8 Number 1


Surface repair mortars at a dam site: J. Mirza and B. Durand

and mortars containing aluminous cement. facilitate removal once the samples had
The polymer-modified cement mortars hardened.
containing SBR and acrylics also gave The manufactured products were first
weighed at the IREQ laboratory, packed in
very good results in many respects. As for pails, then carried to the site in such a manner
epoxy mortars, it can be seen that although as to minimize handling; at the site. Only liquid
their abrasion resistance is very good, their products (water, latex and epoxy) needed to be
other physical properties have not given weighed at the dam.
satisfactory results. Hydraulic cement-based products were
This laboratory study allowed 21 mixed using a small conventional mixer with
products to be selected for the small-scale fixed propellers having a capacity of about 0.05
field tests which began in autumn 1991. m3 , although a conventional mixer with mobile
propellers would have been preferable for all
The products selected were those which the mixes, considering the small volume of the
performed better than the reference mortar batches. The mix water consisted of distilled
during the physico-mechanical and water or bottled spring water. The sand/epoxy
durability tests in the laboratory. Some of mortars were mixed by hand or with a metal
the in-house mixes already developed were rod in containers provided by the
modified according to the results obtained. manufacturers. The mixer was rinsed first with
A manufactured sand/epoxy mortar (E38) river water and then with pure water.
Overall, the mixing procedure went well
was also selected for phase Il; it had not except for a product containing acrylic which
undergone all the laboratory tests but had adhered to the inner walls of the mixer. Once
performed well in some of them. the mixing was completed, the mixes were
transported in plastic pails and poured into
their respective forms to a general thickness of
Small-scale field tests (phase Il) less than 50 mm. Finishing was done with a
The 21 selected mixes were employed at two trowel.
different locations, which made a total of 42 We ended by placing specific mortars
samples in the field, as listed in Table 3. outside the forms to create a slight incline
Two locations on a spillway of a Hydro- between the substrate concrete and the
Québec dam were chosen for the tests: at repair mortars.
the bottom of the spillway's steep incline Once the setting cycle was completed,
(less than 100) and at the top of the all specimens except the sand/epoxy
spillway, at the foot of the sliding gate mortars were covered with a damp piece of
(200). These two zones fulfilled the criteria jute and a polyethylene sheet. The forms
established for this study: severe were removed after 7 days and the spaces
environmental conditions, abrasion— between the joints were filled with mortar.
erosion, freeze— thaw conditions, drying The specimens were thus exposed to
and wetting, thermal cycling, etc.; zone to ambient conditions 7 days after setting.
be repaired was relatively smooth without The 42 samples tested on the spillway
any major flaws and had similar exposure were subjected to stresses related to the
conditions over the entire surface; extreme climatic conditions found in
possibility of two zones needing Quebec characterized by numerous cycles
of freeze—thaw and drying—wetting.
20 Subsequently, for about 2 weeks the
samples were also subjected to the
to be repaired at the same site with similar abrasive effect of waterborne sediments
exposure conditions; and slight risk of and debris of all kinds (spring thaw). After
freezing or bad weather conditions during the spillway gates were closed, the
application of the material in September. samples were inspected at the beginning of
The surfaces were sandblasted before being June 1992. In addition to performing a
cleaned by air-pressured blasting. After that, visual inspection of the materials, the
they were kept wet except for those parts where
the sand/epoxy mortars were to be applied. The bonding strength of the concrete substrate
zones concerned were divided into 21 squares as well as the hardness of the surface were
of 500 mm x 500 mm using wood forms which analysed. The test consisted of applying a
were firmly fixed in the spillway concrete. Oil steel nail to the surface of the material. An
was first applied on the surface of the forms to

Construction and Building Materials 1994 Volume 8 Number l 23


Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 24

empirical scale ranging from I to 10 was comments on the appearance of the sample
established in order to assess the strength with respect to surface, colour, cracking,
and hardness of the material. An index etc.
lower than 7 meant that the product was The gates of the spillway were closed
not very resistant while an index of 9 or 10 for a time in 1992 so that repair work
meant that the material was quite hard, could be done. They were opened later in
with 10 indicating that the surface was left the summer, which meant that the mortar
unmarked. The state of the surface of the samples were exposed to the stresses from
repair mortar was also examined and the floating wood in addition to the effect
compared with its initial condition. of waterborne particles and debris.
To test the bonding strength of the repair Based on the site tests during phase Il of
mortar to the base concrete, the surface the project,
was tapped with a hammer. A hollow
sound meant that the repair material had Table 4 Observations on samples at the bottom of
par- the spillway
Bottom of spillway Top of spillway

TOP TOP
( ) R17

5.1 8 6.4
R17 14

Figure 2 Percentage of disbonded material as at 8 June


R20 R21 1992 (top of spillway)

Disbonded product six (C3, Cl(), C 14, R 19, R2(), A24)


products were identified as being the best
Figure l Percentage of disbonded material as at 8 (12 initially selected). The epoxy mortars
June 1992 (bottom of spillway) were not chosen because of their complex
composition and the limited volume that
would obtain in the mix. One standard
tially or completely disbonded. All of the mortar (C2, prepared according to ASTM
repair mortars were thus 'sounded out'. It C109 and modified) was used as the
should be noted, however, that a thin layer reference mortar and another repair mortar
of water could also cause this effect. (eighth cement-based product, S88C)
The amount of material that disbonded recommended by the contractor was
for the samples applied at the bottom and added. Table 6 shows the products used for
top of the spillway is shown in Figures 1 each apron and its respective piers.
and 2. Tables 4 and 5 show the
approximate percentage of disbonded Large-scale field tests (phase Ill)
material, the index of hardness (or the
material's resistance to scratching) and

Construction and Building Materials 1994 Volume 8 Number 1


Surface repair mortars at a dam site: J. Mirza and B. Durand

Hull-2 generating station at the Chaudiére the selection of this site. Built in 1908, the

Easily
0 7 A small amountof whitish aggregate exposed below the paste
Cll
C14 0 8 Smooth, very good
Ring dam was chosen for large-scale Chaudiére Ring dam comprises 50 aprons
application of the repair products. The separated by 49 piers. Each pier is
criteria used in phase Il were also used in

Construction and Building Materials 1994 Volume 8 Number l 25


Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 26

reinforced concrete slab which acts as a were added to all the cement grout mixes,
diaphragm. Aprons No. 12 and 14 and including the shotcrete mortar. Moreover,
their bordering piers were chosen for use of the shotcrete method to apply
large-scale application of the selected products containing latex (acrylics or SBR)
repair products because of the very proved diffcult. The cement-based product
advanced erosion. Also, as the apron gates (Cl 5) was not jetted but applied by trowel.
were fully opened in 1992/3, the repair This product contains certain additives
mortars were exposed to maximum which cause the grout to harden in 3 min.
erosion. The repairs conducted in this Product A24 was applied by trowel. In
study were therefore subjected to a places
realistic and representative cycle of use. FLOW
The surface of most of the aprons and
piers was damaged by the effect of
abrasion—erosion caused by water flow. 2.2 m 1.55 m 3.75 m
The extent of the erosion varied from one
pier or apron to another, ranging from E
about 25 mm to 100 mm in depth. It
should be noted that some of these surfaces
had previously been repaired using (R19)
different products, but the results were not (C14)
satisfactory.
The surface of each apron as well as the
inner walls of the bordering piers were 45 mm 38m
repaired using the selected products (Table 1.0 m 1.2 m
6) which were applied manually on the
aprons (except for C3 which was also (R20)
applied by the shotcrete method) and by
the shotcrete method (except for A24
which was trowel applied) on the piers (see 3.75 m 3.75 m
Table 6).
Joint • I-component polyu ethane - self leveling (32
22 mm)

Joint : 2•mponent polyurethane - self


Large-scale application of repair materials
leveling (32, 38 45
Concrete sand was used for mortars C2
and C3 instead of the very fine mortar Figure 3 Locations of each product and field-
sand. Two application methods were used moulded joint sealants
on the aprons and piers: the trowel method (apron # 12)
and the shotcrete technique (wet—mix
process). All of the repaired surfaces were
subjected to wet curing: at least 3 days for
cement grout and I day for mortars
containing latex (SBR or acrylics). After FLOW
28 days of curing, the apron gates were
opened slowly over a period of 7 days in
order to subject the repair mortars to
abrasion-erosion. The first inspection was 0.63 m
scheduled for May/June 1993. 1.88 m 1.55 m 3.75 m

Aprons
The surfaces to be repaired were marked
by a 50 mm deep cut made by a diamond
saw. The surface of each spillway was
prepared using jack hammers (30, 16 and
2.5 kg, respectively) followed by

Construction and Building Materials 1994 Volume 8 Number 1


Surface repair mortars at a dam site: J. Mirza and B. Durand

FLOW

6.0 m 6.0 m

PIER 14 PIER 15
Joint : I-convonent polyurethane - non-
sag (20 mm)

Figure 6 Location of each product and field-moulded joint


7.07 m sealants (piers)
Joint : 2-component polysulphide - self-
leveling (25 mm)
Joint : 2-component polyurethane - sew- Application of the field-moulded joint
leveling (25 mm) sealants
Figure 4 Locations of each product and field- This opportunity was used to evaluate the
moulded joint sealants (apron # 14) field-moulded joint sealants in the
construction joints that were created
between the various surface repair
where the layer needed to be thicker than materials. Such a study, i.e. the evaluation
75 mm, the products were first jetted to a of fiel&moulded sealants in hydraulic
thickness of 25 to 35 mm, with the final structures affected by severe climatic
layer being applied an hour later. conditions, appears nowhere in the
literature.
Figures 5 and 6 show the locations of
each product applied to the piers. Application of the field-moulded joint
sealants required additional time and was
FLOW
also a new study. We took this
opportunity to test the application of
these sealants both on the aprons and
piers.
Construction joints were created
between each of the products applied to
the apron and piers. The cuts were made
6.0 m 6.0 m using a diamond saw in the same direction
PIER 11 PIER 13 as the water flow as well as at a 90 0 angle.
The joints were created to decrease the
Joint : I-convonent plyurethane - non-sag effect of the mechanical and thermal
(25 mm) stresses or the expansion/contraction
caused by shrinkage and/or freeze—thaw.
Figure 5 Location of each product and field-moulded joint
sealants (piers) The inside surface of each joint was
sandblasted and then cleaned by air-
pressured blasting. The back-up rods (25%
larger than the joints) were installed in the
joints.
The field-moulded joint sealants used
for the study consist of a two-component
polyurethane (self-levelling and non-sag),
a two-component polysulfide (self-

Construction and Building Materials 1994 Volume 8 Number l 27


Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 28

levelling and non-sag), and a one- to test the behaviour and durability of the
component polyurethane (non-sag). The sealants but with varying rates of flow in
self-levelling and non-sag sealants from the apron joints.
the same products were applied in the The two-component sealants were mixed
same direction as the water flow as well as just before being applied to the joints but
at a 900 angle. The purpose was the single-component sealant was jetted.
Cost per square foot of the selected materials The one-component polyurethane field-
moulded joint sealant was used for all of
the pier joints.
Cost (Cdn $)
Product Apron floor
The repaired surfaces were flushed using
a wet spoon and a mixture of soap and
water a few minutes before application.
Cl 7 10 7 9 This process allowed the surface to be
CIO 5 brought to the same level as the repair
C14 mortar,
16 by hand which prevented cavitation damage
C14 12 R19 during water flow.
8 R20 The joints were covered with a wet
polyethylene sheet and curing
lasted at least I day for single-
10
component sealants. With respect
A24 to two-component sealants, the surfaces
S88C were covered with a polyethylene sheet (on
the pier) or with several planks of wood
(on the apron).
The application of field-moulded joint
sealants on aprons # 12 and # 14 is shown
O in Figures 3 and 4 and on the two adjacent
WALL piers of apron # 12 (in the same direction
as the water flow) in Figure 5. Only two
small joints were created in the same
direction and perpendicularly to the
water flow on apron # 14 (Figure 6).
After 28 days, the apron gates were
opened slowly over a period of 7
days. An inspection of the repaired
surfaces was planned for May/June
1993.

ResulG of the economic feasibäty


study
16
This study provided the cost of each
14 product (Table 7 and Figure 7) applied on
12 large-scale field tests. The relatively high
10 cost of the application of normal Portland
cement mortar (Cl) and the silica fume
8 mortar (C2) is
6
24
attributed to the intensive manual handling
of inexpensive raw materials. These are
received in bulk and transported in smaller
quantities to the area being repaired, where
Figure 7 Cost per square foot of the selected they have to be mixed thoroughly before
products application. In addition, they must be

Construction and Building Materials 1994 Volume 8 Number 1


Surface repair mortars at a dam site: J. Mirza and B. Durand

protected from rain and the elements, added immediately before the repair
which also adds to the handling costs. mortar is applied so that they do not have
Thus, in the case of conventional Portland time to dry and cause a lack of
cement and sand mix (Cl), the unit cost per homogeneity between the old concrete and
square feet installed is approximately $7 the repair mortar. Should this happen, the
per square foot whereas for mix CIO the resulting bond could prove inferior to the
average cost is approximately $5 per bond that would have been obtained
square foot. When material costs alone are without any bonding agent.
compared, the Portland cement mix is far Curing is a crucial phase and must be
less expensive, but if the overall cost is performed carefully. The repaired surfaces
considered, CIO is cheaper. may be covered by a damp absorbent
Materials handling is simplified by material and a polyethylene sheet. Newly
purchasing prepackaged units. In so far as repaired surfaces should not be exposed to
these units are delivered in waterproof direct sunlight and strong wind. An
bags, there is no necessity for additional adequate curing agent can replace water
protection. Mixing is also greatly for zones hard to reach.
facilitated by using precisely premixed It is recommended that the surface of all
units. epoxy-based products be kept dry. The
ambient temperature must be maintained at
Concluding remarks a constant level for the duration of the
setting or, failing that, temperature rises
Regardless of the product used during should be avoided. The use of a bonding
renovation work, each of the three phases agent containing pure epoxy could increase
(surface preparation, product application the subsequent bond strength but may
and curing) requires careful execution in significantly decrease the resulting
order to ensure the success of the whole permeability of the sand/epoxy. As the
job. Several views exist with regard to the coemcient of thermal expansion is usually
surface preparation of concrete: for greater for sand/epoxy mortars than for
example, sandblasting followed by a concrete, this type of product is not
clearwater rinse (as in our small-scale field recommended for applications where wide
tests), or chipping and sandblasting variations in temperature may occur,
followed by hydroblast. Whether forms are unless the thermal-compatibility tests show
used or the zones are delimited with a adequate performance in this respect.
diamondcharged saw depends on the
particular zone; it is left to the contractor
to choose the appropriate method. The Acknowledgements
application of repair products is usually
straightforward. As with concrete, steps The authors are grateful to J. Maniez, L.-
must be taken to ensure the mix is properly M. Landry and L.-P. Mendes of Hydro-
compacted, that no air voids are left, that Québec as well as the Canadian Electrical
no segregation occurs, and that a trowel be Association for funding this research
used for the finishing while taking care to project. Thanks also go to Mr A. Brosseau
minimize bleeding. Application should and Dr R. Roberge of Vice-présidence
take place as soon as mixing is complete. Technologie et IREQ, Hydro-Québec, and
to various members of that department for
Wet curing of all the hydraulic cement-
their contribution to the various tests. Final
based products should be performed with
drinking water for 24 h for polymer- thanks are due to C. Biondic and L. Kelly-
Régnier for translation and careful editing.
modified cement-based mortars, and at
least 72 h for cement mortars not
containing any polymers. The repair References
surfaces should be kept damp for at least I I Mirza, J. and Durand, B. Effect of curing on some
h before applying repair materials. The use properties of cementitious mortars with and without
polymer modifications. Proc. 6th Int. Conf. on
of a bonding grout made of Portland
Durability of Building Materials and Components to be
cement, latex or both could increase the published
bond strength, but these grouts must be

Construction and Building Materials 1994 Volume 8 Number l 29


Surface repair mortars at a dam site: J. Mirza and B. Durand
Table 30

2 Mirza, J. Coating and repairing materials for


concrete hydraulic structures damaged by
erosion. Canadian Electrical Association Report
#630 G 561, 1988

Construction and Building Materials 1994 Volume 8 Number 1

You might also like