You are on page 1of 1

UNIT RATE ANALYSIS (UPA) FORMAT

Work Item : 1.2 Wall Finish


Unit : pc
Estimated Quantity (Q) : 1000.00 Unit Rate: 19.69

Local Currency (BDT)


Ref. No. Equipment Costs Q'ty Unit
Unit Rate Amount
1 Equipment Costs 5.00 pc 0.00
2 transport 1.00 0.00
3 0.00
4 0.00
5 0.00
Sub-total (1) 0.00

Local Currency (BDT)


Ref. No. Labor Costs Q'ty Unit
Unit Rate Amount
1 Skilled 2.00 person 750.00 1500.00
2 Unskilled 3.00 person 550.00 1650.00
3 0.00
4 0.00
5 0.00
Sub-total (2) 3150.00

Local Currency (BDT)


Ref. No. Material Costs Q'ty Unit
Unit Rate Amount
1 Tiles 205.00 sqft 60.00 12300.00
2 White Cement 2.00 bag 550.00 1100.00
3 Water 300.00 liter 5.00 1500.00
4 Cement 2.00 bag 480.00 960.00
5 Sand 17.00 cft 40.00 680.00
Sub-total (3) 16540.00

Local Currency (BDT)


Ref. No. Other Direct Costs Q'ty Unit
Unit Rate Amount
1 0.00
2 0.00
3 0.00
4 0.00
Sub-total (4) 0.00

(5) Sub-Total Amount of Specification Item: (1)+(2)+(3)+(4) = 19690.00