Professional Documents
Culture Documents
DEP 31.40.11.32-Gen.
September 2011
ECCN EAR 99
This document contains information that is classified as EAR99 and, as a consequence, can neither be exported nor re-exported to any country which is under an
embargo of the U.S. government pursuant to Part 746 of the Export Administration Regulations (15 C.F.R. Parts 746) nor can be made available to any national of such
country. In addition, the information in this document cannot be exported nor re-exported to an end-user or for an end-use that is prohibited by Part 744 of the Export
Administration Regulations (15 C.F.R. Parts 744).
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 2
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global
Solutions International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference
international, regional, national and industry standards.
The objective is to set the recommended standard for good design and engineering practice to be applied by Shell
companies in oil and gas production, oil refining, gas handling, gasification, chemical processing, or any other such
facility, and thereby to help achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at
each locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by
these Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part
of a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI
disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or
person whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination
of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell
Company. The benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies
affiliated to these companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and
the DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be
returned after use, including any copies which shall only be made by users with the express prior written consent of
Shell GSI. The copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe
custody and Shell GSI may at any time require information satisfactory to them in order to ascertain how users
implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 3
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................5
1.1 SCOPE........................................................................................................................5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS .........5
1.3 DEFINITIONS .............................................................................................................5
1.4 CROSS-REFERENCES .............................................................................................7
1.5 SUMMARY OF MAIN CHANGES...............................................................................7
1.6 COMMENTS ON THIS DEP .......................................................................................7
2. GENERAL REQUIREMENTS ....................................................................................8
3 GEODETIC CONTROL ..............................................................................................9
3.1 HORIZONTAL DATUM AND PROJECTIONS............................................................9
3.2 VERTICAL DATUM.....................................................................................................9
3.3 TIME DATUM..............................................................................................................9
4 SURVEY EQUIPMENT.............................................................................................10
4.1 SURFACE POSITIONING – DGNSS .......................................................................10
4.2 TOUCHDOWN MONITORING .................................................................................10
4.3 SUBSEA ACOUSTIC POSITIONING – ULTRA SHORT BASELINE SYSTEM.......10
4.4 SUBSEA ACOUSTIC POSITIONING – LONG BASELINE SYSTEM ......................10
4.5 SUBSEA MEASUREMENTS – ATTITUDE / ORIENTATION / HEIGHT..................11
5 PERSONNEL............................................................................................................13
5.1 GENERAL .................................................................................................................13
5.2 SURVEY OPERATIONS MANAGER .......................................................................13
5.3 SURVEY PROJECT MANAGER ..............................................................................13
5.4 PARTY CHIEF/SENIOR SURVEYOR ......................................................................13
5.5 SURVEY ENGINEER ...............................................................................................13
5.6 ONLINE SURVEYOR ...............................................................................................14
6 PRE-LAY SURVEY ..................................................................................................15
7 AS-LAID SURVEY....................................................................................................16
8 EVENTING................................................................................................................18
8.1 FIELD JOINTS ..........................................................................................................18
8.2 PIPELINE CROSSINGS ...........................................................................................18
8.3 PIPELINE LATERAL BUCKLE TRIGGERS .............................................................19
8.4 ANODES ...................................................................................................................19
8.5 BUCKLE ARRESTORS ............................................................................................20
8.6 WEIGHT COAT.........................................................................................................20
8.7 GENERAL PIPELINE DAMAGE ...............................................................................21
8.8 FREE SPANS ...........................................................................................................21
8.9 PIPELINE BURIAL....................................................................................................21
8.10 DEBRIS.....................................................................................................................23
8.11 CATHODIC PROTECTION VALUES .......................................................................23
9 AS-TRENCHED AND AS-BUILT SURVEYS...........................................................24
9.1 AS-TRENCHED SURVEY ........................................................................................24
9.2 AS-BUILT SURVEYS................................................................................................24
10 DELIVERABLES ......................................................................................................25
10.1 CHARTING ...............................................................................................................25
10.2 REPORTING.............................................................................................................25
10.3 DIGITAL PIPELINE AS-BUILT POSITION DATA.....................................................26
11 REFERENCES .........................................................................................................27
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 4
APPENDICES
APPENDIX A USBL ACOUSTIC POSITIONING ...................................................................28
APPENDIX B GYROCOMPASS ............................................................................................30
APPENDIX C DGNSS HEALTH CHECK ...............................................................................32
APPENDIX D MEASUREMENT ACCURACY & INSTALLATION TOLERANCE ..................34
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 5
1. INTRODUCTION
1.1 SCOPE
This DEP specifies requirements and gives recommendations for surveys in support of
pipeline construction, including at what stages they are to be performed, for what purpose,
and by what means. It also includes the requirements for pre-lay surveys. Principal may
elect to use portions of this DEP for specific in-service pipeline surveys, see (8).
This DEP precludes the early stage activity requirements prior to pre-lay survey, such as
pre-planning, desktop studies, scouting, archaeological and pipeline route surveys
(geophysical and geotechnical samplings) to determine the suitability of the selected
route(s), and any mandatory surveys required by the national and/ or local regulations. For
these early stage activities, Principal’s Geomatics group is recommended.
This new DEP-Gen. is a revision of the former deep water projects standard of the same
number dated May 2008; see (1.5) regarding the changes.
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The word shall indicates a requirement.
The word should indicates a recommendation.
The word may is an option to be confirmed with Principal
The word work is used to define the work to be executed by the Contractor as defined in
the Invitation to Tender or Contract Scope of Work.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 6
1.3.2 Abbreviations
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets ( ). Other documents referenced by this DEP are listed in (11).
2. GENERAL REQUIREMENTS
Pre-lay surveys may be required prior to any structure and pipelay installation operation.
This requirement varies from project to project. This event may be necessary due to the
time gap between the original survey performed during the design stage and the installation
start date. In the event pre-lay survey is required by the project team or by the national
and/or local regulations, this shall be carried out in close consultation with the project team
such that its start date and completion do not impact the construction works.
The objectives of a pre-lay survey are:
• To confirm the location and pipeline route(s) are clear of obstructions that may
impede the installation process
• To ensure that the anchoring corridors, in case an anchored barge is used during
installation, are clearly mapped of seabed obstructions that may slow the
structure/pipelay installation process.
• To confirm status of pre-lay intervention works
A pre-lay survey may consist of either:
• A remotely operated vehicle (ROV) survey
• A Geophysical survey - Towed sensor or autonomous underwater vehicle (AUV)
If the pre-lay survey results show debris/relics of historical or archaeological significance,
the process of notification as described in (8.10) shall be followed.
Pipeline inspection surveys are required at various stages of installation, operations, and
any subsequent inspection works. The stages during which a pipeline inspection survey
would typically be required include the following:
a) Pipeline installation support.
b) As-Laid Surveys
c) As-Trenched Surveys
d) As-Built Surveys (after post-lay interventions such as trenching/rock dumping or
remedial works such as span rectification).
e) Periodic Inspection works
The objectives of a pipeline inspection survey are further defined as:
1) Confirmation of location and integrity of the pipeline.
2) Location of all pipelines, cables and any other under water structures that may affect
the pipeline under inspection.
3) Confirmation of the seabed topography.
4) Establish and confirm the locations given in the referenced drawings for subsea
structures and seabed features respectively.
5) Confirmation of the status of relevant third party installations.
A pipeline inspection survey may consist of either:
i. A Geophysical survey - Towed sensor or AUV
ii. An ROV investigation of pipeline condition, crossings and any peripheral pipeline
assemblies.
iii. Alternatively, a combination of both ROV and Geophysical surveys.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 9
3 GEODETIC CONTROL
The selection of coordinates system and any survey control points used in any aspect of
the work (either onshore or offshore), shall be approved by Principal before use. Principal
(with the assistance of local Shell Geomatics group) shall provide details of geodetic
parameters for the proposed work site, Contractor will review geodetic details, and
immediately advise of any discrepancies or if unable to achieve required configuration with
contractor’s navigation software system. Principal may accept alternate geodetic algorithms
that would yield similar results, after review and approval from the local Shell’s Geomatics
group.
Details of geodetic system and survey control used during the work shall be properly
documented and included in the final report to Principal.
4 SURVEY EQUIPMENT
The operating frequency and signal architecture of the LBL system must be appropriate to
the water depth, environment and positioning requirement. The distribution of transponders
on the seabed must be planned to provide positional coverage within the area
encompassed by the resulting network with sufficient redundancy and adequate fix
geometry over the entire area of interest. Typically a medium frequency system (18-36
kHz) should be used to establish positioning with a relative accuracy of better than 1 meter.
Extra high frequency (EHF) (50-110 kHz) is typically used to establish positioning with
relative accuracy better than 10 centimetres. However, modern developments in signal
processing and architecture mean that positional accuracy is no longer related solely to
operational frequency.
The methods used to install transponders on the seabed must be consistent with the most
efficient utilisation of vessel time and facilitate the installation and removal of transponders
by ROV where appropriate. Design and fabrication of the transponder frames must comply
with the field’s requirement for either short-term or long-term utilization, where the size and
mass incorporates the appropriate stability and cathodic protection.
The geometry of the transponder network and the equipment and methodology employed
to conduct the calibration must support calibration with an accuracy that is consistent with
the end requirement for positioning. In particular the instrumentation used to determine the
speed of sound in water and the relative depths of the array transponders must be selected
and deployed in a manner that is consistent with the expected variation in sound speed at
array depth and the horizontal separation between transponders. The calibration process
must yield sufficient redundant observations to enable the computation of statistical
estimates of the calibration quality and also include appropriate QC checks to identify gross
error in the resulting transponder coordinates. Where the magnitude of the variation in tidal
height at the work site may result in a significant impact on the accuracy of subsequent
positioning operations the seabed equipment should include instrumentation to enable the
accurate real-time measurement of tidal height during those operations.
Contractor utilizing the array shall maintain all relevant information of the calibration (if
applicable) or positioned LBL targets (i.e. baseline, sound velocity, logged positioning files,
range measurements, transponder locations, offsets, etc…). Contractor shall also ensure
that sufficient redundant measurements are taken to ensure a high level of confidence in
any final reported positions [i.e. four (4) or greater range fix, multiple observations on target
transponder, acceptable statistical values for computed position, Low Root Mean Square
(RMS), etc.]
Contractor must demonstrate the effective control of error in the positioning solution
through rigorous operational procedures consistent with industry best practice. Sufficient
redundancy must be provided in equipment to identify bias in the derived values for the
speed of sound in seawater and the depths of objects being positioned within the network.
The level of redundancy during positioning must be consistent with the accuracy
requirement and provide appropriate statistical measures of the quality of the computed
positions.
The absolute depth of all local datum points throughout the field shall be measured and
referenced to Mean Sea Level or other such vertical datum as specified by Principal.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 13
5 PERSONNEL
5.1 GENERAL
The survey contractor shall engage a team with capabilities and experience consistent with
the project’s requirements. The survey contractor shall make available the curriculum vitae
(CVs) of the proposed staff and any proposed alternates two (2) weeks prior to project
mobilization. The survey contractor shall identify the individual who will become the single
point of contact, and can address questions regarding the technical, commercial, and
logistics aspects of the work. The survey contractor shall be responsible for providing all
necessary safety training, equipment and protective clothing for personnel. This should
include but not be limited to hard hat, safety boots, eye protection, flame-retardant clothing
and hearing protection to required international standards.
Survey contractor should provide key support personnel to the project, which may include:
• Survey Operations Manager
• Survey Project Manager
• Party Chief / Senior Surveyor
• Survey Engineer
• Online Surveyor
The staffing requirements and quantity shall be agreed with Shell prior to the project
mobilization. Contractor shall inform of the Principal of any replacement personnel prior to
carrying out thereof. Key personnel shall not be replaced without notification and obtaining
Principal consent, which shall not be unreasonably withheld. Contractor shall allow
adequate overlap time to ensure knowledge transfer, and continuous work.
6 PRE-LAY SURVEY
The purpose of the pre-lay survey is to ensure that the location, pipeline route and the
anchoring corridor (for anchored type barge) during the installation are clear of seabed
obstructions.
A pre-lay survey in deepwater shall normally be performed with sensors mounted on an
ROV, and would typically include the same tools required for the as-laid survey as
described in (7). Contractor shall propose method by which pre-lay survey is conducted in
water depths not suitable for ROV survey for approval by Principal.
Pre-lay survey for pipeline, flowline and umbilical routes, including startup and laydown
cable routes, shall extend to accommodate a project designated route corridor. Pre-lay
surveys shall be carried out to the same quality and specification as described in (7).
Apart from those debris/relics of historical or archaeological significance, which requires
appropriate notification to the parties concerned as described in (8.10) any other debris
shall also be evented as follows:
• Logged the position and describe the object
• Logged its new position if it has been moved
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 16
7 AS-LAID SURVEY
The purpose of the As-Laid survey is to record the installed position and initial post-
installation condition of the pipeline. Any significant events shall be logged for inclusion in
the As-Built documentation. The pipeline location shall be determined in three (3)
dimensions, with all significant pipeline appurtenances logged and documented. The
pipeline data shall be logged at a rate sufficient to meet this DEP. As-laid surveys shall
follow (8) for data logging and minimum requirement guidelines.
The survey shall normally be performed with sensors mounted on an ROV, and would
typically include:
a) Survey-grade gyrocompass with Pitch and Roll and Heading output.
b) Precision depth sensor (pressure sensor).
c) Precision altimeter.
d) Dual head sector scanning sonar system.
e) USBL transponder and/or responder.
f) LBL transducer for operations within any calibrated LBL array areas.
g) Centre mounted colour camera.
h) Port and Starboard boom mounted colour cameras.
i) Pipe tracking system, utilized when a pipeline is suspected of being buried.
j) Doppler seabed tracking system utilized for smoothing raw USBL data in deep water.
k) Swathe bathymetry system [ROV mounted dual head scanning sonar (DHSS)
system may be used as an option; however, the use of swathe bathymetry system is
preferred for As-Trenched/As-Built Surveys]
The majority of the above sensors require specific calibration routines to be adhered to;
inspection of the relevant survey methodologies would be required in conjunction with the
Manufacturers’ quoted recommendations.
The pipeline survey shall commence from the first pipeline joint weld at the initiation
assembly, and be completed at the final pipeline joint weld at the termination assembly.
Before commencement of event logging the "Off-track" and "Distance along line"
calculations and signage conventions in use must be checked for correctness. Particular
care shall be taken if the survey is to be run in reverse MP (KP) order.
Coordinates of the pipeline, features, and anomalies shall be determined continuously. .
The standard deviation of the data must be equal to or less than the accuracy of the
positioning system.
Completed As-Laid surveys of pipelines that do not require post-lay intervention such as
trenching, rock dumping etc or remedial works such as span rectification etc will be
classified as As-Built.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 17
The standard navigation and pipeline specific data to be logged during an As-Laid survey
shall include the following:
a) Surface vessel position – common reference point (CRP), and Raw DGNSS antenna
positions.
b) Surface vessel gyrocompass heading data.
c) USBL positioning data for all sub surface vehicles including dX, dY, dZ, Pitch, Roll,
and, if possible, Heave.
d) ROV’s USBL positioning beacon location.
e) ROV’s LBL transducer location for operations within any calibrated LBL array areas.
f) ROV gyrocompass heading, including Pitch and Roll.
g) ROV DHSS scan data.
h) ROV Depth Sensor and Altimeter data.
i) ROV pipe-tracker data (if applicable)
j) ROV’s mounted cameras (including Centre, and Port & Starboard boom mounted);
all video shall be recorded digitally.
k) Swathe bathymetry data (if this system is opted over the ROV mounted DHSS
system).
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 18
8 EVENTING
In addition to the navigation logging described in (7), the Online Surveyor shall perform
Eventing in real-time. Eventing is the digital annotation of the pipeline and associated
features that may affect the stability/longevity of the installed pipeline. Eventing shall
include continuous capture of video images of the pipeline that corresponds to real-time
positioning data. During the Eventing process, any anomalies or project-identified features
shall require a position fix. The position fix may include a sample data set to improve the
confidence level of the feature’s location.
Features and anomalies to be evented shall include, but are not limited to:
a) Field joint, including the individual condition.
b) Pipeline crossings: The location of the crossing, and whether any pipeline protection
is in place such as mattresses. This shall be cross-referenced to any spans that are
caused by the crossing.
c) Anode, including the individual condition.
d) Buckle Arrestors, including individual condition.
e) Weight coat (if applicable), condition along the pipeline, only annotated in areas of
deterioration/damage.
f) General pipeline damage - All dents and gouges, buckling of pipeline
g) Flanges: Location of flanges, if within an LBL array the positional data should be
from LBL techniques. Condition and type of flanges, Absence of cathodic protection,
and physical protection frames.
h) Free spans: Location of the start and end of all free spans, Maximum free span
height, and Descriptor outlining cause of free span mainly used when spans are
caused by pipeline crossings.
i) Burial Location: of the start and end of burial sections, Burial depth - if this is required
in the Scope of Work, and Descriptor if burial is caused by a specific event.
j) Debris: The type of debris, whether metallic or non-metallic, Proximity of the debris to
pipeline, including whether the debris is actually in contact with the pipeline.
Descriptor providing details of the debris type, this is especially important for larger
pieces of debris. Any indication of debris that may be of historical or archaeological
significance shall be immediately reported to the Principal Representative. Such
debris shall not be disturbed without the concurrence of the Principal Representative.
k) Cathodic Potential Values: The location of cathodic readings that are below the
project DEP.
l) Any other non-specific events that do not fall into any specific category.
m) The speed of the survey shall be adjusted so that the online surveyor can adequately
keep up with the eventing task. All significant observations, such as spans, damage
and unsupported crossings, shall be confirmed with the Principal Representative.
The third party pipeline shall be traversed for a distance of at least 25m (80 ft) either side of
the crossing point. The ROV shall be flown along the crown of the third party pipeline,
whenever possible. The pipeline heading is to be determined from this data to provide
adequate orientation control for crossing drawings. In addition if an anchor moored vessel
is used for construction activities and if the mooring line crosses an existing pipeline, a pre
and post anchor survey covering a distance of at least 50 m (160 ft) beyond the anchor
corridor shall be performed to confirm the condition of the crossed pipeline before and after
crossing.
The extent and condition of any physical separation barrier such as mattresses shall also
be examined. This shall include the size of the individual barriers, orientation, and quantity.
Additionally, note shall be taken if the barriers are butt joined, overlapping, or possess a
physical separation between consecutive barrier components.
In the case of pipelines physically touching, clear annotation shall be made indicating that
the two pipes are in physical contact. Physical contact will directly affect the cathodic
protection data.
The common essentials that are to be noted for a pipeline crossing:
a) Pipeline names and type.
b) The existence and type of pipeline separation barriers.
c) Height of separation if required to do so by Principal.
d) Subtended angle between the two pipelines.
e) Coating damage (if applicable).
f) Span lengths created by the crossing
g) Maximum Span height created by the crossing
8.4 ANODES
There are four (4) main items to be assessed when eventing anodes. These are:
• Location
• Type
• Wear or erosion
• Marine Growth
The Location and Type (bracelet, strip etc.) are straightforward and require no
explanation. The type will normally be known by the client from the pipeline DEPs; this may
then be checked while performing the As-Laid survey.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 20
When addressing Wear or Erosion during an As-laid survey on a new pipeline, the anodes
will naturally be at 100% capacity, therefore the following will not normally apply.
• Severe erosion: The majority of the anode has a heavily corroded surface, and less
than 25% of physical material remains.
• Medium erosion: Up to 50% of the anode is covered by deep pitting, especially
along edges and mounting faces, and between 75% to 25% of physical material
remains.
• Light erosion: moderate pitting especially along edges, however, the majority of the
flat exposed surface is clear of erosion.
• Newly Installed: Check that attachment mechanism to the pipeline is in place, and
that the anode appears to make solid physical contact with the pipeline.
Additionally, the presence of Marine Growth on the anode will indicate the general level of
erosion activity on the anode in question. When an anode is functioning correctly there will
be little marine growth (irrespective of overall erosion level). However, if the anode were
coated with significant marine growth, this would indicate that there is minimal electrolytic
activity - possibly indicating that the physical bond to the pipeline has failed or is failing.
The whole area of anode review is not easy to quantify with rigid specifications, because
anode design, DEPs, and specifications vary. Therefore, if there is some doubt as to the
classification of specific anodes, the inspection videos should be reviewed by experienced
personnel to validate the original online classification.
Areas that are classified as "Grade 1" requires detailed inspection as serious damage to
the pipeline may be in evidence. All areas of this type must be reported to the Principal
Representative, and reviewed.
pipe-tracking system, adequate time must be set aside for the procedure. The pipe-tracking
data must be logged digitally; the update rate of the unit will influence the speed at which
the survey operations may be completed.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 23
8.10 DEBRIS
Debris is concerned with any non-metallic and metallic objects in the direct vicinity of the
pipeline. However, sufficient descriptive annotation must be noted to adequately describe
the form of the debris, so that an accurate evaluation of pipeline damage risk may be
performed.
There are a number of items that may be directly attached to the pipeline during normal lay
activities, to assist with the deployment of the pipeline. These items would normally be
evented, but are not normally considered hazardous to the pipeline's integrity.
Particular emphasis shall be placed on ferrous metallic debris that either touches the
pipeline directly, or is in close proximity to the pipeline. This type of debris may require
further review and additional survey time to investigate fully.
Any indication of debris, which may be of historical or archaeological significance, shall be
immediately reported to the Principal Representative. Such debris shall not be disturbed
without the concurrence of the Principal Representative.
When working in the Gulf of Mexico (GoM) region, BOEMRE (Bureau of Ocean Energy
Management, Regulation and Enforcement) regulatory document NTL2005-G07
“Archaeological Resource Surveys and Reports [or most current Notice to Lessees (NTL)]
found at http://www.boemre.gov/ntls/) shall be followed.
10 DELIVERABLES
As-built data shall be delivered to Principal in the following formats:
10.1 CHARTING
The project specific co-ordinate system including spheroid, datum (and datum relation to
WGS84), projection and projection system parameters shall be as specified in the scope of
work.
Charts shall include the proposed pipeline route with approved permitted installation
corridor and the as-installed location of the pipeline.
Chart will include the locations and annotation of all crossings, anodes, damaged areas,
free spans, burial, debris, etc.
Charts shall contain legends that correspond to features shown on the charts.
Charts shall be provided in electronic format (AutoCAD and ArcGIS).
10.2 REPORTING
The following sets out the minimum requirement for reporting of As-laid / As-built surveys
by the Contractor. Unless stated otherwise in the CONTRACT/Scope of Work, it shall apply
to all As-Laid / As-Built surveys.
The report shall be concise and allow easy access to the survey results. It shall provide
salient facts and a critical review of all aspects of the survey(s).
Sample reporting format may be as shown below (where applicable):
a) Title Page
b) Location Map
c) Table of Contents
i) Introduction
ii) Project Details
• LBL Array installation
• As-built coordinates of sub-sea installations
iii) Geodetic Parameters
• Projection Parameters
• Local Datum Transformation Parameters
iv) Equipment and Instrumentation
• DGNSS system
• USBL equipment
• EHF/medium frequency (MF) LBL equipment
• Conductivity, temperature, and depth (CTD) equipment
• ROV and accessories
• ROV mounted DHSS, Video Cameras etc.
v) Calibration and System Checks
• DGNSS System Check
• Gyro Compass Verification Check
• USBL System Calibration
• LBL Calibration Procedure
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 26
11 REFERENCES
SHELL STANDARDS
Deepwater jumper design, measurement, fabrication and testing DEP 37.80.00.38-Gen.
AMERICAN STANDARDS
Archaeological Resource Surveys and Reports NTL 2005-G07
Digital Pipeline Location Data NTL 2009-G15
http://www.gomr.boemre.gov/homepg/regulate/regs/ntls/2009NTLs/
09-g15.pdf
Issued by:
US Department of the Interior, Bureau of Ocean Energy
Management, Regulation and Enforcement
381 Elden Street
Herndon, VA 20170-4817
http://www.boemre.gov/ntls/
BRITISH STANDARDS
UKOAA Data Exchange Format P5/94 UKOOA P5/94
Pipeline Position Data
Issued by:
United Kingdom Offshore Operators Association
6th Floor East
Portland House
Bressenden Place
London SW1E 5B
UK
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 28
A.1 GENERAL
An USBL or Super Short Baseline System (SSBL) measures a relative offset to a subsea
target providing an acoustic range and bearing from a transducer mounted on the surface
vessel.
The USBL system shall be interfaced to a calibrated Gyro Compass and Motion Sensor to
allow for the correction of observations for heading, heave, pitch and roll.
• The Motion Sensor shall be mounted as close as possible to the USBL transducer.
• The transducer (either tracking or fixed) shall be rigidly mounted through a gate
valve. An over the side mount may be acceptable with prior Principal approval but
it must be stout and able to withstand the stress due to waves and vessel motions.
• The Mounting within the gate valve should facilitate the raising and lowering of the
transducer pole without the necessity to re-calibrate the system
• In its operational position the transducer shall be clear of the hull, propellers,
thrusters and other possible noise sources.
• Contractor shall maintain a permanent record of transponder codes and operating
frequencies and the co-ordinates of all transponders deployed in the survey area (if
appropriate).
• Offsets between target transponders and key points on the subsea equipment,
vehicle, or tow body that is being positioned shall be carefully measured and
recorded.
APPENDIX B GYROCOMPASS
B.1 INTRODUCTION
Both conventional mechanical gyrocompasses and fibre optic Gyro-compasses [Fibre Optic
Gyro (FOG)] have inherent error sources:
• Latitude Error
• Speed Error
• Alignment Error
By quantifying the magnitude and sign of the alignment error and ensuring that the latitude
and speed settings are correct, a gyrocompass can realistically be calibrated to operate
within the manufacture’s specification.
A gyrocompass can be checked statically in a workshop environment and dynamically while
the vessel is at the harbour or at sea. The precision of the check and resulting standard
deviations of both the observations and the results will be dependent on the stability of the
vessel during the check, and the accuracy of the method used. The absolute accuracy of
the check will be dependent on the initial accuracy of the known azimuth used to calculate
the vessels heading, and the technique used to transfer the known baseline azimuth to the
heading of the vessel. Timing of the observations is also crucial, as the heading of the
vessel could change with respect to the known baseline azimuth, between observations.
falling tide does not endanger the stability of the vessel by allowing the mooring lines to
become too tight.
Equally, it is important to minimize the delay between reading the bow and stern prisms.
Consideration should be given to employing two (2) total stations to allow simultaneous
observation of the prisms.
B.3.2 GNSS Heading Technique
The GNSS is a cost-effective way of conducting gyrocompass checks. However, the GNSS
techniques implemented shall meet or exceed the accuracies required by the Project.
If a suitably accurate GNSS Heading system is available for use, its results shall be time
tagged and logged and then compared to a comparable data set of time tagged gyro
readings.
C.1 GENERAL
If requested by Principal, the DGNSS equipment to be used on a project shall be checked
at dockside to confirm it is operating correctly and producing accurate results. To carry out
the static check a total station is set up on the dock on a known point. It is back sighted
along a known azimuth and range and bearing observations are made to the ship’s DGNSS
antenna. Coordinates are computed for the antenna based on the dockside control and are
compared to the DGNSS positions computed on the ship using its normal positioning
techniques.
C.4 REPORTING
a) Summary of results.
b) Procedures adopted and general methodology.
c) Processed baseline data and witness diagrams.
d) All raw recorded data.
e) All processed data
f) All datum transformation information, if used.
ECCN EAR99 DEP 31.40.11.32-Gen.
September 2011
Page 34
D.1 INTRODUCTION
In the absence of project specific installation/construction tolerances or measurement
accuracies, provided by Principal, then the following table shows the typical default
requirements (see Tables 1). The final installation or construction tolerances will be
determined during the detailed design phase and therefore, the final survey accuracy
requirements may also change at that time. However, it is expected that the accuracies
shown in the table are sufficient to allow proper planning of survey procedures and
equipment requirements.
Measurement Accuracy
Description Installation Tolerance Comment
(95% confidence level)
Measurement Accuracy
Description Installation Tolerance Comment
(95% confidence level)
- Flowline Orientation: ± 2°
Termination
Assembly (FTA)