Inspection and Test Plan (ITP) for Fabrication Pressure Vessel Page. 1 of 2
Rev. : 0
Document No. CCK-QC-ITP-Q027 Date : 11/11/2013
Contract Ref. Activity Identification /Location Involvement & Signature
Fabrication Pressure Vessel
Activit Verification / Inspection Quality Control / Record C.A. CCK OWN Remark
Reference Documents Characteristic to be Verified Acceptance Criteria
y No. Activity Format
1. Fabrication and Inspection Procedure For
Project Specification N/A FI R
Pressure Vessel Document Control Procedure
2. Welding Procedure Specification& Doc.Control Pro./ WPS,PQR
Project Specification N/A FI R
Procedure Qualification Record Form
3 Material Approval Request Project Standard 1. Approve Vendor List Project Specification Record Form no. P-01 N/A FI R