Barangay Sigad

ITEM I. SUB-GRADE PREPARATION:

Materials: Delivered on Site

20 cu.m. Backfilling Materials

Labor: 5 Days

1 Construction Foreman
3 Skilled Laborers
4 Common Laborers

ITEM II. PORTLAND CEMENT CONCRETE PAVEMENT

Materials: Delivered on Site

21 cu.m. Graded Gravel


11 cu.m. Washed Sand
189 bags Portland Cement
36 pcs 2” x 6” x 10’ Coco Lumber
6 pcs 10mm x 6m RSB
3 kgs Assorted Common Wire Nail
2 pcs Hacksaw Blade

Equipment Rental: 4 Days

1 unit One Bagger Concrete Mixer

Labor: 6 Days

1 Construction Foreman
3 Skilled Laborers
4 Common Laborers
Barangay Managa-naga

ITEM I. FABRICATION OF STEEL POSTS, PAINTING, CONCRETE WORKS & ELECTRICAL INSTALLATIONS

Materials: Delivered on Site

7 pcs 2” GI Pipe Schedule 40


35 pcs 10mm x 6m RSB
5 kgs #16 Tie Wire
5 pcs Cutting Disc
3 kgs Welding Rod
3 pcs Hacksaw Blade
2 liters Primer Red Oxide
2 liters Latex Paint
2 pcs 2” Paint Brush
1 pcs 3” Paint Brush
14 bags Portland Cement
1 cu.m. Graded Gravel
1 cu.m. Washed Sand
3 pcs ¼” Marine Plywood
5 kgs Assorted CWN
48 pcs 2” x 2” x 10’ Coco Lumber
300 meters #6 Drop Wire
7 pcs 50 Watts Weather proof Streetlights
7 meters #14 PDW Wire
2 roll Electrical Tape

Equipment Rental: 2 Days

1 unit Welding Machine


1 unit Portable Grinder

Labor: 10 Days

1 Construction Foreman
2 Skilled Laborer
2 Common Laborers
Barangay Managanaga

ITEM I. EXCAVATION, FORMWORKS & STEEL REINFORCEMENT

Materials: delivered on site

18 pcs ¼” Ordinary Plywood


75 pcs 2” x 2” x 10’ Coco Lumber
8 kgs Assorted CWN
60 pcs 12mm x 6m RSB
30 pcs 10mm x 6m RSB
10 kgs #16 Tie Wire
5 pcs Hacksaw Blade

Labor: 7 Days

1 Construction Foreman
2 Skilled Laborers
2 Common Laborer

ITEM II. BOULDER LAYING & CONCRETE WORKS;

Materials: delivered on site


1 cu.m. 4” – 6” Boulderito
6 cu.m. Graded Gravel
3 cu.m. Washed Sand
39 bags Portland Cement

Equipment Rental: 2 Days

1 unit One Bagger Concrete Mixer

Labor: 3 Days

1 Construction Foreman
2 Skilled Laborers
2 Common Laborers