PLASTERING OF WALL:
Labor : 6 Days
1 Construction Foreman
3 Skilled Laborer
3 Common Laborer
Labor : 4 days
1 Construction Foreman
3 Skilled Laborer
3 Common Laborer
1 Construction Foreman
3 Skilled Laborer
3 Common Laborer
Labor : 3 days
1 Construction Foreman
3 Skilled Laborer
3 Common Laborer
1 Construction Foreman
3 Skilled Laborer
3 Common Laborer