Professional Documents
Culture Documents
Chapter
15 Resource Planning
TRUE/FALSE
1. An ERP system revolves around a single comprehensive database that is made available
across the entire organization.
Answer: True
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource, planning, ERP
2. Companies that fully customize their ERP implementation reap the greatest rewards from
such systems since they can continue to use the same processes to which all employees are
accustomed.
Answer: False
Reference: Enterprise Resource Planning
Difficulty: Moderate
Keywords: enterprise, resource, planning, ERP, implementation
5. Dependent demand occurs because the quantity required is a function of the demand for other
items held in inventory.
Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Easy
Keywords: dependent, demand, inventory
513
Chapter 15 Resource Planning
6. A component is an item that may go through one or more operations to be transformed into or
become part of one or more parents.
Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Easy
Keywords: component, parent, transform
7. Lumpy dependent demand can result even from continuous independent demand.
Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: lumpy, dependent, demand, continuous
8. Part commonality refers to the degree to which a component has more than one immediate
parent.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: part, commonality, component, parent
10. Gross requirements are the total demand derived from all parent production plans.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirements, demand, parent
11. A bill of materials (BOM) shows all of the components of an item, the parent–component
relationships, usage quantities, and lot size derived from engineering and process designs.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: BOM, bill, materials, parent, component
12. An intermediate item must have at least one parent and at least one component.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: intermediate, parent, component
514
Chapter 15 Resource Planning
13. The master production schedule (MPS) is the part of the material-requirements plan that
specifies when components must be ordered or assembled.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: master, production, schedule, MPS, material, requirements, plan
14. Available to promise inventory is the amount of end items that marketing can promise to
customers by a certain date.
Answer: True
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: ATP, available, promise, inventory, MPS
15. The portion of the master production schedule furthest in the future is often frozen to reduce
forecasting requirements.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MPS, master, production, schedule, freezing
16. Planned receipts are estimates of the amount of inventory available each week after gross
requirements have been satisfied.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipts, projected, on-hand, inventory
17. A planned order release provides an indication of when an order for a specified quantity of an
item is to be issued.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release
18. For items manufactured in-house, one component of lead-time is waiting time.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lead, time, waiting
19. Periodic order quantity (POQ) is a rule that tends to keep more inventory on hand than lot-
for-lot quantity, but less inventory on hand than fixed-order quantity.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: periodic, fixed, order, quantity, lot, POQ, FOQ, L4L
515
Chapter 15 Resource Planning
20. Lot-for-lot (L4L) is a rule that maintains the same order quantity each time an order is issued.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, L4L, order, quantity
23. The process with the least capacity is called a capacity constrained resource if its output is
less than market demand.
Answer: False
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, resource
24. A transfer batch combined with a constraint buffer makes a full process batch at a capacity
constrained resource.
Answer: True
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: DBR, CCR, capacity, constrained, resource, process, transfer, batch
25. The bill of resources (BOR) is a record of all the required material, equipment time, staff, and
other resources needed, the parent–component relationships, and the usage quantities.
Answer: True
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: BOR, bill, resources
516
Chapter 15 Resource Planning
MULTIPLE CHOICE
26. A companywide process that cuts across traditional functional areas, business units,
geographic regions, and product lines is a(n):
a. enterprise process.
b. drum-buffer-rope process.
c. kinetic process.
d. full-business process.
Answer: a
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource
517
Chapter 15 Resource Planning
33. Which best defines the gross requirements for a component item?
a. The forecasted customer demand for the component
b. The amount of safety stock needed to buffer against uncertainties
c. The sum of gross requirements for all parents of the component
d. The total demand for the component derived from all immediate parents
Answer: d
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: component, parent
518
Chapter 15 Resource Planning
34. MRP can be used to best advantage under which one of the following circumstances?
a. When the item’s demand depends only on customer demand
b. When the item’s demand is uniform
c. When the item’s demand is constant
d. When the item’s demand depends on its parent’s demand
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning
36. Which one of the following systems is an input to the MRP system?
a. Shop-floor scheduling system
b. Financial reporting system
c. Master production-scheduling system
d. Purchasing system
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, input
37. If a planned receipt for an item is due in week 6 and the item’s lead-time is two weeks, in
which week will the corresponding planned order release occur?
a. Week 2
b. Week 4
c. Week 6
d. Week 8
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, receipt, release
519
Chapter 15 Resource Planning
38. Which one of the following statements about lot-sizing rules is TRUE?
a. The periodic order quantity (POQ) rule seeks to create inventory remnants.
b. If the POQ rule is used, an item’s lot size can vary each time an order is placed.
c. The lot-for-lot (L4L) rule is a special case of the fixed-order quantity (FOQ) rule.
39. Which one of the following is an MRP lot-sizing rule that attempts to minimize the amount of
average inventory?
a. Periodic order quantity (POQ), with P = 2
b. Fixed order quantity (FOQ)
c. Economic order quantity (EOQ)
d. Lot for lot (L4L)
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, L4L, lot
520
Chapter 15 Resource Planning
42. Which one of the following is a feature of MRP II, but not available in basic MRP systems?
a. Financial reporting
b. Action notices
c. Dispatch lists
d. Capacity reporting
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, MRP II, resource
44. The Big Mistake Company uses an MRP system. However, the company’s database contains
many inaccuracies. Which type of inaccuracy is most likely to result in incorrect planned
order release quantities for its dependent demand items?
a. Incorrect routings
b. Incorrect bills of materials
c. Incorrect cost and pricing data
d. Incorrect machine capacity data
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: dependent, demand
45. Which one of the following conditions enhances the effectiveness or success in implementing
MRP?
a. Accurate inventory records
b. Small lot sizes
c. Few BOM levels
d. A volatile manufacturing environment
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, implementation
521
Chapter 15 Resource Planning
Date 1 2 3 4 5 6 7 8
Gross 30 30 60 75 70
requirements
Scheduled 60
receipts
Projected 0
on Hand
Planned
receipts
Planned order
releases
What are the quantities of planned order releases for item ABC for the first five weeks
(weeks 1, 2, 3, 4, and 5)?
a. 30, 0, 60, 0, 145
b. 60, 0, 145, 0, 0
c. 0, 30, 60, 0, 0
d. 30, 0, 60, 145, 0
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, planned release
522
Chapter 15 Resource Planning
Date 1 2 3 4 5 6 7 8
Gross 50 20 30 40 20
requirements
Scheduled 25
receipts
Projected
on Hand 40
Planned
receipts
Planned order
releases
What are the quantities of planned order releases for item XYZ for the first six weeks
(weeks 1, 2, 3, 4, 5, and 6)?
a. 35, 0, 0, 60, 0, 0
b. 35, 0, 60, 0, 0, 0
c. 5, 30, 0, 40, 20, 0
d. 35, 0, 0, 40, 20, 0
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, order, release
523
Chapter 15 Resource Planning
49. Use the following MRP record to answer the following question.
Date 1 2 3 4 5 6 7 8
Gross
requirements 100 50 70 40 90 50
Scheduled 100
receipts
Projected
on Hand 20
Planned
receipts
Planned order
releases
524
Chapter 15 Resource Planning
Table 15.1
Date 1 2 3 4 5 6 7 8
Gross
requirements 40 140 60 40 180 65 90
Scheduled
receipts 200
Projected
on Hand 100
Planned
receipts
Planned order
releases
50. Use the information in Table 15.1. In which week will the second planned order release
occur?
a. Week 1
b. Week 2
c. Week 3
d. Week 4, 5, 6, 7, or 8
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, release
51. Use the information in Table 15.1. If the safety stock level were 30 units instead of 0 units, in
which week would the first planned receipt occur?
a. Week 1
b. Week 2 or 3
c. Week 4 or 5
d. Week 6 or 7
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipt
525
Chapter 15 Resource Planning
526
Chapter 15 Resource Planning
Date 1 2 3 4 5 6 7 8
Gross
requirements 60 90 150
Scheduled
receipts 160
Projected
on Hand 0
Planned
receipts
Planned order
releases
What are the quantity and the week of the first planned order release?
a. 20 units; week 1
b. 140 units; week 2
c. 150 units; week 1
d. 150 units: week 2
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, release
527
Chapter 15 Resource Planning
Date 1 2 3 4 5 6 7 8
Gross
requirements 50 100 90 100
Scheduled
receipts 120
Projected
on Hand 20
Planned
receipts
Planned order
releases
528
Chapter 15 Resource Planning
Table 15.2
Consider the following MPS, BOM, and inventory data. Blank MRP records are provided at
the end of this exam.
Master Production Schedule: The following table shows the MPS start quantities.
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
Data Category C D E F
Lot-sizing rule L4L L4L FOQ-250 POQ(P = 2)
Lead-time (wks) 3 1 3 1
Beginning (on-
hand) inventory 50 80 90 30
Scheduled
receipts 80 (wk 1) None 250 (wk 3) 205 (wk 1)
529
Chapter 15 Resource Planning
56. Use the information in Table 15.2. Which one of the following statements about item C is
TRUE?
a. It has a planned receipt of 80 units in week 3.
b. Its second planned order release is for 200 units in week 3.
c. It has a planned receipt of 180 units in week 6.
d. Its first planned order release is for 130 units in week 1.
Answer: b
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: planned, order, release
57. Use the information in Table 15.2. Which one of the following statements on item C is
TRUE?
a. There will be no action notices for item C.
b. There will be exactly one action notice—to release a new order.
c. There will be exactly two action notices—to release a new order and to delay the scheduled
receipt.
d. There will be more than two action notices.
Answer: c
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: action, notice
58. Use the information in Table 15.2. Which one of the following statements about item F is
TRUE?
a. The first planned order release is for 205 units in week 3.
b. Its first planned receipt is for 215 units in week 4.
c. There will be exactly one action notice, which calls for the release of a new order.
d. There will be exactly one action notice, which calls for the delay of the scheduled receipt
until week 2.
Answer: d
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: action, notice
59. Use the information in Table 15.2. Which one of the following statements about item E is
TRUE?
a. There will be an action notice to expedite the scheduled receipt up to week 2.
b. There is a planned receipt of 250 units in week 2.
c. There is one planned receipt for the next 6 weeks.
d. There is a planned order release of 250 units in week 3.
Answer: a
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: action, notice
530
Chapter 15 Resource Planning
Table 15.3
60. Use the information in Table 15.3. Which one of the statements concerning item RST is
TRUE?
a. The first planned receipt occurs in week 5.
b. There is an action notice needed to expedite the schedule receipt by one week.
c. The planned receipt in week 7 is 80 units.
d. There are exactly two planned order releases needed.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, release
61. Use the information in Table 15.3. Which of the statements concerning item RST is TRUE?
(Examine each answer independently.)
a. If the safety stock level were 30 units instead of 0 units, the planned receipt in week 7
would be 110 units.
b. If the scheduled receipt in week 2 were delayed until week 3, there would be a planned
order release in week 1.
c. If the safety stock level were 20 units instead of 0 units, there would be a planned order
release in week 2.
d. If the gross requirements for week 8 were 100 units instead of 60 units, the projected on-
hand inventory for week 8 would be 0 units.
Answer: c
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: planned, release
531
Chapter 15 Resource Planning
532
Chapter 15 Resource Planning
Table 15.4
Scheduled
receipts
Projected
on Hand 40
Planned
receipts
Planned order
releases
63. Use the information from Table 15.4. If an FOQ of 100 units is used, how many planned
order releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release
64. Use the information from Table 15.4. If an FOQ of 75 units is used, how many planned order
releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release
533
Chapter 15 Resource Planning
65. Use the information from Table 15.4. If an L4L lot-sizing rule is used, how many planned
order releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release
66. Use the information from Table 15.4. If a POQ lot-sizing rule is used, where P = 3, how
many planned order releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release
67. Use the information from Table 15.4. Which lot-sizing rule results in the highest average
inventory?
a. FOQ = 100
b. FOQ = 75
c. L4L
d. POQ, P = 3
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing
68. Management wishes to use a POQ lot-sizing rule for an item that experiences an average
demand of 30 units per week. If the desired average lot size is 120 units, what should P be?
a. Zero or one weeks
b. Two or three weeks
c. Four or five weeks
d. More than five weeks
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing, POQ
534
Chapter 15 Resource Planning
69. Management wishes to use an FOQ lot-sizing rule for an item based on the economic order
quantity. If the annual demand is 1,200 units, the holding cost is $10 per unit per year, and
the setup cost is $50 per lot, which one of the following fixed-order quantities is most
appropriate?
a. 90 units
b. 110 units
c. 130 units
d. 150 units
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing, FOQ
70. Use the information in Case Study 15.1. If level-by-level processing is used, what is a correct
order for processing components A, B, C, and D?
a. A B C D
b. D A B C
c. B A D C
d. C B A D
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: order, processing
71. Use the information in Case Study 15.1. If item C has a manufacturing lead-time of two
weeks, and a planned receipt of 65 units is needed in week 4, which of the following
statements is TRUE?
a. The planned order release in week 2 for item C is 130 units.
b. The gross requirements for item B in week 4 is 65 units.
c. The gross requirements for item B in week 2 is 130 units.
d. The gross requirements for item B in week 2 is 65 units.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirements
535
Chapter 15 Resource Planning
Table 15.5
Viola Products produces one item with the following bill of materials.
End Item
Item G (2) Item D (3) Item E (2) Item J (2) Item F (3) Item H (5)
72. Use Table 15.5 to answer this question. How many additional units of D are needed to
produce 20 end items?
a. Fewer than 75
b. More than 75 but fewer than 95
c. More than 95 but fewer than 115
d. More than 115
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
73. Use Table 15.5 to answer this question. How many additional units of J are needed to
produce 20 end items?
a. Fewer than 175
b. More than 175 but fewer than 205
c. More than 205 but fewer than 245
d. More than 245
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
536
Chapter 15 Resource Planning
74. Use Table 15.5 to answer this question. How many additional units of H are needed to
produce 20 end items?
a. Fewer than 250
b. More than 250 but fewer than 350
c. More than 350 but fewer than 450
d. More than 450
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
75. Use Table 15.5 to answer this question. How many additional units of G are needed to
produce 20 end items?
a. Fewer than 50
b. More than 50 but fewer than 60
c. More than 60 but fewer than 70
d. More than 70
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
76. Use Table 15.5 to answer this question. How many additional units of G are needed to
produce seven end items?
a. 0
b. 11
c. 22
d. 33
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
77. Use Table 15.5 to answer this question. How many additional units of H are needed to
produce seven end items?
a. 130
b. 145
c. 160
d. 175
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
537
Chapter 15 Resource Planning
78. Use Table 15.5 to answer this question. How many additional units of J are needed to
produce seven end items?
a. 25
b. 36
c. 47
d. 58
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
79. Use Table 15.5 to answer this question. How many additional units of D are needed to
produce seven end items?
a. 33
b. 30
c. 27
d. 24
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM
80. Which of the following is NOT used to derive an item’s gross requirements?
a. The MPS for immediate parents that are end items
b. The planned order releases for parents below the MPS level
c. The MPS components that are not purchased items
d. Any other requirements not originating in the MPS, such as the demand for replacement
parts
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirements, MRP, explosion, material, planning
81. A computer-generated memo used by inventory planners to make decisions about releasing
new orders and adjusting due dates of scheduled receipts is a(n):
a. enterprise report.
b. infinite capacity.
c. action notice.
d. input–output report.
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: action, notice
538
Chapter 15 Resource Planning
82. A technique used for projecting time-phased capacity requirements for workstations is called:
a. capacity requirements planning.
b. time-adjusted output control.
c. input–output control.
d. work center planning.
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: capacity, requirements, planning
83. Which of the following capabilities would be found in a typical MRP II system?
a. Simulation
b. Counseling
c. Hiring
d. Marketing
Answer: a
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: MRP II, manufacturing, resource, planning
84. Which of the following uses of MRP in promoting a healthy environment is NOT used?
a. An MRP system can track waste in a bill of materials as a component of an item.
b. When the master production schedule is developed for a product, reports can be generated
that project the quantity of waste.
c. When the master production schedule is developed for a product, reports can be generated
that project the timing of waste.
d. The MRP system can be used to communicate directly with the International Organization
for Standardization to file ISO 9000 documentation.
Answer: d
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: MRP, environment
539
Chapter 15 Resource Planning
88. The rope in a drum-buffer-rope system serves to tie the release of:
a. materials directly to the processing rate of the CCR.
b. finished goods directly to the processing rate of the CCR.
c. materials directly to the release of finished goods to the customer.
d. finished goods directly to the shipping buffer.
Answer: a
Reference: Drum-Buffer-Rope
Difficulty: Moderate
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, constraint
540
Chapter 15 Resource Planning
90. In a drum-buffer-rope system, the lot size that moves from one work center to another for
additional processing is a(n):
a. process batch.
b. operations batch.
c. transfer batch.
d. rope batch.
Answer: c
Reference: Drum-Buffer-Rope
Difficulty: Easy
Keywords: DBR, drum, buffer, rope, transfer, batch
93. Which of the following statements about service resource planning is TRUE?
a. The service analogy to the BOM in a manufacturing company is a bill of lading (BOL).
b. One resource that every service provider manages is cash.
c. There is no such thing as dependent demand in the service sector.
d. As services are completed, the accounts receivable decrease.
Answer: b
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: service, resource
541
Chapter 15 Resource Planning
96. The service analogy to the bill of materials in a manufacturing company is the:
a. bill of resources.
b. bill of services.
c. bill of sub-services.
d. bill of tender.
Answer: a
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: BOR, bill, resources
542
Chapter 15 Resource Planning
102. MRP ____________ is a process that converts the requirements of various final
products into a material requirements plan that specifies the replenishment schedule of all the
subassemblies, components, and raw materials needed by the final products.
Answer: explosion
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: explosion, MRP, material, requirements, plan
103. The ____________ is a record of all components of an item, the parent-component
relationships, and usage quantities derived from engineering and process design.
Answer: bill of materials, BOM
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: BOM, bill, materials
104. A(n ) ____________ item has one or more parents but no components.
Answer: purchased
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: purchased, item, component
105. A(n) ____________ is an intermediate item that is assembled from one or more
components.
Answer: subassembly
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: subassembly, intermediate, component
106. ____________ is the degree to which a component has more than one immediate
parent.
Answer: Part commonality
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: part, commonality, component, parent
107. The sums of the quantities in the master production schedule must equal those in the
____________.
Answer: sales and operations plan
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: master, production, schedule, MPS, MRP, material, requirements, plan
543
Chapter 15 Resource Planning
108. A(n) ____________ is a record that divides the future into time periods called time
buckets.
Answer: inventory record
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: inventory, record, time, bucket
109. ____________ are the total demand derived from all parent production plans.
Answer: Gross requirements
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirement, parent
110. ____________ are orders that have been placed but not yet completed.
Answer: Scheduled receipts
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipts, order
111. ____________ is an estimate of the amount of inventory available each week after
gross requirements have been satisfied.
Answer: Projected on-hand inventory
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: inventory, projected, on-hand
112. Waiting time and process time are two components of ____________.
Answer: lead-time
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: waiting, processing, lead, time
113. ____________ is a lot-sizing rule under which the lot size ordered covers the gross
requirements of a single week.
Answer: Lot-for-lot, L4L
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: L4L, lot-for-lot, sizing
114. A(n) ____________ is inventory carried into a week but too small to prevent a
shortage.
Answer: remnant
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: remnant, inventory
115. The lot-for-lot (L4L) rule minimizes inventory investment but it also maximizes the
number of ____________.
Answer: orders, orders placed
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, lot-for-lot, L4L, order
544
Chapter 15 Resource Planning
116. ____________ is a technique used for projecting time-phased capacity requirements for
workstations.
Answer: Capacity requirements planning, CRP
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: CRP, capacity, requirements, planning
117. ____________ ties the basic MRP system to the company’s financial system.
Answer: Manufacturing resource planning, MRP II
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, MRP II, manufacturing, resource
118. ____________ is a planning and control system that regulates the flow of work-in-
process materials at the bottleneck or the capacity constrained resource in a productive
system.
Answer: Drum-buffer-rope (DBR)
Reference: Drum-Buffer-Rope System
Difficulty: Easy
Keywords: drum, buffer, rope, DBR, CCR, bottleneck
119. Every time a manufacturer uses one resource, they make a lot size of 300. Once a group
of 30 units are completed they are taken to the next step in the process. The lot of 300 is the
____________ and the group of 30 is the ____________.
Answer: production batch, transfer batch
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: production, transfer, batch
545
Chapter 15 Resource Planning
SHORT ANSWERS
121. What are the differences and similarities among material requirements planning,
manufacturing resource planning, and enterprise resource planning systems?
Answer: The materials requirement planning (MRP) system can be considered a subset
of the manufacturing resource planning (MRP II) system, containing all of the
production-related capabilities without the tie-in to the company’s financial and other
core and supporting process systems. The MRP II system could be considered a
subset of an enterprise resource planning (ERP) system, containing everything an
ERP system has without the single source of data, streamlined data flows, and
availability of a wealth of real-time information for all employees.
Reference: Multiple Sections
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, input
122. Compare MRP, DBR, and Lean as planning and control systems and propose a new
planning and control system that takes the best elements from each. Which elements from
each do you include and why?
Answer: The authors indicate that MRP is well-suited for products with many levels of
components and more customization. MRP has been around the longest and
explicitly deals with dependent demand, working well when demand is lumpy. DBR
excels when capacity is an important issue in an assemble-to-order or make-to-stock
operation in which volumes are higher and products more standardized. Lean systems
work well with high volumes, line flows, and either a make-to-stock or assemble-to-
order strategy where the manufacturing environment is predictable. Answers will
vary for the integration portion of the question.
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, input
123. What are the key inputs to an MRP system?
Answer: The key inputs are the bill of materials, master production schedule, and
inventory records.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, input
124. Explain the key differences between the FOQ, POQ, and L4L lot-sizing rules.
Answer: A fixed-order-quantity (FOQ) rule maintains the same order quantity each time
an order is issued but varies the time interval between orders. A periodic-order-
quantity (POQ) rule allows a different order quantity to be specified but issues the
order at fixed time intervals. A lot-for-lot (L4L) rule covers the gross requirements of
a single week’s production. POQ and L4L systems avoid remnants and thus have
smaller average inventory than FOQ. Because their average inventory is lower, they
are less able to respond to last-minute changes in customer requests.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: fixed, periodic, order, quantity, lot, sizing
546
Chapter 15 Resource Planning
125. What are two key prerequisites for successful implementation of an MRP system, given
that top management supports the project?
Answer: Key prerequisites include data integrity, BOM structure, magnitude of lot sizes,
and environmental volatility.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, implementation
126. Explain why MRP does a better job of estimating the need to replenish inventory items
than does the fixed-order quantity system in a dependent-demand environment.
Answer: MRP works better for dependent-demand environments because statistical
forecasting for components with lumpy demand results in large forecast errors. It also
provides managers with information useful for planning capacities and estimating
financial requirements, and it automatically updates the demand and inventory-
replenishment schedules of components when the production schedule of parent
items changes.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, lumpy
127. Can MRP be adapted for use in services and, if so, how would it work?
Answer: Service providers must also plan the use of resources and facilitating goods. A
bill of resources (BOR) is a record of all the required materials, equipment, time,
staff, and other resources needed to provide a service, the parent–component
relationships, and the usage quantities. Naturally, the services themselves cannot be
inventoried but must instead be supplied on demand.
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: BOR, bill, resources, facilitating, goods
PROBLEMS
1 2 3 4 5 6 7 8
Gross requirements 90 20 40 60 60
Scheduled receipts 40
Planned receipts
547
Chapter 15 Resource Planning
Answer:
Periods 8
Lot Size
Item Period (P) for POQ 3 (FOQ)
Description Lead Time 2
1 2 3 4 5 6 7 8
Gross requirements 90 20 40 60 60
Scheduled receipts 40
Periods 8
Period (P) for Lot Size
Item POQ (FOQ)
Description Lead Time 1
1 2 3 4 5 6 7 8
Gross requirements 90 20 40 60 60
Scheduled receipts 40
Planned receipts
548
Chapter 15 Resource Planning
Answer:
Periods 8
Period (P) for Lot Size
Item POQ (FOQ)
Description Lead Time 1
1 2 3 4 5 6 7 8
Gross requirements 90 20 40 60 60
Scheduled receipts 40
Planned receipts 20 40 60 60
1 2 3 4 5 6 7 8
Gross requirements 90 20 40 60 60
Planned receipts
549
Chapter 15 Resource Planning
Answer:
Periods 8
Period (P) for Lot Size
Item POQ (FOQ) 100
Description Lead Time 2
1 2 3 4 5 6 7 8
Gross requirements 90 20 40 60 60
1 2 3 4 5 6 7 8
Gross requirements 40 30 30 50 40
Scheduled receipts
Planned receipts
550
Chapter 15 Resource Planning
Answer:
Periods 8
Period (P) for Lot Size
Item POQ (FOQ) 150
Description Lead Time 2
1 2 3 4 5 6 7 8
Gross requirements 40 30 30 50 40
Scheduled receipts
132. Use the bill of materials and inventory records to determine the quantity of
purchased items necessary to assemble 20 end items if the manufacturer uses lot-for-
lot ordering. There are no end items currently on hand.
Component On-hand Component On-hand
A 5 D 15
B 75 E 3
C 10 F 20
END ITEM
A(2) C(2)
551
Chapter 15 Resource Planning
Answer:
20 End Items 40 As less 5 on hand 35 As
35 As 70 Bs
35 As 70 Ds less 15 Ds on hand 55 Ds
Purchased Qty to
Item Order
B 85
D 55
E 27
F 40
133. A company has a standing order for 10 units every other week beginning in week
1. Complete the following MRP schedule if their minimum order is 50 units.
Periods 8
Period (P) for Lot Size
Item POQ (FOQ)
Description Lead Time 2
1 2 3 4 5 6 7 8
Gross requirements 40 30 30 50 40
Scheduled receipts
Planned receipts
552
Chapter 15 Resource Planning
Answer:
Periods 8
Lot Size
Item Period (P) for POQ (FOQ)
Description Lead Time 2
1 2 3 4 5 6 7 8
Gross requirements 40 30 30 50 50
Scheduled receipts 10 10 10 10
Planned receipts 50 50
Bill of Material:
-Item A uses 2 each of component D, 1 each of component C and 2 each of
subassembly B.
-Subassembly B uses 2 each of component E.
553
Chapter 15 Resource Planning
Answer:
Material
Requirements
Planning
Lead Time 1
Safety Stock
1 2 3 4 5 6 7 8 9 10
Gross requirements 40 80 60 40 80
Scheduled receipts 40
Planned receipts 80 60 40 80
554
Chapter 15 Resource Planning
Lot Size
Item C Descr: Period (P) for POQ 3 (FOQ)
Lead Time 2
Safety Stock
1 2 3 4 5 6 7 8 9 10
Gross requirements 20 40 30 20 40
Scheduled receipts
Planned receipts 50 60
Lead Time 1
Safety Stock
1 2 3 4 5 6 7 8 9 10
Gross requirements 40 80 60 40 80
Scheduled receipts
555
Chapter 15 Resource Planning
Lot Size
Item E Descr: Period (P) for POQ (FOQ)
Lead Time 2
Safety Stock
1 2 3 4 5 6 7 8 9 10
135. Consider the process shown that is trying to produce to meet a market demand of 500
units per week.
a. Where should buffers be placed?
b. Which resource is the drum?
c. Where should the rope be placed?
d. Which resource is the bottleneck?
e. Which resource is the CCR?
556
Chapter 15 Resource Planning
Answer:
a. A constraint buffer should be placed between steps 4 and 5 to protect the bottleneck
which is Step 5, Coating. A shipping buffer should be placed at the end of the line,
after Step 6, Inspection.
b. The resource functioning as the drum is the bottleneck, Step 5.
c. The rope should connect Step 1 and Step 5.
d. The bottleneck is Step 5.
e. A CCR exists if the process with the least capacity can still meet market demand,
which is not the case in this scenario.
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: drum, buffer, rope, DBR, CCR, bottleneck
Scheduled
receipts
Projected
on Hand
Planned
receipts
Planned order
releases
557