You are on page 1of 4

O I L S A N D S R E V I E W.

C O M : : T H E U N C O N V E N T I O N A L O I L A U T H O R I T Y : : M AY 2 0 1 3 : : $ 1 0

INNOVATORS
INNOVATIONS
– special issue –

Smaller,
better,
faster
Fred Haney’s vision turns
modular construction
theory on its head

14 How Cenovus Energy is able to dominate the


quest for in situ technology improvement

21 MEG Energy’s RISER production enhancement


system fortifies its position as an efficiency leader

29 Why an oxyfuel technology developed for space


could revolutionize SAGD steam generation
PM40069240
INNO VATO R S & I n n o vat i o n s

Smaller,
better,
faster
Fred Haney’s vision turns modular construction theory on its head

By Graham Chandler

Fred Haney likes most sports, but business development and sales, thinking about terminations and you can get the cabling onto all
it’s golf that suits his character provides some background. connections. the modules.”
best. Why? “The sport chal- “First-generation modular was “The biggest challenge we “3rd Generation really does
lenges yourself to improve,” things like main pipe racks and had was taking the amount of take the approach and turn it on
says Haney, executive director backbone racks—that’s been work off-site to its maximum its head,” adds McArthur. “When
of design engineering at Fluor around since the early ’90s.” for remote sites,” says Haney. we started doing that and having
Corporation. Second generation happened “Getting E&I [electrical and the module strategy driving the
That drive for improvement in the early 2000s, McArthur instrumentation] and cabling was layout, we started reconfiguring
helped propel Haney’s inven- continues. This takes the same one part. And getting a tighter fit how we live with the traditional
tion and his team’s creation of building block approach but adds of modules so that we had fewer layout of a facility and it led
Fluor’s 3rd Generation Modular more complicated equipment. interconnections. So we had us almost by happenstance to
Execution, which is bringing the “It’s still a mechanical approach— to think differently on how we reconfigure our work process.
oilsands industry up to 60 per cent pipes, equipment, steel on a would lay out a facility; we had to When we started reconfiguring
reductions in facility plot space module,” he explains, adding that change our thinking so modular- the work process, that was the
requirements and 20 per cent in this strategy took 30–40 per cent ization would drive the layout and 3rd Generation.”
capital cost savings for all types of work out of the field. not the opposite.” The process takes a typical plant
of plant construction. The second-generation ap- Haney says that was the real layout and shrinks space require-
It was the recession days of proach took a tremendous amount breakthrough. The only way to ments by more than 60 per cent.
2008-09 when Haney spot- of engineering to successfully make the system work was to McArthur notes that this reduces
ted a need for improvement in execute. It was fairly successful, shun traditional design methods the amount of materials—less steel,
modular construction. “We had but they were looking for more. and go to what he calls a process less pipe, less electrical cable—
projects that were not meeting Haney’s team looked at block layout approach, which driving the cost down and reducing
clients’ expectations,” he recalls, what was good and bad about allows minimization of inter- the amount of labour needed at the
pointing to cost overruns and modular projects—onshore and connections to two or less. “You site. Moreover, the overall number
schedule slippage. Despite the offshore. “We took a look at will end up having a facility where of modules is reduced because
savings modularization was of- why we weren’t moving to the
fering, labour was still a key issue. next level, and a lot of it had to
So Haney and his team needed do with electrical and control The inventor: Fred Haney, executive director of design engineering
to find a way to take even more systems and getting cable onto at Fluor Corporation, has invented a modular facility
work out of the field. modules and getting that work construction system that is designed to relocate up to 90 per
Scott McArthur, Fluor off-site,” says Haney. Inclusion cent of field construction hours to the mod yard, reducing total
Canada’s general manager of of these systems demanded new installed costs by up to 20 per cent compared to current practices.

16 OILSANDS REVIEW | MAY 2013


INNO VATO R S & I n n o vat i o n s


— —

The biggest
challenge now is
getting the mindset
shifted so that you
can execute to this
new methodology.

PHOTO: Charles HOpe

— —

OILSANDSREVIEW.COM 17
INNO VATO R S & I n n o vat i o n s

Fluor is taking things that are nor- The shift in mindset described and providing a little more cost would be interchangeable on
mally not modules and making by Haney was an important sell. certainty and schedule certainty,” different types of projects. “For
them modules; things that were “It took very heavy involvement Haney says. It fits with world example, a design may have eight
traditionally fabricated in the field in buy-in from our operations trends in the resource extraction modules for this application, and
are put into the module. people,” says Peplinski. “It all industries because projects are you may only need six of them.
Haney says it’s such a novel appeared very congested. They getting more and more remote as On another location, you may
approach that “the biggest chal- were concerned about ergonomic easy finds deplete. need seven of them; you just plug
lenge now is getting the mindset and human factors—will the Looking ahead, Haney sees in that extra module.” It will still
shifted so that you can execute to valves be accessible, will meters a total integrated engineering, be 3rd Generation, defined as
this new methodology.” and equipment be accessible, procurement, fabrication and an integrated EPFC solution with
And that is happening al- can they easily be pulled for construction (EPFC) solution standardization and replication.
ready on several large oilsands maintenance, will the walkways using 3rd Generation. That would The approach is attractive,
projects. “We probably have for example, to SAGD projects
seven or eight projects currently where phased growth has
executing in this mode,” says
In situ facility plot size reduction become the norm. “They’re not
Haney. Among these are Suncor trying to build, say, a million-

Source: fluor corporation


Energy Inc.’s pending MacKay barrel-per-day [project] in one
River Phase 2 project and Shell Plot area approximately fell swoop,” says McArthur.
Canada’s Quest Carbon Capture 84,000 square metres “They are trying to get there in


and Storage Project, currently stages so they manage their cash
being constructed, near Fort flow, their investment.” Once the
Saskatchewan, Alta. Plot area approximately first investment is successfully
Shell’s interest in 3rd 200,000 square metres ▼ running, they can essentially
Generation came early in the install replicas for succeeding
Quest project planning. “We phases, eliminating “too much
started early in the [front-end reinventing of the wheel.”
engineering and design] phase, SAGD operations were where
when engineering was maybe most of the initial 3rd Generation
only five per cent complete,” research was done. “We did a
says Steven Peplinski, resident lot of work on SAGD facilities to
engineering team manager for give us the real sweet spot,” says
Quest. “Rather quickly we made Haney. “For example, we have
a decision based on the benefits what I call metrics that tells us
we saw.” the most cost-effective approach
And true to the 3rd Generation on a capital basis and also looked
concept, modularization drove at what’s the sweet spot on a [net
The 3rd generation module concept would take, for example,
the layout. “We had an available a 200,000-square-metre plot area for an in situ oilsands facility present value] basis.” He says
plot space within our Scotford and shrink that down to 84,000 square metres. that a 10,000-barrel-per-day
Upgrader, which would have facility may be the lower limit for
been barely adequate for Quest be wide enough, et cetera. But it provide clients with overall cost the approach—at 5,000 barrels
[on a conventional basis],” says hasn’t proven to be a barrier: with reduction, and cost and schedule per day, commerciality may be
Peplinski. “By adopting 3rd 80 per cent of the engineering certainty. “But you still have to be a struggle. “We’ve looked at all
Generation, we actually used less design now complete, construc- able to execute to achieve those sizes and we have a very good
space than we had allocated.” tion should wrap up in 2014.” results,” he says. “It’s great to database of what a modular
One of its biggest attractions Overall, savings are proving to say we have a design tool, but we design should look like using 3rd
for Shell was site safety through be significant for most projects: really have an execution platform Generation.”
reduction in on-site person- Haney cites 20 per cent cost for the whole thing, and that’s a Haney finds it most rewarding
nel. “We are doing a brownfield reductions over standard second key element.” that owners are accepting the
construction—right next to an generation. “This is our execu- The other area going forward change. “They are now seeing
operating upgrader,” he adds. tion basis for projects now.” On a “is you are going to see a lot they can’t just do the status quo,
“Our initial assessment was we 30,000- or 40,000-barrel-per- more standardization, replica- they have to change themselves.”
would need maybe 1,000 people day SAGD facility, savings of that tion of facilities combined with The industrial innovation
on site; currently, peak workforce magnitude can easily run into modules,” says Haney. “A pro- stems from Haney’s personal
looks like we’ll have about half tens of millions. ject I’m doing in Spain right now, inspirations.
of that. Just having less people Numbers that high get global for example, is a modular facility “The single most important
on a construction site next to an attention. “We are executing that’s going to be replicated motivator which keeps me en-
operating unit means less expos- it in all our projects in Calgary, several times using standard gaged in what I accomplish is the
ure hours, fewer people to bring but also now on a global basis, modules. In 10 years, you’re ability to learn something new
on site every day and simpler because modular execution going to see replicable modular every day. My approach to design
evacuation should the need arise. and modular methods are being facilities much more than you is to understand the basis which
So that was a big bonus for us.” recognized as a way of controlling do today.” He says the modules drives design decisions.”

18 OILSANDS REVIEW | MAY 2013

You might also like