PROJECT : SM MOA BLOCK-4

FCU MONITORING (VRF) AS OF MAY 25, 2021

UNIT PIPING ELECTRICAL


UNIT INSTALLED REMARKS
PIPING PRESSURE TEST INSULATION FCU DRAIN TERMINATION WIRING ECB
THIRD FLOOR
FCU L3-08B
FCU L3-09B
FCU L3-13B
FOURTH FLOOR
FCU L4-16B
FCU L4-17B
FCU L4-24B
FIFTH FLOOR
FCU L5-48B
FCU L5-49B
FCU L5-54B

LEGEND:
DONE
IN PROGRESS
NOT DONE
N/A
PROJECT : SM MOA BLOCK-4
FCU MONITORING (CHWP) AS OF MAY 05, 2021

FAN COIL UNITS DUCTING PIPING ELECTRICAL


UNIT
DELIVERED INSTALLED SAD RAD MACHINE CONNECTIONS INSULATION DIFFUSERS HOOK UP INSULATION FCU DRAIN WIRING
BASEMENT
FCU B-01 NA NA NA NA NA
FCU B-02 NA NA NA NA NA
FCU B-03 NA NA NA NA NA
FCU B-04
GROUND FLOOR
FCU G-02
FCU G-03
FCU G-04
FCU G-05
FCU G-06 NA NA NA NA NA
FCU G-07 NA NA NA NA NA
FCU G-08
FCU G-09
FCU G-10 NA NA NA NA NA
FCU G-11
FCU G-12 NA NA NA NA NA
FCU G-13A NA NA NA NA NA
FCU G-14A NA NA NA NA NA
FCU G-15
FCU G-16A NA NA NA NA NA
FCU G-17A NA NA NA NA NA
FCU G-18A
FCU G-19A NA NA NA NA NA
FCU G-24A NA NA NA NA NA
FCU G-24B NA NA NA NA NA
FCU G-25 NA NA NA NA NA
SECOND FLOOR
FCU L2-01
FCU L2-02 NA NA NA NA NA
FCU L2-05A
FCU L2-06 NA NA NA NA NA
FCU L2-07 NA NA NA NA NA
FCU L2-08 NA NA NA NA NA
FCU L2-09 NA NA NA NA NA
FCU L2-10 NA NA NA NA NA
FCU L2-11A NA NA NA NA NA
FCU L2-11B NA NA NA NA NA
FCU L2-12 NA NA NA NA NA
FCU L2-13 NA NA NA NA NA
FCU L2-14 NA NA NA NA NA
FCU L2-15 NA NA NA NA NA
FCU L2-16 NA NA NA NA NA
THIRD FLOOR
FCU L3-01
FCU L3-02
FCU L3-03
FCU L3-04
FCU L3-05A
FCU L3-05B
FCU L3-06A
FCU L3-06B
FCU L3-07 NA NA NA NA NA
FOURTH FLOOR
FCU L4-01
FCU L4-02
FCU L4-03
FCU L4-04
FCU L4-05 NA NA NA NA NA
FCU L4-06 NA NA NA NA NA
FCU L4-07 NA NA NA NA NA
FCU L4-08 NA NA NA NA NA
FCU L4-09A NA NA NA NA NA
FCU L4-10 NA NA NA NA NA
FCU L4-11
FCU L4-12A NA NA NA NA NA
FCU L4-12B NA NA NA NA NA
FCU L4-13A NA NA NA NA NA
FCU L4-13B NA NA NA NA NA
FCU L4-14
FCU L4-15A NA NA NA NA NA
FCU L4-15B NA NA NA NA NA
FCU L4-15C NA NA NA NA NA
FCU L4-22
LOWER FIFTH FLOOR
FCU L5-01
FCU L5-02
FCU L5-03 NA NA NA NA NA
FCU L5-04
FCU L5-05
FCU L5-06 NA NA NA NA NA
FCU L5-07
FCU L5-08 NA NA NA NA NA
FCU L5-09
FCU L5-10
FCU L5-11 NA NA NA NA NA
FCU L5-12 NA NA NA NA NA
FCU L5-13
FCU L5-14
FCU L5-15 NA NA NA NA NA
FCU L5-16 NA NA NA NA NA
FCU L5-17
FCU L5-18
FCU L5-19
FCU L5-20
FCU L5-21
FCU L5-22 NA NA NA NA NA
FCU L5-23 NA NA NA NA NA
FCU L5-24A NA NA NA NA NA
FCU L5-24B NA NA NA NA NA
FCU L5-25
FCU L5-26 NA NA NA NA NA
FCU L5-27A NA NA NA NA NA
FCU L5-27B NA NA NA NA NA
FCU L5-28
FCU L5-29
FCU L5-30
FCU L5-31 NA NA NA NA NA
FCU L5-32 NA NA NA NA NA
FCU L5-33 NA NA NA NA NA
FCU L5-34 NA NA NA NA NA
FCU L5-35A NA NA NA NA NA
FCU L5-35B NA NA NA NA NA
FCU L5-36 NA NA NA NA NA
FCU L5-37 NA NA NA NA NA
FCU L5-38
FCU L5-39
FCU L5-40
FCU L5-41 NA NA NA NA NA NA NA NA NA NA
FCU L5-42 NA NA NA NA NA
FCU L5-43 NA NA NA NA NA
FCU L5-44 NA NA NA NA NA
FCU L5-45
FCU L5-46
UPPER FIFTH FLOOR
FCU L5M-13A
FCU L5M-13B

LEGEND:
DONE
IN PROGRESS
NOT DONE
N/A
ELECTRICAL
REMARKS
MCP

DAMAGED FCU

TBA

SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
SERVING AT SM BRIDGE
FLOOR MOUNTED AT 4TH
NA UNIT DELETED

UNIT DAMAGED
PROJECT : SM MOA BLOCK-4
MSFD MONITORING AS OF MAY 31, 2021

INSTALLATION ELECTRICAL
NOT INSTALLED PERCENTAGE
ITEM INSTALLED INSTALLED CONDUITING POWER-UP FLASHING TARGET DATE
TOTAL UNITS (UNITS) (Power Side) (Initial Test) KW
(UNITS)
THIRD FLOOR
A. MSFD AT GL: A-B/ 4-5 24 21 3 87.50% 0.00% May 31, 2021 240 W May 31, 2021 May 31, 2021
B. MSFD AT GL: A-B/ 7-9 9 9 0 100.00% 100.00% Done 90 W Done Done
C. MSFD AT GL: B-C/ 8-9 24 24 0 100.00% 100.00% Done 240 W Done Done
D. MSFD AT GL: E-F/8-9 24 24 0 100.00% 100.00% Done 240 W Done Done
FOURTH FLOOR
A. MSFD AT GL: A-B/ 2-3 16 16 0 100.00% 100.00% Done 160 W Done May 31, 2021
B. MSFD AT GL: A-B/ 4-5 24 24 0 100.00% 100.00% Done 240 W May 31, 2021 May 31, 2021
C. MSFD AT GL: C-D/ 8-9 16 16 0 100.00% 100.00% Done 160 W May 31, 2021 May 31, 2021
D. MSFD AT GL: F-G/ 8-9 24 24 0 100.00% 100.00% May 31, 2021 240 W Done May 31, 2021
E. MSFD AT GL: H-J/ 1-2 16 16 0 100.00% 100.00% Done 160 W May 30, 2021 May 31, 2021
F. MSFD AT GL: J-K/ 1-2 8 8 0 100.00% 80 W Done
FIFTH FLOOR
A. MSFD AT GL: A-B/ 2-3 16 15 1 93.75% 0.00% May 31, 2021 160 W Done May 31, 2021
B. MSFD AT GL: A-B/ 5-6 24 23 1 95.83% 0.00% May 31, 2021 240 W Done May 31, 2021
C. MSFD AT GL: F-G/ 8-9 24 24 0 100.00% 0.00% May 31, 2021 240 W May 31, 2021 May 31, 2021
D. MSFD AT GL: D-E/ 1-2 24 24 0 100.00% 100.00% May 31, 2021 240 W Done May 31, 2021

TOTAL UNITS 273 268 5 98.17%

NOTE: FLASHING BY MDI - FLASHING AT MSFD SIDES


FLASHING BY RWSI - FLASHING OUTSIDE OF MSFD FOR WATER TIGHTNESS
REMARKS

THIRD FLOOR
Ongoing Flashing/Wiring/Balance 3 Units for Delivery
Completed/Ready for Power & Interlock Termination
Completed/Ready for Power & Interlock Termination
Completed/Ready for Power & Interlock Termination
FOURTH FLOOR
On-going Homerun Installation
For Flashing by MDI/RWSI/Homerun Installation
For Flashing/Wiring Re-termination/Homerun Installation
Ongoing Eletrical Works/Homerun Installation
For Flashing/Wiring Re-termination/Homerun Installation
Additional Units/For Electrical Works/Homerun Installation
FIFTH FLOOR
For Electrical Works/Homerun Installation/Balance 1 Unit for Delivery
For Electrical Works/Homerun Installation/Balance 1 Unit for Delivery
Ongoing Electrical Works / For Flashing by MDI/RWSI
Homerun Installation

WATER TIGHTNESS
PROJECT : SM MOA BLOCK-4
SUBJECT: BALANCE OF WORKS
LOCATION: IDF/POWER ROOM MONITORING AS OF MAY 31, 2021

FCU (CHWP) FCU (VRF) Ducting Electrical OTHER WORKS TARGET


AREA Works ECB/Fans DATE REMARKS
Installed Piping Drain Electrical Installed Piping Drain Electrical Penetration's Flashing Restoration
THIRD FLOOR
1. G.L. C-D/8-9 100% N/A N/A Balance Power Supply for VRF FCU
2. G.L. C-D/3-4 N/A N/A N/A Balance Power Supply for VRF FCU
3. G.L. G-H/6-7 N/A N/A N/A Balance Power Supply for VRF FCU
4. G.L. H-J/3-4 80% N/A N/A 100%
5. G.L. G-H/1-2 80% 90% N/A N/A N/A 20%
6. G.L. K-L/8-9 90%
7. G.L. M-N/3-4
FOURTH FLOOR
1. G.L. A-B/2-3 80% N/A Balance Power Supply for VRF FCU
2. G.L. A-B/3-4 90% N/A N/A 80%
3. G.L. C-D/2-3 80% 80% N/A N/A 70% N/A 80%
4. G.L. B-C/2-3 90% 100% N/A N/A Balance Power Supply for VRF FCU
5. G.L. J-K/5-6 90% 50% 70% N/A N/A 60%
6. G.L. C-D/8-9 100% N/A Balance Power Supply for VRF FCU
7. G.L. L-M/8-9 50% 80% N/A N/A 30%
8. G.L. M-N/3-4 90%
FIFTH FLOOR
1. G.L. A-B/2-3 70% N/A 50% N/A 50%
2. G.L. C-D/8-9 80% No FCU 90% 80% 0% 100% 70% On-going Works
3. G.L. G-H/1-2 90% 80% 0% N/A N/A 70% On-going Works
4. G.L. J-K/7-8 N/A
5. G.L. K-L/3-4 90% 80% 0% N/A 70% On-going Works
6. G.L. L-M/6-7 70% N/A 80%

LEGEND: DONE
PROJECT : SM MOA BLOCK-4
VEU MONITORING (VRF) AS OF MAY 31, 2021

Copper Condensate Ther- Pressure Pressure Charging Target Date of


UNIT Location Area Served Status Electrical Flaring Flushing Remarks
Piping Drain mostat Test (Initial) Test (Final) of Freon Completion
A. ACCU G-01 GF Carpark - G.L. K-L/7-8 N/A N/A
VEU G-16B GF - G.L. L-M/6-7 GF Reception
VEU G-17B GF - G.L. L-M/6-7 GF Sec / CCTV
VEU G-21B GF - G.L. L-M/3-4 GF IDF 500A Installed

B. ACCU L2-01 2F AHU Room near Stair 6 - G.L. F-G/1-2 Installed N/A N/A
VEU G-20B GF - G.L. G-H/2-3 GF POWER near Stair 6 Installed Done Done
VEU G-26B GF - G.L. D-E/3-4 GF ME Installed Done Done
VEU L2-04B 2F - G.L. G-H/1-2 2F IT/IDFnear Stair 6 Installed Done Done
VEU L3-15B 3F - G.L. H-J/3-4 3F POWER near Checkout Installed Done Done Balance Refnet 26172T
Done Done
VEU L3-10B 3F - G.L. G-H/1-2 3F IDF 500A near Stair 6 Installed Done Done c/o DAIKIN
VEU L5-49B 5F - G.L. G-H/1-2 5F IDF 500A near Stair 6 Installed Done Done
VEU L5-50B 5F - G.L. H-J/1-2 5F POWER 528 near Stair 6 Installed Done Done
VEU L2-03B 2F - G.L. D-E/1-2 2F IT/IDFnear Stair 7 Installed Done Done
VEU L3-09B 3F - G.L. C-D/3-4 3F ME/IDF near Back to Stock Installed Done Done

C. ACCU L5M-01 5UF near Stair 1 - G.L. C-D/8-9 Installed 90% N/A N/A
VEU L5-48B 5F - G.L. C-D/8-9 5F IDF 528 near Stair 1 Not delivered 90% FCU Unit not yet
Done Done
VEU L4-16B 4F - G.L. C-D/8-9 4F IDF/POWER 528 near Stair 1 Installed Done Done Done Done delivered by DAIKIN
VEU L3-08B 3F - G.L. C-D/8-9 3F IDF/POWER 528 near Stair 1 Installed Done Done Done Done

D. ACCU L5M-01 5F near Stair 2 - G.L. J-K/8-9 Installed N/A N/A


VEU L5-52B 5F - G.L. J-K/7-8 5F POWER 528 near Stair 2 Installed Done Done
VEU L5-53B 5F - G.L. L-M/6-7 5F POWER 526 near Coworker Kt. Installed Done

E. ACCU L5-02 5F near Stair 2 - G.L. J-K/8-9 Installed Done N/A N/A
VEU L4-09B 4F - G.L. L-M/8-9 4F Beverage 247 Installed Done Done
VEU L4-21B 4F - G.L. L-M/8-9 4F POWER 527 Installed Done Done
Done Done
VEU L4-20B 4F - G.L. J-K/5-6 4F POWER 526b Installed Done Done
VEU L3-12B 4F - G.L. K-L/8-9 3F POWER near Stair 2 Installed Done Done
VEU L3-13B 4F - G.L. G-H/7-8 3F IDF 500A near G-2 Installed Done Done

F. ACCU L5M-03 5UF Chiller Plant Room N/A N/A


VEU L2-05B 2F - G.L. L-M/3-4 2F IDF 500A Installed Done Done
VEU L3-11B 3F - G.L. M-N/3-4 3F IDF/POWER 526B near Stair 4 Installed Done Done Done
VEU L4-19B 4F - G.L. M-N/3-4 4F IDF 500A near Stair 4 Installed Done Done
VEU L5-54B 5F - G.L. K-L/3-4 5F ME/IDF 500A near Coworker Lck. Installed Done Done

G. ACCU L5-03 5UF Plant Room Installed Done N/A N/A


VEU L5-47B 5F - G.L. A-B/2-3 5F IDF 500A near Lift G-1 & G-3 Installed Done Done Done Done Done
VEU L4-23B 4F - G.L. A-B/3-4 4F POWER near Warehouse Installed Done Done Done Done Done
Done Done
VEU L4-17B 4F - G.L. A-B/2-3 4F IDF near Lift G-1 & G-3 Installed Done Done Done Done Done
VEU L4-24B 4F - G.L. B-C/2-3 4F IDF near Home Delivery Installed Done Done Done Done Done
VEU L4-18B 4F - G.L. C-D/2-3 4F IDF/POWER 526c near Stair 7 Installed Done Done Done Done Done