You are on page 1of 45

Chapter 15  Resource Planning

Chapter

15 Resource Planning

TRUE/FALSE

1. An ERP system revolves around a single comprehensive database that is made available
across the entire organization.
Answer: True
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource, planning, ERP

2. Companies that fully customize their ERP implementation reap the greatest rewards from
such systems since they can continue to use the same processes to which all employees are
accustomed.
Answer: False
Reference: Enterprise Resource Planning
Difficulty: Moderate
Keywords: enterprise, resource, planning, ERP, implementation

3. Material requirements planning (MRP) is a computerized information system developed


specifically to aid in managing dependent demand inventory and scheduling replenishment
orders.
Answer: True
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: material, requirements, planning, MRP

4. A parent is any item manufactured from one or more components.


Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Easy
Keywords: parent, component

5. Dependent demand occurs because the quantity required is a function of the demand for other
items held in inventory.
Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Easy
Keywords: dependent, demand, inventory

513
Chapter 15  Resource Planning

6. A component is an item that may go through one or more operations to be transformed into or
become part of one or more parents.
Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Easy
Keywords: component, parent, transform

7. Lumpy dependent demand can result even from continuous independent demand.
Answer: True
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: lumpy, dependent, demand, continuous

8. Part commonality refers to the degree to which a component has more than one immediate
parent.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: part, commonality, component, parent

9. Part commonality tends to increase inventory costs.


Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: part, commonality, inventory

10. Gross requirements are the total demand derived from all parent production plans.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirements, demand, parent

11. A bill of materials (BOM) shows all of the components of an item, the parent–component
relationships, usage quantities, and lot size derived from engineering and process designs.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: BOM, bill, materials, parent, component

12. An intermediate item must have at least one parent and at least one component.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: intermediate, parent, component

514
Chapter 15  Resource Planning

13. The master production schedule (MPS) is the part of the material-requirements plan that
specifies when components must be ordered or assembled.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: master, production, schedule, MPS, material, requirements, plan

14. Available to promise inventory is the amount of end items that marketing can promise to
customers by a certain date.
Answer: True
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: ATP, available, promise, inventory, MPS

15. The portion of the master production schedule furthest in the future is often frozen to reduce
forecasting requirements.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MPS, master, production, schedule, freezing

16. Planned receipts are estimates of the amount of inventory available each week after gross
requirements have been satisfied.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipts, projected, on-hand, inventory

17. A planned order release provides an indication of when an order for a specified quantity of an
item is to be issued.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release

18. For items manufactured in-house, one component of lead-time is waiting time.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lead, time, waiting

19. Periodic order quantity (POQ) is a rule that tends to keep more inventory on hand than lot-
for-lot quantity, but less inventory on hand than fixed-order quantity.
Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: periodic, fixed, order, quantity, lot, POQ, FOQ, L4L

515
Chapter 15  Resource Planning

20. Lot-for-lot (L4L) is a rule that maintains the same order quantity each time an order is issued.
Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, L4L, order, quantity

21. Data integrity is not vital to successful MRP implementation.


Answer: False
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: data, integrity, MRP, material, requirements, planning

22. MRP II ties MRP to the company’s financial system.


Answer: True
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, MRP II, material, requirements, manufacturing, resource

23. The process with the least capacity is called a capacity constrained resource if its output is
less than market demand.
Answer: False
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, resource

24. A transfer batch combined with a constraint buffer makes a full process batch at a capacity
constrained resource.
Answer: True
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: DBR, CCR, capacity, constrained, resource, process, transfer, batch

25. The bill of resources (BOR) is a record of all the required material, equipment time, staff, and
other resources needed, the parent–component relationships, and the usage quantities.
Answer: True
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: BOR, bill, resources

516
Chapter 15  Resource Planning

MULTIPLE CHOICE

26. A companywide process that cuts across traditional functional areas, business units,
geographic regions, and product lines is a(n):
a. enterprise process.
b. drum-buffer-rope process.
c. kinetic process.
d. full-business process.
Answer: a
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource

27. New information entered in the database of an ERP system is a(n):


a. data packet.
b. transaction.
c. record.
d. file.
Answer: b
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource, planning, transaction, ERP

28. A front-office module for an ERP system includes the:


a. manufacturing component.
b. accounting and finance component.
c. sales and marketing component.
d. human resources component.
Answer: c
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource, planning, ERP, front, office

29. Which of the following is a back-office module in a typical ERP system?


a. Customer service
b. Sales
c. Marketing
d. Human resources
Answer: d
Reference: Enterprise Resource Planning
Difficulty: Easy
Keywords: enterprise, resource, planning, ERP, front, office

517
Chapter 15  Resource Planning

30. Which of the following statements about ERP systems is best?


a. Recent studies have shown that the most successful ERP implementations use
standardized systems.
b. ERP systems written in XML require complete replacements of a company’s legacy
systems.
c. A company must adapt their ERP system to their existing processes in order for all
employees to gain a benefit from the new system.
d. An ERP system requires a regular synchronization of all of the module databases, which
is usually accomplished automatically when the business is not conducting business.
Answer: a
Reference: Enterprise Resource Planning
Difficulty: Moderate
Keywords: enterprise, resource, planning, ERP

31. Which of the following is NOT an example of dependent demand items?


a. Shoelaces, shoes
b. Wheels, car
c. Carafes, coffeemakers
d. Ice skates, roller skates
Answer: d
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: dependent, demand

32. Any item manufactured from one or more components is a(n):


a. parent.
b. component.
c. intermediate item.
d. purchased item.
Answer: a
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: parent, component

33. Which best defines the gross requirements for a component item?
a. The forecasted customer demand for the component
b. The amount of safety stock needed to buffer against uncertainties
c. The sum of gross requirements for all parents of the component
d. The total demand for the component derived from all immediate parents
Answer: d
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: component, parent

518
Chapter 15  Resource Planning

34. MRP can be used to best advantage under which one of the following circumstances?
a. When the item’s demand depends only on customer demand
b. When the item’s demand is uniform
c. When the item’s demand is constant
d. When the item’s demand depends on its parent’s demand
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning

35. Which of the following statements about MRP is TRUE?


a. To be classified as a successful MRP user, a company must use either the L4L or POQ
rules for lot sizing.
b. MRP gross requirements for a parent item are equal to the planned order releases of its
components.
c. MRP logic is based on the logic of uniform, continuous demand, and item independence.
d. MRP gross requirements for a component depend on the planned order releases of its
immediate parents.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, component

36. Which one of the following systems is an input to the MRP system?
a. Shop-floor scheduling system
b. Financial reporting system
c. Master production-scheduling system
d. Purchasing system
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, input

37. If a planned receipt for an item is due in week 6 and the item’s lead-time is two weeks, in
which week will the corresponding planned order release occur?
a. Week 2
b. Week 4
c. Week 6
d. Week 8
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, receipt, release

519
Chapter 15  Resource Planning

38. Which one of the following statements about lot-sizing rules is TRUE?
a. The periodic order quantity (POQ) rule seeks to create inventory remnants.
b. If the POQ rule is used, an item’s lot size can vary each time an order is placed.
c. The lot-for-lot (L4L) rule is a special case of the fixed-order quantity (FOQ) rule.

d. All lot-sizing rules seek to minimize inventory levels.


Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing, POQ, periodic, order

39. Which one of the following is an MRP lot-sizing rule that attempts to minimize the amount of
average inventory?
a. Periodic order quantity (POQ), with P = 2
b. Fixed order quantity (FOQ)
c. Economic order quantity (EOQ)
d. Lot for lot (L4L)
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, L4L, lot

40. MRP explosion means estimating the total number of:


a. subassemblies, components, and raw materials needed for each parent item.
b. raw materials to be purchased from all suppliers.
c. parts to be produced for each parent item.
d. parts needed to be produced less the number of parts on hand for each parent item.
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, explosion

41. Which of the following statements concerning MRP is TRUE?


a. Dependent-demand items tend to experience relatively constant demand rates.
b. MRP systems use independent demands for each component item.
c. Capacity requirements planning (CRP) uses open orders (scheduled receipts) and planned
order releases to estimate capacity requirements for critical workstations.
d. The most accurate way to forecast dependent demand is to examine past usage rates.
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, capacity

520
Chapter 15  Resource Planning

42. Which one of the following is a feature of MRP II, but not available in basic MRP systems?
a. Financial reporting
b. Action notices
c. Dispatch lists
d. Capacity reporting
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, MRP II, resource

43. Which of the following statements about MRP II is TRUE?


a. It is computationally faster than regular MRP.
b. It is limited only to aiding order-launching decisions.
c. It incorporates informal systems through the use of expert systems technology.
d. It provides more extensive information than MRP because it is tied to the company’s
financial system.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP II, manufacturing, resource, planning

44. The Big Mistake Company uses an MRP system. However, the company’s database contains
many inaccuracies. Which type of inaccuracy is most likely to result in incorrect planned
order release quantities for its dependent demand items?
a. Incorrect routings
b. Incorrect bills of materials
c. Incorrect cost and pricing data
d. Incorrect machine capacity data
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: dependent, demand

45. Which one of the following conditions enhances the effectiveness or success in implementing
MRP?
a. Accurate inventory records
b. Small lot sizes
c. Few BOM levels
d. A volatile manufacturing environment
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, implementation

521
Chapter 15  Resource Planning

46. Which of the following statements on MRP is TRUE?


a. The payoffs from MRP tend to be greater when there are more BOM levels and larger lot
sizes.
b. When MRP systems are enhanced to include financial reporting, they are called basic MRP
systems, or “little mrps.”
c. The fixed-order quantity (FOQ) eliminates remnants.
d. MRP is an inventory control system that derives the gross requirements of the end items
from purchase commitments with vendors.
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning

47. Use the following MRP record to answer the question.

ITEM: ABC Lot Size P = 2


Description: Lead Time: 2 weeks

Date 1 2 3 4 5 6 7 8

Gross 30 30 60 75 70
requirements

Scheduled 60
receipts

Projected 0
on Hand

Planned
receipts

Planned order
releases

What are the quantities of planned order releases for item ABC for the first five weeks
(weeks 1, 2, 3, 4, and 5)?
a. 30, 0, 60, 0, 145
b. 60, 0, 145, 0, 0
c. 0, 30, 60, 0, 0
d. 30, 0, 60, 145, 0
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, planned release

522
Chapter 15  Resource Planning

48. Use the following MRP record to answer the question.

ITEM: XYZ Lot Size P = 1


Description: Lead Time: 1 week

Date 1 2 3 4 5 6 7 8

Gross 50 20 30 40 20
requirements

Scheduled 25
receipts

Projected
on Hand 40

Planned
receipts

Planned order
releases

What are the quantities of planned order releases for item XYZ for the first six weeks
(weeks 1, 2, 3, 4, 5, and 6)?
a. 35, 0, 0, 60, 0, 0
b. 35, 0, 60, 0, 0, 0
c. 5, 30, 0, 40, 20, 0
d. 35, 0, 0, 40, 20, 0
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, order, release

523
Chapter 15  Resource Planning

49. Use the following MRP record to answer the following question.

ITEM: XYZ Lot Size P = 2


Description: Lead Time: 1 week

Date 1 2 3 4 5 6 7 8
Gross
requirements 100 50 70 40 90 50

Scheduled 100
receipts

Projected
on Hand 20

Planned
receipts

Planned order
releases

What is the planned order release quantity in week 4?


a. 0 units
b. Greater than 0 units but fewer than or equal to 50 units
c. Greater than 50 units but fewer than or equal to 100 units
d. Greater than 100 units
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, planned, release

524
Chapter 15  Resource Planning

Table 15.1

ITEM: QRS Lot Size P = 2


Description: Lead Time: 3 weeks

Date 1 2 3 4 5 6 7 8
Gross
requirements 40 140 60 40 180 65 90

Scheduled
receipts 200

Projected
on Hand 100

Planned
receipts

Planned order
releases

50. Use the information in Table 15.1. In which week will the second planned order release
occur?
a. Week 1
b. Week 2
c. Week 3
d. Week 4, 5, 6, 7, or 8
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, release
51. Use the information in Table 15.1. If the safety stock level were 30 units instead of 0 units, in
which week would the first planned receipt occur?
a. Week 1
b. Week 2 or 3
c. Week 4 or 5
d. Week 6 or 7
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipt

525
Chapter 15  Resource Planning

52. Use the following MRP record to answer the question.

What will be the projected on-hand inventory quantity in week 7


a. Fewer than or equal to 30 units
b. Greater than 30 units but fewer than or equal to 60 units
c. Greater than 60 units but fewer than or equal to 90 units
d. Greater than 90 units
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: projected, inventory

526
Chapter 15  Resource Planning

53. Use the following MRP record to answer the question.

ITEM: ABC Lot Size P = 2


Description: Lead Time: 2 weeks

Date 1 2 3 4 5 6 7 8
Gross
requirements 60 90 150

Scheduled
receipts 160

Projected
on Hand 0

Planned
receipts

Planned order
releases

What are the quantity and the week of the first planned order release?
a. 20 units; week 1
b. 140 units; week 2
c. 150 units; week 1
d. 150 units: week 2
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, release

527
Chapter 15  Resource Planning

54. Use the following MRP record to answer the question.

ITEM: QRS Lot Size P = 2


Description: Lead Time: 2 weeks

Date 1 2 3 4 5 6 7 8
Gross
requirements 50 100 90 100

Scheduled
receipts 120

Projected
on Hand 20

Planned
receipts

Planned order
releases

Which one of the following statements about item QRS is TRUE?


a. Exactly one action notice is needed.
b. The first planned receipt occurs in week 1.
c. The second planned order release quantity is 90 units.
d. The total planned order release quantity (summing up all eight weeks) is 190 units.
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipt

528
Chapter 15  Resource Planning

55. Use the following MRP record to answer the question.

How many action notices are needed for item A?


a. Zero
b. One
c. Two
d. Three or more
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: action, notice

Table 15.2
Consider the following MPS, BOM, and inventory data. Blank MRP records are provided at
the end of this exam.
Master Production Schedule: The following table shows the MPS start quantities.

Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
Data Category C D E F
Lot-sizing rule L4L L4L FOQ-250 POQ(P = 2)
Lead-time (wks) 3 1 3 1
Beginning (on-
hand) inventory 50 80 90 30
Scheduled
receipts 80 (wk 1) None 250 (wk 3) 205 (wk 1)

529
Chapter 15  Resource Planning

56. Use the information in Table 15.2. Which one of the following statements about item C is
TRUE?
a. It has a planned receipt of 80 units in week 3.
b. Its second planned order release is for 200 units in week 3.
c. It has a planned receipt of 180 units in week 6.
d. Its first planned order release is for 130 units in week 1.
Answer: b
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: planned, order, release

57. Use the information in Table 15.2. Which one of the following statements on item C is
TRUE?
a. There will be no action notices for item C.
b. There will be exactly one action notice—to release a new order.
c. There will be exactly two action notices—to release a new order and to delay the scheduled
receipt.
d. There will be more than two action notices.
Answer: c
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: action, notice

58. Use the information in Table 15.2. Which one of the following statements about item F is
TRUE?
a. The first planned order release is for 205 units in week 3.
b. Its first planned receipt is for 215 units in week 4.
c. There will be exactly one action notice, which calls for the release of a new order.
d. There will be exactly one action notice, which calls for the delay of the scheduled receipt
until week 2.
Answer: d
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: action, notice

59. Use the information in Table 15.2. Which one of the following statements about item E is
TRUE?
a. There will be an action notice to expedite the scheduled receipt up to week 2.
b. There is a planned receipt of 250 units in week 2.
c. There is one planned receipt for the next 6 weeks.
d. There is a planned order release of 250 units in week 3.
Answer: a
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: action, notice

530
Chapter 15  Resource Planning

Table 15.3

60. Use the information in Table 15.3. Which one of the statements concerning item RST is
TRUE?
a. The first planned receipt occurs in week 5.
b. There is an action notice needed to expedite the schedule receipt by one week.
c. The planned receipt in week 7 is 80 units.
d. There are exactly two planned order releases needed.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, release

61. Use the information in Table 15.3. Which of the statements concerning item RST is TRUE?
(Examine each answer independently.)
a. If the safety stock level were 30 units instead of 0 units, the planned receipt in week 7
would be 110 units.
b. If the scheduled receipt in week 2 were delayed until week 3, there would be a planned
order release in week 1.
c. If the safety stock level were 20 units instead of 0 units, there would be a planned order
release in week 2.
d. If the gross requirements for week 8 were 100 units instead of 60 units, the projected on-
hand inventory for week 8 would be 0 units.
Answer: c
Reference: Material Requirements Planning
Difficulty: Hard
Keywords: planned, release

531
Chapter 15  Resource Planning

62. Use the following MRP record to answer the question.

Which one of the statements concerning item LMN is TRUE?


a. There will be exactly two action notices needed.
b. The planned order release quantity in week 4 is 80 units.
c. The planned receipt quantity in week 6 is 30 units.
d. The projected on-hand inventory in week 8 is 70 units.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: projected, inventory, on-hand

532
Chapter 15  Resource Planning

Table 15.4

Item XYZ Lot Size


Description Lead Time: 2 weeks
Date 1 2 3 4 5 6 7 8 9 10
Gross
requirements 25 75 100 75 50

Scheduled
receipts

Projected
on Hand 40

Planned
receipts

Planned order
releases

63. Use the information from Table 15.4. If an FOQ of 100 units is used, how many planned
order releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release

64. Use the information from Table 15.4. If an FOQ of 75 units is used, how many planned order
releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release

533
Chapter 15  Resource Planning

65. Use the information from Table 15.4. If an L4L lot-sizing rule is used, how many planned
order releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release

66. Use the information from Table 15.4. If a POQ lot-sizing rule is used, where P = 3, how
many planned order releases are there for item XYZ?
a. Zero or one
b. Two or three
c. Four or five
d. More than five
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, order, release

67. Use the information from Table 15.4. Which lot-sizing rule results in the highest average
inventory?
a. FOQ = 100
b. FOQ = 75
c. L4L
d. POQ, P = 3
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing

68. Management wishes to use a POQ lot-sizing rule for an item that experiences an average
demand of 30 units per week. If the desired average lot size is 120 units, what should P be?
a. Zero or one weeks
b. Two or three weeks
c. Four or five weeks
d. More than five weeks
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing, POQ

534
Chapter 15  Resource Planning

69. Management wishes to use an FOQ lot-sizing rule for an item based on the economic order
quantity. If the annual demand is 1,200 units, the holding cost is $10 per unit per year, and
the setup cost is $50 per lot, which one of the following fixed-order quantities is most
appropriate?
a. 90 units
b. 110 units
c. 130 units
d. 150 units
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, sizing, FOQ

Case Study 15.1


Sunshine Manufacture produces three products: X, Y, and Z. The production of these end
items is controlled by an MRP system. Each end item X is assembled with two components of
A and one component of B. Each end item of Y is assembled with two components of C and
one component of A. End item Z is assembled from one unit of D and one unit of C; D is
manufactured from one unit of A; and C is manufactured from one unit of B.

70. Use the information in Case Study 15.1. If level-by-level processing is used, what is a correct
order for processing components A, B, C, and D?
a. A B C D
b. D A B C
c. B A D C
d. C B A D
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: order, processing

71. Use the information in Case Study 15.1. If item C has a manufacturing lead-time of two
weeks, and a planned receipt of 65 units is needed in week 4, which of the following
statements is TRUE?
a. The planned order release in week 2 for item C is 130 units.
b. The gross requirements for item B in week 4 is 65 units.
c. The gross requirements for item B in week 2 is 130 units.
d. The gross requirements for item B in week 2 is 65 units.
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirements

535
Chapter 15  Resource Planning

Table 15.5
Viola Products produces one item with the following bill of materials.

End Item

Item C (2) Item A (3) Item B (5)

Item G (2) Item D (3) Item E (2) Item J (2) Item F (3) Item H (5)

A recent check of their inventory reveals the following quantities on hand.


Item Quantity Item Quantity Item Quantity
A 7 D 3 G 22
B 6 E 4 H 15
C 3 F 5 J 11

72. Use Table 15.5 to answer this question. How many additional units of D are needed to
produce 20 end items?
a. Fewer than 75
b. More than 75 but fewer than 95
c. More than 95 but fewer than 115
d. More than 115
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

73. Use Table 15.5 to answer this question. How many additional units of J are needed to
produce 20 end items?
a. Fewer than 175
b. More than 175 but fewer than 205
c. More than 205 but fewer than 245
d. More than 245
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

536
Chapter 15  Resource Planning

74. Use Table 15.5 to answer this question. How many additional units of H are needed to
produce 20 end items?
a. Fewer than 250
b. More than 250 but fewer than 350
c. More than 350 but fewer than 450
d. More than 450
Answer: d
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

75. Use Table 15.5 to answer this question. How many additional units of G are needed to
produce 20 end items?
a. Fewer than 50
b. More than 50 but fewer than 60
c. More than 60 but fewer than 70
d. More than 70
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

76. Use Table 15.5 to answer this question. How many additional units of G are needed to
produce seven end items?
a. 0
b. 11
c. 22
d. 33
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

77. Use Table 15.5 to answer this question. How many additional units of H are needed to
produce seven end items?
a. 130
b. 145
c. 160
d. 175
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

537
Chapter 15  Resource Planning

78. Use Table 15.5 to answer this question. How many additional units of J are needed to
produce seven end items?
a. 25
b. 36
c. 47
d. 58
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

79. Use Table 15.5 to answer this question. How many additional units of D are needed to
produce seven end items?
a. 33
b. 30
c. 27
d. 24
Answer: b
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: bill, materials, BOM

80. Which of the following is NOT used to derive an item’s gross requirements?
a. The MPS for immediate parents that are end items
b. The planned order releases for parents below the MPS level
c. The MPS components that are not purchased items
d. Any other requirements not originating in the MPS, such as the demand for replacement
parts
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirements, MRP, explosion, material, planning

81. A computer-generated memo used by inventory planners to make decisions about releasing
new orders and adjusting due dates of scheduled receipts is a(n):
a. enterprise report.
b. infinite capacity.
c. action notice.
d. input–output report.
Answer: c
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: action, notice

538
Chapter 15  Resource Planning

82. A technique used for projecting time-phased capacity requirements for workstations is called:
a. capacity requirements planning.
b. time-adjusted output control.
c. input–output control.
d. work center planning.
Answer: a
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: capacity, requirements, planning

83. Which of the following capabilities would be found in a typical MRP II system?
a. Simulation
b. Counseling
c. Hiring
d. Marketing
Answer: a
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: MRP II, manufacturing, resource, planning

84. Which of the following uses of MRP in promoting a healthy environment is NOT used?
a. An MRP system can track waste in a bill of materials as a component of an item.
b. When the master production schedule is developed for a product, reports can be generated
that project the quantity of waste.
c. When the master production schedule is developed for a product, reports can be generated
that project the timing of waste.
d. The MRP system can be used to communicate directly with the International Organization
for Standardization to file ISO 9000 documentation.
Answer: d
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: MRP, environment

85. The capacity constrained resource schedule is called the:


a. rope.
b. drum.
c. buffer.
d. TOC.
Answer: b
Reference: Drum-Buffer-Rope
Difficulty: Easy
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, constraint

539
Chapter 15  Resource Planning

86. The purpose of the drum-buffer-rope system is to:


a. maximize the use of every productive resource in the system.
b. balance the capacity of every productive resource in the system.
c. regulate the flow of materials at the capacity constrained resource.
d. increase the flow of materials through the entire system in excess of market demand.
Answer: c
Reference: Drum-Buffer-Rope
Difficulty: Moderate
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, constraint

87. The buffer in a drum-buffer-rope system is placed immediately:


a. before materials are released to the production floor.
b. after the capacity constrained resource.
c. after materials are shipped to the customer.
d. before the capacity constrained resource.
Answer: d
Reference: Drum-Buffer-Rope
Difficulty: Moderate
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, constraint

88. The rope in a drum-buffer-rope system serves to tie the release of:
a. materials directly to the processing rate of the CCR.
b. finished goods directly to the processing rate of the CCR.
c. materials directly to the release of finished goods to the customer.
d. finished goods directly to the shipping buffer.
Answer: a
Reference: Drum-Buffer-Rope
Difficulty: Moderate
Keywords: DBR, drum, buffer, rope, CCR, capacity, constrained, constraint

89. Which of these statements comparing DBR and MRP is best?


a. The master production scheduling and component scheduling processes take place
simultaneously in both systems.
b. Both MRP and DBR can use lot-for-lot batch sizes everywhere but at the bottleneck.
c. Both MRP and DBR focus their scheduling efforts on one resource, the bottleneck.
d. Factories managed with DBR have a bottleneck or capacity constrained resource but
factories managed with MRP do not.
Answer: b
Reference: Drum-Buffer-Rope
Difficulty: Hard
Keywords: DBR, drum, buffer, rope, lot-for-lot, L4L, bottleneck, MRP

540
Chapter 15  Resource Planning

90. In a drum-buffer-rope system, the lot size that moves from one work center to another for
additional processing is a(n):
a. process batch.
b. operations batch.
c. transfer batch.
d. rope batch.
Answer: c
Reference: Drum-Buffer-Rope
Difficulty: Easy
Keywords: DBR, drum, buffer, rope, transfer, batch

91. The process batch at the constraint in a drum-buffer-rope system should:


a. be the same size as that at any non-constraint.
b. be the same size as the transfer batch.
c. be of such a size as to maximize the number of setups for the constraint
d. be of such a size as to improve utilization of the constraint.
Answer: d
Reference: Drum-Buffer-Rope
Difficulty: Easy
Keywords: DBR, drum, buffer, rope, process, batch, size

92. In terms of resource planning, service goods must focus on maintaining:


a. dependent demand levels at a maximum.
b. capacity to serve customers.
c. off-line resources in order to serve customers.
d. independent demand resources at a maximum.
Answer: b
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: service, resource, capacity, planning

93. Which of the following statements about service resource planning is TRUE?
a. The service analogy to the BOM in a manufacturing company is a bill of lading (BOL).
b. One resource that every service provider manages is cash.
c. There is no such thing as dependent demand in the service sector.
d. As services are completed, the accounts receivable decrease.
Answer: b
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: service, resource

94. An example of a dependent demand item in a service is a:


a. menu in a restaurant.
b. jukebox in a club.
c. operating suite at a hospital.
d. a pilot’s checklist for an airline.
Answer: c
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: dependent, demand, service

541
Chapter 15  Resource Planning

95. Facilitating goods in a hotel’s bill of resources would include:


a. a housekeeper.
b. a fax machine.
c. a towel.
d. a front-desk clerk.
Answer: c
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: facilitating, goods, BOR, bill, resources

96. The service analogy to the bill of materials in a manufacturing company is the:
a. bill of resources.
b. bill of services.
c. bill of sub-services.
d. bill of tender.
Answer: a
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: BOR, bill, resources

FILL IN THE BLANK


97. A companywide process that cuts across functional areas, business units, geographic regions,
and product lines is a(n) ____________.
Answer: enterprise process
Reference: Enterprise Resource Planning
Difficulty: Moderate
Keywords: enterprise, resource, process, planning
98. XML based ERP systems have a high degree of ____________, the ability of one piece of
software to interact with others.
Answer: interoperability
Reference: Enterprise Resource Planning
Difficulty: Moderate
Keywords: enterprise, resource, planning, ERP, software, interoperability
99. In MRP, a(n) ____________ is any item manufactured from one or more components.
Answer: parent
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: parent, component
100. In MRP, a(n) ____________ is an item that may go through one or more operations to
be transformed into or become part of one or more parents.
Answer: component
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: component, parent

542
Chapter 15  Resource Planning

101. ____________ is a computerized information system developed specifically to aid in


managing dependent-demand inventory and scheduling-replenishment orders.
Answer: MRP, material requirements planning
Reference: Material Requirements Planning
Difficulty: Easy
Keywords: MRP, material, requirements, plan, dependent, demand

102. MRP ____________ is a process that converts the requirements of various final
products into a material requirements plan that specifies the replenishment schedule of all the
subassemblies, components, and raw materials needed by the final products.
Answer: explosion
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: explosion, MRP, material, requirements, plan
103. The ____________ is a record of all components of an item, the parent-component
relationships, and usage quantities derived from engineering and process design.
Answer: bill of materials, BOM
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: BOM, bill, materials
104. A(n ) ____________ item has one or more parents but no components.
Answer: purchased
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: purchased, item, component
105. A(n) ____________ is an intermediate item that is assembled from one or more
components.
Answer: subassembly
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: subassembly, intermediate, component
106. ____________ is the degree to which a component has more than one immediate
parent.
Answer: Part commonality
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: part, commonality, component, parent
107. The sums of the quantities in the master production schedule must equal those in the
____________.
Answer: sales and operations plan
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: master, production, schedule, MPS, MRP, material, requirements, plan

543
Chapter 15  Resource Planning

108. A(n) ____________ is a record that divides the future into time periods called time
buckets.
Answer: inventory record
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: inventory, record, time, bucket
109. ____________ are the total demand derived from all parent production plans.
Answer: Gross requirements
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: gross, requirement, parent
110. ____________ are orders that have been placed but not yet completed.
Answer: Scheduled receipts
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: planned, receipts, order
111. ____________ is an estimate of the amount of inventory available each week after
gross requirements have been satisfied.
Answer: Projected on-hand inventory
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: inventory, projected, on-hand
112. Waiting time and process time are two components of ____________.
Answer: lead-time
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: waiting, processing, lead, time
113. ____________ is a lot-sizing rule under which the lot size ordered covers the gross
requirements of a single week.
Answer: Lot-for-lot, L4L
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: L4L, lot-for-lot, sizing
114. A(n) ____________ is inventory carried into a week but too small to prevent a
shortage.
Answer: remnant
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: remnant, inventory
115. The lot-for-lot (L4L) rule minimizes inventory investment but it also maximizes the
number of ____________.
Answer: orders, orders placed
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: lot, lot-for-lot, L4L, order

544
Chapter 15  Resource Planning

116. ____________ is a technique used for projecting time-phased capacity requirements for
workstations.
Answer: Capacity requirements planning, CRP
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: CRP, capacity, requirements, planning
117. ____________ ties the basic MRP system to the company’s financial system.
Answer: Manufacturing resource planning, MRP II
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, MRP II, manufacturing, resource

118. ____________ is a planning and control system that regulates the flow of work-in-
process materials at the bottleneck or the capacity constrained resource in a productive
system.
Answer: Drum-buffer-rope (DBR)
Reference: Drum-Buffer-Rope System
Difficulty: Easy
Keywords: drum, buffer, rope, DBR, CCR, bottleneck

119. Every time a manufacturer uses one resource, they make a lot size of 300. Once a group
of 30 units are completed they are taken to the next step in the process. The lot of 300 is the
____________ and the group of 30 is the ____________.
Answer: production batch, transfer batch
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: production, transfer, batch

120. A(n) ____________ is a record of a service firm’s parent-component relationships all of


the materials, equipment, time, staff, and other productive assets associated with them,
including usage quantities.
Answer: bill of resources
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: resource, planning, service, bill

545
Chapter 15  Resource Planning

SHORT ANSWERS

121. What are the differences and similarities among material requirements planning,
manufacturing resource planning, and enterprise resource planning systems?
Answer: The materials requirement planning (MRP) system can be considered a subset
of the manufacturing resource planning (MRP II) system, containing all of the
production-related capabilities without the tie-in to the company’s financial and other
core and supporting process systems. The MRP II system could be considered a
subset of an enterprise resource planning (ERP) system, containing everything an
ERP system has without the single source of data, streamlined data flows, and
availability of a wealth of real-time information for all employees.
Reference: Multiple Sections
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, input
122. Compare MRP, DBR, and Lean as planning and control systems and propose a new
planning and control system that takes the best elements from each. Which elements from
each do you include and why?
Answer: The authors indicate that MRP is well-suited for products with many levels of
components and more customization. MRP has been around the longest and
explicitly deals with dependent demand, working well when demand is lumpy. DBR
excels when capacity is an important issue in an assemble-to-order or make-to-stock
operation in which volumes are higher and products more standardized. Lean systems
work well with high volumes, line flows, and either a make-to-stock or assemble-to-
order strategy where the manufacturing environment is predictable. Answers will
vary for the integration portion of the question.
Reference: Planning and Control Systems for Manufacturers
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, input
123. What are the key inputs to an MRP system?
Answer: The key inputs are the bill of materials, master production schedule, and
inventory records.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, input
124. Explain the key differences between the FOQ, POQ, and L4L lot-sizing rules.
Answer: A fixed-order-quantity (FOQ) rule maintains the same order quantity each time
an order is issued but varies the time interval between orders. A periodic-order-
quantity (POQ) rule allows a different order quantity to be specified but issues the
order at fixed time intervals. A lot-for-lot (L4L) rule covers the gross requirements of
a single week’s production. POQ and L4L systems avoid remnants and thus have
smaller average inventory than FOQ. Because their average inventory is lower, they
are less able to respond to last-minute changes in customer requests.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: fixed, periodic, order, quantity, lot, sizing

546
Chapter 15  Resource Planning

125. What are two key prerequisites for successful implementation of an MRP system, given
that top management supports the project?
Answer: Key prerequisites include data integrity, BOM structure, magnitude of lot sizes,
and environmental volatility.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, implementation
126. Explain why MRP does a better job of estimating the need to replenish inventory items
than does the fixed-order quantity system in a dependent-demand environment.
Answer: MRP works better for dependent-demand environments because statistical
forecasting for components with lumpy demand results in large forecast errors. It also
provides managers with information useful for planning capacities and estimating
financial requirements, and it automatically updates the demand and inventory-
replenishment schedules of components when the production schedule of parent
items changes.
Reference: Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, plan, lumpy
127. Can MRP be adapted for use in services and, if so, how would it work?
Answer: Service providers must also plan the use of resources and facilitating goods. A
bill of resources (BOR) is a record of all the required materials, equipment, time,
staff, and other resources needed to provide a service, the parent–component
relationships, and the usage quantities. Naturally, the services themselves cannot be
inventoried but must instead be supplied on demand.
Reference: Resource Planning for Service Providers
Difficulty: Moderate
Keywords: BOR, bill, resources, facilitating, goods

PROBLEMS

128. Complete the following MRP schedule:


Periods 8
Lot Size
Item Period (P) for POQ 3 (FOQ)
Description Lead-Time 2

1 2 3 4 5 6 7 8

Gross requirements 90 20 40 60 60

Scheduled receipts 40

Projected on-hand inventory 50

Planned receipts

Planned order releases

547
Chapter 15  Resource Planning

Answer:

Periods 8
Lot Size
Item Period (P) for POQ 3 (FOQ)
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 90 20 40 60 60

Scheduled receipts 40

Projected on-hand inventory 50 40 60 60

Planned receipts 60 120

Planned order releases 60 120


Reference: Output from Material Requirements Planning
Difficulty: Moderate
Keywords: POQ, periodic, order, quantity

129. Complete the following MRP schedule using L4L:

Periods 8
Period (P) for Lot Size
Item POQ (FOQ)
Description Lead Time 1

1 2 3 4 5 6 7 8

Gross requirements 90 20 40 60 60

Scheduled receipts 40

Projected on-hand inventory 50

Planned receipts

Planned order releases

548
Chapter 15  Resource Planning

Answer:

Periods 8
Period (P) for Lot Size
Item POQ (FOQ)
Description Lead Time 1

1 2 3 4 5 6 7 8

Gross requirements 90 20 40 60 60

Scheduled receipts 40

Projected on-hand inventory 50 0 0 0

Planned receipts 20 40 60 60

Planned order releases 20 40 60 60


Reference: Output from Material Requirements Planning
Difficulty: Moderate
Keywords: POQ, periodic, order, quantity

130. Complete the following MRP schedule:


Periods 8
Period (P) for Lot Size
Item POQ (FOQ) 100
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 90 20 40 60 60

Scheduled receipts 100

Projected on-hand inventory 50

Planned receipts

Planned order releases

549
Chapter 15  Resource Planning

Answer:

Periods 8
Period (P) for Lot Size
Item POQ (FOQ) 100
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 90 20 40 60 60

Scheduled receipts 100

Projected on-hand inventory 50 60 60 40 40 40 80

Planned receipts 100 100

Planned order releases 100 100


Reference: Output from Material Requirements Planning
Difficulty: Moderate
Keywords: FOQ, fixed, order, quantity

131. Complete the following MRP schedule:


Periods 8
Period (P) for Lot Size
Item POQ (FOQ) 150
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 40 30 30 50 40

Scheduled receipts

Projected on-hand inventory 60

Planned receipts

Planned order releases

550
Chapter 15  Resource Planning

Answer:

Periods 8
Period (P) for Lot Size
Item POQ (FOQ) 150
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 40 30 30 50 40

Scheduled receipts

Projected on-hand inventory 60 20 20 140 110 110 60 60 20

Planned receipts 150

Planned order releases 150


Reference: Output from Material Requirements Planning
Difficulty: Moderate
Keywords: MRP, material, requirements, planning, FOQ, fixed, order, quantity

132. Use the bill of materials and inventory records to determine the quantity of
purchased items necessary to assemble 20 end items if the manufacturer uses lot-for-
lot ordering. There are no end items currently on hand.
Component On-hand Component On-hand
A 5 D 15
B 75 E 3
C 10 F 20

END ITEM

A(2) C(2)

B(2) D(2) E(1) F(2) B(3)

551
Chapter 15  Resource Planning

Answer:
20 End Items  40 As less 5 on hand  35 As
35 As  70 Bs
35 As  70 Ds less 15 Ds on hand  55 Ds

20 End Items  40 Cs less 10 on hand  30 Cs


30 Cs  30 Es less 3 on hand  27Es
30 Cs  60 Fs less 20 on hand  40 Fs
30 Cs  90 Bs

90 Bs + 70 Bs  160 Bs less 75 on hand  85 Bs

Purchased Qty to
Item Order
B 85
D 55
E 27
F 40

Reference: Output from Material Requirements Planning


Difficulty: Moderate
Keywords: BOM, inventory, record, bill, materials

133. A company has a standing order for 10 units every other week beginning in week
1. Complete the following MRP schedule if their minimum order is 50 units.
Periods 8
Period (P) for Lot Size
Item POQ (FOQ)
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 40 30 30 50 40

Scheduled receipts

Projected on-hand inventory 60

Planned receipts

Planned order releases

552
Chapter 15  Resource Planning

Answer:
Periods 8
Lot Size
Item Period (P) for POQ (FOQ)
Description Lead Time 2

1 2 3 4 5 6 7 8

Gross requirements 40 30 30 50 50

Scheduled receipts 10 10 10 10

Projected on-hand inventory 60 30 30 10 30 40 40 50 0

Planned receipts 50 50

Planned order releases 50 50


Reference: Output from Material Requirements Planning
Difficulty: Moderate
Keywords: L4L, lot, MRP, material, requirements, planning

134. Consider the MPS, BOM, and inventory data shown.


Master Production Schedule: The following table shows the MPS start quantities.
Finished Item
A 1 2 3 4 5 6 7 8

Finished Item A MPS Start 20 40 30 20 40

Bill of Material:
-Item A uses 2 each of component D, 1 each of component C and 2 each of
subassembly B.
-Subassembly B uses 2 each of component E.

Selected Inventory Data:

Item Lot Size Technique Lead Time Scheduled Receipts On-Hand


B L4L 1 40 in period 1
C POQ=3 2 40
D FOQ=250 1 100
E L4L 2 160 in period 2

Construct the MRP schedule using the preceding information.

553
Chapter 15  Resource Planning

Answer:

Material
Requirements
Planning

Period (P) for Lot Size


Item B Descr: POQ (FOQ)

Lead Time 1
Safety Stock

Usage Quantity for Item: A 2

1 2 3 4 5 6 7 8 9 10

Gross requirements 40 80 60 40 80

Scheduled receipts 40

Projected on-hand inventory

Planned receipts 80 60 40 80

Planned order releases 80 60 40 80

554
Chapter 15  Resource Planning

Lot Size
Item C Descr: Period (P) for POQ 3 (FOQ)

Lead Time 2
Safety Stock

Usage Quantity for Item: A 1 B

1 2 3 4 5 6 7 8 9 10

Gross requirements 20 40 30 20 40

Scheduled receipts

Projected on-hand inventory 40 20 20 30 40 40

Planned receipts 50 60

Planned order releases 50 60

Lot Size 250


Item D Descr: Period (P) for POQ (FOQ)

Lead Time 1
Safety Stock

Usage Quantity for Item: A 2 B 0 C

1 2 3 4 5 6 7 8 9 10

Gross requirements 40 80 60 40 80

Scheduled receipts

Projected on-hand inventory 100 60 60 230 170 170 130 130 50 50 50

Planned receipts 250

Planned order releases 0 250

555
Chapter 15  Resource Planning

Lot Size
Item E Descr: Period (P) for POQ (FOQ)

Lead Time 2
Safety Stock

Usage Quantity for Item: A B 2 C D

1 2 3 4 5 6 7 8 9 10

Gross requirements 160 120 80 160

Scheduled receipts 160

Projected on-hand inventory

Planned receipts 120 80 160

Planned order releases 120 80 160

Reference: Output from Material Requirements Planning


Difficulty: Hard
Keywords: MRP, material, requirements, plan, lot, L4L, FOQ, POQ, periodic, order,
fixed

135. Consider the process shown that is trying to produce to meet a market demand of 500
units per week.
a. Where should buffers be placed?
b. Which resource is the drum?
c. Where should the rope be placed?
d. Which resource is the bottleneck?
e. Which resource is the CCR?

Step 1: Material release schedule


Step 2: Drilling (capacity is 500 units/week)
Step 3: Tapping (capacity is 450 units/week)
Step 4: Grinding (capacity is 600 units/week)
Step 5: Coating (capacity is 400 units/week)
Step 6: Inspection (capacity is 1000 units/week)

Step 1 Step 2 Step 3 Step 4 Step 5 Step 6

556
Chapter 15  Resource Planning

Answer:
a. A constraint buffer should be placed between steps 4 and 5 to protect the bottleneck
which is Step 5, Coating. A shipping buffer should be placed at the end of the line,
after Step 6, Inspection.
b. The resource functioning as the drum is the bottleneck, Step 5.
c. The rope should connect Step 1 and Step 5.
d. The bottleneck is Step 5.
e. A CCR exists if the process with the least capacity can still meet market demand,
which is not the case in this scenario.
Reference: Drum-Buffer-Rope System
Difficulty: Moderate
Keywords: drum, buffer, rope, DBR, CCR, bottleneck

Blank MRP Record

Item Lot Size


Description Lead Time:
Date 1 2 3 4 5 6 7 8 9 10
Gross
requirements

Scheduled
receipts

Projected
on Hand

Planned
receipts

Planned order
releases

557

You might also like