Professional Documents
Culture Documents
1
Materials requirements planning (MRP)
Materials requirements planning (MRP) is the logic for
determining the number of parts, components, and materials
needed to produce a product.
The MRP is designed to answer three questions:
What is needed?
How much is needed?
When is it needed?
MRP provides time scheduling information specifying when
each of the materials, parts, and components should be ordered
or produced.
Dependent demand drives MRP. 2
What MRP does?
3
Independent and Dependent Demand
4
Independent demand:
..
5
Dependent demand:
Demand for items are directly related to demand of other
product(component, RW, subassemblies)
Requirements are derived from delivery schedules of end items
So MRP is appropriate to control inventories of
RW
components parts
Subassemblies
WIP
E.g. demand for a tyre is dependent demand
6
CONT..
Effective use of dependent demand inventory models
requires the following
1. Master production schedule
2. Specifications or bill of material
3. Inventory availability
4. Purchase orders outstanding
5. Lead times
7
Lead Times
8
MRP Inputs
10
Benefits of MRP
Increased customer satisfaction due to meeting
delivery schedules
Faster response to market changes
Improved labor & equipment utilization
Better inventory planning and scheduling
Reduced inventory levels without reduced
customer service
11
MPS
MPS, which derived from aggregate production
plan, is a schedule for specific end items. But
MRP is a computational technique that converts
the MPS for end products into a detailed
schedule for the raw materials and components
used in the end products.
MRP determine quantity and timing of
dependent demand items.
12
Cont..
Management Engineering
Return on Aggregate Design
investment production plan completion
Capital
Change
production
Master production plan?
schedule
13
Types of Variables or Data:
Master production
schedule Change
master
Change production
requirements? Material requirements schedule?
plan
Change capacity?
Capacity requirements
plan
No Is execution
Realistic? meeting the
plan?
Yes
Execute capacity plans
Execute
material plans 14
MPS Can be expressed in any of the following
terms:
A customer order in a job shop (make-to-order)
company
(assemble-to-order or forecast) company
An end item in a continuous (stock-to-forecast)
company
15
MPS
17
Cont..
18
Bills of Material:
a listing of all of the raw materials, parts, subassemblies,
and assemblies needed to produce one unit of a product.
Each finished product has its own bill of materials.
Provides product structure: Visual depiction of the
requirements in a bill of materials, where all
components are listed by levels.
Items above given level are called parents
Items below given level are called children
19
Cont..
21
Lead Times
The time required to purchase, produce, or assemble
an item is called LT.
For production – the sum of the order, wait, move,
setup, store, and run times is TL
For purchased items – the time between the
recognition of a need and the availability of the item
for production is also LT
22
MRP Processing
Processes the following for each time period:
Gross requirements: Total expected demand
Scheduled receipts: Open orders scheduled to arrive
Projected on hand: Expected inventory on hand at the
beginning of each time period
Net requirements: Actual amount needed in each time period
Planned-order releases: Planned amount to be ordered in
each time period
Planned-order receipts: Quantity expected to be received at
the beginning of the period
23
Basic MRP logic
Input MPS, BOM, inventory status, LT
Do parts explosion
Offset requirements by LT
Netting of requirements from gross by
considering availabilities.
Lot sizing of net requirements for procurement of
production
24
Example
26
EXAMPLES
Component On hand
B 4
C 10
D 8
E 60
27
Cont..
28
Cont..
29
Format of MRP
30
e.g.
Consider the two product structure trees shown below:
A. Develop a MRP for item D. Given that the master schedule calls for 80
units of A in week 4 and 50 units of C in week 5.
B. There’s a beg. inv. of 110 units on hand and all items have lead times of
one week.
31
Solution
32
Cont..
33
Have =110
34
If a shutter has 100 at week 4 and 150 at week 8 is
needed, develop MRP with LT 1Weeks for shutter and 2
weeks for frames and 1 week for wood
70 scheduled receipt at week 1 of wood
Shutter
Wood
Frames (2)
sections (4)
35
solution
36
E.g.
Lead Times
A A 1 day
B 2 days
C 1 day
2 1
B(4) C(2) D 3 days
E 4 days
F 1 day
3 4 3 1
D(2) E(1) D(3) F(2) Demand
Day 10 50 A
Day 8 20 B (Spares)
Day 6 15 D (Spares)
39
Cont..
40
e.g.
X
Item On-Hand Lead Time (Weeks)
X 50 2
A(2) B(1) A 75 3
B 25 1
C 10 2
C(3) C(2) D(5) D 20 2
Requirements
Requirementsinclude
include95
95units
units(80
(80firm
firmorders
ordersand
and15
15forecast)
forecast)of
ofXX
in
inweek
week10
10
41
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
ItIttakes
takes22 LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
A’s
A’sforfor On- Net requirements 20
hand Planned order receipt 20
each
eachXX 25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80 42
43
44
45
46
Exercise
47
Lot-Sizing Techniques
48
e.g.
If beginning inventory of an item is =35
LT= 1 , Co= $ 100/yr, Cc=$1/week determine
MRP of the following.
49
Lot-for-Lot Example
50
51
52
53
EXAMPLES
beg. Inv. 25 data's are per week
54
MRP Output
Primary Reports
Planned Orders – schedule indicating the amount and timing of future
orders
Order Releases – Authorization for the execution of planned orders
Changes – revisions of due dates or order quantities, or cancellation of
orders
Secondary Reports
Performance-control reports – Evaluation of system operation, including
deviations from plans and cost information
Planning reports – Data useful for assessing future material requirements
Exception Reports – Data on major discrepancies encountered
55
Capacity planning
Capacity is the ability of resources (such as people,
machine, etc.) to serve customers, process information or
make products with the expression of ‘how much’ and ‘how
well’ the machine or the people produces.
Unit of measurement
For line and continuous processing (such as oil refinery)
since the machine makes the product and people support the
machine, the unit of measurement is the quantity per hours.
56
Types of capacity
1. Design capacity
Maximum obtainable output
2.Effective capacity, expected variations
Maximum capacity subject to planned and expected variations
such as maintenance, coffee breaks, scheduling conflicts.
3.Actual output
Rate of output actually achieved cannot exceed effective capacity.
It is subject to random disruptions: machine break down,
absenteeism, material shortages and most importantly the
demand.
57
Material Requirements Planning II
Initiates the idea of extending the value stream through
manufacturing and shipping process. That extension brings
production planning, machine capacity scheduling, demand
forecasting.
Labor hours
Material costs
Capital costs
Virtually any
resource
System is generally called MRP II or Material Resource
Planning
58
Cont..
59
MRP II
Market Master
Finance Manufacturing
Demand production schedule
Rough-cut Capacity
capacity planning planning
Adjust
production plan
Yes No Requirements No Yes
Problems? schedules Problems?
60
MRP in Services
61
Enterprise Resource Planning (ERP)
62
Cont…
64
Typical ERP System
65
Advantages of ERP Systems
67
End of Chapter Two
Thanks a lot !!
68