Professional Documents
Culture Documents
continued >
FEDERAL ENERGY MANAGEMENT PROGRAM
All of these basic measures will con- ➢ Verify server airflow temperature at be used to gather air temperatures and to
tribute to increasing the cooling capacity inlet and outlet (before RDHx). develop trend information prior to installing
of your existing data center systems and a RDHx system. Generally in a data center,
may help avoid the complexity of install- ➢ Check air temperature at RDHx an EMCS with centralized, automated,
ing new, additional cooling capacity. outlet. direct digital control can coordinate energy
use of cooling systems such as CRAC
3.1 Site preparation and installation ➢ Measure RDHx coolant flow and
units, thus maximizing performance of
inlet and outlet temperatures.
• Determine chiller and cooling tower the rack-mounted RDHx devices.
system capacity. ➢ Confirm inlet coolant temperature
at each RDHx is above dew point 4.3 Metering for energy management
• Locate and determine access and The LBNL demonstration project clearly
temperature.
connections to existing chilled- validated the old energy-use axiom that
water, treated-water, and tower- ➢ Check for leaks at pump and in generally states that you cannot man-
water systems. piping arrangements. age energy without monitoring energy.
Adequate metering and monitoring is
• Examine server racks for missing ➢ Review and test new control essential to provide reliable energy-use
blanking and side plates. sequences. data to sustain the performance of the
• Remove or relocate obstructions to RDHx installation.
routing new piping under floor. 4 Lessons Learned
4.4 Rethinking rack arrangements
This demonstration project at LBNL
• Install new circulating pump(s), RDHx technology may make creating
provided lessons-learned that may be
flow-balancing valves, and fittings, what is usually referred to as “hot aisle
relevant to other RDHx projects. One
as necessary. isolation” less important. Using a RDHx
unexpected result was the amount of excess
cooling capacity created within the data can sufficiently reduce server outlet
• Route piping and flexible hose.
center. The newly found capacity required temperatures to point where hot and cold
• Install isolation and balancing valves. coordinating RDHx cooling capacity with aisles are no longer relevant. In a new
the existing CRAC units. Standard CRAC data center design, adjoining server racks
• Prepare servers for possible return-air control methods, which are may not need to have their outlet air-
down-time. beyond the scope of this bulletin, can flows facing each other. A series airflow
present a challenging situation. arrangement, where air from a rack outlet
• Add new temperature sensors. supplies air to an adjoining rack’s inlet,
4.1 Airflow management can be implemented. Depending on the
• Install heat exchanger door; check
rack arrangement in an existing data
flexible pipe clearances. Airflow from under-floor outlets needed
center, an RDHx system can simplify air
to be directed correctly. The location and
• Purge and pressure test system for management by eliminating the need for
adjustment of the supply outlets such as
leaks. hot and cold aisle isolation.
adjustable perforated tiles, was optimized
prior to fitting RDHx devices. Air leaks
3.2 Commissioning around the rear-door heat exchangers 5 References
LBNL encountered a variety of minor required sealing since the doors did not Hydeman, M. “Lawrence Berkeley
initial start-up issues related to the fit and always fit tightly. Additionally, LBNL National Laboratory (LBNL) Case Study
finish of the RDHx devices such as air found that RDHx devices were not well of Building 50B, Room 1275 Data Center
leaking around the RDHx devices and air suited for all rack designs, especially from 2007 to 2009.” Taylor Engineering,
short-circuiting within the racks. During racks older than 10 years. The poten- LLC. December 2009
startup, it is essential to monitor all liquid tial for hot-air short-circuiting within
and air temperatures and coolant flow-rates the racks is widespread. To limit this
to optimize RDHx performance. It is recom- situation, LBNL installed server rack 6 Acknowledgements
mended that the following are commis- blanking-plates and side-panels. In addi-
sioned as part any RDHx installation: Primary Author:
tion, LBNL used brush-type seals around
RDHx hoses to mitigate this air-leak Geoffrey C. Bell, P.E.
➢ Confirm point-to-point connections Lawrence Berkeley National Laboratory
pathway.
of temperature sensors. One Cyclotron Road
4.2 Monitoring performance a necessity M.S. 90-3111
➢ Ensure airflow leakage around the Berkeley, CA 94720
RDHx and recirculation within the An EMCS, BAS (Building Automation
Voice: 510.486.4626
rack is minimized. System), or other monitoring system, should
e-mail: gcbell@lbl.gov
FEDERAL ENERGY MANAGEMENT PROGRAM
June 2010
Printed with a renewable-source ink on paper containing at least 50% wastepaper, including 10% post consumer waste.