Title: Prepare a Bill of Material of an Aquaculture Facility
Performance Objectives: Given one Competency of the qualification assigned to
you, you should be able to prepare the bill of materials and
cost estimates.
Supplies/ Materials: TR and CBC
Equipment’s: PC, Printer with Ink, Aquaculture facility
Steps/Procedure:

1. Visit available Aquaculture Facility (Fish pond, pen, cages, or tanks)

2. Measure the needed data for you to make a lay out plan

3. Make a lay out plan of that facility based on the measurements that you
have made.

4. Prepare a bill of materials based on the lay out plan of the facility.

5. Compile you output from measuring, lay outing, up to bill of material


preparation.

Assessment Method:

Portfolio
Performance Criteria Checklist 2.4-3

CRITERIA YES NO
1. Materials needed for the project are listed and itemized
2. Specification materials are listed based on the plan
3. Cost of project is computed and recorded in line with project
requirement and duration