You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/251980239

Factors influencing project quality in the design phase of building projects: A


case in the Department of Building and Engineering Services of Botswana

Article · December 2010


DOI: 10.1109/IEEM.2010.5674525

CITATIONS READS

0 62

3 authors, including:

Cornelis Cristo van Waveren Kai-Ying Chan


University of Pretoria University of Pretoria
38 PUBLICATIONS   141 CITATIONS    34 PUBLICATIONS   207 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Knowledge Transfer in PBOs View project

Project Management Offices View project

All content following this page was uploaded by Kai-Ying Chan on 24 July 2018.

The user has requested enhancement of the downloaded file.


Factors Influencing Project Quality in the Design Phase of Building Projects: A
Case in the Department Of Building and Engineering Services of Botswana

E.N.D. Dodoo, C.C. van Waveren, K.-Y. Chan


Graduate School of Technology Management, University of Pretoria, Pretoria, South Africa
(corro@up.ac.za)

Abstract –There were numerous complaints regarding During the project design phase the objectives, constraints
the quality of building projects ran by the Department of and specifications of the project are defined by a team of
Building and Engineering Services (DBES) in Botswana. The individuals [3]. In building projects many uncertainties
aim of this study is to evaluate participants involving DBES could be eliminated during the early stage by addressing
projects by using 16 factors in the project design phase the scope of the project, the deliverables, the cost
which may influence the quality of building projects.
involved, as well as the schedule for delivery [4].
Empirical results show that DBES lacks commitment to
continuous quality improvement and poor use of lessons Effective management for project quality starts when the
learned to improve quality. The key focus area is adherence deliverables (that satisfy the need) are determined at this
to project management principles and poor level in this area phase [5]. Customer satisfaction is considered as one of
may contribute towards DBES’s poor project quality. the four project quality pillars that emerge from the
Moreover, this study identified 3 types of groups based from conceptual foundation [6] and thus customer / user
the respondents’ attributes and explored the differences in requirements at the initial stages of projects (i.e. design
group means. phase) should be specified or defined clearly to avoid
design deficiencies which may cause contract
Keywords – building projects; project quality; project
modifications during the implementation of the project
design phase, project management principles
[7].

In this study the authors identified three categories of


I. INTRODUCTION
factors in the project design phase that may influence
The Department of Building and Engineering project quality. These categories are: project management
Services (DBES) in Botswana is a merger of the previous principles, involvement of role players, and project scope.
Department of Architecture and Building Services 1) Project Management Principles: These principles
(DABS) and Department of Electrical and Mechanical are most often learnt from experience and may be applied
Services (DEMS). This newly merged department, DBES, to all projects to ensure success. In this study the
is responsible for the implementation of government following principles to be included during the design
building infrastructure development projects. DBES has a phase of DBES’s projects have been identified:
pure project management structure where people working x DBES’s selection process of the design team on
on a project are grouped together under a project manager meeting the client’s requirements and
that report to an executive officer. It appears that the expectations
merging of the two departments has not lead to better x Adherence to design brief from clients
project quality. There were numerous complaints from x DBES’s commitment to continuous quality
Botswana government on DBES building projects. In improvement
previous research, the project design phase has a greater x DBES leadership commitment to the adherence of
impact on overall project quality [1]. This paper identified procedures and specifications at the design phase
16 factors during the design phase that may influence the x Comprehensiveness of drawings and
quality of projects and evaluating participants involved in specifications
DBES projects against these factors in order to identify x Visibility of the total life cycle cost during the
key focus area. Moreover, the characteristics of the design phase
respondents were also taken into account to identify x Use of lessons learned to improve the quality of
behavioural differences. designs
2) Involvement of Role Players: Inputs from project
II. LITERATURE REVIEW AND FRAMEWORK participants (role players) during the design phase will
clarify project scope, planning and scheduling and
Building projects start with the project design phase eliminate uncertainties in the future [8]. Involvement of
where it ‘translates the primary concept into an expression the following role players during design phase are
of a spatial form which will satisfy the owner’s important to DBES project quality:
requirements into an optimum and economic manner’ [2].

978-1-4244-8503-1/10/$26.00 ©2010 IEEE 651


Proceedings of the 2010 IEEE IEEM

x End-users standard deviation of the attributes of the respondents and


x Management of DBES the factors (seen as variables in this study) in the design
x All Stakeholders phase. Moreover, a reliability test was done on these
x Building Contractors variables to determine how well the items measured a
3) Project Scope: Inadequate or poor scope single, unidimensional latent construct. The second part of
definition may negatively collate to the project data analysis explored the differences in ratings of the
performance and result in failure of projects [9]. factors between the independent groups (which are
Moreover, it may lead to poor design basis and adversely identified based from the attributes of the respondents).
affect projects [10]. Project scope related factors Independent samples t-tests were used to explore any
identified in this study are: significant differences in the group means.
x Sufficient project information provided by DBES
x Completeness and clarity of the scope definition IV. ANALYSIS OF DATA AND DISCUSSION
provided by DBES
x Pre-project planning effort on government projects A. Descriptive statistics: Attributes of respondents
by DBES
The frequency counts of the respondents’ attributes
x Stability (less changes in) of design brief or project
are illustrated in Table 1. The results of the frequency
requirement during the design phase
counts further identified two possible independent groups
x Management of changes in design brief at the
(with equal group sizes) within the same attribute.
design phase
Exploring the years of experience in Table I,
respondents working equal to and less than 10 years
III. RESEARCH METHODOLOGY
contributed to 58.6% of the population (i.e.
32.9%+25.7%); on the other hand, respondents working
A. Data collection
more than 10 years in DBES projects constitutes to
41.4%. Two independent groups with similar group sizes
This research applies a quantitative research
were identified in the total sample population as ‘” 
methodology and uses a questionnaire survey to collect
years’ (denoted as Group 0) and ‘> 10 years’ (denoted as
data. A total of 115 questionnaires were distributed to
Group 1). Moreover, in the profession or training
participants (units of analysis) involved in DBES building
attribute, those professions which were constructional
projects. The survey sample comprises 5 Project
related (i.e. architectural & quantity surveyor services,
Managers, 15 Architects, 15 Quantity Surveyors, 15 Civil
civil & structural engineering) constituted to 48.6%
Engineers, 15 Structural Engineers, 15 Mechanical
(denoted as Group 1) while the other professions were
Engineers, 15 Electrical Engineers, 10 client
ministries/departments and 10 PPADB (Public TABLE I
Procurement and Asset Disposal Board) registered FREQUENCY COUNTS OF RESPONDENTS CHARACTERISTICS
contractors in grade E. A total of 70 completed Respondents’ characteristics
questionnaires were returned resulting in a response rate Variables Frequency
Counts (%)
of 61%. From the returned questionnaires, it was found
1-5 years 32.9
that respondents who have more than 5 years of Years of 6-10 years 25.7
experience constitute to 70% of the population and all of experience 11-20 years 31.4
the respondents have participated in DBES building More than 20 years 10
projects; this indicates the validity of the sample and data Architectural services 15.7
collected. Quantity surveyor services 14.3
Mechanical engineering 20
Profession or
Electrical engineering 27.1
B. Questionnaire design and statistical methods training
Civil engineering 8.6
Structural engineering 10
There are two parts in the questionnaire design: Others 4.3
i. Attributes of the respondents: years of experience, Sector of Public 51.4
employment Private 48.6
professions or trainings, sectors of employment.
ii. Factors during design phase that influence building
TABLE II
project quality. INDEPENDENT GROUPS IDENTIFIED
Respondents were asked to use a Likert scale of 5 to Frequency
rate each factor from 1 (very low) to 5 (very high). These Group code Group description
Counts (%)
ratings were used to evaluate DBES during the project Years of Group 0 ”\HDUV 58.6
design phase. Lower ratings will indicate key focus areas experience Group 1 > 10 years 41.4
Profession or Group 0 Non-constructional 51.4
where DBES may take into considerations to improve training Group 1 Constructional 48.6
building project quality. Sector of Group 0 Public 51.4
In the first part of the data analysis, the SPSS employment Group 1 Private 48.6
statistical software was used to determine the means and

652
Proceedings of the 2010 IEEE IEEM

non-constructional (i.e. electrical and mechanical or equal to satisfactory level under these factors assessed.
engineering) and constituted to 51.4% (denoted as Group There is internal consistency (or reliability) in the
0). These two groups may be associated with participants factors measured under each category; i.e. all the
in the previous two departments mentioned in the &URQEDFK
V Į’s are greater than 0.6, which indicates
introduction section (i.e. DABS & DEMS). Participants reliable scales. In other words, the average scores of all
working on DBES building projects who are employed in the means of factors under the corresponding category can
the public sector (denoted as Group 0) and the private represent the score of that particular category. It was
sector (denoted as Group 1) are two independent groups found that the average score for the category Adherence to
with similar group sizes. The above analysis is Project Management Principles (2.7082) was the lowest
summarized in Table II. These groups will be used in the amongst all three categories. Moreover, within this
independent samples t-test in order to compare the group category, DBES’s commitment to continuous quality
means of factors. improvement, and use of lessons learned to improve the
quality of design had the two lowest means (below 2.6)
B. Descriptive analysis: Factors in design phase and visibility of the total life cycle cost during design
phase (the third lowest) amongst the seven factors. This
As mentioned in the research methodology section, finding implies that DBES’s poor project quality may be
questionnaires survey was used and the respondents were the result of participants involving in DBES building
asked to rate the factors in the questionnaires so that one projects not satisfactorily adhere to project management
can assess DBES in the design phase. In Table III, principles, especially with regards to the three particular
descriptive statistics of all the factors are presented. factors mentioned above, during its project design phase.
From Table III one can notice that none of the factors
has the mean score above 3 (which is the mid-point on a C. Independent samples t-test results
scale of 5). This observation implies that respondents
working on DBES building projects do not perform above As shown earlier, two independent groups exist in
each of the respondent attributes (see Table II). We
TABLE III examine how these groups rate the 16 factors differently
MEANS AND STANDARD DEVIATIONS OF FACTORS (significant at 5% level). Table IV shows the independent
Variables Means S.D. samples t-test results for Group 0 and Group 1 where
Category A: Adherence to project management principles in
respondents differ in years of experience. Tables V and
project design phase VII show the t-test results for the other two respondents’
Į PHDQ 6'  attributes.
A1: Selection process of the design team 2.83 1.129 In Table IV, there are no significant differences
A2: Design brief from clients 2.83 1.204 between the group means, except factors B2 and C5.
A3: DBES’s commitment to continuous
Group 0 (respondents working equal to or less than 10
2.57 1.149 years on DBES building projects) scored higher in factor
quality improvement
A4: DBES leadership commitment to B2 (involvement of the end users) as compared to Group
adherence of procedures and specifications at 2.80 0.957 1 (more than 10 years). Moreover, Group 0’s score on B2
the design phase
is higher than the mid-point (i.e. 3 on the scale of 5). This
A5: Comprehensiveness of drawings and
specifications
2.73 0.977 may be interpreted that respondents who have more years
A6: Visibility of the total life cycle cost during of experience working on DBES building projects have
2.63 1.066
the design phase known the end-users’ needs and requirements from their
A7: Use of lessons learned to improve the past experience. Thus they are not necessarily eager to
2.57 1.124
quality of designs
involve end-users during the design phase as compared to
Category B: Involvements of role players in project design
phase respondents who have less working experience. Another
Į PHDQ 6'  interpretation may be that respondents who have more
B1: Involvement of building contractors 2.63 1.132 years of working experience feel ‘business as usual’ and
B2: Involvement of the end-users 2.90 1.276
there may be a lack of enthusiasm in them. On the other
hand, it is assumed that respondents with less years of
B3: Involvement of the management of DBES 2.80 1.001
working experience are young and are eager to strive for
B4: Involvement of all stakeholders 2.61 0.906 perfection by involving the end-users in the design phase.
Category C: Project scope For factor C5 (process of management of changes in
Į PHDQ 6'  design brief), respondents in Group 0 again score higher
C1: Clarity and completeness of the project
information provided by DBES
2.84 0.973 than those in Group 1. This is an interesting finding
C2: Completeness and clarity of the scope showing that respondents who have less years of
2.81 0.952 experience actually are better in managing changes in
definition provided by DBES
C3: Pre-project planning effort on government
2.64 1.077 design brief. One of the interpretations may be that
projects by DBES respondents are young and have learnt the most updated
C4: Stability (less changes in) of design brief
or project requirement during the design phase
2.70 0.998 project management tools and techniques to better
C5: Process of management of changes in manage the process regarding to changes in design brief.
2.80 1.016
design brief

653
Proceedings of the 2010 IEEE IEEM

TABLE IV TABLE V
INDEPENDENT SAMPLES T-TEST RESULTS: FACTORS INDEPENDENT SAMPLES T-TEST RESULTS: FACTORS
Years of experience Profession or training
Group 0 Group 1 Mean Group 0 Group 1 Mean
Variables Variables
”\HDUV > 10 years difference non-constructional constructional difference
t-testa t-testa
Mean S.D. Mean S.D. Mean S.D. Mean S.D.
p-valueb p-valueb
A1 2.98 1.084 2.62 1.178 0.355 A1 2.83 1.207 2.82 1.058 0.01
A2 2.90 1.2 2.72 1.222 0.178 A2 2.78 1.198 2.88 1.225 -0.105
A3 2.68 1.192 2.41 1.086 0.269 A3 2.72 1.186 2.41 1.104 0.310
A4 2.88 1.029 2.69 0.85 0.188 A4 2.94 1.013 2.65 0.884 0.297
A5 2.8 0.872 2.62 1.115 0.184 A5 2.75 1.079 2.71 0.871 0.044
A6 2.61 0.972 2.66 1.203 -0.045 A6 2.78 1.124 2.47 0.992 0.307
A7 2.76 1.157 2.31 1.039 0.446 A7 2.78 1.222 2.35 0.981 0.425
B1 2.80 1.077 2.38 1.178 0.426 B1 2.78 1.174 2.47 1.080 0.307
B2 3.17 1.321 2.52 1.122 0.653* B2 2.83 1.298 2.97 1.267 -0.137
B3 2.93 0.959 2.62 1.049 0.306 B3 2.75 1.025 2.85 0.989 -0.103
B4 2.71 0.929 2.48 0.871 0.225 B4 2.83 0.971 2.38 0.779 0.451*
C1 2.95 0.893 2.69 1.072 0.262 C1 2.86 1.073 2.82 0.869 0.038
C2 2.98 0.821 2.59 1.086 0.389 C2 2.94 0.924 2.68 0.976 0.268
C3 2.78 1.037 2.45 1.121 0.332 C3 2.86 1.046 2.41 1.076 0.449
C4 2.80 0.954 2.55 1.055 0.253 C4 2.72 0.974 2.68 1.036 0.046
C5 3.00 0.894 2.52 1.122 0.483* C5 2.97 0.910 2.62 1.101 0.355

a. mean difference between groups


b. significance at 5 percent-level (p-value<0.05) V. CONCLUSIONS AND RECOMMENDATIONS
* mean difference is statistically significant at p<0.05
Due to numerous complaints about DBES building
projects, the purpose of this empirical paper is to assess
Table V shows that almost all the factors are rated participants in DBES building projects under 16 factors
equally between the two groups with the exception of during the project design phase which influences project
factor B4 (involvement of all stakeholders). Respondents quality. In this section the most important findings are
in Group 0 (non-constructional; previously worked for summarized and discussed. Further recommendations are
DEMS) score higher than those in Group 1 suggested.
(constructional; previously worked for DABS). This may This paper has shown statistical evidence of less than
be accounted to the fact that the type of work performed satisfactory performance of project participants during
by Group 0 (i.e. electrical and mechanical engineering) is DBES building projects design phase. That is, all factors
more operational and maintenance related (e.g. planning have less than 3 (mid-point on a scale of 5) mean values.
and lying of electricity cables or maintaining mechanical The key focus area that needs the most attention is
systems) as compared to Group 1 (i.e. more architectural). Adherence to Project Principles during design phase
During project design phase, Group 0 needs more (which has the lowest score out of the three categories).
comprehensive information and involvement from all the DBES may improve upon three factors in order to address
stakeholders in order to add its service. this problem, namely: commitment to continuous quality
In Table VI, it is shown that all the factors score the improvement, use lessons learned to improve quality of
same between the two groups, except factor B2 designs and visibility of the total life cycle cost during
(involvement of the end-users) in which the respondents design phase.
in Group 0 (employed in public sector) score higher than From the descriptive analysis of the respondents
Group 1 (employed in private sector). Moreover, the attributes this study identified two independent groups
Group 0 score is higher than the mid-point of the scale within each of the attribute. Independent samples t-test
which indicates a more than satisfactory level. There is a was performed to explore any significant differences with
phenomenon that corresponds to this finding. It is noticed regard to the ratings of the factors.
that in DBES projects during the design process, the end- As compared to participants with less than 10 years,
users provide design needs and requirements to the DBES those with longer experience are less able to manage
project participants who are employed in the public sector changes in the design brief. This study assumes that
(e.g. government officials) and this information is then respondents with less years of experience are younger and
passed on to the participants in the private sector (e.g. have learnt the most updated project management tools
design consultants). Thus participants from the public and techniques which may help them to better manage
sector seem to be closer to the end-users because of the design brief change processes. However, on the other
direct communication channel that exists between them. hand, respondents who have longer experience may not
necessarily have previous project manage education. It is
recommended to provide continued education with the

654
Proceedings of the 2010 IEEE IEEM

TABLE VI
INDEPENDENT SAMPLES T-TEST RESULTS: FACTORS
Sector of employment
Group 0 Group 1 Mean
Variables
public sector private sector difference
t-testa
Mean S.D. Mean S.D. p-valueb
A1 2.86 1.099 2.79 1.175 0.067
A2 2.72 1.210 2.94 1.205 -0.219
A3 2.58 1.204 2.56 1.106 0.025
A4 2.81 1.009 2.79 0.914 0.011
A5 2.61 0.994 2.85 0.958 -0.242 Fig. 1. Inter-relationships amongst end-users, participants from the public
A6 2.44 0.998 2.82 1.114 -0.379 sectors and the private sectors.
A7 2.42 1.105 2.74 1.136 -0.319
B1 2.42 1.105 2.85 1.132 -0.436
B2 3.25 1.273 2.53 1.187 0.721* factors can also be taken into consideration during the
B3 2.89 1.036 2.71 0.970 0.183 project design phase. Thirdly, relationships between these
B4 2.64 0.899 2.59 0.925 0.051 factors can be explored by using regression analysis. A
C1 2.94 0.984 2.74 0.963 0.209 certain factor may have a positive or negative impact on
C2 2.78 0.959 2.85 0.958 -0.075
C3 2.64 1.125 2.65 1.041 -0.008
another one. For example, involvement of all stakeholders
C4 2.72 0.944 2.68 1.065 0.046 may positively impact on the process of managing
C5 2.86 0.990 2.74 1.053 0.126 changes in the design brief. Such analysis can further
provide recommendations to improve DBES building
focus on project management within DBES to those project quality.
participants who have no previous knowledge of project
management. ACKNOWLEDGMENT
T-tests further explore another important issue.
Participants of DBES projects from the public sector (e.g. The authors would like to express their appreciations
government officials) has direct communication with the to participants in DBES building projects during the
end-user and pass on the information regarding design questionnaire survey. Secondly to Graduate School of
requirements to the participants in the private sector (e.g. Technology Management for providing academic support.
design consultants). Information may be inaccurately
interpreted and may be lost when transferring it from the REFERENCES
public sector to the private sector. Inaccurate information
[1] J.B. Pocock, “A model air force construction quality
may contribute to the reasons for poor design quality
management system”, Mater thesis, Dept of Architectural
(which does not meet specifications). Therefore, it is Engineering, Pennsylvania State University, U.S.A., 1998
recommended to have all three parties involved in the [2] D.W.M. Chan, and M..M. Kumaraswamy, “A comparative
project design phase so that direct communication can study of causes of time overruns in Hong Kong
exist amongst all of them (see Fig 1). construction projects”, International Journal of Project
Lastly, there seem to be a problem of co-ordination Management, vol. 15, no. 1, pp. 55-63. 1997
between the non-constructional group (i.e. electrical & [3] M.J. Leseure, and N.J. Brookes, “Knowledge management
mechanical services) and the constructional (i.e. benchmarks for project management”, Journal of
architectural). This can be seen from the statistical Knowledge Management, vol. 8, no. 1, pp. 103-116, 2004.
[4] H. Steyn, et al., Project Management: A multi-disciplinary
evidence of less involvement of all stakeholders from the
approach, Pretoria: FPM Publishing, 2007.
constructional side. Not involving all stakeholders may [5] M.C. Carruthers, Principles of Management for Quality
lead to correctional work after the building is completed. Projects. London: London International Thomson Business
For example, if an architect does not involve an electrical Press, 1999.
engineer during the design phase, the building plan may [6] T.J. Kloppenborg, and J.A. Petrick, Managing Project
have an air-conditioning system in the position where the Quality, USA: Management Concept Inc, 2002.
electrical engineer finds difficulties in operating or [7] M.I. Darwish, O. Moshen. , I. Alramadan, and M.
maintaining at later stage. It is therefore recommended to Algahtani, Factors Affecting Design and Documentation
include all stakeholders during the design phase for better Quality in the Construction Industry, CEM520:
Construction Contracting Administration, 2007.
co-ordination at the later stage of projects (i.e. design for
[8] A.P.C. Chan, D. Scott, and A.P.L. Chan, “Factors affecting
maintainability). the success of a construction project”, Journal of
Several future studies are suggested. Firstly, DBES Construction Engineering and Management, vol. 130, iss.
may also be evaluated under factors during other project 1, pp. 153-155, 2004.
phases, e.g. execution phase. This may further point out [9] P. Dumont, G. Gibson, and J. Fish, “Scope management
other key focus areas to ensure better project quality. using the project definition rating index (PDRI)”, ASCE
Secondly, this study only considers three key focus areas Journal of Management in Engineering, vol. 13, no.5, pp.
(i.e. the three categories) of the design phase; the 54 -60, 1997.
framework may be extended further by exploring other [10] C.-S Cho, and G.E. Gibson Jr., “Building project scope
definition using project definition rating index”, Journal of
focus areas as well. For example, environmental impact
Architectural Engineering, vol. 7, iss. 4, pp. 115-125, 2001

655
View publication stats

You might also like