Summary of Finishing Manpower at Pretreatment Electrical Building(23-Jan t0 04-FEB)

Sl. No. Date Mason for Block works Mason for Plaster Helpers Painters
1 23-Jan 3 6 9 11
2 24-Jan 4 5 11 7
3 25-Jan 3 7 12 7
4 26-Jan 3 10 15 0
5 27-Jan 4 8 11 7
6 28-Jan 2 8 11 7
7 29-Jan Friday
8 30-Jan 2 7 13 7
9 31-Jan 2 9 15 6
10 1-Feb 2 6 12 6
11 2-Feb 2 6 12 7
12 3-Feb 2 6 11 7
13 4-Feb 1 2 7 7
cal Building(23-Jan t0 04-FEB)
Water proofing
Mason Technician Total
4 0 33
5 0 32
5 0 34
6 2 36
4 2 36
5 6 39

5 4 38
4 3 39
3 2 31
2 3 32
3 0 29
1 3 21