Professional Documents
Culture Documents
6.1 Project
x NWRWS & K DEPARTMENT intends to appoint a Consultant for “Providing
Consultancy Services for Planning of Water Distribution system for the Command Area
of Kalpasar Reservoir’’ in the State of Gujarat - India.
x Earlier only preliminary planning has been done with the help of topo sheets and for
10,000 MCM water availability. Now, with latest water availability and with the
CARTOSAT and duly field surveying using high end DGPS and total station mentioned
in detailed scope, the consultant has to plan the most effective water distribution
system, either open channel or underground pipeline or combination of both, which is
most suitable in the terms of technical viability, financially most economical and having
minimum major issues related to land acquisitions while covering maximum command
area with revised water availability.
x Considering above, quantities mentioned in the Form Fin-2 are very tentative and most
likely to vary. The consultant should quote their rates for the above quantities. The
payment will be given as per actual quantity executed and the rates quoted by the
Consultant in the schedule. In this regard, no claims of any decrease / increase in
quantities up to 30% in any proportion will be entertained. If executed quantities
increase more than 30%, decision of rate will be decided based on mutual agreement.
In case, where the quantities decrease more than 30%, the Consultant is bound to
execute the Work at quoted rates only.
x This report will be part of detailed project report (DPR) of the whole Kalpasar project,
in this work the following major components are included.
a) The latest water availability at 50 % dependability is 7770 MCM including Narmada
water through Narmada Diversion Canal. The whole planning is to be done considering
this much water availability and priority is to be given to the command area which is
not covered under any existing irrigation scheme. Moreover, if required supplementary
irrigation to water resources scheme or lift irrigation scheme can be included. However,
finalization of command area shall be done in consultation with Engineer-In-Charge
and decision of Engineer-In-Charge will be considered as final. Moreover, separate
planning shall be given for water availability:
1) at 50% dependability with Narmada Diversion Canal (NDC)
2) at 50% dependability without Narmada Diversion Canal
3) at 75% dependability without Narmada Diversion Canal
4) at 75% dependability with Narmada Diversion Canal
Page 64 of 149
The entire work is to be done for water availability at option no.1 (i.e. 7770 MCM) will
include satellite image, field survey, Geotechnical investigation, Design along with
detailed estimates, land acquisition statement and GIS data base for this option only.
Based on the planning submitted for option-1, only separate planning for other three
water availability options are to be submitted by the Consultant. The Consultant shall
require to quote the item rate of item no. 2 of Form Fin-2 considering above mentioned
Provision. The area to be covered under irrigation is to be ascertained by the consultant
as per detailed planning.
The tentative water availability
50% dependability with NDC-7770 MCM
50% dependability without NDC-5539.35 MCM
75% dependability with NDC-5200 MCM
75% dependability without NDC- 2969.32 MCM
However before start the planning final water availability is to be confirm with engineer-
in-charge
b) The DPR shall also contain Base map showing existing / proposed irrigation schemes
by NWRWS & KALPSAR DEPARTMENT, existing crop pattern, agro climate
condition, proposed cropping pattern, command area drainage, water management,
climate of command area, present source of irrigation in command area, GIS Database
based on the final alignment study.
The Agency shall be responsible to provide Consultancy Services for the project components
as specified in details in Section 2: Project Description of this RFP and also in full compliance
to the Work Specifications, General Conditions of Contract, Special Conditions of Contract
and other provisions contained in the Contract that may be awarded by the NWRWS & K
DEPARTMENT to Agency.
x The Contract period for providing the services shall be 09 months.
Page 65 of 149
6.2 Scope of work & services
Brief scope of services of project includes the following scope of work:
a) Assistance for Procurement of 2.5 m stereo resolution CARTOSAT-1 Images falling
on canal/pipeline or combination of both study area covering 30,000 Sq. Km (Approx.)
as per Area of Interest (AOI).
Page 66 of 149
h) Fixing of main canal / pipeline or combination of both Apex Points along approved
alignment by fixing Monumentation of RCC pillar /stone pillar of size 200 mm x 200
mm x 750mm size at every apex point or at 500 m interval.
i) Fixing TBM in CC 1:2:4: at every 01 Km interval having size of pillar 300 mm x 300
mm x 750 mm at site on main canal/pipeline or combination of both.
j) Fixing PBM in CC 1:2:4: at every 05 Km interval having size of pillar 500 mm x 500
mm x 750 mm at site on main canal/pipeline or combination of both.
m) Preparation of Detailed Design Drawings for main canal / pipeline alignment (or
combination of both), cross section showing bed width, side slopes, service road,
inspection path width, spoil bank section, outer toe drain section, maintenance land
width, detailed estimates etc. Plotting cross section at every 10 m interval so as to
cover the canal sections in full cutting, full bed banking or partial cutting and partial
banking or pipeline sections as the case may be. Preparation of detailed designs for
structures and pumping stations falling on the main canal / pipeline alignment including
electro mechanical components along with detailed estimation.
n) For distribution network other than main canal / pipeline alignment, preparation of
preliminary design for a typical canal / pipeline stretch, preliminary typical design for
each type of structures falling on these network alignments along with preliminary
estimate for the said distribution system.
o) Preparation of Village wise land plan schedule: Collection of original village map from
concerned department by consultant, geo-referencing of village map, transferring the
final alignment on the village maps. Preparation of Land acquisition statement,
collection of ownership record and preparation of land acquisition statement.
p) Creation of GIS Database based on the final alignment study, salient features of
project, Detailed Project Report, Design, Drawing, Land Acquisition Plan Schedule etc.
Page 67 of 149
GIS Application Shall be developed using Open Source Software of Any other software
with license permission & it will be handover to the department. and supply, installation
& commissioning to NWRWS & Kalpasar Department along with transfer of entire GIS
Database to department.
x Generation of DEM (Digital Elevation Model), extraction of Ground levels within AOI,
generation of profile along the proposed canal.
x DGPS Ground Control Points (GCPs) established on field to be used for processing of
CARTOSET Imagery.
x Final AOI shall be considered as per instruction of Engineer In Charge.
Note:
a) Agency /Consultant shall assist NWRWS & Kalpasar Department for the
procurement of CARTOSAT-1 from NRSC-Hyderabad.
Page 68 of 149
Figure 1 Tentative Area Of Interest (AOI)
Page 69 of 149
x Working out the fortnightly crop water requirement of the planned ICA of the canals
by Modified Penman Method.
x The latest water availability at 50 % dependability is 7770 MCM including Narmada
water through Narmada Diversion Canal. The whole planning is to be done
considering this much water availability and priority is to be given to the command
area which is not covered under any existing irrigation scheme. Moreover, if
required supplementary irrigation to water resources scheme or lift irrigation
scheme can be included. However, finalization of command area shall be done in
consultation with Engineer-In-Charge and decision of Engineer-In-Charge will be
considered as final. Moreover, separate planning shall be given for water
availability options:
1) at 50% dependability with Narmada Diversion Canal (NDC)
2) at 50% dependability without Narmada Diversion Canal
3) at 75% dependability without Narmada Diversion Canal
4) at 75% dependability with Narmada Diversion Canal
The entire work is to be done for water availability at option no.1 (i.e. 7770 MCM)
will include satellite image, field survey, Geotechnical investigation, Design along
with detailed estimates, land acquisition statement and GIS data base for this
option only. Based on the planning submitted for option-1, only separate planning
for other three water availability options are to be submitted by the Consultant. The
Consultant shall require to quote the item rate of item no. 2 of Form Fin-2
considering above mentioned Provision. The area to be covered under irrigation is
to be ascertained by the consultant as per detailed planning.
The tentative water availability
50% dependability with NDC-7770 MCM
50% dependability without NDC-5539.35 MCM
75% dependability with NDC-5200 MCM
75% dependability without NDC- 2969.32 MCM
However before start the planning final water availability is to be confirm with
engineer-in-charge
x The proposed distribution system may be open canal type or underground pipeline
type or combination of both depending upon the topography, financial implication
on account of land acquisition, construction and maintenance.
x The proposed distribution system shall be finalized considering demand/shortfall
of existing and proposed industrial, drinking and irrigation water supply scheme.
x Consultant shall propose allocation and delivery points for new/existing industrial
Page 70 of 149
and drinking water supply.
x Priority for the planning of irrigation to be given where there is no existing irrigation
facility available. However, if required supplementary irrigation of water resources
scheme or lift irrigation scheme can be included to work out the design capacity of
canal/pipeline or combination of both and cultural command area considering the
various water availability described in detailed scope of work. Detailed distribution
network planning up to 400 hector command area is required to be carried out
using CARTOSAT imagery data.
x Separate statement showing village wise, taluka wise culturable command
area(CCA)for all the option shall be submitted.
x Working out the merits and demerits of each alignment and recommendation for most
techno-economically feasible alignment.
6.3.4 Establishment of Ground control points using high end DGPS for
CARTOSAT imagery.
For processing of satellite images (CARTOSAT), establishment of Ground Control network
using high end DGPS having accuracy of +/- 3 mm required as per detailed specifications
furnished below;
x Base Station: at center of AOI - 24 Hrs. Observation
Page 71 of 149
x DGPS raw data (Rinex data) should be processed w.r.t. IGS Station of SOI as per
whole to part method and coordinates of each control point to be arrived to be used for
processing of CARTOSAT-1 imagery and finalizing the alignment alternatives for field
surveying using high end DGPS and ETS.
x DGPS control points preferably should be established on existing stable permanent
structure wherever available, otherwise pillar of size 300 x 300 x 750 mm should be
embedded and observation to be carried out.
x Each DGPS control point established should be connected with nearest available SOI GTS
%R0XVLQJGLJLWDOOHYHORQO\$FFXUDF\VKRXOGEH¥NZKHUHWKHNLVOHQJWKLQ.PDQG
accuracy should be in mm.
x Providing reduced level as per MSL to all TBM and PBM which will be established along
the proposed canal as per item No.7 and 8 of form fin 2.
x DGPS raw data (Rinex data) should be processed w.r.t. IGS Station of SOI as per whole
to part method and coordinates of each control point to be arrived to be used for processing
of Cartoset imagery.
x The objective of the mapping is to provide sufficient detail to enable the design of the
main canal/pipeline or combination of both including all electro-mechanical
component.
x Carrying out Survey investigation by DGPS and Total station 150mt. on either side
from center line i.e 300 mt. corridor in longitudinal section at 30 mt. interval and cross
sections mostly 10 mt. interval normally. But when abrupt changes are encountered,
additional points for level will have to be taken as instructed by Engineer in- charge.
x The agency shall have to make necessary site clearance for carrying out the survey
work at the site of work at his own cost.
Page 72 of 149
x Agency has to provide two hard and one soft copy of graphical plot of L-section and all
cross sections of 300 mt. or as directed by Engineer-In-Charge and the contour map
with the interval of 0.50 mt.
x Satellite print or google map will not be accepted for the work.
x Agency has also to mark the permanent structure if any such as road, school, well,
Vadi, voklo, houses in the contour sheet.
x The work shall also be carried out in all-weather condition and all types of terrain.
x The objective of the mapping is to provide sufficient detail to enable the design of the
main canal/pipeline or combination of both including all electro-mechanical
component.
x Based on the irrigation principal and size of the canal/pipeline or combination of both
to be finalized depending upon the features available on the base map
x Work out the details of the of structures, crossings, pumping station, sections of canal
through open channel or underground pipeline or combination of both shall be worked
out
x Preparation of alignment drawing to the scale of 1:4,000 along with the profile for main
canal/pipeline.
6.3.6 Fixing of Apex Point along main canal / pipeline or combination of both
alignment by fixing monumentation of RCC pillar of size 200 mm x 200
mm x 750mm sise at every apex point at 500 m interval.
Page 73 of 149
Agency/consultant has to fix stone at 500 M interval on central line and/or apex stones
at every deviation of alignment duly indicating apex No. and chainage.
x The details of chainage stones and apex stones respectively is as follows:
Providing and fixing RCC /Stone pillars of size (size 200 x 200 x 750 mm) with 500 mm
below the ground and 250 mm above ground.
6.3.7 Fixing TBM in CC 1:2:4: at every 01 Km interval having size of pillar 300
mm x 300 mm x 750 mm at site for main canal/pipeline or combination of
both.
x Consultant shall construct and establish temporary bench marks at every 1 Km.
x TBM locations shall however be decided in consultation with NWRWS & Kalpasar
Department.
x The permissible error shall not exceed the codal provisions of leveling done in
kilometers.
x RCC Pillar /Stone Pillar size for TBM shall be 300 mm x 300 mm x 750 mm.
x Values of temporary bench marks shall be fixed with reference to the Permanent Bank
Mark established by SOI as indicated by the Engineer-in-Charge.
x A proper system shall be evolved for numbering the TBMs as directed by Engineer-in-
Charge. A plan to a scale 1: 50000 indicating location and levels of all TBM / PBMs
established in the command area shall be prepared and submitted to the NWRWS &
KALPSAR DEPARTMENT.
6.3.8 Fixing PBM in CC 1:2:4: at every 05 Km interval having size of pillar 500
mm x 500 mm x 750 mm at site for main canal/pipeline or combination of
both.
x The PBM s shall be constructed as per standard practice in and at location as may be
directed by Engineer-in-Charge. This should be located preferably at one corner of the
field, which will not hamper the agricultural operations or as instructed by the Engineer-
in-charge.
x Permanent Bench marks with values at 5 Km interval should be fixed on site.
x The level of PBM shall be established on top of steel plate of size 10 cm x 10cm, 5mm
thickness anchored with 10mm twisted rod of length 150 mm at the center of plate.
x Adequate care shall be taken by the consultant for curing the concrete laid for the
PBMs. The PBMs shall be numbered in oil paint for identification where black cotton
soil is met with the foundation will have to be taken to extra depth and filled with M-10
CC and standard size bench mark shall be constructed over this
Page 74 of 149
x The permissible error shall not exceed the Codal provisions of leveling done in
kilometers.
x RCC Pillar size for 500 mm x 500 mm x 750 mm shall be embedded at site out of which
500 mm below the ground and 250 mm above the ground
x Values of PBM shall be fixed with reference to the Bank Mark established by SOI as
indicated by the Engineer-in-Charge.
Page 75 of 149
diameter of the sample shall be 100mm Undisturbed samples shall be collected by thin
walled sampling tubes (Shelby tubes) having the area ratio less than 10%. The
sampling tube shall be of stainless steel without welded joint and having a cutting shoe
with the inside and outside clearance ration of 2%. Rate of penetration of the UDS is
such that maximum retention of the sample can be achieved. All boring works shall be
carried out in all types of soils, cemented sands, gravels, soft and hard Murrum, etc.
The Consultant shall have to mobilize appropriate machinery / equipment for drilling,
samplers and core boxes etc.
x Rock coring shall be performed in case rock strata are encountered. Rock
coring/drilling shall be performed with a swivel type triple/double split tube core barrel
and side discharge of minimum NX size drill bit. The core shall have a minimum
diameter of 54 mm. Standard Penetration Test (SPT) shall be carried out on rock
strata, where coring resulted in low recovery and zero Rock Quality Designation
(RQD). These hard materials can be defined as soils with SPT N values not in excess
of 130 blows per foot. SPT ‘N’ values in excess of 130 blows per foot will be defined
as Rocks.
x During the drilling or coring operation, the approximate penetration rate of the drilling
and coring bit shall be monitored and recorded in order to investigate the potential
presence of voids or cavities within the subsurface soils or rocks.
x Carefully place the rock core in suitable wooden boxes that are partitioned so that the
rock from each core run shall be kept separate. Rock cores shall be suitably labeled
and arranged neatly in the boxes. Clearly mark the depths of the run and the amount
of recovery.
x Soil and rock samples shall be classified by a Geotechnical Engineer and approved by
the Engineer-In-Charge. Geotechncial engineer must remain present during the
investigation on site. Prepare and maintain a field log of boring. Clearly record the type
and details of the drilling equipment, the number of blows, hammer weight and fall, and
the amount of recovery for soil samples, and the percent recovery and RQD (Rock
Quality Designation) as well as the amount of any water loss for rock core runs. Soil
sample classifications shall be adjusted according to after the completion of the
laboratory tests. A clear color picture of all rock cores placed in the box with visible
labels shall also be obtained and provided in the report.
Page 76 of 149
practice.
2) Conducting SPT, collection of disturbed samples as per standard practice
(b) Field Testing: Following tests are required to be conducted but not limited to this.
Laboratory Testing for soil samples as per codal provision-
1) Grain size Analysis
2) Atterberg’s limit
3) Specific gravity
4) Permeability at center of the hole of each Centre line holes
5) Tri-axial shear (UU/CU/CD)/direct shear/UCS based on the soil type
6) Consolidation test for clayey samples
7) Free swell and
8) Swell pressure at zero moisture representative samples in black cotton soil
Laboratory Testing for rock samples as per codal provision-
9) Petrographic analysis
10) Uni-axial compression test
11) Specific gravity
12) Water absorption
13) Durability test
14) Bulk density and porosity
(c) Minimum 10% of samples should be tested at Gujarat Engineering & Research
Institute (GERI) as per Government of Gujarat norms.
Page 77 of 149
6.3.9.3 Reports:
After carrying out laboratory / field tests on samples and engineering analysis, the Consultant
shall provide soil report. The report shall include but not limited to the following,
a) Classification of soil strata and borehole logs
b) Laboratory and field test results
c) Engineering analysis of test results, soil characteristics and parameters.
d) The report shall also include:
1) Geological information of the area / region
2) A Set of longitudinal and transverse soil profile along with co-ordinates and
levels.
3) Geological mapping of the whole area/region.
4) All field and test results shall be plotted against depth as well as in tabular
form.
The Final report shall be prepared as factual report presenting the results of the geotechnical
investigations, the calculation methods used and the field procedure employed.
Page 78 of 149
derived and taken on pro-rata basis for preliminary estimate of the system. Similarly,
typical design of one typical structure of each type is to be submitted and taken on pro-
rata basis for preliminary estimate of the distribution system. The preliminary designs
and earthwork quantities to be derived for preliminary estimation, shall be based on
the CARTOSAT data procured. Borrow area and leads shall be decided in consultation
with the Engineer-In-Charge.
Design of economical canal sections should be as per I.S., MOST & Departmental norms.
Prepare detailed canal cross sections showing land width required for following conditions
including hydraulic design.
- Canal in full cutting,
- Canal in full banking or bed banking or
- Canal in partial cutting and partial filling
Page 79 of 149
Canal System for Irrigation.
x Design: IS 10430:2000 (Reaffirmed 2013)- Criteria for Design of Lined Canals and
Guidelines for Selection of Type of Lining.
x Earth Work: IS 4701:1982 (Reaffirmed 2013)- Code of Practice for Earth Work on
Canals
Page 80 of 149
x IS 7784(Part 2/Sec2):2000(Reaffirmed 2013): Code of Practice for Design of Cross
Drainage Work: Part 2- Specific Requirement Section 2: Super passages.
x IS 7784(Part 2/Sec3):1996(Reaffirmed 2011): Code of Practice for Design of Cross
Drainage Work: Part 2- Specific Requirement Section 3: Canal Syphon.
x IS 7784(Part 2/Sec4):1999(Reaffirmed 2013): Code of Practice for Design of Cross
Drainage Work: Part 2- Specific Requirement Section 4: Level Crossing.
x IS 7784(Part 2/Sec5):2000(Reaffirmed 2013): Code of Practice for Design of Cross
Drainage Work: Part 2- Specific Requirement Section 5: Syphon Aqueduct.
Pumping station:
The design of pumping station should be as per the relevant latest codal provision and
standard practices. It is required to finalize the details of pumping station such as locations,
type, size, no., capacities and power requirement in this Work.
x All the data details, drawings, reports, detailed design for distribution system and
preliminary designs and schematic hydraulic and structural drawings submitted by the
Consultant/agency shall be the property of the Department. The Consultant shall not
use any parts of the same design or publish the contents thereof in any manner.
x The Consultant shall note that all information furnished shall be treated as confidential
and shall be used by the Consultant only for the purpose for which such information
was intended and shall not disclose the same to any other party without prior approval
of the Department.
x The Consultant shall prepare detailed canal cross sections for various conditions like,
canal in full cutting, canal in full or bed banking or canal in partial cutting and partial
filling, following in general the requirements laid down in BIS specifications. However,
looking to the size and purpose of the canal/pipeline, each parameter/dimensions will
need to be decided in consultation with the department.
Page 81 of 149
6.3.10.6 PREPARATION OF PLANS & ESTIMATES
x The Consultant shall prepare probable cost estimates in consultation with the
department for each component of the works included in the scope of the present
consultancy assignment i.e. for the canal/pipeline or combination of both work, head
regulator, associated structures, pumping stations and other ancillary works.
x The consultant shall have to give separate estimate for each individual structure.
x Consultant has to submit the detailed estimates for main canal / pipeline or
combination of both including associated structures and pumping stations only.
Consultant also has to submit preliminary estimates for whole distribution system other
than main canal / pipeline or combination of both including associated structures falling
on these network alignments.
x The estimates shall be prepared in the format to be prescribed by the department on
the basis of sanctioned SOR of NWRWS&K department.
x For Non-SOR items, unit cost of work shall be decided in consultation with the EIC. In
the estimate the provision for quality control, work contingencies, establishment etc be
made as per directions of the EIC.
x Fixing Cutting points at village limit, survey number / field bund limit on the cadastral
survey map.
Page 82 of 149
x Identification of survey numbers of the proposed alignment duly superimposed on the
digitized maps and village maps as per revenue records available with the local
authorities.
x Taking out off-set distances from nearest boundary corners in order to ensure that the
scale variation is taken care of.
x Generation of combined statement with details of survey numbers, area and Owner.
x All field data and records generated shall contain sufficient details to enable OWNER
/DEPARTMENT to initiate acquisition.
x The database of the land records collected from the various authorities shall be
generated in a Microsoft windows based software package in English and Gujarati
languages as per requirement of the State/ Central Govt.
x The data shall include names/ details of district, taluka, village, village-wise plot details,
extent of area, land Owner/Department, land enjoyer, type of land, land cost, crop
cultivation etc.
Page 83 of 149
as a part of project deliverables.
x Cost of required Hardware, software and other infrastructure for hosting and
commissioning shall be borne by agency/consultant.Consultant shall procure and hand
over to department the required hardware, which can run the generated GIS data base
smoothly.
x The specification of the same shall be as per the below but not limited to this.
Intel Xeon E2124 3.3GHz Processor Dynamic Smart Array B100i with 4 SATA Ports
Support Embedded Broadcom BCM5720 Dual Port 1Gbe LOM 8GB (1x8GB) DDR4-
2400T ECC with 64 GB Expandable 1 X non-hot plug, non-redundant FAN 1 Open
Bay [Max: 4LFF Hot Plug HDD] 4 PCIe 3.0 Slots; 4 USB 2.0 & 6 USB 3.0 Ports
ILO Management (Standard) Intelligent Provisioning (Standard) ILO Essentials (Ops);
ILO Firmware 28" LED Monitor / USB Keyboard + Mouse 3 yr onsite Server warranty
Windows Server 2019 Standard In addition to this all auxiliary hardware required to
run the software shall be included and all expenses towards this activity are deemed
to be included in the item no 12 of form fin 2.
Page 84 of 149
Module Functionalities, Data and information required
format. The module provides tools for map viewing, querying & spatial
analysis. Tools for visualization of canals and retrieving technical details or
documents of any specified location of canal
Pre-Engineering x Topographic maps
Manager x Field updated up-to-date Base Map
x Detailed Engineering Survey Reports & Drawings
x Geotechnical investigation Reports
x Cadastral information such as village maps, extent of
area, records of notifications served &
compensation
x Permission letters and procedure of crossings
This module will have feature for storing and retrieval of all the surveyed and
investigated data on GIS platform with all drawings hyperlinked to features.
This will ease out the design process and assist the Engineering Manager.
Construction x Structures- aqueducts, syphon, head regulator, gates and
bridges etc.
Manager
x Canal / pipeline Network
x Cadastral Village maps
x Land acquisition data
x Crossing details
x Soil survey data
x As built information and drawings
Library x Extensive library of different categories – Eg. Standards
/codes, activities, guidelines, regulations etc.
(Document
x Document versioning
Management x Allows add/edit/delete of information in specific categories
System)
Project Manager x This module facilitates to operate and control the above
modules in a systematic way
x Secured data access and User Control
Page 85 of 149
conditions, proposed cropping pattern, command area drainage , water management,
climate of command area, present source of irrigation in command area, GIS Database
based on the final alignment study, salient features of project, Detailed Project Report,
Design, Drawing, Land Acquisition Plan Schedule etc., GIS Application Shall be
developed using Open Source Software of Any other software with license permission
& it will be handover to the department. and supply & installation to NWRWS &
Kalpasar Department along with transfer of entire GIS Database to the department.
x Initially Interim Project reports shall be submitted to Engineer-In-Charge in 03 copies
for approval and it should be submitted in three parts as described below:
1. Interim report Part 1 will be submitted after completion of item 1 to 4 described in form
Fin 2
- Processing 2.50m resolution CARTOSAT imagery.
- Detailed distribution planning up to 400 hector and Carrying out crop water
requirement study.
- Reconnaissance survey.
- Establishment of GCP for CARTOSAT imagery.
The above report should consist of details of above mentioned activities but not
limited to the following points.
x Detail of command area, taluka district wise for each option
x Detail of final alignment with detailed map and list of structures and
locations and magnitude of pumping station.
x crop water study including distribution system planning upto 400 ha for
all option
x total approximate cost of complete water distribution system for each
water availability option.
2. Interim report Part 2 will be submitted after completion of item 5 to 10 described in
Form Fin 2
- Field surveying Using high end DGPS and ETS including generation of L\s and
C/S.
- Fixing of Apex point.
- Fixing of TBM.
- Fixing of PBM.
- Geotechnical investigation and testing.
- Detailed design drawing along with estimates.
Page 86 of 149
The above report should consist of details of above mentioned activities but not limited
to the following points.
x Detail of command area, taluka district wise for each option
x Detail of final alignment with detailed map and list of structures and
locations and magnitude of pumping station.
x Detailed distribution planning up to 400 hector for all option and
Carrying out crop water requirement study.
x total estimated cost of complete water distribution system based on
preliminary design and geotechnical investigation for each water
availability option
x Final Detailed Project Report incorporating all the interim reports and additional
information / data /clarification etc. as sought by Competent Authority shall be prepared
and submitted in 5 hard copies.
x Final Detailed Project Report of this work will be the part of DPR being prepared by
NIOT & NCCR, Chennai for the whole Kalpasar project. The format of this detailed
project report should be as per the guideline of CWC.
x Technical Presentations to be done at any level for the executed work shall be done
by the Consultant as desired by the Engineer-in-Charge.
6.5 Deliverables:
Page 87 of 149
Sl. Particulars of submission Drawing Draft Final
Scale submission submission
(if any) Hard Copy + Hard Copy +
Soft copy Soft copy
4) Base map finalized based on 1:4,000 01 Set each 03 Set each
Cartoset & Field survey showing the
canal alignment with profile as per
scope & specification
5) Interim Report Part 1 01 Set each 03 Set each
10) Land Acquisition Plan /Schedule 1:4,000 01 Set each 03 Set each
(Village wise)
11) Web Based Canal Asset -- -- To be installed at
Management System – Software NWRWS Office
with operational manuals
Page 88 of 149
6.6 Activity wise time schedule and terms of payment
The Consultant shall adhere to the time schedule for completion of the assignment. The time schedule stipulated shall be adhered to as far as possible.
In case of delay in submission by the consultant for acceptable reasons, appropriate time limit extension will be granted by the department.
Page 89 of 149
4. The Agency is to use the advance payment only to pay for Equipment, Plant, Materials and mobilization expenses required specifically
for execution of the contract. The agency shall demonstrate that advance payment has been used in this way by supplying copies of
invoices or other documents to the EIC.
5. Recovery of the advance payment shall commence from 20% financial progress of total work and full recovery of advanced shall be
completed by the end of 80% financial progress of the total work.
distribution system alignment for approval of department. Carrying out crop x 10% after acceptance of final report.
water requirement study based on existing command area detail, soil type,
agroclimatic zone etc. to work out the design capacity of distribution system.
Page 90 of 149
Sl. Item Description
No. Terms of payment
3. Reconnaissance Survey: Carrying out field reconnaissance survey for identify x 50% after submission of main canal / pipeline alignment
minimum /shortest length for fixing of main canal / pipeline alignment corridor x 30% after acceptance of main canal / pipeline alignment
considering the obstacles / obstructions, environmentally sensitive locations, for field survey.
feasibility of main canal / pipeline alignment using Survey of India Topo Maps x 5% on submission after interim report part 1
duly superimposing the developmental plan, major development and x 5% on acceptance after interim report part 1.
10% after acceptance of final report.
environmentally sensitive area on key map procured by CARTOSAT imagery. x
Tentatively fixing of main canal / pipeline alignment corridor for approval of
department for carrying out surveying using DGPS and total station.
4. Establishment of Ground control points using high end DGPS for x 50% after completion of field work and submission of
CARTOSAT imagery DGPS report.
x 30% after acceptance of main canal / pipeline alignment
for field survey.
x 5% on submission after interim report part 1
x 5% on acceptance after interim report part 1.
x 10% after acceptance of final report.
Page 91 of 149
Sl. Item Description
No. Terms of payment
5. Surveying by DGPS and TOTAL STATION including measuring of x 50% after completion and verification of field survey.
alignment of earthan dam/canal and creating the cross section and x 30% after submission of L/S and C/S.
longitudinal section profile at 30mt interval/or closer as directed plotting x 5% on submission after interim report part 2
etc complete on approved final alignment by department. The survey x 5% on acceptance after interim report part 2.
work shall be carried out for 150mt distance on both sides. x 10% after acceptance of final report.
6. Fixing of Apex Point along main canal / pipeline or combination of both x 80% after completion of field work.
alignment by fixing monumentation of RCC pillar of size 200 mm x 200 x 5% on submission after interim report part 2
mm x 750mm sise at every apex point at 500 m interval. x 5% on acceptance after interim report part 2.
x 10% after acceptance of final report.
7. Fixing TBM in CC 1:2:4: at every 01 Km interval having size of pillar x 80% on completion and verification of field work.
300 mm x 300 mm x 750 mm at site on main canal / pipeline or x 5% on submission after interim report part 2
combination of both alignment. x 5% on acceptance after interim report part 2.
x 10% after acceptance of final report.
Page 92 of 149
Sl. Item Description
No. Terms of payment
8. Fixing PBM in CC 1:2:4: at every 05 Km interval having size of pillar x 80% on completion and verification of field work.
500 mm x 500 mm x 750 mm at site on main canal / pipeline or x 5% on submission after interim report part 2
combination of both alignment x 5% on acceptance after interim report part 2.
x 10% after acceptance of final report.
9. Geo-technical Investigation and recommendation of soil strata for x 80% on completion and verification of field work and
design of distribution system alignment / structures on main testing.
canal/pipeline or combination of both alignment only. x 5% on submission after interim report part 2
x 5% on acceptance after interim report part 2.
x 10% after acceptance of final report.
10. i) For Main Canal / Pipeline alignment x 40% after acceptance of design report
Preparation of detailed design drawings of canal / pipeline x 40% on acceptance of detailed estimates.
(considering the water availability given by the Engineer-In-Charge), x 5% on submission after interim report part 2
cross section showing bed width, side slopes, service road, inspection x 5% on acceptance after interim report part 2.
path width, spoil bank section, outer toe drain section, maintenance x 10% after acceptance of final report.
land width etc. Plotting cross section at every 10 m interval so as to
cover the sections in full cutting, full bed banking or partial cutting and
partial banking as the case may be along with detailed estimates.
Preparation of detailed designs for structures falling on main distribution
alignment and pumping stations including electro mechanical
components along with detailed estimates.
Page 93 of 149
Sl. Item Description
No. Terms of payment
ii) For distribution system other than Main Canal / Pipeline alignment
Preparation of preliminary design for a typical canal / pipeline stretch,
preliminary typical design for each type of structure along with
preliminary estimate for the said distribution system.
Complete item (i) and (ii) combined.
11. Preparing of Village wise land plan schedule: Collection of original x 80% on submission of land acquisition statement.
village map from concerned department by consultant, geo-referencing x 5% on submission after interim report part 3
of village map, Transferring the final alignment on the village maps. x 5% on acceptance after interim report part 3.
preparation of Land acquisition statement, collection of ownership x 10% after acceptance of final report.
record and preparation of land acquisition statement.
Page 94 of 149
12. Creation of GIS Database based on the final alignment study, salient x 80% on submission of software modules.
features of project, Detailed Project Report, Design, Drawing, Land x 5% on submission after interim report part 3
Acquisition Plan Schedule etc., GIS Application Shall be developed x 5% on acceptance of interim report part 3
using Open Source Software of Any other software with license x 10% after acceptance of final report.
permission & it will be handover to the department. and supply &
installation to NWRWS & Kalpasar Department along with transfer of
entire GIS Database to department.
Page 95 of 149